ML24185A178

From kanterella
Revision as of 11:37, 4 October 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

NRC Email Response to Peach Bottoms Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations
ML24185A178
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 07/03/2024
From: Tanya Hood
Reactor Decommissioning Branch
To: David Helker
Constellation Nuclear
References
EPID L-2023-LLN-0004
Download: ML24185A178 (1)


Text

From: Tanya Hood To: Helker, David P:(Constellation Nuclear)

Cc: Gropp Jr, Richard W:(Constellation Nuclear); Amy Snyder

Subject:

Peach Bottom Unit 1 - Request For Additional Information Re: Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations (EPID L-2023-LLN-0004)

Date: Wednesday, July 3, 2024 9:35:00 AM Attachments: RAIs for Peach Bottom Unit 1-Request for Alternative Schedule to Complete Decommissioning Beyond 60.pdf

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION RE: REQUEST FOR ALTERNATIVE SCHEDULE TO COMPLETE DECOMMISSIONING BEYOND 60 YEARS OF PERMANENT CESSATION OF OPERATIONS (EPID L-2023-LLN-0004)

Dear David P. Helker:

By letter dated October 20, 2023, (Agencywide Documents Access and Management System Accession No. ML23293A305), as supplemented by letter dated May 13, 2024 (ML24134A179), Constellation Energy Generation, LLC (Constellation, the licensee) submitted a request for Peach Bottom Atomic Power Station, Unit 1 (Peach Bottom Unit 1).

The proposed request would allow the completion of decommissioning for Peach Bottom Unit 1 beyond 60years of permanent cessation of operations.

The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information submitted by the licensee and determined that additional information is required to complete its review. The requested additional information is attached. The draft questions were sent to Richard Gropp Jr. of your staff to ensure that they were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. Please respond within 30 days.

If you have any questions, please contact me.

Tanya E. Hood, Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards 301-415-1387