Category:Letter
MONTHYEARNL-24-0384, Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves2024-10-18018 October 2024 Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves NL-24-0320, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,.2024-09-27027 September 2024 License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,. NL-24-0349, Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided2024-09-20020 September 2024 Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided IR 05000348/20244012024-09-10010 September 2024 Security Baseline Inspection Report 05000348-2024401 and 05000364-2024401 NL-24-0341, Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency2024-09-10010 September 2024 Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency ML24247A1102024-09-0505 September 2024 Corporate Notification Letter Aka 210-day Letter NUREG Rev 12 NL-24-0259, License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes2024-09-0404 September 2024 License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes NL-24-0340, Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R322024-09-0404 September 2024 Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R32 ML24242A1332024-08-29029 August 2024 Issuance of Amendment Nos. 250 and 247, Regarding License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions (EPID L-2024-LLA-0098) - Non-Proprietary ML24233A0022024-08-27027 August 2024 Request for Withholding Information from Public Disclosure for Joseph M. Farley Nuclear Plant, Units 1 and 2, License Amendment Request Supplement to Change Technical Specification 3.6.5, Containment Air Temperature Actions ML24240A0812024-08-27027 August 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Revised Completion Time IR 05000348/20240052024-08-26026 August 2024 Updated Inspection Plan for Joseph M. Farley Nuclear Plant, Units 1 and 2 - Report 05000348/2024005 and 05000364/2024005 IR 05000348/20244022024-08-26026 August 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000348/2024402 and 05000364/2024402 ML24226B2112024-08-22022 August 2024 Regulatory Audit Summary in Support of License Amendment Requests to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions NL-24-0321, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information2024-08-16016 August 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information IR 05000348/20240022024-08-12012 August 2024 – Integrated Inspection Report 05000348-2024002 and 05000364-2024002 and Exercise of Enforcement Discretion ML24215A3772024-08-0707 August 2024 2024 Farley Requal Inspection Corporate Notification Letter ML24201A2032024-08-0101 August 2024 Request for Withholding Information from Public Disclosure for Joseph M. Farley Nuclear Plant, Units 1 and 2, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions ML24200A1392024-07-25025 July 2024 Regulatory Audit in Support of Review of the License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature ML24199A2072024-07-24024 July 2024 TS 3-6-5 LAR - Individual Notice Transmittal Letter and NSHC - Rev 1 (1) - Letter NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 NL-24-0281, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions2024-07-18018 July 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML24184A0452024-07-0202 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A3762024-07-0101 July 2024 Nonacceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, Using Risk-Informed Process for Evaluations NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0230, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-3602024-06-28028 June 2024 License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-360 NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in 05000348/LER-2024-002-01, Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel2024-06-19019 June 2024 Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) 05000348/LER-2024-001, Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits Due to Setpoint Drift2024-06-17017 June 2024 Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits Due to Setpoint Drift NL-24-0238, RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information2024-06-14014 June 2024 RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information NL-24-0229, Notice of Intent to Pursue Subsequent License Renewal2024-06-0707 June 2024 Notice of Intent to Pursue Subsequent License Renewal ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, ML24143A0412024-05-28028 May 2024 Supplemental Information Needed for Using the Risk-Informed Process for Evaluation for the LAR to Change Technical Specification 3.6.5, Containment Air Temperature, Actions NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 NL-24-0188, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 IR 05000348/20240012024-04-24024 April 2024 Integrated Inspection Report 05000348/2024001 and 05000364/2024001 NL-24-0137, RIPE License Amendment Request to Change Containment Air Temperature Actions2024-04-19019 April 2024 RIPE License Amendment Request to Change Containment Air Temperature Actions IR 05000348/20240102024-04-16016 April 2024 NRC Inspection Report 05000348/2024010 and 05000364/2024010 05000364/LER-2024-002, for Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel2024-04-15015 April 2024 for Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel NL-24-0134, Renewed National Pollutant Discharge Elimination System (NPDES) Permit2024-04-12012 April 2024 Renewed National Pollutant Discharge Elimination System (NPDES) Permit IR 05000348/20240112024-04-12012 April 2024 Fire Protection Team Inspection Report 05000348/2024011 and 05000364/2024011 NL-24-0088, Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency2024-04-0505 April 2024 Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. ML24061A1692024-03-22022 March 2024 PM Reassignment Letter Farley March 2024 2024-09-05
[Table view] |
Text
Edwin D. Dean, Site Vice President Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant 7388 North State Highway 95 Columbia, AL 36319
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION - JOSEPH M. FARLEY NUCLEAR PLANT
Dear Edwin Dean:
In a telephone conversation on August 1, 2024, Mr. Virgel Furr, Operations Engineer, and Mr.
Christopher Nesiba, Licensed Operator Continuing Training Superintendent, made arrangements for the NRC to inspect the licensed operator requalification program at the Joseph M. Farley Nuclear Plant. The inspection is planned for the week of September 9, 2024, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that you have committed to maintain your plant-referenced simulator in accordance with ANSI/ANS-3.5-2009, American National Standard for Nuclear Power Plant Simulators for Use in Operator Training and Examination.
In accordance with 10 CFR 55.59, the NRC has requested that you submit by August 30, 2024, the material as specified in paragraph A of the Enclosure, in order to support the NRC's inspection program needs. The NRC has further requested that you have all items as specified in paragraph B of the Enclosure available for review for the inspectors on the first day they arrive on site. Mr. Nesiba has been advised of this request and provided with the name of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018).
The public reporting burden for this collection of information is estimated to average four hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.August 7, 2024 E. Dean 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. Virgel Furr at (404)-997-4811, (Internet E-mail:
virgel.furr@nrc.gov), or me at (404) 997-4703, (Internet E-mail: thomas.stephen@nrc.gov).
Sincerely, Thomas A. Stephen, Chief Operations Branch 1 Division of Reactor Safety Docket Nos.: 50-348 and 50-364 License Nos.: NPF-2 and NPF-8
Enclosure:
Materials Request List cc: Distribution via Listserv Signed by Stephen, Tom on 08/07/24
ML24215A377 Cover Letter Only: X Non-Sensitive X Publicly Available X SUNSI Review Sensitive Non-Publicly Available OFFICE RII/DRS RII/DRS RII/DRS RII/DRP RII/DRP RII/DRS NAME K. Wallace S. Furr M. Donithan S. Temple A. Blamey T. Stephen DATE 08/02/24 08/02/24 08/05/24 08/06/24 08/02/24 08/06/24 Materials Request List
The items listed below are necessary to support the Licensed Operator Requalification Program Inspection (IP-71111.11) in September 2024 at the Farley Electric Generating Station Units 1&2. Items listed under In-office inspection material must be received in the NRC Region II office by the due date specified below. Items listed under On-site inspection material should be ready for review upon arrival of the inspectors on September 9, 2024.
A. In office inspection material due by August 30, 2024:
- 1. Complete list of all licensed individuals (active and inactive; RO and SRO) including license restrictions.
- 2. Copy of an Organizational Chart for the training department including simulator staff.
- 3. Spreadsheets and/or test outlines which show the usage of written examination questions, JPMs, and simulator scenarios (i.e. outlines/sample plans).
- 4. Copy of the weekly examination schedules for the weeks that the 2024 annual operating exams will be administered, including a list of personnel scheduled for testing the week of September 9, 2024.
- 5. Copies of the written examinations that were administered for the last biennial requalification examination (for all weeks), including all re-take examinations.
- 6. Ten (10) job performance measures (JPMs), both simulator and in-plant, and six (6) simulator scenarios associated with the current annual operating test. The JPMs and scenarios to be reviewed should include those that will be administered the week of September 9, 2024, with any remaining JPMs and scenarios reviewed selected from other weeks of the annual operating test. (exam security related item)
7.Self-assessment reports, corrective action reports, and Licensee Event Reports, written since the last requalification inspection, resulting from or concerning human performance errors, including any examination security issues.
- 8. A copy of site procedure(s) governing the conduct (process and content) of license operator requalification training (classroom and simulator), examination development/administration, remedial training, and examination security.
- 9. A copy site procedure(s) governing simulator configuration control, maintenance, and fidelity, including all testing methods used to fulfill ANSI/ANSB3.5-2009 requirements.
10.Copy of the program evaluation of the previous biennial requalification cycle.
Enclosure B. Onsite inspection material due by September 9, 2024:
- 1. Requalification training attendance records for the current biennial training cycle.
- 2. Examination results since last requalification inspection (weekly operating & written examinations); copies of examinations with pass/failure rates outside the average.
- 3. Simulator scenarios and JPMs (in-plant and simulator) that have been or will be administered for this requalification exam. (exam security related item)
- 4. All training feedback forms since the last requalification inspection.
- 5. Documentation regarding all remedial training conducted for examination failures since the last requalification inspection.
- 6. Complete list of all individuals that reactivated their licenses since the last requalification inspection.
- 7. Records associated with license reactivation, including:
- a. Documentation of time on shift under instruction.
- b. Security system and HP/dosimetry records for plant areas toured by reactivating individual and accompanying licensed operator.
- 8. Records providing documentation of maintenance of active license status (time on shift) for all licensed operators since last requalification inspection.
- 9. Medical records for all licensed (active and inactive) operators.
10.Simulator maintenance and testing records, including:
- a. List of all open simulator discrepancies
- b. List of all simulator discrepancies closed within the past 12 months
- c. List of simulator performance tests
2