Order Establishing 781115 Prehearing Meeting to Discuss NRC Objections to License Application & State of Wa Petition to Intervene.Objections Relate to Failure to Establish InterestML20062A988 |
Person / Time |
---|
Site: |
Columbia |
---|
Issue date: |
10/11/1978 |
---|
From: |
Bowers E Atomic Safety and Licensing Board Panel |
---|
To: |
|
---|
References |
---|
NUDOCS 7810190160 |
Download: ML20062A988 (4) |
|
|
---|
Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20210U4531999-08-12012 August 1999 Comment Opposing Proposed Rule 10CFR50 Re Consideration of Potassium Iodide (Ki) in Emergency Plans.Urges NRC to Retain Current Policy for Ki Usage GO2-97-089, Comment Supporting Proposed Rule 10CFR73 Re Changes to Power Plant Security Requirements1997-05-0707 May 1997 Comment Supporting Proposed Rule 10CFR73 Re Changes to Power Plant Security Requirements ML17292A7151997-02-25025 February 1997 Comment Supporting Proposed Generic Communications, Effectiviness of Ultrasonic Testing Sys in ISI Program. ML20134L3351997-02-14014 February 1997 Order Imposing Civil Monetary Penalty Re Licensee Activities Conducted from 960628-960904 ML17291A9101995-07-0707 July 1995 Comment on Review of NRC Insp Rept Content,Format & Style. NRC Insp Repts Should Provide Balanced Perspective, Reflecting Licensee Strengths & Positive Aspects of Programs & Activities Reviewed GO2-95-080, Comment on Proposed GL, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Util Believes That Ability to Justify Actuator Capability by Analysis Should Not Be Restricted to Population of Small Valves1995-04-26026 April 1995 Comment on Proposed GL, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves. Util Believes That Ability to Justify Actuator Capability by Analysis Should Not Be Restricted to Population of Small Valves GO2-94-187, Comment Opposing Proposed Rule 10CFR26 Re Consideration of Changes to FFD Requirements1994-08-0808 August 1994 Comment Opposing Proposed Rule 10CFR26 Re Consideration of Changes to FFD Requirements ML20058L9561993-07-26026 July 1993 Decommissioning Trust,Consisting of Asset Summary for Period Ending 930630,asset Summary Adjusted for Accurals for Period Ending 930630 & List of Assets as of 930630 ML20045D7551993-06-18018 June 1993 Comment on Proposed Rule 10CFR26 Re Mods to fitness-for-duty Program Requirements.Supports Rule W/Listed Exceptions ML20044E1511993-05-30030 May 1993 Comment Supporting Petition for Rulemaking PRM-50-58 Re VEPCO Petition to Change Frequency of Emergency Planning Exercises from Annual to Biennial ML17290A3901993-05-21021 May 1993 Comments on Proposed Insp Procedure 38703, Commercial Grade Procurement Insp. ML17289A9151992-10-0909 October 1992 Comment on Proposed Changes to SALP Program.Util Supports Comments Being Filed by NUMARC & Legal Firm of Winston & Strawn GO2-92-164, Comment on Proposed Rule 10CFR50 Re Loss of All Alternating Current Power & Draft Reg Guide 1.9,task DG-1021.Supports Detailed Comments Submitted by Numarc,As Representing Licensee Views1992-07-10010 July 1992 Comment on Proposed Rule 10CFR50 Re Loss of All Alternating Current Power & Draft Reg Guide 1.9,task DG-1021.Supports Detailed Comments Submitted by Numarc,As Representing Licensee Views GO2-92-136, Comment Supporting Proposed Rules 10CFR19 & 20 Re Extension of Implementation Date Concerning 10CFR201992-06-0404 June 1992 Comment Supporting Proposed Rules 10CFR19 & 20 Re Extension of Implementation Date Concerning 10CFR20 ML20091D1631992-04-0303 April 1992 Comment Opposing Proposed Rule 10CFR2 Re Policy & Procedure for Enforcement Actions.Concerned That Policy Seems to Be Creating New Requirements Through Examples Given ML20091Q8661992-01-31031 January 1992 Comment Opposing Draft NUREG-1022,Rev 1, Event Reporting Sys,10CFR50.72 & 50.73,Clarification of NRC Sys & Guidelines for Reporting ML17289A2931992-01-24024 January 1992 Comment on Draft Reg Guide Task DG-8007 (Proposed Rev 1 to Reg Guide 8.7) Re Instructions for Recording & Reporting Occupational Radiation Exposure Data ML17289A2541992-01-0606 January 1992 Comment on Draft Reg Guide Task DG-8004 Re Radiation Protection Programs.Reg Guide Provides Good Guidance for Maintaining Effective Radiation Protection Programs Aimed at Achieving Occupational Doses That Are ALARA GO2-91-103, Comment Opposing Proposed Rules 10CFR71,170 & 171, Rev of Fee Schedules;100% Fee Recovery1991-05-16016 May 1991 Comment Opposing Proposed Rules 10CFR71,170 & 171, Rev of Fee Schedules;100% Fee Recovery GO2-90-181, Comment Opposing Proposed Rule 10CFR26 Re fitness-for-duty. Rev Would Restrict Licensee from Taking Appropriate Action on Preliminary Positive Test1990-10-30030 October 1990 Comment Opposing Proposed Rule 10CFR26 Re fitness-for-duty. Rev Would Restrict Licensee from Taking Appropriate Action on Preliminary Positive Test ML17285B3701990-07-0505 July 1990 Comment Supporting Petition for Rulemaking PRM-50-55 Re Frequency of FSAR Revs,Per 10CFR50.71(e)(4) Requirements GO2-89-115, Comment Supporting Proposed Rule 10CFR50, Acceptance of Products Purchased for Use in Nuclear Power Plant Plant Structures,Sys & Components. Util Accepts NUMARC Comments1989-07-0606 July 1989 Comment Supporting Proposed Rule 10CFR50, Acceptance of Products Purchased for Use in Nuclear Power Plant Plant Structures,Sys & Components. Util Accepts NUMARC Comments ML20247N7531988-07-28028 July 1988 Petition for Rulemaking PRM-50-53 Requesting NRC Action to Review Undue Risk Posed by BWR Thermal Hydraulic Instability.Nrr Should Issue Order Requiring All GE BWRs to Be Placed in Cold Shutdown for Stated Reasons ML17279A8041987-10-19019 October 1987 Endorsement 28 to Nelia Policy NF-270 ML20098C8851984-08-24024 August 1984 Undated marked-up Transcript of Jj Stein Testimony Re Util Financial Qualifications to Design & Construct Nuclear Reactor ML20082K0471983-10-14014 October 1983 Show Cause Petition Requesting Revocation of CP & Denial of OL ML20082K0301983-10-13013 October 1983 Affidavit of Sandler in Support of Coalition for Safe Power 831014 Show Cause Petition ML20072N4411983-07-0808 July 1983 Notice of Appearance in Proceeding.Certificate of Svc Encl ML20072H2981983-03-25025 March 1983 Brief in Opposition to Coalition for Safe Power Appeal from ASLB 830222 Memorandum & Order Dismissing 820223 Petition to Intervene.Petitioner Failed to Particularize & Support Contentions.Certificate of Svc Encl ML20069D3441983-03-10010 March 1983 Brief Supporting Appeal from ASLB 830222 Memorandum & Order. ASLB Erred in Concluding Petitioner Failed to Show Dilatory Conduct by Util & Was Not Entitled to Hearing on CP Extension.Certificate of Svc Encl ML20069D2761983-03-10010 March 1983 Notice of Appeal of ASLB 830222 Memorandum & Order on Issue of Util Delay ML20070M6521983-01-24024 January 1983 Response in Opposition to Coalition for Safe Power 820223 Request for Hearing on Amend to CPPR-93.Petitioner Failed to Establish Interest in Proceeding or How Interest Will Be Affected by Proceeding.Certificate of Svc Encl ML20028C7851983-01-10010 January 1983 Suppl to Request for Hearing & Petition for Leave to Intervene,Listing Contentions.Certificate of Svc Encl ML20070J0401982-12-22022 December 1982 Response Supporting Coalition for Safe Power 821209 Motion for 1-wk Delay of Prehearing Conference Scheduled for 830119-20.Applicant Does Not Concede That Basis for Request Constitutes Good Cause.Certificate of Svc Encl ML20070D0001982-12-0909 December 1982 Motion for Delay of 830119 & 20 Prehearing Conference. Schedule Burdensome Due to Two Major Holiday Periods.Four Days of Preparation Lost.Certificate of Svc Encl ML20049J2331982-03-10010 March 1982 Answer Opposing Coalition for Safe Power 820223 Request for Hearing on CP Amend.Cp Amend Involves No Significant Hazards Consideration.Alternatively,Petitioner Failed to Meet Interest,Affects & Aspect Stds.Certificate of Svc Encl ML20049H5231982-02-22022 February 1982 Requests for Public Hearing Re Order Extending Const Completion Date.States Interest & Specific Aspects & Contentions Affecting Petitioners.Certificate of Svc Encl ML20009E3061981-07-23023 July 1981 Response Opposing Porter County Chapter Intervenors' 810519 Fourth Request for Production of Documents.Request Is W/O Merit & Should Be Denied ML20098D0881980-04-25025 April 1980 MOU Between WPPSS & Doe,Acting by & Through BPA Re Roles & Responsibilities Under Project Agreements Concerning Const & Operation of Net Billed Projects ML17272A8861980-02-0606 February 1980 Transcript of 800206 Briefing to NRC in Bethesda,Md Re Sacrificial Shield Wall,Pipe Whip Restraints & Related Structures.Pp 1A-122 ML19261C0571979-02-15015 February 1979 Util Opposes Petitioners Darby,Garrett & Hanford Conversion Project Addl Contention & Legal Argument.Intervention Petition Should Be Disposed of on Basis of Existing Record as Previously Stipulated.Certificate of Svc Encl ML19274D7801979-02-0606 February 1979 Applicant'S Proposed Corrections to Transcript of 790125 Prehearing Conference.Certificate of Svc Encl ML19263C4481979-02-0101 February 1979 Addl Contention & Legal Argument Pursuant to ASLB 790125 Permission.Contends Inadequate Assessment of Safety Risks. Certificate of Svc Encl ML17272A2691979-01-19019 January 1979 Applicant Answer in Opposition to Petitioners Darby Garrett & Hanford Conversion Project Request for Waiver of 10CFR2.708(b).W/encl Certificate of Svc ML19261A6791979-01-10010 January 1979 Second Amended Petition to Intervene,Supplementary Except Where Noted,To 781115 Petition.Addresses Contentions Re Need for Power,Alternatives.Notice of Withdrawal,Affidavit & Certificate of Svc Encl ML19261A6841979-01-10010 January 1979 Requests Waiver of double-spacing Requirement for Filed Documents Because of Added Expense.Assures That Documents Will Be Legible.W/Encl Certificate of Svc ML17272A2231978-12-15015 December 1978 Applicant'S Answer in Opposition to Amended Petition for Leave to Intervene Submitted by SM Garrett,H Vozenilek & Hanford Conversion Project.Asserts That Latter Has No Legal Interest in Proceedings.Certificate of Svc Encl ML20062G4631978-12-14014 December 1978 NRC Staff'S Response to Amended Petition to Intervene Submitted by SM Garrett,H Vozenilek & Manford Conversion Proj.Asserts That Only Manford Conversion Proj Has Met Interest Criteria of 10CFR2.714.Cert of Svc Encl ML20062E0581978-11-15015 November 1978 Amended Petition for Leave to Intervene. Indicates That Intervenors Have Evidence That Has Dev Since 1973 & Other Info Not Considered in the Constr Permit Proc Held in 1973. W/Encl 781107 Appl for Membership in Hanford ML20062E0601978-11-15015 November 1978 Memo in Support of Amended Petition for Leave to Intervene Presents Evidence Dev Since 1973 & Other Info Not Considered in Those Constr Permit Proc.Cert of Svc Plus Insert to Amended Petition for Leave to Intervene. Encl 1999-08-12
[Table view] Category:ORDERS
MONTHYEARML20134L3351997-02-14014 February 1997 Order Imposing Civil Monetary Penalty Re Licensee Activities Conducted from 960628-960904 ML20062C2721978-10-30030 October 1978 Prehearing Conference to Consider Petition Filed in Proceeding Re Subj Facil Will Be Held in Richland,Wa on 781121.Supersedes Order of 781011,setting Date for Hearing on 781115 ML20062B7961978-10-24024 October 1978 Order Establishing Prehearing Conference.Public Prehearing Conference Will Be Held on 781115 to Consider Petitions Filed in Proceeding.No Limited Appearance Statements Will Be Accepted ML20062A9881978-10-11011 October 1978 Order Establishing 781115 Prehearing Meeting to Discuss NRC Objections to License Application & State of Wa Petition to Intervene.Objections Relate to Failure to Establish Interest 1997-02-14
[Table view] |
Text
. . . . . . . . . _ . . . . . .. ..
=
? on.
4
-= r.-
s ~, .. DENT RCC6] $
, 47$ '
% h UNITED STATES OF AMERICA --
gt h - NUCLEAR REGULATORY COMMISSION
%* R'jp++ /0 Before the ' Atomic Safety and Licensing Board <
c In the Matter of ) ,o 7f WASHINGTON PUBLIC POWER SUPPLY )
SYSTEM ) Docket No. 50-397 OL (WPPSS Nuclear Project No. 2)
ORDER RELATIVE TO PETITION FOR LEAVE TO INTERVENE BY SUSAN M. GARRETT, HELEN VOZENILEK, AND HANFORD CONVERSION PROJECT (0 '
N.) The Nuclear Regulatory Commission (NRC) gave notice in l the Federal Register on July 26, 1978, of its receipt of an application for an operating license for WPPSS Nuclear Project No. 2. 43 F.R. 32338. On August 28, 1978, Susan M. Garrett and Helen Vozenilek, as individuals, and as representatives of the Hanford Conversion Project (HCP) submitted a timely petition to intervene. The petition was
- 'r not, served,
- as required, on either the NRC Staff or counsel
\(d for Applicant so that their timely responses were somewhat, delayed. Ms. Garrett and Ms. Vozenilek reside in Portland, Oregon. The members of HCP named in Attachment A living in closest proximity to the plant (Mr. Snow and Ms. Beadle) reside 50 miles or more from the site in Yakima, Washington.
1 78 /c190/60 g
.~ .. . . . . . . . . - . .
~s - i i
i r
i
~
[ The petitioners all proffer the same three bases for a finding of interest, as follows: (1) accidental release of radioactivity would adversely affect their lives and property l because of contamination transported via wind currents, river !
, I flow, and the food chain; (2) they would be affected as rate- i payers; and (3) their recreational use of the Columbia River ,
would be denied t,o them should there be accidental contamina-tion of the river. (
- The petition set forth proposed contentions relative to-I k (1) the lack of a cost / benefit analysis; (2) need for power; (3) permanent waste disposal; (4) transportation of radio-active materials, (5) security measures at the facility; and (6) normal radioactive releases.
The NRC Staff responded on September 18, 1978, but this document inadvertently was not served on petitioners until J
October 6, 1978. The Staff opposes "the petition at this time." The Staff pointed out that the two individual petitioners live over 150 air miles and 200 river miles from the site and members of HCP, with the exception of the two in Yakima, all reside more than 150 miles from the site.
t
[
l
.a . . : . :. : . . : 2. -- - : . . _ :.::. _.;__...- ._
s
~[ T5teStaffalsomentionedthattheallegedpostulatedinjury was not delineated with particularity. The Staff discounted the ratepayer status and mentioned the lack of authorization from members of HCP. The Staff pointed out the right of f petitioners to cure the noted defects up to 15 days before the special prehearing conference.
On September 22, 1978, the Applicant opposed the
,q
) petition on the bases of failure to establish interest, I failure to set forth a valid contention, and no evidence that petitioners' participation may reasonably be expected to assist i in developing a sound record.
By letter of September 27, 1978, the Energy Facility Site Evaluation Council of the State of Washington urged the Board to deny the petition. The State of Washington has ,
requested participation as an interested state under 10 CFR
$2.715(c) only in the event that a hearing is otherwise determined to be appropriate.
The Board will make arrangements for a prehearing con-ference to be held on November 15, 1978. The time and place will be the subject of a subsequent order. If petitioners
( ,
wish to file an amended petition to correct the deficiencies j l
I
. . l
.'s.,
~
= - which have been correctly identified by the Applicant and the Staff, it must be filed by November 1,1978, with service on Applicant and Staff as well as the Board and the Office of the Secretary.
IT IS SO ORDERED.
. F0k THE ATOMIC SAFETY AND LICENSING BOARD m sk 4tl2A=~
Elizabeth S. Bowers, Chairman Dated at Bethesda, Maryland This lith day of October 1978.