Annual Assessment Letter or Oconee Nuclear Station, Units 1, 2, and 3 - NRC Inspection Report 05000269/2019006, 05000270/2019006, and 05000287/2019006
ML20063L851
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 03/03/2020
From: Frank Ehrhardt
NRC/RGN-II/DRP/RPB1
To: Burchfield J
Duke Energy Corp
References
IR 2019006
Download: ML20063L851 (6)


Text

March 3, 2020

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR OCONEE NUCLEAR STATION UNITS 1, 2, AND 3 - NRC INSPECTION REPORT 05000269/2019006, 05000270/2019006, AND 05000287/2019006

Dear Mr. Burchfield:

The NRC completed its end-of-cycle performance review of the Oconee Nuclear Station Units 1, 2 and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2019, through December 31, 2019. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined that performance at Oconee Units 1, 2, and 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2021. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

Additionally, during this period the NRC will schedule an additional inspection per a revised version Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. Licensees will be individually notified when the NRC schedules these inspections.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4611 with any questions you have regarding this letter.

Sincerely,

/RA/

Frank Ehrhardt, Chief Reactor Project Branch 1 Division of Reactor Projects Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55 Enclosure: Oconee Inspection/Activity Plan (03/01/2020 - 12/31/2021)

cc distribution via ListServ

ML20063L851 OFFICE RII:DRP RII:DRP NAME J. Worosilo F. Ehrhardt DATE 02/28/2020 02/28/2020

IP 22 Inspection Activity Plan Report Oconee 03/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count SECURITY BASELINE INSPECTION 3 1, 2, 3 03/23/2020 03/27/2020 IP 71130.02 000734 Access Control 1, 2, 3 03/23/2020 03/27/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2, 3 03/23/2020 03/27/2020 IP 71130.07 000739 Security Training 1, 2, 3 03/23/2020 03/27/2020 IP 71130.09 001656 Security Plan Changes 1, 2, 3 03/23/2020 03/27/2020 IP 71151 001338 Performance Indicator Verification UNIT 3 IN-SERVICE INSPECTION 1 3 04/13/2020 04/17/2020 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

OCONEE INITIAL LICENSE EXAM 4 1, 2, 3 04/27/2020 05/01/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2, 3 06/01/2020 06/12/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

RP PUBLIC RAD SAFETY BASELINE INSPECTION 2 1, 2, 3 07/20/2020 07/24/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2, 3 07/20/2020 07/24/2020 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2, 3 07/20/2020 07/24/2020 IP 71151 000746 Performance Indicator Verification DESIGN BASES ASSURANCE INSPECTION (TEAMS) 6 1, 2, 3 08/03/2020 08/07/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

1, 2, 3 08/17/2020 08/21/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

EMERGENCY PREPAREDNESS EXERCISE 5 1, 2, 3 08/31/2020 09/04/2020 IP 71114.01 000716 Exercise Evaluation 1, 2, 3 08/31/2020 09/04/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2, 3 08/31/2020 09/04/2020 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - OCO 6 1, 2, 3 09/14/2020 09/18/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2, 3 10/05/2020 10/09/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing UNIT 1 IN-SERVICE INSPECTION +SG 2 1 10/19/2020 10/23/2020 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report Oconee 03/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count RP OCCUPATIONAL RAD SAFETY & TRANSPORTATION BASELINE INSPECTION 2 1, 2, 3 10/26/2020 10/30/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 10/26/2020 10/30/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2, 3 10/26/2020 10/30/2020 IP 71151 000746 Performance Indicator Verification OCONEE REQUAL INSPECTION 2 1, 2, 3 03/15/2021 03/19/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance SECURITY BASELINE INSPECTION 1 1, 2, 3 04/19/2021 04/23/2021 IP 71130.02 000734 Access Control 1, 2, 3 04/19/2021 04/23/2021 IP 71130.09 001656 Security Plan Changes 1, 2, 3 04/19/2021 04/23/2021 IP 71151 001338 Performance Indicator Verification OCONEE INITIAL LICENSE EXAM 3 1, 2, 3 05/03/2021 05/07/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2, 3 06/07/2021 06/18/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2, 3 07/12/2021 07/16/2021 IP 71111.07T 000700 Heat Sink Performance DESIGN BASES ASSURANCE INSPECTION (PROGRAMS) 3 1, 2, 3 08/02/2021 08/06/2021 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

1, 2, 3 08/16/2021 08/20/2021 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1, 2, 3 10/17/2021 10/30/2021 IP 71114.02 000717 Alert and Notification System Testing 1, 2, 3 10/17/2021 10/30/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2, 3 10/17/2021 10/30/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2, 3 10/17/2021 10/30/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2, 3 10/17/2021 10/30/2021 IP 71151 001397 Performance Indicator Verification UNIT 2 IN-SERVICE INSPECTION +SG 2 2 11/15/2021 11/19/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 3 1, 2, 3 11/15/2021 11/19/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report Oconee 03/01/2020 - 12/31/2021 Unit Start End Activity CAC Title Staff Count RP OCCUPATIONAL RAD SAFETY BASELINE INSPECTION 3 1, 2, 3 11/15/2021 11/19/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2, 3 11/15/2021 11/19/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 11/15/2021 11/19/2021 IP 71124.04 000728 Occupational Dose Assessment 1, 2, 3 11/15/2021 11/19/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2, 3 11/15/2021 11/19/2021 IP 71151 000746 Performance Indicator Verification 1, 2, 3 11/29/2021 12/03/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 11/29/2021 12/03/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2, 3 11/29/2021 12/03/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 11/29/2021 12/03/2021 IP 71124.04 000728 Occupational Dose Assessment 1, 2, 3 11/29/2021 12/03/2021 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2, 3 11/29/2021 12/03/2021 IP 71151 000746 Performance Indicator Verification This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.