Revised Application for Amend to License DPR-57,revising Tech Spec Page 3.7-26 to Assign Valve X-211A to Penetration X-210A & Withdrawing Request to Delete Valves E11-F027A & B from Table 3.7-4
ML20209D086
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 04/21/1987
From: Gucwa L
GEORGIA POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
Shared Package
ML20209D092 List:
References
A00L-870421, AL-870421, SL-2350, TAC-64785, NUDOCS 8704290174
Download: ML20209D086 (2)


Text

Georg'a Power Company 333 Piedmont Avenue Atlanta, Georg a 30308 Televone 404 526 6526 Mai!ang Address.

Ibst Office Box 4545 Allarta Georgia 30302 b

Georgia Power L T. Gucwa "' " " " ' " ^"' % M Manager Nuclear SWty and Licens ng SL-2350 1300C X7GJ17-H600 April 21, 1987 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Hashington, D.C. 20555 NRC DOCKET 50-321 OPERATING LICENSE DPR-57 PLANT HATCH UNIT 1 REQUEST TO REVISE TECHNICAL SPECIFICATIONS PRIMARY CONTAINMENT ISOLATION VALVES:

REVLSI0fLLO_P_REVIOULSWhi1IIAL Gentlemen:

Georgia Power Company's (GPC'O submittal of March 4, 1987 sought to revise Technical Specificat!cas (TS) providing primary containment isolation valve leak rate testing requirements for Plant Hatch Unit 1.

Based upon discussions with the NRC on April 2,1987, and April 6,1987, we now wish to revise the subject submittal as follows:

1. Proposed changed TS page 3.7-26, as provided in the subject submittal, assigned valve E11-F028A to penetration X-210A. The correct penetration for this valve should be X-211A. Proposed changed TS page 3.7-26a, as provided in the subject submittal, assigned valve E11-F028B to penetration X-2108. The correct penetration for this valve should be X-2118.
2. Valves E11-F027A and B were proposed to be deleted from the table. He understand that this request will not be acted upon at this time, but will be the subject of further review.

Revised TS pages 3.7-26 and 3.7-26a, incorporating the corrections noted in item I above, are hereby provided, with valves E11-F027A and B restored to the table for your convenience in preparation of the amendment for issuance.

3. Valves E11-F0118 and F0260 should be deleted from proposed TS page 3.7-26a. The basis for this proposed change was discussed in the March 4,1987, submittal; however, the actual change was not reflected on proposed TS page 3.7-26a. The enclosed revised page 3.7-26a correctly reflects the deletion of the subject valves U[)0 # $0t b O v

9

GeorgiaPower A U. S. Nuclear Regulatory Commission ATTN: Document Control Desk April 21, 1987 Page Two These changes are editorial in nature and do not impact the safety evaluation or determination of No Significant Hazards previously provided.

Should you have any questions or concerns, please contact this office at any time.

Sincerely, L. T. Gucwa JDH/lc

Enclosure:

Revised TS pages c: Georaia Power Comoany U.S. Nuclear Regulatory Commission Mr. J. P. O'Reilly Dr. J. N. Grace, Regional Administrator Mr. J. T. Beckham, Jr. Mr. P. Holmes-Ray, Senior Resident GO-NORMS Inspector - Hatch Mr. L. P. Crocker, Licensing Project Manager - Hatch l

l 1300C 700775