Letter Sequence Approval |
---|
EPID:L-2021-LLE-0007, Request for One-Time Exemption from Select 10 CFR 55.59 Requirements (Approved, Closed) |
|
|
|
---|
Category:Federal Register Notice
MONTHYEARML24284A2692024-10-28028 October 2024 FRN - Diablo Canyon Notice of Availability of Draft Supplemental Environmental Impact Statement ML24205A0672024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - FRN Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - (EPID L-2024-CRS-0000) - Federal Register Notice ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - ML24114A3102024-05-0303 May 2024 Monthly (28-Day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 14, 2024 ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24003A8892024-01-19019 January 2024 FRN - Diablo Canyon, Units 1 and 2, Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML23354A0362023-12-19019 December 2023 12.19.23 Respondents Second 28(j) Letter ML23341A0032023-12-14014 December 2023 LRA Acceptance and Opportunity for Hearing FRN ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR ML23320A1462023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - FRN ML23293A1062023-11-16016 November 2023 LRA - Receipt and Availability - FRN ML23291A1982023-11-0808 November 2023 Withdrawal of Amendment Request Regarding Alternative Security Measures for Early Warning System (EPID: L-2022-LLA-0029) (Federal Register Notice) ML23192A0232023-07-0303 July 2023 7-3-23 Petitioners Excerpts of Record Volume 2 (9th Cir.)(Case No. 23-852) ML23192A0252023-07-0303 July 2023 7-3-23 Petitioners Excerpts of Record Volume 3 (9th Cir.)(Case No. 23-852) ML23192A0212023-07-0303 July 2023 7-3-23 Petitioners Excerpts of Record Volume 1 (9th Cir.)(Case No. 23-852) ML22265A1022023-01-0505 January 2023 FRN - Diablo Canyon ISFSI Renewal Notice of Docketing and Opp for Hearing ML22053A2612022-06-17017 June 2022 FRN - Post-Shutdown Decommissioning Activities Report (PSDAR) Public Meeting (EPIDs L-2019-LRL-0004, L-2019-LRL-0005, and L-2019-LRL-0006) ML21091A0662021-04-23023 April 2021 FRN - Notice of Issuance of Multiple COVID-19 Exemptions Regarding Various Parts of 10 CFR Issued in March 2021 ML21068A3372021-04-0202 April 2021 Federal Register Notice, One-Time Exemption from Select Requirements of 10 CFR Part 55, Operators' Licenses ML20328A3022020-11-0303 November 2020 85 Fr 69620 - Federal Register Notice Dated 11/3/20 by Department of Energy Californians for Green Nuclear Power, Inc., Et Al (Diablo Canyon Nuclear Power Plant, Units 1 and 2 - Cgnp Public Comments on Pre-submittal Meeting of 11/24/2020) ML20271A0002020-10-13013 October 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for September 2020 ML20245E3952020-09-0303 September 2020 Transmittal Letter with Notice of Issuance, License Amendment; Issuance, Opportunity to Request a Hearing, and Petition for Leave to Intervene ML20245E3122020-09-0303 September 2020 Notice of Issuance, License Amendment; Issuance, Opportunity to Request a Hearing, and Petition for Leave to Intervene ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20072L8482020-03-12012 March 2020 FRN Notification of the Availability of the Post-Shutdown Decommissioning Activities Report in the Federal Register (EPID L-2019-LRL-0004)-Cancellation of Public Meeting ML20055E0632020-02-18018 February 2020 Pacific Gas and Electric Company - Diablo Canyon Power Plant, Unit Nos. 1 and 2 - Federal Register Notice ML20034E1482020-02-13013 February 2020 Letter, Notice of Receipt, Public Meeting and Request for Comment on Post-Shutdown Decommissioning Activities Report ML19163A1362019-09-12012 September 2019 FRN Exemptions from the Requirements of 10 CFR Sections 50.82(a)(8)(i)(A) and 50.82(a)(8)(ii) ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19136A1022019-08-12012 August 2019 Letter, Environmental Assessment and Finding of No Significant Impact Request for Exemptions from 10 CFR 50.82(a)(8)(ii) and 10 CFR 50.82 (a)(8)(i)(A), ML19136A0302019-08-12012 August 2019 FRN: Environmental Assessment and Finding of No Significant Impact Request for Exemptions from 10 CFR 50.82(a)(8)(ii) and 10 CFR 50.82 (a)(8)(i)(A) ML18151A9532018-06-0101 June 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact; Issuance ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18093A1172018-04-17017 April 2018 Request for Withdrawal FRN ML17108A5642017-05-12012 May 2017 OEDO-16-00436 - FRN, Final Director'S Decision - David Lochbaum, Union of Concerned Scientists, Letter 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 NRC-2016-0237, OEDO-16-00436 - FRN, Final Director'S Decision - David Lochbaum, Union of Concerned Scientists, Letter 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 (CAC Nos. MF8123 and MF8124)2017-05-12012 May 2017 OEDO-16-00436 - FRN, Final Director'S Decision - David Lochbaum, Union of Concerned Scientists, Letter 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 (CAC Nos. MF8123 and MF8124) NRC-2016-0151, FRN Re. Withdrawal of an Amendment Request (CAC Nos. MF7731 and MF7732)2017-04-24024 April 2017 FRN Re. Withdrawal of an Amendment Request (CAC Nos. MF7731 and MF7732) ML17100A2292017-04-24024 April 2017 Withdrawal of an Amendment Request ML17100A2302017-04-24024 April 2017 FRN Re. Withdrawal of an Amendment Request NRC-2016-0080, SRM-M150521A-2 - FRN Regarding Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 (CAC Nos. MF6443 and MF6444)2017-04-21021 April 2017 SRM-M150521A-2 - FRN Regarding Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 (CAC Nos. MF6443 and MF6444) ML17090A1902017-04-21021 April 2017 SRM-M150521A-2 - FRN Regarding Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML17095A9322017-04-21021 April 2017 Final Director'S Decision Under 10 CFR Sec. 2.206 Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML16285A2202016-11-0909 November 2016 OEDO-16-00436 - Letter, Acknowledgement to David Lochbaum, Union of Concerned Scientists, Petitioner, 2.206 Petition Related to Apparent 50.9 Violation at Diablo Canyon Nuclear Power Plant ML16285A2392016-11-0909 November 2016 OEDO-16-00436 - FRN, Acknowledgement to David Lochbaum, Union of Concerned Scientists, Petitioner, 2.206 Petition Related to Apparent 50.9 Violation at Diablo Canyon Nuclear Power Plant ML16218A4832016-08-17017 August 2016 FRN, Diablo Canyon Power Plant LRA - Issuance of Exemption from the Requirements of 10 CFR 54.21 ML16084A7172016-04-12012 April 2016 SRM-M150521A-2 - Acknowledgement Letter to Petitioner, Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML16084A7372016-04-12012 April 2016 SRM-M150521A-2 - Acknowledgement Federal Register Notice, Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 2024-08-27
[Table view] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-275 and 50-323; NRC-2021-0078]
Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant, Units 1 and 2 AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) has issued a one-time exemption in response to a February 4, 2021, request from Pacific Gas and Electric Company (the licensee) for an exemption from the operator requalification program requirements at Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Diablo Canyon), to minimize potential operator distractions during plant startup. The exemption affords a one-month extension of the 2-year program requalification and 1-year operator exam requirements, until June 30, 2021. The NRC staff made the required findings that the exemption is authorized by law, will not endanger life or property, and is otherwise in the public interest.
DATES: The exemption was issued on April 1, 2021.
ADDRESSES: Please refer to Docket ID NRC-2021-0078 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods:
e-mail: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. For the convenience of the reader, instructions about obtaining materials referenced in this document are provided in the Availability of Documents section.
- Attention: The PDR, where you may examine and order copies of public documents, is currently closed. You may submit your request to the PDR via e-mail at pdr.resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8:00 a.m. and 4:00 p.m. (ET), Monday through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: Samson Lee, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, telephone: 301-415-3168, e-mail: Samson.Lee@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction The NRC approved the one-time exemption from certain requirements of Part 55 of title 10 of the Code of Federal Regulations (10 CFR), Operators Licenses, for Diablo Canyon. This action was in response to the Pacific Gas and Electric Companys (the licensees) application dated February 4, 2021, which requested a one-time exemption for Diablo Canyon from the requirements of 10 CFR 55.59, Requalification, program to minimize potential operator distractions during plant startup. The exemption affords a one-month extension of the 2-year program requalification and 1-year operator exam
requirements, until June 30, 2021. The NRC staff made the findings required in 10 CFR 55.11, Specific exemptions, that the exemption is authorized by law, will not endanger life or property, and is otherwise in the public interest.
II. Availability of Documents The table in this notice provides the facility name, docket number, document description, and ADAMS accession number for the exemption issued. Additional details on the exemption issued, including the exemption request submitted by the licensee and the NRCs decision, are provided in the exemption approval listed in the table in this notice. For additional directions on accessing information in ADAMS, see the ADDRESSES section of this document.
Diablo Canyon Nuclear Power Plant, Units 1 and 2 Docket Nos. 50-275 and 50-323 DOCUMENT DESCRIPTION ADAMS ACCESSION NO.
Diablo Canyon Power Plant, Units 1 and 2, Request for One-Time Exemption from Select 10 CFR 55.59 ML21049A050 Requirements Diablo Canyon Nuclear Power Plant, Units 1 and 2 -
Exemption from Select Requirements of 10 CFR Part 55, ML21067A058 Operators Licenses (EPID L-2021-LLE-0007)
Dated: April 2, 2021.
For the Nuclear Regulatory Commission.
/RA/
Samson S. Lee, Senior Project Manager, Plant Licensing Branch IV, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.