MONTHYEARML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - ML24205A0672024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - FRN Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - (EPID L-2024-CRS-0000) - Federal Register Notice ML24114A3102024-05-0303 May 2024 Monthly (28-Day) Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 14, 2024 ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24003A8892024-01-19019 January 2024 FRN - Diablo Canyon, Units 1 and 2, Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML23354A0362023-12-19019 December 2023 12.19.23 Respondents Second 28(j) Letter ML23341A0032023-12-14014 December 2023 LRA Acceptance and Opportunity for Hearing FRN ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR ML23320A1462023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - FRN ML23293A1062023-11-16016 November 2023 LRA - Receipt and Availability - FRN ML23291A1982023-11-0808 November 2023 Withdrawal of Amendment Request Regarding Alternative Security Measures for Early Warning System (EPID: L-2022-LLA-0029) (Federal Register Notice) ML23192A0232023-07-0303 July 2023 7-3-23 Petitioners Excerpts of Record Volume 2 (9th Cir.)(Case No. 23-852) ML23192A0252023-07-0303 July 2023 7-3-23 Petitioners Excerpts of Record Volume 3 (9th Cir.)(Case No. 23-852) ML23192A0212023-07-0303 July 2023 7-3-23 Petitioners Excerpts of Record Volume 1 (9th Cir.)(Case No. 23-852) ML22265A1022023-01-0505 January 2023 FRN - Diablo Canyon ISFSI Renewal Notice of Docketing and Opp for Hearing ML22053A2612022-06-17017 June 2022 FRN - Post-Shutdown Decommissioning Activities Report (PSDAR) Public Meeting (EPIDs L-2019-LRL-0004, L-2019-LRL-0005, and L-2019-LRL-0006) ML21091A0662021-04-23023 April 2021 FRN - Notice of Issuance of Multiple COVID-19 Exemptions Regarding Various Parts of 10 CFR Issued in March 2021 ML21068A3372021-04-0202 April 2021 Federal Register Notice, One-Time Exemption from Select Requirements of 10 CFR Part 55, Operators' Licenses ML20328A3022020-11-0303 November 2020 85 Fr 69620 - Federal Register Notice Dated 11/3/20 by Department of Energy Californians for Green Nuclear Power, Inc., Et Al (Diablo Canyon Nuclear Power Plant, Units 1 and 2 - Cgnp Public Comments on Pre-submittal Meeting of 11/24/2020) ML20271A0002020-10-13013 October 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for September 2020 ML20245E3122020-09-0303 September 2020 Notice of Issuance, License Amendment; Issuance, Opportunity to Request a Hearing, and Petition for Leave to Intervene ML20245E3952020-09-0303 September 2020 Transmittal Letter with Notice of Issuance, License Amendment; Issuance, Opportunity to Request a Hearing, and Petition for Leave to Intervene ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20072L8482020-03-12012 March 2020 FRN Notification of the Availability of the Post-Shutdown Decommissioning Activities Report in the Federal Register (EPID L-2019-LRL-0004)-Cancellation of Public Meeting ML20055E0632020-02-18018 February 2020 Pacific Gas and Electric Company - Diablo Canyon Power Plant, Unit Nos. 1 and 2 - Federal Register Notice ML20034E1482020-02-13013 February 2020 Letter, Notice of Receipt, Public Meeting and Request for Comment on Post-Shutdown Decommissioning Activities Report ML19163A1362019-09-12012 September 2019 FRN Exemptions from the Requirements of 10 CFR Sections 50.82(a)(8)(i)(A) and 50.82(a)(8)(ii) ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19136A1022019-08-12012 August 2019 Letter, Environmental Assessment and Finding of No Significant Impact Request for Exemptions from 10 CFR 50.82(a)(8)(ii) and 10 CFR 50.82 (a)(8)(i)(A), ML19136A0302019-08-12012 August 2019 FRN: Environmental Assessment and Finding of No Significant Impact Request for Exemptions from 10 CFR 50.82(a)(8)(ii) and 10 CFR 50.82 (a)(8)(i)(A) ML18151A9532018-06-0101 June 2018 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact; Issuance NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18093A1172018-04-17017 April 2018 Request for Withdrawal FRN NRC-2016-0237, OEDO-16-00436 - FRN, Final Director'S Decision - David Lochbaum, Union of Concerned Scientists, Letter 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 (CAC Nos. MF8123 and MF8124)2017-05-12012 May 2017 OEDO-16-00436 - FRN, Final Director'S Decision - David Lochbaum, Union of Concerned Scientists, Letter 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 (CAC Nos. MF8123 and MF8124) ML17108A5642017-05-12012 May 2017 OEDO-16-00436 - FRN, Final Director'S Decision - David Lochbaum, Union of Concerned Scientists, Letter 10 CFR 2.206 Petition on Apparent Violation of 10 CFR 50.9 NRC-2016-0151, FRN Re. Withdrawal of an Amendment Request (CAC Nos. MF7731 and MF7732)2017-04-24024 April 2017 FRN Re. Withdrawal of an Amendment Request (CAC Nos. MF7731 and MF7732) ML17100A2292017-04-24024 April 2017 Withdrawal of an Amendment Request ML17100A2302017-04-24024 April 2017 FRN Re. Withdrawal of an Amendment Request NRC-2016-0080, SRM-M150521A-2 - FRN Regarding Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 (CAC Nos. MF6443 and MF6444)2017-04-21021 April 2017 SRM-M150521A-2 - FRN Regarding Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 (CAC Nos. MF6443 and MF6444) ML17090A1902017-04-21021 April 2017 SRM-M150521A-2 - FRN Regarding Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML17095A9322017-04-21021 April 2017 Final Director'S Decision Under 10 CFR Sec. 2.206 Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML16285A2202016-11-0909 November 2016 OEDO-16-00436 - Letter, Acknowledgement to David Lochbaum, Union of Concerned Scientists, Petitioner, 2.206 Petition Related to Apparent 50.9 Violation at Diablo Canyon Nuclear Power Plant ML16285A2392016-11-0909 November 2016 OEDO-16-00436 - FRN, Acknowledgement to David Lochbaum, Union of Concerned Scientists, Petitioner, 2.206 Petition Related to Apparent 50.9 Violation at Diablo Canyon Nuclear Power Plant ML16218A4832016-08-17017 August 2016 FRN, Diablo Canyon Power Plant LRA - Issuance of Exemption from the Requirements of 10 CFR 54.21 ML16084A7172016-04-12012 April 2016 SRM-M150521A-2 - Acknowledgement Letter to Petitioner, Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML16084A7372016-04-12012 April 2016 SRM-M150521A-2 - Acknowledgement Federal Register Notice, Friends of the Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 ML16004A1182016-01-0707 January 2016 FRN, Issuance of Confirmatory Orders, Authorize Use of Preemption Authority Granted Under Provisions of Section 161A of the Atomic Energy Act of 1954, as Amended 2024-08-27
[Table view] Category:Letter
MONTHYEARDCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application DCL-24-054, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 IR 05000275/20240012024-04-23023 April 2024 Integrated Inspection Report 05000275/2024001 and 05000323/2024001 ML24114A2032024-04-22022 April 2024 Request for Information for EP Program and Performance Indicator Verification Inspection (Wolf Creek Nuclear Generating Station) Inspection Report 05000482/2024003 ML24106A2882024-04-18018 April 2024 License Renewal Application Environmental Review RCIs and RAIs ML24106A2892024-04-18018 April 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of March 2024 Audit Regarding the Environmental Review of the License Renewal Application DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24108A1122024-04-15015 April 2024 License Amendment Request 24-02 Request for Approval of DCPP Early Warning System to Meet 10 CFR 73.55(i)(2) and 10 CFR 73.55(e)(9)(vi)(A) DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 12, 2019 Mr. James M. Welsch Vice President, Nuclear Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 -
ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RELATED TO EXEMPTION REQUESTS FOR USE OF NUCLEAR DECOMMISSIONING TRUST FUNDS FOR RADIOLOGICAL DECOMMISSIONING, SPENT FUEL MANAGEMENT, AND SITE RESTORATION PLANNING ACTIVITIES (EPID L-2018-LLE-0023)
Dear Mr. Welsch:
Enclosed is a copy of the final Environmental Assessment (EA) and Finding of No Significant Impact (FONSI) related to your exemption requests dated December 13, 2018, for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (Agencywide Documents Access and Management System Accession No. ML183478552). The proposed exemptions would exempt Pacific Gas and Electric Company from Title 10 of the Code of Federal Regulations (10 CFR) paragraph 50.82(a)(8)(i)(A) and 10 CFR 50.82(a)(8)(ii) for use of the Nuclear Decommissioning Trust to fund radiological decommissioning, spent fuel management, and site restoration planning activities.
The final EA and FONSI is being forwarded to the Office of the Federal Register for publication.
Sincerely, fz,_Q, .. t- t-&1'-~
Balwant K. Singal, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosure:
Final EA and FONSI cc: Listserv
ENCLOSURE FEDERAL REGISTER NOTICE
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-275 and 50-323; NRC-2019-0131]
Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant, Units 1 and 2 AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental assessment and finding of no significant impact; issuance.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of exemptions in response to a December 13, 2018, request from Pacific Gas and Electric Company (PG&E, the licensee) for Diablo Canyon Nuclear Power Plant (Diablo Canyon), Units 1 and 2. One exemption would allow the licensee to use an amount of funds from the Diablo Canyon Nuclear Decommissioning Trust (NOT) for decommissioning planning above the amount limitations specified in NRC's regulations.
Another exemption would allow the licensee to use withdrawals from the NOT to fund planning activities associated with spent fuel management and site restoration. The NRC staff is issuing a final environmental assessment (EA) and final finding of no significant impact (FONSI) associated with the proposed exemptions.
DATES: The EA and FONSI referenced in this document are available on [INSERT DATE OF PUBLICATION IN THE FEDERAL REGISTER].
ADDRESSES: Please refer to Docket ID NRC-2019-0131 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
Regulations.gov to Jennifer Borges; telephone: 301-287-9127; e-mail:
Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select "Begin Web-based ADAMS Search." For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room 01-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Balwant K. Singal, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-3016, e-mail: Balwant.Singal@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction The NRC is considering issuance of exemptions from sections 50.82(a)(8)(i)(A) and 50.82(a)(8)(ii) of title 10 of the Code of Federal Regulations (10 CFR) for Facility Operating License Nos. DPR-80 and DPR-82, issued to PG&E for operation of Diablo Canyon, Units 1 and 2, located in San Luis Obispo, California. The licensee requested the exemptions by letter dated December 13, 2018 (ADAMS Accession No. ML18347B552) pursuant to 10 CFR 50.12. In accordance with 10 CFR 51.21, the NRC 2
prepared the following EA that analyzed the environmental impacts of the proposed licensing action. Based on the results of this EA that follow, and in accordance with 10 CFR 51.31(a), the NRC has determined not to prepare an environmental impact statement for these exemption requests and is issuing a FONSI.
II. Environmental Assessment Description of the Proposed Action The proposed action would exempt PG&E from the requirements of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.82(a)(8)(ii). One exemption would allow the licensee to use an amount of funds from the Diablo Canyon NDT for decommissioning planning above the amount limitations specified in NRC regulations for operating reactors. Another exemption would allow the licensee to use withdrawals from the NDT for planning activities associated with spent fuel management and site restoration.
Overall, the proposed action would allow PG&E to withdraw $187.8 million ($2017) 1 from the Diablo Canyon NDT to fund radiological decommissioning, spent fuel management, and site restoration planning activities necessary prior to permanent cessation of operations of Diablo Canyon, Units 1 and 2, in 2024 and 2025, respectively. The proposed action is in accordance with the licensee's application dated December 13, 2018.
Need for the Proposed Action By letter dated November 27, 2018 (ADAMS Accession No. ML18331A553),
PG&E informed the NRC of its intention to permanently cease operation of Diablo Canyon, Units 1 and 2, on November 2, 2024, and August 26, 2025, respectively.
1 In its application, PG&E submitted the decommissioning costs in 2017 dollars to be consistent with presentation of a year-end asset balance in the NOT. If the NRC grants the exemptions, funds would be withdrawn from the NOT in nominal (current) dollars.
3
The requirements of 10 CFR 50.82(a)(8)(ii) restrict the use of NOT for decommissioning planning for operating reactors to three percent of the generic minimum decommissioning amount calculated, consistent with a formula set forth by the regulations at 10 CFR 50.75. Furthermore, as required by 10 CFR 50.82(a)(8)(i)(A),
decommissioning trust funds may be used by the licensee if the withdrawals are for legitimate decommissioning planning activities, consistent with the definition of decommissioning in 10 CFR 50.2. This definition addresses radiological decontamination and does not include activities associated with irradiated fuel management or site restoration activities. Therefore, these regulations would limit withdrawal from the Oiablo Canyon NOT to $37.2 million ($18.6 million per unit) and would allow spending only on planning activities for radiological decommissioning.
PG&E has estimated that a total of $187.8 million ($2017) would be required to be spent on pre-shutdown planning activities; $148.4 million would be for radiological decommissioning, and $39.4 million would be for spent fuel management and site restoration planning activities. The estimated $148.4 million amount is more than three percent of the generic minimum decommissioning amount calculated, consistent with a formula set forth by regulations at 10 CFR 50.75. Furthermore, withdrawals from the decommissioning trust fund cannot be used to fund the PG&E estimated $39.4 million for spent fuel management and site restoration planning activities absent (1) a clear indication that monies in the fund were collected for those purposes and are clearly and consistently accounted for separately,2 or (2) an exemption from the requirements of 10 CFR 50.82{a)(8)(i)(A) for use of funds for those purposes.
2 In 1999, some licensees reporting under 10 CFR 50.75(f) did not distinguish between estimates of costs to complete decommissioning required by the NRC (radiological decommissioning) and other costs associated with cleaning up the site. The NRC staff issued Regulatory Issue Summary 2001-07, Revision 1, "10 CFR 50.75 Reporting and Recordkeeping for Decommissioning Planning," to clarify for licensees the need to preserve the distinction between radiological decommissioning cost estimates and all other decommissioning cost estimates in the reports licensees must submit in accordance with 10 CFR 50.75.
4
Therefore, pursuant to 10 CFR 50.12, PG&E requests exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.82(a)(8)(ii) to allow withdrawal of a total of
$187.8 million ($2017) from the Diablo Canyon NDT to fund radiological decommissioning, spent fuel management, and site restoration planning activities prior to permanent cessation of operations of Diablo Canyon, Units 1 and 2, in 2024 and 2025, respectively, to support direct transition to decommissioning upon permanent cessation of operations.
Environmental Impacts of the Proposed Action The proposed action involves exemptions from the requirements related to use of the NDT that are of a financial nature and allow PG&E to pay for decommissioning planning activities necessary to support direct transition to physical decommissioning upon permanent shutdown of Diablo Canyon, Units 1 and 2. The proposed action also allows PG&E to use these funds to support planning for spent fuel management and site restoration activities.
The NRC has completed its evaluation and concludes that there is reasonable assurance that adequate funds are available in the NDT to complete all activities associated with radiological decommissioning. There is no decrease in safety associated with the NDT being used to fund planning activities associated with radiological decommissioning, spent fuel management, and site restoration. As required by 10 CFR 50. 75, PG&E has submitted a Decommissioning Funding Report for Diablo Canyon by letter dated March 26, 2019 (ADAMS Accession No. ML190948780), which includes a site-specific decommissioning cost estimate for Diablo Canyon, Units 1 and 2.
The regulations at 10 CFR 50.75 require, in part, that the report include the amount of decommissioning funds accumulated, modifications occurring to a licensee's current method of providing financial assurance since the last submitted report, and 5
plans to adjust levels of funds assured for decommissioning to demonstrate that a reasonable level of assurance will be provided that funds will be available when needed to cover the cost of decommissioning. A licensee for a plant that is within five years of its projected end of operation is required to submit this report annually.
The proposed action will not significantly increase the probability or consequences of radiological accidents. Additionally, the NRC staff has concluded that the proposed changes would have no direct radiological environmental impacts. There are no changes in the types or amounts of effluents that are, or may be, released offsite resulting from these exemptions. PG&E must continue to comply with all appropriate NRC regulations related to occupational and public radiation exposure, and thus, the exemptions will not result in an increase to occupational or public doses.
With regard to the potential nonradiological environmental impacts, the proposed action would have no direct impacts on land use or water resources, including terrestrial and aquatic biota, as it involves no new land disturbing activities, new construction or modification of plant operational systems. There would be no changes to the quality or quantity of nonradiological effluents, and no changes to the plant's National Pollutant Discharge Elimination System permits would be needed. In addition, there would be no noticeable effect on socioeconomic conditions in the region, no environmental justice impacts, no air quality impacts, and no impacts to historic and cultural resources from the proposed changes. Therefore, there are no significant nonradiological environmental impacts associated with the proposed action.
Accordingly, the NRC concludes that there will be no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action As an alternative to the proposed action, the NRC staff considered denial of the 6
proposed action (i.e., the "no-action" alternative). Denial of these exemption requests would result in no change in current environmental impacts. Therefore, the environmental impacts of the proposed action and alternative action are similar.
Alternative Use of Resources There are no unresolved conflicts concerning alternative uses of available resources under the proposed action.
Agencies and Persons Consulted On June 6, 2019, the NRC notified the State of California of this EA and FONSI.
No additional agencies or persons were consulted regarding the environmental impact of the proposed action.
Ill. Finding of No Significant Impact The proposed action would exempt PG&E from the requirements of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.82(a)(8)(ii) to allow PG&E to withdraw $187.8 million ($2017) from the Diablo Canyon NOT to fund radiological decommissioning, spent fuel management, and site restoration planning activities. The proposed action would not significantly affect plant safety, would not have a significant adverse effect on the probability of an accident occurring, and would not have any significant radiological or non-radiological impacts. The reason the human environment would not be significantly affected is that the proposed action involves an exemption from requirements that are of a financial nature that do not have an impact on the human environment.
7
The related environmental document is the Diablo Canyon Final Environmental Statement dated May 1973 (ADAMS Accession No. ML15043A481 ), 3 which provides the latest environmental review of operations of Diablo Canyon, Units 1 and 2.
Consistent with 10 CFR 51.21, the NRC conducted the EA for the proposed action, which concluded that there will be no significant environmental impacts associated with the proposed action. This FONSI incorporates by reference the EA included in Section II of this document. Accordingly, the NRC has decided not to prepare an environmental impact statement for the proposed action.
The finding and other related environmental documents may be examined, and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. Publicly available records are accessible electronically from ADAMS Public Electronic Reading Room on the internet at the NRC's website: https://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC's PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 121h day of August, 2019.
For the Nuclear Regulatory Commission.
IRA/
Balwant K. Singal, Senior Project Manager, Plant Licensing Branch IV, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
3 Final Environmental Statement Related to the Nuclear Generating Station Diablo Canyon, Units 1 and 2, Pacific Gas and Electric Company, Docket Nos. 50-275 and 50-323, May 1973.
8
Letter: ML19136A102 EA FRN: ML19136A030 *via email OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DLP/PFPB/BC* NRR/DMLR/MENB/BC NAME BSingal PBlechman FMiller(A) KErwin(A)
DATE 5/21/19 6/04/19 5/29/19 5/29/19*
OFFICE OGG* NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM NAME AGhosh RPascarelli BSingal DATE 8/01/19 8/09/19 8/12/19