MONTHYEARML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility ML23137A1782023-05-22022 May 2023 Correction to Issuance of Amendment to Relocate Selected Surveillance Frequencies to a Risk-Informed Licensee Controlled Program ML23072A0892023-05-0101 May 2023 (Amendments 346 & 286), North Anna 1 & 2 (Amnds 294 & 277), Surry 1 & 2 (Amnds 311 & 311), and Summer 1 (Amd 225) - Issuance of Amendments to Revise TSs to Adopt TSTF-554 Revise Reactor Coolant Leakage Requirements ML23012A0152023-02-21021 February 2023 Issuance of Amendment No. 224 to Change Nozzle Blockage Testing Requirement for Reactor Building Spray System ML22341A1972022-12-15015 December 2022 Extension of Steam Generator Primary Inlet Nozzle Dissimilar Metal Weld Inspection Interval ML22244A1722022-09-22022 September 2022 Issuance of Amendment No. 223 to Relocate Main Steam Isolation Valve Isolation Times to the Updated Final Safety Analysis Report ML22242A1632022-08-31031 August 2022 Correction to Issuance of Amendment to Relocate Selected Surveillance Frequencies to a Risk-Informed Licensee Controlled Program ML22160A3652022-08-16016 August 2022 Issuance of Amendment No. 222 to Relocate Selected Surveillance Frequencies to a Risk-Informed Licensee Controlled Program ML22041A0102022-03-0101 March 2022 V.C. Summer 1, Issuance of Amendment Nos. 283 (Millstone), 291 and 274 (North Anna), and 221 (Summer) to Revise TSs to Adopt TSTF-569 Revision of Response Time Testing Definition ML21319A2622021-12-28028 December 2021 Issuance of Amendment No. 220 to Relocate Unit Staff Qualifications from Technical Specification to Quality Assurance Program Description ML21112A1082021-06-30030 June 2021 Issuance of Amendment No. 219 to Modify Technical Specification 6.9.1.11, Core Operating Limits Report ML19276D3772019-12-11011 December 2019 Issuance of Amendment Revise Company Name to Dominion Energy South Carolina, Inc. ML19080A1032019-04-30030 April 2019 Issuance of Amendment No. 215 Technical Specification 3.8.2, D.C. Sources - Operating ML19074A2222019-04-10010 April 2019 Issuance of Amendment No. 214 Removes the Expired One-Time Extension to Surveillance Requirement 4.3.3.6 and Removes the Index from Technical Specifications ML19023A4202019-03-0707 March 2019 Issuance of Amendment Reactor Coolant System Operational Leakage Technical Specification Surveillance Requirement 4.4.6.2.2 ML19056A4062018-11-30030 November 2018 Virgil C. Summer Nuclear Station NPDES Permit No. SC0030856 Renewal Application, Thermal Mixing Zone Evaluation 2018 Water Quality Monitoring Report ML18253A1152018-10-0505 October 2018 Issuance of Amendment No. 212 Technical Specification Change Request for the Revision of the Surveillance Frequency of the Turbine Trip Functional Unit ML18260A0272018-09-25025 September 2018 Issuance of Exigent Amendment One Time Extension to the Surveillance Frequency 4.3.3.6 of the Core Exit Temperature Instrumentation ML18141A6682018-06-28028 June 2018 Issuance of Amendment No. 210, Revise Technical Specification 6.8.4.g for Integrated Leak Rate Test Peak Calculated Containment Internal Pressure Change ML18157A2122018-06-0707 June 2018 Correction to Amendment No. 199 to Correct an Administrative Error ML18108A1632018-04-20020 April 2018 Correction to Amendments Nos. 79 and 202, to Correct Typographical Errors ML18033A8442018-02-27027 February 2018 Correction to Amendment No. 170 to Correct a Typographical Error ML17206A4122017-10-0404 October 2017 Issuance of Amendment TSTF-411, Revision 1, Surveillance Test Interval Extensions for Components of the Reactor Protection System (WCAP-15376-P-A). ML17011A0502017-03-0909 March 2017 Issuance of Amendment to Revise Completion Date of Implementation Milestone 8 of the Cyber Security Plan ML16348A2002017-01-18018 January 2017 Issuance of Amendment to Revise Technical Specification 3.5.4 Limiting Condition for Operation Refueling Water Storage Tank ML16264A4112016-10-26026 October 2016 Issuance of Amendment to Revise Technical Specification 3/4.7.1.2, Emergency Feedwater System ML15231A6052016-05-16016 May 2016 Issuance of Amendment to Change Licensing Basis to Incorporate a Supplemental Analysis to the Steam Generator Tube Rupture Accident ML16104A2952016-05-0606 May 2016 Issuance of Amendment to Adopt TSTF-523, Revision 2 RC-16-0043, License Amendment Request Technical Specification 3/4.7.1.2, Emergency Feedwater System.2016-04-0707 April 2016 License Amendment Request Technical Specification 3/4.7.1.2, Emergency Feedwater System. ML16063A0902016-03-0909 March 2016 Issuance of Exigent Amendment Regarding Technical Specification 3.7.1.2 RC-16-0035, (VCSNS) Unit 1 - Exigent License Amendment Request - LAR (16-00848) Technical Specification Change Request for the Emergency Feedwater System Limiting Condition for Operation 3.7.1.2 Action B2016-03-0101 March 2016 (VCSNS) Unit 1 - Exigent License Amendment Request - LAR (16-00848) Technical Specification Change Request for the Emergency Feedwater System Limiting Condition for Operation 3.7.1.2 Action B ML15208A0292015-10-15015 October 2015 Issuance of Amendment ML15170A0872015-08-18018 August 2015 Issuance of Amendment to Revise the Radiation Emergency Plan ML15063A3552015-04-13013 April 2015 Issuance of Amendment to Revise Emergency Action Levels to a Scheme Based on NEI 99-01, Revision 6 ML14287A2892015-02-11011 February 2015 Issuance of Amendment Regarding Transition to a Risk-Informed, Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c) ML14122A3092014-05-29029 May 2014 Issuance of Amendment 198 Regarding the Cyber Security Plan Implementation Schedule Milestone 8 ML14030A3742014-03-11011 March 2014 Issuance of Amendment for Technical Specification Change Related to Control Room Emergency Filtration System ML14010A1822014-02-28028 February 2014 Issuance of Amendment to Revise Technical Specifications to Adopt TSTF-510 ML13354B6432014-02-0606 February 2014 Issuance of Amendment for the Technical Specification Change Related to Snubber Surveillance Requirements ML13326A2042014-02-0505 February 2014 Issuance of Amendment Extending Integrated Leak Rate Test Interval ML12292A0562012-12-21021 December 2012 Issuance of Amendment Regarding Deviation of Scope of the Cyber Security Plan Implementation and Facility Operating Condition 2.E ML12270A3012012-10-12012 October 2012 Issuance of Amendment ML12184A1352012-07-0909 July 2012 Issuance of Amendment ML12146A0172012-05-30030 May 2012 Issuance of Amendment on Beacon Core Monitoring and Operations Support System ML12121A0342012-05-0101 May 2012 Issuance of Amendment Extending Integrated Leak Rate Test ML11346A0062012-03-20020 March 2012 Issuance of Amendment Regarding Quality Assurance Program ML12047A1922012-03-0606 March 2012 Issuance of Amendment No. 187 Regarding Surveillance Frequency of Solids State Protection Westinghouse Type AR Relays 18 Months ML11326A2502012-02-22022 February 2012 Issuance of Amendment Regarding Reactor Coolant System Leakage Detection Systems ML11201A3122011-08-24024 August 2011 Issuance of Amendment 184 Regarding Cyber Security Plan 2024-08-05
[Table view] |
Text
0 0 V.C. SUMMER NUCLEAR STATION NRC JOB PERFORMANCE MEASURE JPS-010 Respond to Trip of a Main Feedwater Pump (NRC)
Revision No. I
\77)
0 PAGE 0 Respond to Trip of a Main Feedwater Pump (NRC) II 11 II Iiti TRAINEE EVALUATOR II II ii I EVALUATOR SIGNATURE DATE II II II II EVALUATION METHOD: PERFORM II II EVALUATION LOCATION: SIMULATOR II II II ESTIMATED TIME: 15.0 MINUTES TIME STARTED: II I 10CFR55.45(a)3 IDENTIFY ANNUNCIATORS AND II CONDITION-INDICATING SIGNALS AND PERFORM II APPROPRIATE REMEDIAL ACTIONS WHERE II II APPROPRIATE II II II TIME CRITICAL: No FAULTED JPM: No II II TRAINEE PERFORMANCE: SATISFACTORY UNSATISFACTORY II II II II II I
iiII READ TO OPERATOR:
WHEN I TELL YOU TO BEGIN, YOU ARE TO PERFORM THE ACTIONS AS DIRECTED IN THE II II II ii INITIATING CUES. I WILL DESCRIBE GENERAL CONDITIONS UNDER WHICH THIS TASK II II IS TO BE PERFORMED AND PROVIDE THE NECESSARY TOOLS WITH WHICH TO PERFORM THIS I' II TASK. BEFORE STARTING, I WILL EXPLAIN THE INITIAL CONDITIONS, WHICH STEPS II ii TO SIMULATE OR DISCUSS, AND PROVIDE INITIATING CUES. Ii I' WHEN YOU COMPLETE THE TASK SUCCESSFULLY, THE OBJECTIVE FOR THIS II III. JOB PERFORMANCE MEASURE WILL BE SATISFIED.
INITIAL CONDITIONS:
- 1. Plant is operating at 100% power with all controls in automatic.
TOOLS AND EQUIPMENT NEEDED:
NONE REFERENCED DOCUMENTS: REV DATE AOP*210.3 FEEDWATER PUMP MALFUNCTION 05/l4/96 1.
FEEDWATER SYSTEM 10/10/97
- 2. SOP*210
PAGE 1 Ir i J[ Respond to Trip of a Main Feedwater Pump (NRC)
TASK STANDARDS:
- 1. Plant is stabilized at programmed S/G level (55-65%) with feed flow and steam flow matched.
- 2. 'B' MFP placed in service with speed control in AUTO.
- 3. Plant does not trip due to S/G level problems.
INITIATING CUES:
- 1. Respond to secondary events as BOP operator.
TERMINATING CUES:
- 1. 'B' MFP speed control in AUTO.
SAFETY CONSIDERATIONS:
- 1. NONE
(*) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
STEP STANDARD
- 1. Verifies Feedwater Pump trip. Acknowledges FWP A/B/C TRIP annunciator.
Determines 'B' MWP tripped from TRIP indication on pump reset switch.
STEP STANDARD
- 2. Checks operating FW pump speed Verifies operating pump speed increasing cnntrol- or full demand on master speed controller jNOTE 3: Examiner (as CRS) directs operator to reduce load to 90% after student I determines power must be reduced to 86%-91%. To expedite the JPM, the I examiner may direct the operator to increase power decrease to I 3%/minute once a 1%/minute rate is established.
STEP STANDARD
- 3. Reduces load to 90%. Reduces turbine load using DECREASE on LOAD SELECTOR at l%/minute. Reactor power indicates - 90% and/or GEN GROSS MW (on IPCS) indicates - 900 MW.
COMMENTS:
iNOTE 4: As TBAO, cue operator that HP and LP stop vlvs. for "B" FWP turbine are closed.
STEP STANDARD 4 Verifies "B" HP and LP stop Directs TBAO to check stop valves valves closed.
STEP STANDARD
- 5. Verifies turning gear TURN GEAR indication for 'B' MFP engagement. indicates red light ON.
JOB PERFORMANCE MEASURE CHECKLIST PAGE 3 (S) DENOTES SEQUENCED ELEMENT
(*) DENOTES CRITICAL ELEMENT SAT. UNSAT.
PERFORMANCE CHECKLIST:
INOTE 6: A. Simulator operator (as TBO) informs operator that MFP "B" turbine I trip was due to janitor cleaning B. CRS directs BOP to place tripped MFP EAP controller in MANUAL with 0% demand and restart the tripped MFP. C. Examiner directs operator to simulate MFP trip test and continue with MIP startup (for the sake of time).
STEP STANDARD S-6. Resets MFP turbine. Momentarily places 'B' MFP TRIP/RESET switch to RESET. Green TRIP light OFF, amber RESET light ON "FWP A/B/C TRIP" annunciator clears.
COMMENTS:
STEP STANDARD S*7. Raises 'B' MFW speed. Places Pump B SPEED CHNG in the SLOW RAISE position until Pump B RPM (SI-3348) no longer increases COMMENTS:
STEP STANDARD Shifts speed control to the Places Pump B SPEED CHNG in the FAST S*8.
EAP. RAISE position until 'B' MFP high speed stop is reached indicated by red light ON
9 JOB PERFORMANCE MEASURE CHECKLIST 0 PAGE 4 (S) DENOTES SEQUENCED ELEMENT
(*) DENOTES CRITICAL ELEMENT PERFORMANCE CHECKLIST: SAT. UNSAT.
COMMENTS:
STEP STANDARD
- 9. Place 'B' MFP in service Balances FW flows and places Pump B SPEED CNTRL in AUTO per SOP-210, step III.D 2.6.
STEP STANDARD
- 10. Close MFPT steam drains MOV-l-5B, TURB DRN VLV indicates green light ON, red light OFF.
STEP STANDARD AUX VLV PP (for B) indicates green light
- 11. Stop aux oil pump ON, red light OFF Examiner Stops JPM At This Point TIME STOPPED
S:
0 PAGE 5 11 Respond to Trip of a Main Feedwater Pump (NRC) II II NRC KA
REFERENCES:
KA NUMBER IMPORTANCE FACTOR RO SRO 000054.EA2.02 Ability to determine the 4.1 4.4 difference between a loss of all MFW and a trip of one MFW pump.