(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
|
---|
Category:Morning Report
MONTHYEARML0805605022008-02-25025 February 2008 Morning Report MR 3-2008-0006 - Management Changes for Firstenergy Nuclear Operating Company ML0805100062008-02-19019 February 2008 Changes in Perry/ Davis Besse Senior Management ML0802307042008-01-23023 January 2008 Morning Report MR 3-2008-0002: Firstenergy Nuclear Operating Co. (FENOC) Names Paul Harden Vice President of Nuclear Support ML0630703062006-11-0303 November 2006 Changes in Perry / Davis-Besse Senior Management ML0517504572005-06-24024 June 2005 Morning Report 3-2005-0013 - Firstenergy Management Changes ML0420902982004-07-27027 July 2004 Firstenergy Names Executive Vice-President and Chief Operating Officer ML0418402452004-07-0202 July 2004 Unplanned Onsite Release of Small Quantity of Gaseous Radioactive Effluent ML0417705752004-06-25025 June 2004 Firstenergy Nuclear Operating Company (FENOC) Announces Management Changes ML0409903062004-04-0808 April 2004 Synchronized to Grid ML0409703332004-04-0606 April 2004 Synchronized to Grid ML0409605012004-04-0505 April 2004 Syncronized to Grid ML0408906362004-03-29029 March 2004 Morning Report MR 3-2004-0025: Davis-Besse Synchronized to Grid ML0408602412004-03-26026 March 2004 Morning Report 3-2004-0024: Davis-Besse Reactor Plant Is Critical ML0408502882004-03-25025 March 2004 Morning Report 3-2004-0023: Davis-Besse Plant Status ML0407902272004-03-19019 March 2004 Status ML0407802252004-03-18018 March 2004 Morning Report MR 3-2004-0021, Davis-Besse Plant Status. ML0407604472004-03-16016 March 2004 Status ML0407502882004-03-15015 March 2004 Status, Morning Report ML0407202682004-03-12012 March 2004 Status ML0407103622004-03-11011 March 2004 Status ML0407004292004-03-10010 March 2004 Status ML0406903002004-03-0909 March 2004 Morning Report 3-2004-0015: Plant Status Update and Restart Approval ML0402105142004-01-21021 January 2004 Firstenergy Announces Management Changes ML0327310182003-09-30030 September 2003 Management Change ML0326001702003-09-17017 September 2003 Plan Heat-Up for Reactor Coolant System Pressure Test Suspended Because of Emergent Issues ML0325501722003-09-12012 September 2003 Entry Into Mode 4 and Mode 3 2008-02-25
[Table view] |
Text
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III March 12, 2004 Licensee/Facility: Notification:
FIRSTENERGY NUCLEAR OPERATING CO.
Davis-besse MR Number: 3-2004-0018 Akron, Ohio Date: 03/12/2004 Dockets: 050-00346 RIII-Via Teleconf. with Site
[1] B&W-L-LP License No:
Subject:
Davis-Besse Plant Status Discussion:
This information is current as of 7:30 am (EST) on March 12, 2004. The plant is currently in Mode 2. The plant entered Mode 2 on March 11, 2004, at 10:40 a.m. and the reactor became critical on March 11, 2004, at 1:42 p.m.
Upcoming key events include entering Mode 1, performing a readiness and effectiveness review prior to initial grid synchronization, initial grid synchronization, performing a readiness and effectiveness review prior to exceeding 50%
power, placing a second main feedwater pump in service, reaching 100% power. Absent significant performance or equipment problems these events are scheduled to be accomplished in the next five to seven days.
Ongoing resident inspector coverage and around-the-clock inspection and oversight of licensee activities continues with NRC resident inspectors or examiners from Region III and other Regions. This coverage is expected to be in place for approximately two weeks.
Regional Action: For Information Only
Contact:
Org: Phone No: Email:
LIPA, C A R3 (630) 829-9619 CAL@nrc.gov