MONTHYEARML0805605022008-02-25025 February 2008 Morning Report MR 3-2008-0006 - Management Changes for Firstenergy Nuclear Operating Company ML0805100062008-02-19019 February 2008 Changes in Perry/ Davis Besse Senior Management ML0802307042008-01-23023 January 2008 Morning Report MR 3-2008-0002: Firstenergy Nuclear Operating Co. (FENOC) Names Paul Harden Vice President of Nuclear Support ML0630703062006-11-0303 November 2006 Changes in Perry / Davis-Besse Senior Management ML0517504572005-06-24024 June 2005 Morning Report 3-2005-0013 - Firstenergy Management Changes ML0420902982004-07-27027 July 2004 Firstenergy Names Executive Vice-President and Chief Operating Officer ML0418402452004-07-0202 July 2004 Unplanned Onsite Release of Small Quantity of Gaseous Radioactive Effluent ML0417705752004-06-25025 June 2004 Firstenergy Nuclear Operating Company (FENOC) Announces Management Changes ML0409903062004-04-0808 April 2004 Synchronized to Grid ML0409703332004-04-0606 April 2004 Synchronized to Grid ML0409605012004-04-0505 April 2004 Syncronized to Grid ML0408906362004-03-29029 March 2004 Morning Report MR 3-2004-0025: Davis-Besse Synchronized to Grid ML0408602412004-03-26026 March 2004 Morning Report 3-2004-0024: Davis-Besse Reactor Plant Is Critical ML0408502882004-03-25025 March 2004 Morning Report 3-2004-0023: Davis-Besse Plant Status ML0407902272004-03-19019 March 2004 Status ML0407802252004-03-18018 March 2004 Morning Report MR 3-2004-0021, Davis-Besse Plant Status. ML0407604472004-03-16016 March 2004 Status ML0407502882004-03-15015 March 2004 Status, Morning Report ML0407202682004-03-12012 March 2004 Status ML0407103622004-03-11011 March 2004 Status ML0407004292004-03-10010 March 2004 Status ML0406903002004-03-0909 March 2004 Morning Report 3-2004-0015: Plant Status Update and Restart Approval ML0402105142004-01-21021 January 2004 Firstenergy Announces Management Changes ML0327310182003-09-30030 September 2003 Management Change ML0326001702003-09-17017 September 2003 Plan Heat-Up for Reactor Coolant System Pressure Test Suspended Because of Emergent Issues ML0325501722003-09-12012 September 2003 Entry Into Mode 4 and Mode 3 2008-02-25
[Table view] |
Text
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III Morning Report Date: APR 06, 2004 Licensee/Facility: Notification:
FIRSTENERGY NUCLEAR OPERATING CO. MR Number: 3-2004-0027 Davis-besse Date: 04/06/2004 Oak Harbor, Ohio RIII- Via Teleconf. with Site Dockets: 050-00346
[1] B&W-L-LP
Subject:
Davis-Besse Synchronized to Grid Discussion:
This information is current as of 10:00 a.m. (EDT) on April 6, 2004. The plant is currently in Mode 1 at 100% percent power. The plant performed a down-power evolution April 5 to establish plant conditions to support de-energizing the D2 non-essential 4.16 kV switchgear bus and replacement of a faulty feeder breaker to the D2 bus. The feeder breaker was identified as faulty when, during a routine breaker swap preventive maintenance evolution, the breaker failed to open using the remote control switch. Following the down-power evolution, the D2 bus was de-energized, and the breaker was removed from the enclosure. The D2 bus was re-energized via the normal alternate power source, and the plant returned to 100% power. The replacement breaker will be installed following completion of trouble-shooting efforts on the faulty breaker. Around-the-clock resident inspector coverage was utilized to monitor plant evolutions and maintenance activities.
The Davis-Besse Oversight Panel will continue to monitor plant activities utilizing enhanced inspection oversight coverage. For non-routine evolutions occurring after normal working hours, enhanced inspection oversight coverage will continue to be expanded to monitor these activities.
Regional Action: For Information Only
Contact: