Morning Report 3-2004-0024: Davis-Besse Reactor Plant Is CriticalML040860241 |
Person / Time |
---|
Site: |
Davis Besse ![Cleveland Electric icon.png](/w/images/7/78/Cleveland_Electric_icon.png) |
---|
Issue date: |
03/26/2004 |
---|
From: |
NRC/RGN-III |
---|
To: |
|
---|
References |
---|
MR 3-2004-0024 |
Download: ML040860241 (1) |
|
|
---|
Category:Morning Report
MONTHYEARML0805605022008-02-25025 February 2008 Morning Report MR 3-2008-0006 - Management Changes for Firstenergy Nuclear Operating Company ML0805100062008-02-19019 February 2008 Changes in Perry/ Davis Besse Senior Management ML0802307042008-01-23023 January 2008 Morning Report MR 3-2008-0002: Firstenergy Nuclear Operating Co. (FENOC) Names Paul Harden Vice President of Nuclear Support ML0630703062006-11-0303 November 2006 Changes in Perry / Davis-Besse Senior Management ML0517504572005-06-24024 June 2005 Morning Report 3-2005-0013 - Firstenergy Management Changes ML0420902982004-07-27027 July 2004 Firstenergy Names Executive Vice-President and Chief Operating Officer ML0418402452004-07-0202 July 2004 Unplanned Onsite Release of Small Quantity of Gaseous Radioactive Effluent ML0417705752004-06-25025 June 2004 Firstenergy Nuclear Operating Company (FENOC) Announces Management Changes ML0409903062004-04-0808 April 2004 Synchronized to Grid ML0409703332004-04-0606 April 2004 Synchronized to Grid ML0409605012004-04-0505 April 2004 Syncronized to Grid ML0408906362004-03-29029 March 2004 Morning Report MR 3-2004-0025: Davis-Besse Synchronized to Grid ML0408602412004-03-26026 March 2004 Morning Report 3-2004-0024: Davis-Besse Reactor Plant Is Critical ML0408502882004-03-25025 March 2004 Morning Report 3-2004-0023: Davis-Besse Plant Status ML0407902272004-03-19019 March 2004 Status ML0407802252004-03-18018 March 2004 Morning Report MR 3-2004-0021, Davis-Besse Plant Status. ML0407604472004-03-16016 March 2004 Status ML0407502882004-03-15015 March 2004 Status, Morning Report ML0407202682004-03-12012 March 2004 Status ML0407103622004-03-11011 March 2004 Status ML0407004292004-03-10010 March 2004 Status ML0406903002004-03-0909 March 2004 Morning Report 3-2004-0015: Plant Status Update and Restart Approval ML0402105142004-01-21021 January 2004 Firstenergy Announces Management Changes ML0327310182003-09-30030 September 2003 Management Change ML0326001702003-09-17017 September 2003 Plan Heat-Up for Reactor Coolant System Pressure Test Suspended Because of Emergent Issues ML0325501722003-09-12012 September 2003 Entry Into Mode 4 and Mode 3 2008-02-25
[Table view] |
Text
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III March 26, 2004 Licensee/Facility: Notification:
FIRSTENERGY NUCLEAR OPERATING CO.
Davis-besse MR Number: 3-2004-0024 Akron, Ohio Date: 03/26/2004 Dockets: 050-00346 RIII-Via Teleconf. with Site
[1] B&W-L-LP License No:
Subject:
Davis-Besse Reactor Plant is Critical Discussion:
This information is current as of 9:00 a.m. (EST) on March 26, 2004. Davis-Besse completed its maintenance outage to repair feed water and steam line turbine bypass valves and recommenced start-up activities. The plant is currently in Mode 2 at normal operating temperature and pressure. The plant entered Mode 2 at 3:07 a.m. this morning, March 26, achieved criticality at 4:56 a.m., and is continuing with power ascension activities.
Ongoing resident inspector coverage, and enhanced inspection oversight will continue to be utilized to evaluate operational evolutions. Around-the-clock oversight, with NRC resident inspector and examiner support from Region III and other Regional Offices, was re-initiated on March 25 at 4:00 p.m., and will continue during operational evolutions until full power routine operations are achieved.
Regional Action: For Information Only