(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Letter Sequence Other |
---|
|
|
MONTHYEARML0434802082004-12-0808 December 2004 G20040836/LTR-04-0744 - Paul Blanch & Arnold Gundersen Ltr Vermont Yankee Nuclear Power Station Project stage: Request ML0434801502004-12-29029 December 2004 G20040836/LTR-04-0744 - Paul Blanch and Arnold Gundersen Ltr. Re. Vermont Yankee Nuclear Power Station Project stage: Other 2004-12-29
[Table View] |
|
---|
Category:Letter
MONTHYEARBVY 24-028, Pre-Notice of Disbursement from Decommissioning Trust2024-10-31031 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-10-30030 October 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20240012024-06-28028 June 2024 NRC Inspection Report No. 05000271/2024001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24053A2572024-03-0101 March 2024 Withdrawal of Requested Licensing Action for a License Amendment Submitted for Approval of the License Termination Plan BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G IR 05000271/20230022024-02-20020 February 2024 NRC Inspection Report Nos. 05000271/2023002 and 07200059/2023001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust 2024-09-18
[Table view] |
Text
December 29, 2004 Paul M. Blanch 135 Hyde Road West Hartford, CT 06117 Arnold Gundersen 139 Killarney Drive Burlington, VT 05401
Dear Messrs. Blanch and Gundersen:
I am responding to your letter to Chairman Diaz, dated December 8, 2004, regarding the Vermont Yankee Nuclear Power Station (Vermont Yankee). In your letter, you raised concerns about Vermont Yankees conformance with its design basis and compliance with applicable Nuclear Regulatory Commission regulations. Based on these concerns, you requested that the Chairman intervene in the licensees application for a power uprate to ensure reconciliation of Vermont Yankees design basis. You also sent an e-mail to Mr. Rick Ennis, the Vermont Yankee Project Manager, and requested that this letter be treated as supplemental information to the petition you submitted, dated July 29, 2004, under the process specified in Title 10 of the Code of Federal Regulations (10 CFR) Section 2.206. Therefore, we will respond to the issues related to the design basis at Vermont Yankee in conjunction with the response to your petition.
In your letter, you expressed concerns about the engineering inspection conducted at Vermont Yankee earlier this year. NRC staff was available to answer questions regarding this inspection at the public meeting in Brattleboro, Vermont on December 16, 2004.
Furthermore, if you have identified any specific information indicating that Vermont Yankee does not meet applicable regulatory requirements, you are encouraged to provide that information to NRC so that we can evaluate the issue and take appropriate action. Thank you for taking the time to provide your concerns to us.
Sincerely,
/RA by RBorchardt for/
J. E. Dyer, Director Office of Nuclear Reactor Regulation Docket No. 50-271
December 29, 2004 Paul M. Blanch 135 Hyde Road West Hartford, CT 06117 Arnold Gundersen 139 Killarney Drive Burlington, VT 05401
Dear Messrs. Blanch and Gundersen:
I am responding to your letter to Chairman Diaz, dated December 8, 2004, regarding the Vermont Yankee Nuclear Power Station (Vermont Yankee). In your letter, you raised concerns about Vermont Yankees conformance with its design basis and compliance with applicable Nuclear Regulatory Commission regulations. Based on these concerns, you requested that the Chairman intervene in the licensees application for a power uprate to ensure reconciliation of Vermont Yankees design basis. You also sent an e-mail to Mr. Rick Ennis, the Vermont Yankee Project Manager, and requested that this letter be treated as supplemental information to the petition you submitted, dated July 29, 2004, under the process specified in Title 10 of the Code of Federal Regulations (10 CFR) Section 2.206. Therefore, we will respond to the issues related to the design basis at Vermont Yankee in conjunction with the response to your petition.
In your letter, you expressed concerns about the engineering inspection conducted at Vermont Yankee earlier this year. NRC staff was available to answer questions regarding this inspection at the public meeting in Brattleboro, Vermont on December 16, 2004.
Furthermore, if you have identified any specific information indicating that Vermont Yankee does not meet applicable regulatory requirements, you are encouraged to provide that information to NRC so that we can evaluate the issue and take appropriate action. Thank you for taking the time to provide your concerns to us.
Sincerely,
/RA by RBorchardt for/
J. E. Dyer, Director Office of Nuclear Reactor Regulation Docket No. 50-271 DISTRIBUTION: G20040836/LTR-04-0744 PUBLIC BSheron, NRR/ADPT DSkay PDI-2 R/F KCyr, OGC REnnis LReyes OPA CRaynor EMerschoff OCA SCollins, RI WKane NRR Mail Room CAnderson, RI MVirgilio KGrimes JStang PNorry LCox VBucci, OIG WDean AHowe BPoole, OGC SBurns CHolden JDyer, NRR TKim, EDO Package: ML043480162 Incoming: ML043480208 Response Accession: ML043480150 *Concurred by phone OFFICE PDI-1/PM PDI-2/LA PDI-VY/SC OGC PDI/D RI DLPM/D NRR/D NAME DSkay CRaynor AHowe BPoole CHolden WLanning* TMarsh (JLyons for) RBorchardt for JDyer DATE 12/21/04 12/13/04 12/13/04 12/21/04 12/13/04 12/13/04 12/13/04 12/28/04 OFFICIAL RECORD COPY