G20040836/LTR-04-0744 - Paul Blanch and Arnold Gundersen Ltr. Re. Vermont Yankee Nuclear Power Station
ML043480150
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 12/29/2004
From: Dyer J
Office of Nuclear Reactor Regulation
To: Blanch P, Gundersen A
- No Known Affiliation
Skay D, NRR/DLPM, 415-1322
Shared Package
ML043480162 List:
References
G20040836, LTR-04-0744, TAC MC5370
Download: ML043480150 (3)


Text

December 29, 2004 Paul M. Blanch 135 Hyde Road West Hartford, CT 06117 Arnold Gundersen 139 Killarney Drive Burlington, VT 05401

Dear Messrs. Blanch and Gundersen:

I am responding to your letter to Chairman Diaz, dated December 8, 2004, regarding the Vermont Yankee Nuclear Power Station (Vermont Yankee). In your letter, you raised concerns about Vermont Yankees conformance with its design basis and compliance with applicable Nuclear Regulatory Commission regulations. Based on these concerns, you requested that the Chairman intervene in the licensees application for a power uprate to ensure reconciliation of Vermont Yankees design basis. You also sent an e-mail to Mr. Rick Ennis, the Vermont Yankee Project Manager, and requested that this letter be treated as supplemental information to the petition you submitted, dated July 29, 2004, under the process specified in Title 10 of the Code of Federal Regulations (10 CFR) Section 2.206. Therefore, we will respond to the issues related to the design basis at Vermont Yankee in conjunction with the response to your petition.

In your letter, you expressed concerns about the engineering inspection conducted at Vermont Yankee earlier this year. NRC staff was available to answer questions regarding this inspection at the public meeting in Brattleboro, Vermont on December 16, 2004.

Furthermore, if you have identified any specific information indicating that Vermont Yankee does not meet applicable regulatory requirements, you are encouraged to provide that information to NRC so that we can evaluate the issue and take appropriate action. Thank you for taking the time to provide your concerns to us.

Sincerely,

/RA by RBorchardt for/

J. E. Dyer, Director Office of Nuclear Reactor Regulation Docket No. 50-271

December 29, 2004 Paul M. Blanch 135 Hyde Road West Hartford, CT 06117 Arnold Gundersen 139 Killarney Drive Burlington, VT 05401

Dear Messrs. Blanch and Gundersen:

I am responding to your letter to Chairman Diaz, dated December 8, 2004, regarding the Vermont Yankee Nuclear Power Station (Vermont Yankee). In your letter, you raised concerns about Vermont Yankees conformance with its design basis and compliance with applicable Nuclear Regulatory Commission regulations. Based on these concerns, you requested that the Chairman intervene in the licensees application for a power uprate to ensure reconciliation of Vermont Yankees design basis. You also sent an e-mail to Mr. Rick Ennis, the Vermont Yankee Project Manager, and requested that this letter be treated as supplemental information to the petition you submitted, dated July 29, 2004, under the process specified in Title 10 of the Code of Federal Regulations (10 CFR) Section 2.206. Therefore, we will respond to the issues related to the design basis at Vermont Yankee in conjunction with the response to your petition.

In your letter, you expressed concerns about the engineering inspection conducted at Vermont Yankee earlier this year. NRC staff was available to answer questions regarding this inspection at the public meeting in Brattleboro, Vermont on December 16, 2004.

Furthermore, if you have identified any specific information indicating that Vermont Yankee does not meet applicable regulatory requirements, you are encouraged to provide that information to NRC so that we can evaluate the issue and take appropriate action. Thank you for taking the time to provide your concerns to us.

Sincerely,

/RA by RBorchardt for/

J. E. Dyer, Director Office of Nuclear Reactor Regulation Docket No. 50-271 DISTRIBUTION: G20040836/LTR-04-0744 PUBLIC BSheron, NRR/ADPT DSkay PDI-2 R/F KCyr, OGC REnnis LReyes OPA CRaynor EMerschoff OCA SCollins, RI WKane NRR Mail Room CAnderson, RI MVirgilio KGrimes JStang PNorry LCox VBucci, OIG WDean AHowe BPoole, OGC SBurns CHolden JDyer, NRR TKim, EDO Package: ML043480162 Incoming: ML043480208 Response Accession: ML043480150 *Concurred by phone OFFICE PDI-1/PM PDI-2/LA PDI-VY/SC OGC PDI/D RI DLPM/D NRR/D NAME DSkay CRaynor AHowe BPoole CHolden WLanning* TMarsh (JLyons for) RBorchardt for JDyer DATE 12/21/04 12/13/04 12/13/04 12/21/04 12/13/04 12/13/04 12/13/04 12/28/04 OFFICIAL RECORD COPY