Category:Letter
MONTHYEARBVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000271/20220022023-02-22022 February 2023 Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station - NRC Inspection Report No. 05000271/2022002 BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond ML22347A2792022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 IR 05000271/20224012022-12-15015 December 2022 NRC Inspection Report No. 05000271/2022401, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont (Letter Only) BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection BVY 22-027, Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station2022-11-11011 November 2022 Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station BVY 22-026, Pre-Notice of Disbursement from Decommissioning Trust2022-10-31031 October 2022 Pre-Notice of Disbursement from Decommissioning Trust ML22273A1492022-10-0404 October 2022 Review of Decommissioning Funding Status 2022 BVY 22-025, Pre-Notice of Disbursement from Decommissioning Trust2022-10-0404 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-023, Pre-Notice of Disbursement from Decommissioning Trust2022-09-0101 September 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-022, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-22022 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-16016 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-020, Pre-Notice of Disbursement from Decommissioning Trust2022-08-0101 August 2022 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20220012022-08-0101 August 2022 NRC Inspection Report No. 05000271/2022001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 22-019, Pre-Notice of Disbursement from Decommissioning Trust2022-07-0606 July 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022 Notification of Revised Decommissioning Cost Estimate 2024-01-04
[Table view] |
See also: IR 05000271/2014403
Text
Mr. Christopher Wamser Site Vice President Entergy Nuclear Operations, Inc. Vermont Yankee Nuclear Power Station PO Box 250 Vernon, VT 05354
SUBJECT: VERMONT YANKEE NUCLEAR POWER STATION - NRC BASELINE SECURITY INSPECTION REPORT 05000271/2014403
Dear Mr. Wamser:
On April 17, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Vermont Yankee Nuclear Power Station. The NRC inspectors discussed the results of this inspection with Mr. Jack Boyle, Engineering Director, and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report.
NRC inspectors documented two findings of very low security significance (Green) in this report. These findings involved violations of NRC requirements. The NRC is treating these violations as Non-Cited Violations (NCV) consistent with Section 2.3.2a of the Enforcement Policy. If you contest the violations or significance of the NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555 0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001; and the NRC resident inspector at the Vermont Yankee Nuclear Power Plant.
Two cross-cutting aspects were assigned to the findings in the area of Human Performance. One cross-cutting aspect was assigned in the area of Human Performance, Conservative Bias, because Entergy did not use decision making-practices that emphasize prudent choices over those that are simply allowable (H.14). The second cross-cutting aspect was assigned in the area of Human Performance, Documentation, because Entergy did not create and maintain complete, accurate, and up-to-date documentation (H.7). If you disagree with a cross-cutting aspects assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region I; and the NRC resident inspector at the Vermont Yankee Nuclear Power Plant. Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, the transmittal document is decontrolled. May 22, 2014 In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,/RA/
Anthony Dimitriadis, Branch Chief Plant Support Branch 1 Division of Reactor Safety Docket No. 50-271 License No. DPR-28 Nonpublic
Enclosure:
Inspection Report 05000271/2014403
w/Attachment:
Supplemental Information (OUO-SRI) cc w/o encl; w/o OUO-SRI: Distribution via ListServ cc w/encl; w/OUO-SRI: P. Ryan, Security Manager C. Recchia, Commissioner, Department of Public Service J. Giarrusso, Division Chief, MA Emergency Management Agency P. Plummer, Acting Director, State of New Hampshire Homeland Security