ND-18-0100, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.05.03.1 (Index Number 630)

From kanterella
Revision as of 22:42, 7 March 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.6.05.03.1 (Index Number 630)
ML18036A169
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/02/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.6.05.03.i, ND-18-0100
Download: ML18036A169 (6)


Text

Michael J. Yox 7825 River Road Regulatory Affairs Director Waynesboro, GA 30830

^ Southern Nuclear Vogtle 3 & 4 706-848-6459 tei 410-474-8587 cell myox@southernco.com FEB 0 2 2018 Docket No.;52-025 52-026 ND-18-0100 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.6.05.03.1 [Index Number 6301 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of January 25, 2018, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.6.05.03.1

[Index Number 630] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.05.03.1 [Index Number 630]

MJY/pgl/amw

U.S. Nuclear Regulatory Commission ND-18-0100 Page 2 of 3 To:

Southern Nuclear Operating Companv / Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKlnney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. D. Williams Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. 0. Chamberlain Mr. D. R. Culver Mr. R. L. Beiike Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. T. C. Brimfield Mr. A. J. Lerch Mr. C. J. Even Ms. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Oalethoroe Power Corporation Mr. K. T. Haynes Mr. R. B. Brinkman Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-18-0100 Page 3 of 3 Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. 8. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0100 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0100 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.6.05.03.1 [Index Number 630]

U.S. Nuclear Regulatory Commission ND-18-0100 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment:

3. The lightingfixtures located in the MCR utilize seismic supports.

Inspections. Tests. Analyses:

i) Inspection will be performed to verify that the lighting fixtures located in the MCR are located on the Nuclear Island.

ii) Analysis of seismic supports will be performed.

Acceptance Criteria:

i) The lighting fixtures located in the MCR are located on the Nuclear Island.

ii) A report exists and concludes that the seismicsupports can withstand seismic design basis loads.

ITAAC Completion Description Following installation of the Main Control Room (MCR) lighting fixtures, an inspection is performed to verify the lighting fixtures are located on the Nuclear Island. Additionally, an analysis of the lighting fixture supports is performed and a report exists that concludes the lighting fixture seismic supports can withstand seismic design basis loads.

The inspection ofthe MCR lighting fixtures is performed in accordance with Nuclear Quality Site Instruction 08110.1-V (Reference 1) to confirm the lighting fixtures are located on the Nuclear Island. Detailed design drawings are used to confirm the satisfactory installation of the MCR lighting fixtures. The inspection includes verification of each lighting fixture location and the support configuration. The results of the inspection are documented in reportsfor Unit 3 and Unit 4 (References 2 and 3, respectively). The reports conclude the lighting fixtures are located on the Nuclear Island.

An analysis of the lighting fixture seismic supports is performed to confirm the supports can withstand seismic design basis loads. The MCR lighting fixture supports are designed as Seismic Category I Equipment. The supports consist of steel unistrut channels welded to the ceiling of the MCR and steel chains that attach the light fixture to the unistrut channels. The seismic loading conditions are established using the AP1000 seismic floor response spectra and the equivalent static load method of analysis described in the Vogtle 3&4 Updated Final Safety Analysis Report (UFSAR) (Reference 4). Lateral loads acting on the support chains are considered negligible based on guidance from the American Society of Civil Engineers (ASCE)

Standard 7-05 (Reference 5). Structural integrity is demonstrated by calculating and concluding the maximum seismic loads are less than or equal to the applicable design code allowable limits. The results of the analysis are documented in APP-SH25-S3C-002 (Reference 6) and conclude the lighting fixture seismic supports can withstand seismic design basis loads.

The inspection reportand analysis are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC 2.6.05.03.1 Completion Packages (References 7 and 8, respectively).

U.S. Nuclear Regulatory Commission ND-18-0100 Enclosure Page 3 of 3 List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of ITAAC Findings pertaining to the subject ITAAC and associated corrective actions. This finding review, which includes now-consolidated ITAAC Index 631, found no relevant ITAAC findings associated with this ITAAC.

References favaiiabie for NRG inspection)

1. NuclearQuality Site Instruction QS110.1-V, Rev. 011, "Inspection Planning and Reporting"
2. Unit 3 Main Control Room Lighting Inspection Report, IR-XXXXXX
3. Unit 4 Main Control Room Lighting Inspection Report, IR-YYYYY
4. Vogtle 3&4 UFSAR, Subsection 3.7.3.5
5. ASCE, "Minimum Design Loads for Buildings and Other Structures, American Society of Civil Engineers"
6. APP-SH25-S3C-002, Rev. 3, "API000 Seismic Category 1 Standard Conduit Supports"
7. ITAAC 2.6.05.03.1 Unit 3 Completion Package
8. ITAAC 2.6.05.03.1 Unit 4 Completion Package
9. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"