ML16015A050

From kanterella
Revision as of 07:09, 5 February 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
ISFSI - Three-Year Update to the Decommissioning Funding Plan
ML16015A050
Person / Time
Site: Maine Yankee
Issue date: 12/16/2015
From: Pizzella C
Maine Yankee Atomic Power Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
OMY-15-053
Download: ML16015A050 (30)


Text

Maine Yankee 321 Old Ferry Road, Wiscasset, Maine 04578 December 16, 2015 OMY- 15-053 Re: 10 CFR 72.4 and 10 CFR 72.30 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 50-309)

Subject:

Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Pursuant to the requirements of 10 CFR 72.3 0(c) and 10 CFR 70.4, Maine Yankee Atomic Power Company (Maine Yankee) is providing the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP). Enclosure 1 updates the Maine Yankee ISFSI decommissioning cost estimate and the cost estimate for the management of irradiated fuel and Greater than Class C Waste submitted with the original Maine Yankee ISFSI DFP on December 17, 2012 (Reference 1), as revised on January 8, 2013 (Reference 2). It includes adjustments to account for changes in costs. The update does not include any adjustments for additional radiological contamination, because the extent of radioactive contamination at the Maine Yankee ISFSI remains unchanged.

10 CFR 72.3 0(c) defines specific events that must be considered in the subsequent updates.

Since the submittal of the original Decommissioning Funding Plan for the ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISF SI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.
4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

In addition, Maine Yankee complies with the requirements of 10 CFR 72.30(b)(1) through (b)(6), as follows.

Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 2 10 CFR 72.30(b)(1) requires the licensee to provide "information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI." Maine Yankee has established an account within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that segregates the funds for decommissioning of the ISFSI from the larger balance of funds for ongoing management of irradiated fuel and GTCC waste held in the NDT. Currently, the trust has sufficient funds to meet the revised DCE for the Maine Yankee ISFSI.

10 CER 72.30(b)(2) requires the licensee to provide a detailed cost estimate for decommissioning. Enclosure 1 provides a revised DCE for the Maine Yankee ISFSI that:

1) Utilizes an independent contractor to perform the decommissioning activities in accordance with 10 CFR 72.30O(b)(2)(i); 2) Includes an adequate contingency factor in accordance with 10 CFR 72.30(b)(2)(ii); and 3) Includes the cost of meeting the criteria for unrestricted release in accordance with 10 CFR 72.30(b)(2)(iii). In addition, the revised Maine Yankee ISFSI DCE specifically considered the effects of the events described in 10 CFR 72.30(c) on the costs of decommissioning and the extent of contamination. The revised Maine Yankee ISFSI DCE estimates the total cost to decommission the Maine Yankee ISFSI to be $27.4 million and $28.1 million (in 2015 and 2016 dollars, respectively), inclusive of radiological and non-radiological removal.

10 CFR 72.30(b)(3) requires the licensee to identify and justify the key assumptions contained in the DCE. Enclosure 1 provides the revised DCE for the Maine Yankee ISFSI, including the key assumptions and the justification for their use.

10 CFR 72.30(b)(4) requires the licensee to provide a description of the method of assuring funds for decommissioning from 10 CFR 72.30(e), including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. Maine Yankee will periodically reassess the decommissioning cost estimate in accordance with 10 CFR 72.30(c).

On a periodic basis, Maine Yankee will submit rate cases to Federal Energy Regulatory Commission (FERC) that will include revised cost estimates for decommissioning and the management of irradiated fuel and GTCC waste. If necessary, additional funds may be recovered from the purchasers.

Maine Yankee has successfully litigated a couple of breach of contract damages claims against the Department of Energy (DOE) for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. A third breach of contract damages claim for the period 2008-20 12 is with the federal court for decision and additional damages claims against the DOE relating to the government's breach of contract are expected to continue as long as the irradiated fuel and GTCC waste remain on site.

Annually, Maine Yankee submits the reports required by 10 CFR 50.75(f)(2),

10 CFR 50.82(a)(8)(v) and 10 CFR 50.82(a)(8)(vii) to establish how it satisfies the obligations defined in those regulations regarding the assurance of decommissioning funding and the status of funding for the management of irradiated fuel.

Maine Yankee Atomic Power Company OMY- 15-053/December 16, 2015/Page 3 10 CFR 72.3 0(b)(5) requires the licensee to define the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination. No subsurface material is assumed to require remediation regarding radionuclides.

This is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the ISFSI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters; 4) nuclear activation of the Vertical Concrete Casks (VCCs),

VCCs liners, and ISFSI are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent.

10 CFR 72.30(b)(6) requires a certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning. Enclosure 2 provides the certification of financial assurance.

In addition, Enclosure 3 provides an estimate of the total costs associated with the Maine Yankee ISFSI for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI through 2033.

A summary of the revised DCE and the cost estimate for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI will be incorporated into the Post-Shutdown Decommissioning Activities Report (PSDAR) and the License Termination Plan (LTP).

If you have any questions, please do not hesitate to contact me at (860) 267-6426 x304.

Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer

Enclosures:

1. Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation
2. Certification of Financial Assurance
3. Total Costs Associated with the Maine Yankee ISFSI, including Cost Estimate for Managing Irradiated Fuel and GTCC Waste

Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 4

References:

1. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012 (OMY- 12-073)
2. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Revised Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013 (OMY-13-003) cc: D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager P. 1. Dostie, SNSI, State of Maine J. Hyland, State of Maine

ENCLOSURE 1 TO OMY-15-053 DECOMMISSIONING STUDY OF THE MAINE YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation Prepared for Maine Yankee Atomic Power Company Knight Cost Engineering Services, LLC November, 2015

Knight Cost Engineering Services, LICKCS25-20-30Rv0 KCES 2015 - 2015-300Rev. O Table of Contents

1.0 INTRODUCTION

............................................................................... 3 2.0

SUMMARY

...................................................................................... 4 3.0 DECOMMISSIONING COST ESTIMATING APPROACH ............................ 7 4.0 ASSUMPTIONS................................................................................. 8 5.0 SCHEDULE ....................................................................................... 10 6.0 PROJECT MANAGEMENT ....................................... ........................... 12 61 OVERSIGHT STAFF................................................................................. 12 6.2 DECOMMISSIONING GENERAL CONTRACTOR ............................................. 13 6.3 SECURITY ............................................................................................ 13

7.0 REFERENCES

................................................................................... 14 APPENDIX A............................................................................................ 15 Page 2 of 15

Knight Cost Engineering Services, LLCKES25-20-30Rv0 KCES 2015- 2015-300 Rev. O 1.0 INTRODhUCTION The purpose of this study is to identify the costs associated with the decommissioning of the Maine Yankee (MY) Independent Spent Fuel Storage Installation (ISFSI). This estimate includes only the structures, systems and land within the NRC licensed area. The MY ISFSI is located within the site boundary of the former Maine Yankee nuclear power plant in the Town of Wiscasset, Maine. The site is approximately 1200 feet north of the former plant site in an area used as a vehicle parking lot. The NAC-UMS fuel storage and transport canister system chosen by MY is licensed by the NRC for both storage and transportation.

The ISF SI consists of the storage system and concrete storage pads, a Protected Area (PA) for spent fuel storage and a Security/Operations Building for equipment and staff. The PA contains 16, 3 foot thick concrete pads, each 31 feet by 31 feet. There are 64 dry storage casks on the 16 pads, 60 for spent fuel and four for sections of the reactor vessel internals that are classified as Greater Than Class C (GTCC) waste. Each vertical concrete cask has a two and a half-inch steel liner surrounded by 28.3 inches of reinforced concrete.

Page 3 of 15

Knight Cost Engineering Services, LLCKCS21 20-30Rv0 KCES 2015 - 2015-300 Rev. O 2.0

SUMMARY

Decommissioning is the safe removal of a facility or site from service and the reduction of radioactivity to a level that permits either the release of the property for unrestricted use and NRC license termination; or a restricted release of the property and NRC license termination. This estimate includes all costs incurred to release the property for unrestricted use.

On June 17, 2011, the NRC published a final rule amending its regulations to improve decommissioning planning. The rule became effective on December 17, 2012. This rule requires licensees to report additional details in their decommissioning cost estimate. To assist in the implementation of the new rule, the NRC issued NUIREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness."

NUREG-1757 does not apply to licensees under i0CFR Part 50 nor does it eliminate the need to follow Regulatory Guide 1.202 or NUJREG-1713. It does provide additional information to support the development of the cost estimate. This cost estimate was prepared in accordance with the guidelines provided in RG 1.202 and NUREG-1713. In addition, it does take into account the guidelines identified in NUJREG-1757.

NUJREG- 1757 specifies that a contingency of 25% is to be included in the estimate. This estimate takes exception to this contingency level for two reasons. First, the estimate is conservative in that the entire storage pad, concrete overpacks and overpack liners are assumed to be disposed of as potentially contaminated. Second, the MY site has recently been successfully decommissioned, and the land released from the operating license, with the exception of land associated with the ISFSI and laydown area. The lessons learned from that project will be incorporated in the MY ISFSI decommissioning. For this reason it is felt that a 10% contingency is adequate to cover unknown and unplanned occurrences.

The original Decommissioning Funding Plan for the Maine Yankee Independent Spent Fuel Storage Installation (ISFSI) to comply with 10 CFR 72.30(b) was submitted on December 17, 2012, with a revision submitted on January 8, 2013. 10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates. Since the submittal of the original Decommissioning Funding Plan for the Maine Yankee ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.
4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

Page 4 of 15

Knight Cost Engineering Services, LLC KCES 2015- 2015-300 Rev. 0 The total cost including contingency is $27.4 million, $21.6 million for radiological removal and

$5.9 million for non-radiological removal. Table 2-1 provides a summary of costs. Cost details are provided in Appendix A TABLE 2-1

SUMMARY

OF COSTS Non-Radiological radiological Total Cost Removal $ Removal $

Grand Total Building $27,423,524 $21,556,946 $5,866,578 Tax on General Contractor $0 $0 $0 General Contractor with contingency $17,757,734 $13,958,910 $3,798,824

$9,665,790 $7,598,036 $2,067,754 Site Costs with contingency

$16,143,394 $12,689,919 $3,453,476 General Contractor Site Costs $8,787,082 $6,907,305 $1,879,777 MY ISFSI $24,930,477 $19,597,224 $5,333,253

$15,126,261 $11,890,375 $3,235,886 PERIOD DEPENDENT COSTS 1.1 MY Site Costs $8,787,082 $6,907,305 $1,879,777 1.1.1 Project Management $4,111,355 1.1.2 Security Staff $2,303,834 1.1.3 Fees $719,678

$565,721 $153,957 1.1.4 Insurance $582,818 $458,139 $124,679 1.1.5 Legal $200,000 $157,215 $42,785 1.1.6 Property Taxes $869,397 $683,411 $185,986

.1.2 General Contractor $6,339,179 $4,983,070 $1,356,109 1.2.1 Decommissioning General Contractor S3,344,685 1.2.2 Waste Packaging Crew $1,062,680 1.2.3 Equipment & Materials $1,931,813 ACTIVITIES $9,804,216 $7,706,849 $2,097,367 1.3 Project Engineering $12,346 $9,705 $2,641 1.3.1 Procedure Development and Review - Offsite $6,173 Preparation of QA and Safety Documents -

1.3.2 Offsite (in parallel with 1.2.1) $6,173 Site Mobilization and General Employee Training (GET) $95,166 1.4 $74,808 $20,358 1.4.1 Site Mobilization $23,364 1.4.2 General Employee Training $65,348 1.4.3 Site Specific Training $6,455 1.5 Site Preparation - Performed by Staff $12,025 $9,452 $2,572 Page 5 of 15

Knight Cost Engineering Services, LLC KCES 2015-2015-300 Rev, O

SUMMARY

OF COSTS, continued 1.5.1 Initial site Survey 1.5.2 Setup work areas

,1.5.3 Decontamination Readiness Review 1.6 Disconnect all utilities to work areas. $6,012 $4,726 $1,286 1.6.1 Electrical $3,006 1.6.2 Ventilation $1,503 1.6.3 Piping $1,503 1.7 Removal inside fences $8,082,872 $7,570,361 $512,511 1.7.1 Remove compacted gravel $371,230 $371,230 1.7.2 Remove VCCs $5,464,765 $5,464,765 $0 1.7.2.1 Exterior Concrete $3,651,744 $0 $0 1.7.2.2 Steel liner $1,813,021 1.7.3 Remove Concrete Pad $2,105,596 $2,105,596 1.7.4 Remove Security Fence $63,016 $63,016

'1.7.5 Remove Light Towers $7/8,265 $78,265 1.8 Removal outside fences $1,539,000 $1,539,000 1.8.1 Security/Operations Building $561,356 $561,356 1.8.2 Remove paved area inside nuisance fence $.86,508 $86,508 1.8.3 Remove nuisance fence $73,685 $73,685 1.8.4 Miscellaneous Pads $79,464 $79,464 1.8.5 Miscellaneous structures $419,709 $419,709 1.8.6 Remove buried utilities $153,213 $153,213 1.8.7 SOB electrical service $8,815 $8,815 1.8.8 Remove road inside licensed area $140,067 $140,067 1.8.9 Remove vehicle barriers $16,184 $16,184 Final Site Survey Structure gone - By DGC 1.9 Staff $25,000 $19,652 $5,348 1.9.1 Prepare Final Status Survey Plan 1.9.2 Soil Sampling 1.9.3 Direct Survey 1.9.4 Sampling Analysis 1.9.5 Prepare Final Status Survey Report 1.10 Orise Site Release Confirmation 1.11 Outside areas $8,712 $8,712 1.11.1 Backfill, grade and seed $8,712 $8,712 1.12 Demolition Crew Demobilization $16,909 $13,292 $3,617 1.13 Final Project Report- Offsite $6,1]73 $4,853 $1,321 Page 6 of 15

Knight Cost Engineering Services, LLCKES21-20530R.0 KCES 2015- 2015-300 Rev. O 3.0 DECOMMISSIONING COST ESTIMATING APPROACH Two types of costs were determined in this estimate: activity costs and level of effort costs. The activity costs were developed utilizing a unit cost factor approach. Site material quantities for concrete, steel and equipment where developed from site specific drawings. Productivity factors were applied to these quantities to determine activity durations. Labor crews were developed and applied to the material quantities to determine labor costs and person-hours. The activity durations were used to develop a project schedule.

The level of effort costs such as equipmenit rental and the General Contractor (GC) staff were developed based on the project schedule duration. A rental equipment file was developed for the construction effort. The GC staff is assumed to be on-site for the duration of the project. The Oversight staff cost is another level of effort cost that. is included in the cost estimate.

Bulk removal of the storage pad and concrete storage casks is assumed to be performed using an excavator with a hydraulic hammer attachment. The steel liner will be segmented utilizing torch cutters. All of this waste will be trucked off-site for processing. This leads to a large disposal volume; however, at a lower rate for bulk processing than for direct burial. In addition, there will be far less characterization and iterative decontamination. Clean structures will be demolished using mechanical means and disposed of at a local landfill.

In addition to the removal labor there is a dedicated waste packaging crew included in this estimate.

This crew will consolidate, package and prepare containers for transportation. The waste packaging crew is estimauted to remain on site for the duration of the project. This crew consists of 2 laborers; 1 Health Physics Technician; 1 Equipment Operator and 1 Foreman.

Page 7 of 15

Knight Cost Engineering Services, LLCKES21-20530Rv0 KCES 2015 - 2015-300 Rev. O 4.0 ASSUMPTIONS Following is a list of assumptions developed by KCES in completing this study. These assumptions are based on the most current decommissioning methodologies and site-specific considerations.

1. Component quantities were developed from actual plant listings.
2. Concrete volumnes were developed from plant drawings.
3. The oversight staff is assumed to be similar in size and configuration as it is currently.
4. The oversight staff positions and costs were supplied by the Company and represent September, 2015 salary and benefit data.
5. Subcontractor base labor rates and fringe benefits were taken directly from the 2015 R. S. Means Heavy Construction Cost Data and adjusted to Maine based on the City Cost Indexes for Bath, ME.
6. Activity labor costs do not include any allowance for delays between activities, nor is there any cost allowance for craft labor retained on-site while waiting for work to become available.
7. All skilled laborers will be supplied locally and hired by the Decommissioning General Contractor (DGC).
8. The cost for Utility personnel assisting the DGC to develop decommissioning activity specifications is included in the Utility Staff costs.
9. The separate DGC staff salaries, including overhead and profit, were determined by KCES.
10. Transportation costs for LLW are included in the bulk disposal rate.
11. The ISFSI Concrete Pad, VCC exterior concrete and VCC liner steel are assumed to be low-level radioactive wastes that will be disposed of at the Waste Control Specialists facility in Texas (a licensed facility) at $0.25 per pound.
12. The following buildings are disposed of as Clean waste in local landfill. A disposal rate of $91.80 per ton has been used in this estimate and is based on information provided in the 2015 R. S. Means Building Construction Cost Data.

Compacted gravel around pads Security Fence Light Towers Security/Operations Building Paved area inside nuisance fence Page 8 of 15

Knight Cost Engineering Services, LIC ES01-21530Rv0 KCES 20!5 - 2015-300 Rev. O Nuisance fence Miscellaneous Pads Miscellaneous structures Buried utilities SOB electrical service Road inside licensed area Vehicle barriers

13. All costs used in these calculations were current on September, 2015.
14. The costs of all required safety analyses and safety measures for the protection of the general public, the environment, and decommissioning workers are included in the cost estimates.
15. It is assumed that all UMS canisters containing both spent fuel and GTCC will have been removed from site prior to the start of decommissioning.
16. Property taxes are included in the estimate at the current cost of $869,397 per year.
17. Fees are included in the estimate at the current cost of $719,678 per year.
18. Insurance costs are included in the estimate at the current cost of $582,818 per year.
19. Legal costs are included in the estimate at the current cost of $200,000 per year.
20. The decommissioning will be performed under the current regulations.
21. Removal of the pad and concrete overpacks will be performed in Tyvek coveralls.

Productivity rates have been adjusted to account for this.

22. The removal of the berm is not included in the estimate.
23. No subsurface material is assumed to require remediation regarding radionuclides. This assumption is justified because: 1)the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the 1SF SI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters; 4) nuclear activation of the VCCs, VCCs liners, and ISFSI pad are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface material occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent Page 9 of 15

IKnight Cost Engineering Services, LLC KE 2015-2015-300 KCES 05 0530Rv Rev. O 5.0 SCHEDULE A scenario-specific schedule has been developed for estimate.

Activity durations were determined based on the unit cost factor approach. Plant material inventory quantities were developed from site specific material. Unit rates for cost, man hours and schedule hours were applied to the material quantities. From this calculation the removal or decontamination cost, total man hours and total schedule hours were detei'mined for an activity.

The schedule hours are then entered into the schedule to determine project duration. Two work crews are assumed for the concrete pad and concrete overpacks. All other work was assumed to be performed by one crew. Work outside of the security fence will be performed in parallel with the work inside the fence. The total project duration is 17.97 months.

Figure 5-1 provides the detailed decommissioning schedule.

Page 10 of 15

Knight Cost Eri[ineering Services, LLC KCES 2015- 2015-300 Rev. 0 Figure 5-1 Project Schedule

  • I C]* air i use .yi rev i r.u Si -, I

__l_

2-i- a5*8 Eus0'am ay 3

t1C n-dlaiPpi~ay SitellDydITdelgI tdld*! Wb oes at--"

eedraud6 w,* r INgig,S Devesaaaladbvew-Otedays Sb elseds.TtW 8S s ft4*ue b'mewt a m 6day 4ays de1r Idap dayl 1 da 1$. 1114 Thu'1/11114 ThjIl6114 The111411 Woe 112114 Ff1d22/14 Mera 1/27114 We.* 1Wa4.

Wed 1/6*/14 WTu 11131/14 Mn 111611 The 1111114 flu 1/N4/I4 655 1117)14 I

I jj beilt81 8 t we/iitma.lS aye Tim 1/2N14 Wed 1/3144 11I da. 1iae1114S Tee 1111 ml I , I

  • 14 66041*I*Fm IIII I Vee n:.8 0*Tdais PWed1261 Wed 11111 I

beedledd be m 58/ ayeS Tlsi1/'114 Pt 4r/411W St  ::::::-::::::::*.*-~**-*~**~-'**'~-.*.*.-.-.*.-.-..

  • blU 4i* ell~n 60Tday" TIs'Wi261 'Wed6/1--

Stedm, 14,1.U days flwh/23/4 Pit116/4 IIw 21 aeee slaPdllu 48.1$ dais I 741/714 Man 216/14 IRemsee Sbslylala ra 7I days 16.3d Tis 3I/II/j4 Fit 3t148

  • Mtie Gemeeedw lays Tee s Pt 111 w/11
:1 l:1 iUMM* *U1561IUON21t,7 aeys P14111 Tue 6/13/1 M~

0MflatUm C FadWne 64 bcye Tne6/3/4 s we6/7/1 Page 11 of 15

Knight Cost Engineering Services, LLCKES21 20-30Rv0 KCES 2015 - 2015-300 Rev. O 6.0 PROJECT MANAGEMENT There are three components to project management during decommissioning, Oversight Staff (staff), Decommissioning General Contractor Staff (DGC) and Security. The person levels for each are identified below.

6.1 OVERSIGHT STAFF The staff size is assumed to be maintained at the current level and at a similar configuration during the decommissioning. In addition, the staff is augmented with one final status survey resource and one licensing person to assist mnthe decommissioning. The staff will provide DGC oversight as well as maintain license compliance. Table 6-1 provides a summary of this staff.

TABLE 6-1 OVERSIGHT STAFF Staff Number President 1 Cask Relicensing Project Manager1 Workers Concerns Manager 1 Director of Operations I ISFSI Manager 1 ISFSI QA Manager 1 ISFSI RPM I ISFSI Operations Specialist 1 ISFSI Administrator 1 Licensing Specialist 1 FSS Manager 1 ISFSI Technical Specialist1 Assistant Director of Operations 1 Program Manager I Program Manager 1 Program Manager 1 Public/Government Affairs 1 Regulatory Affairs 1 General Counsel1 Licensing EngineerI VP CFO & Treasurer Business Administrator 1 Accounting Manager I Sr. Accountant 1 Sr. Accountant 1 Benefits 1

  • IT Services 1 Security Manager1 28' Page 12 of 15

Knight Cost Engineering Services,. LLC KE 2015-2015-300 KCES 05 0Rv Rev. O 6.2 DECOMMISSIONING GENERAL CONTRACTOR The DGC will be responsible for all of the physical work. The staff will oversee the work crews.,

schedule work and supply HP support. The DOGC will be responsible for finishing the project on time and on budget. Table 6-2 provides a Summary of the DGC staff.

TABLE 6-2 DGC STAFF 2015 Base Man Position Salary. Level Project Superintendent $200,000 1.00 QA Auditor/Inspector $64,000 1.00 Health & Safety Supervisor $89,205 1.00 Packaging/Shipping Specialist $66,522 1.00 Cost Control Accountant $65,071 1.00 Scheduler II $65,000 1.00 Demolition Specialist $56,000 1.00 industrial Safety $67,000 1.00 Engineering Supervisor $113,000 1.00 Project Supervisor $81,000 1.00 Decontamination Tech $35,000 2.00 Instrumentation Tech $42,248 1.00 Tool Crib Attendant $33,976 1.00 14.00 6.3 SECURITY Once spent fuel and G3TCC waste are removed from the site the security force will be significantly reduced. This estimate assumes a force of 13 guards, four supervisors and one manager. This will allow a security person level of 5 guards during work time and two guards all other times. . While this staff level may be high for industrial standards, we have decided to maintain the security staff at conservatively high level. The guard force was assumed to consist of various levels of guards and the rate used has been adjusted accordingly.

Page 13 of 15

Knight Cost Engineering Services, LLCKCS01 21530Rv0 KCES 2015 - 2015-300 Rev. 0 7.0 REFER]ENCES

1. R.S. Means, Inc, Building Construction Cost Data, Kingston, Massachusetts, 2015.
2. Regulatory Guide 1.202, "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors"
3. NUREG-1713, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors"
4. NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness"
5. 10CFR 72.30, Financial Assurance and Recordikeeping for Decommissioning
6. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012.
7. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013.

Page 14 of 15

Knight Cost Engineering Services, LICKES21-20-30Rv0 KCES 2015 - 2015-300 Rev. O APPENDIX A Page 15 of 15

iii W.* i. 5 55 i' SI. (55 S S Ws lu0ls 11 an~ms*I.a *mt i55ta~i.5lli m um~ 5am a-.- la saUs UsaOW Usas4 tarn.. tiiw 5-~l iairnn oa

  • unsta i~hl*JS aSjami ma. mm. simmml -

arm mut*

-- a-ll i+i almios sa wliiis 7. 13 -

eta. ii.iiim.

is Dma.~W (5.5W CM 5W. Ma inn mm lasH. Haul 1114.3 i win mm urns ma? sum iU urn mm u.s mm 2,1mm 'a ma mm testis usia 5Mm in taul Minis sum sam tans muss a.tnu us Imum.ill urn mm wins u.N. 271mm Ia urn mm u.s mm &itam in arm mm turns Hams 11143 iM isa mm tans stUns 2It4 in sun m iu.ns ass. ,,tti.u in urn mm inns mis. tiitm Ia 5 mm mm wins sum 3.tlmm its LW& II NIiii awn mm wins SliMe 21,455 its urn mm u.s mu 211455 in urn mm ia.s ma. suisa in m.Tila-irn .it..a mm mas sutn s.iwm in 1 inst mm wins .iu~aa 21169 in an mu aim us. s.nem in

-a-l~l~ win mm tans pins &itsu in ms mm urns urSa suimm in mats mm tens stunt sum in a- at? mm u.s arm s.,tim in mm mm urns aria ..tieu in

~i-i lml u.n wi.ii mm mm wins wins asa slim aiim.

~ii4u an in I*

mns 41 - tim.?. mm tans mm. atisa in awn mm tans s. sitmm us u.s mm usui similE itiss in

.mnim. am.. urn nun ama sa Its, -

5WW* 77.3 is isus'aI. Ua5W CM simat? Unsti u4is mw is mn ties tans use tin wins maui tistis

- a-i-a n.os an utah. ira ans ilitia

,~a.n ii,. u.s asii Sian its. hiSs iii.m mu. tnt ass a.iu

.uan tim gas wine ursa tiut urns a.ni it u25SU4 UisU litaisil tewi' in - aiim mans mUll ia..ta maw Sittlil iii p..

mlisn -- in - am am saYs. aa.m ama -- in - -- maw main am iiA Itat iii Pisittis auwits --

is a- ii,. neens 41s.ts m*is isa mua ,'alrni-~t ill

5. a-Ma W.hta is isis smut am.u uumis Hielas us.

H.-~i -~ SW. Pan item tans am z.iam mita 1.3555 am am aim mu tees mum mm stint. stem tans Hata ama

  • isg i.il aiim stem tans itata hum I ma aim tans mis. han aiim trim aims ma.. as...

SiA win uns 1mm 1.3i55 UhI aim tani siam. 5s.w alit aim tans StiLe ,asm ii aim iim.u inns itiuuli hum mesa nan iins.m is-ala mm-- ~16. tilt

33*15 1.3.5

-ima Waef,*

5 5744 m m ~m 45*425.7i1inJ 253 4 Ii.) 1454 Mi-be-tm-.

  • 4-4,,v .*

3 143 55 twu, idp.4.ma 3 SN U 34.1U Wma-3 f3331 amw a

33 31 Smo N 33 33su

]mlmee.

-- 4hmem.-

-- 5. - mm at v sumN U4N -

GWI- 4 - 1.44 34004 0551 0a45m 34 4534 I 531 5U83 44- Wm 4.. 34 5157 I aa3 345JI 45-4 0*4 - =J4 45 em tw . am 5*5.13 IA 4- 337*4..av 15 33 I 5333 3 Is .m tim 31254 S -~m Sm - 334 N 1 525.5 3*64 acI-a  ! e I 4-*, 0123ee 314 mm 511*53 u ma.. slams, 31.45-15 5525* 55. 34

$1447

  • ~ .4215 rn~ o S 2911 0 4 3453 52543 16.5* N N 516* 521i4 37714 43 5 36 3 13.7 Pm ~ N 4-~m* -a sla s4 a m ISAIS aim?

g44*me 34 a-tWa t mm 5 i 4 11133 33 115.33 33 i4 am 33 4

ails i,.

122 51414555.334513N151i11 30 4 30 133 ails aIls 44 4451 33m1 Otaa. 1 44 a-adS 1.33 $143 5 44beNSS I Sm am 33 33*64 14 ala 33 a¶vs m IA 455551eTS455t5*1 5*6 12 25 sam p.m.

514 mmSt~

14.1 mm' 34 331 05 15.45 C-Me 5,444-55 54 0544355555 1 5~ as wu~~

a r44344~ as pese444-

  • 515544554- as sea-m I 04054.44-5 as 55adsg~

I ~ as sa-I 04.444555 as ssas~a-.

I - 55 wesia-~.g

  • ~ as sa44a-~uam as eta-45a-s 3 4-55145 as 1545,444-3445 I 51517.4. as ~

I 1adIs4- as sasoam 3 4455 35.4 55453 7 L* 45.5 564 3 F~S 45.34 51154 3 4- sau sias 33 '-4

  • 515- 3 51 4 Se k..45ee44-440544454.5 33 Se u 3 15125.33 I-'-- 33 3454 M4 F-4-44.5O 142 a Itkls mm mja C- 44.14. 04545 I 444-44 as as 05~44C-am..s I Mka.4...a, as as wsa-.s.asu I 51253.5534- as as 44a-5545

2824 d 4.3. 3.34 2~ 3332 2824 0 3.272 21*8.

-- - WA - - - - - - Ossa LEAVe - We -

~2 223.7*2 4824MM MUMU 282We ~V3M 82323282 1MMA~ 2~43 -~ ~ £~ L~ 4.3 4.3 33 4.3

~22~ 3M 33 3UF3Mm~23 1 2342*3~

3M 223 143 We2.3M3MM 7 282322 3M 3M 33p3M4~3.

  • ~3M2222We 3Mo~ aM ~

7~2- 3M 3M 3.We2~3M 1 I3M3M23~2.

3M 3M 3.2343333232 3Ma 3M W314i28I~223

'3M.- 3M 2~ 33 W343.~i3.23

¶~ 3M 3M Wm328We434

¶ 1282332We 3M 3M 3822.42833.343.

2 223We 2742M 1 7.*M 214.

2 3232 42342 333 21 3.3 3MW 13. 73. 73.

We. - 17 23323 2332 8.232 flU 2? 3533 2253 p17341* 4 2223w 213 22 24M 3323 2737 7 737273 223 27 23*223 2323 24.13 233*~. -- 32 3M 3 6 2ft323 542312 217.32 IA) 231238272382 4 73 542 233 353 3,23 We 3.531 2353, We- 3M 3M 33223Ao*~

  • 52~223 3M 3.33333123.3.3.

7 22834.We34 3M 3.3 W3We~3M 3M 3M 33 33323428.3.

23338.422 3M 3M 333333288.38.

7 32322 3M 3M w*33~We 3M 33 3332833343.

7 ~We 3M 3M 3333213.233.

2W~I3.28. 3M 3M 333332333.

7 73332sh 3M 3M 33332123.323 2 ~3M..123 3M 3M 332.34213234223 7 23123 3M 213 33 2.34323.3.3.

123233233 3M 3M 333333343.

I 33321 2243 2233 I 743. - um 3234 21.a..

2 ~2 5322 2733 21 -u 6 MM 73 213 23 272.35 213 34 37 743 73 33 2MM8823., 1227.

22.73 27*3 3 3*1 3m 71.2J 823343 * ,3 73O 430 28 213 22.3

  • 23 23 43 24 273 215
  • 3 17137 2421 3 3 3.3
  • 4 24444 2 2232.32 372*21 3*3 235 3 27 334.,. 4334 i *t 34I 4,e 3tlS WeIl

'U 32 M~ 73 3.72 247228332733.122

.1.2Z 32327.#23 3)2 334 0 3211 2*732 33 7 2 2 2 2 22 27.43,222 24428.32 3 3 3 33432 3M*

232.427 24.72232 3 313)44 23

- 3321 ~3L ft 33224 33 33.4. Sm 27J 24 31223 71333 332 723.3 233 aM ~3U2 73 2323 3237233.324347 G.3~32.4~3. Th8.328.542343823473537454138.322.21333..

We 223.54 33 *233.8... 22 7332 MUAI 143.2 33 23 23 23 3M 3M 33 223 73.323 731223 3218. 213mM 3M 3532323 21122)223 32737 232.32 3 27*1531 77.22 38.232 A 2.32 73 3.21 72*27 322*7 7*2.32.2 43238 23 227 22.327 738. 43.22.1 V.3..3fl 2138.7.22 237 232243.8. 33 723233.3 24 24*22 23222 2.3 4253 832*2 3.3 63 73.2 733.57 0.38234 3334 3.3 33 3.3 22282 33.3 7223. 332332 22 2 733.2 32~2 743.2 MU 23 23 33 3M 33 3M

~ 8 2533242 2,2273 3M 23.323 22.3 223*33 2222.343

77) 2322233222 Pd A 73 73 733 2.23 3.2.3 23227 2732.32II 3 2173122 24.73,23 2333 33 #3 33 3.2.32. .27.ft 222222.18. We flat 3.

23 332 23 23 3233 232323 .331 42 233 3M 3~3.7 73 733 7543113333327 71333.3.,.37 177227..8.3..23..24.273747242.21*8.*2A2322*2322282*2

.3 733 133 333.333.2124

Usa mm 464 - lmm1. - lUsa - 3551% 21n.

-- - LOAWS. d... 2*4 - V - VS. - LSA. - - -

Us64 Y~ Y~M lmm*4 ~ ILmm64 1.~ 1*4Us Ca. Us Us lb 1s.Us a~5 ~a 12.4 ~i~A Wam l~

  • W.~24 V*4l. 5*.d~ C*412 Tammi Usm5 1445 ~0Us am ma. 48 515 d1 U lam 365 mm as.aja..m a.,.,. nn I14amm Urn junam. ua.inis In IOU 164 56 1.0U 16.16 15 52116 16014 USA1a I.7A Us.a.3~I14U A In Us.m4a. ad Oil l~ I.1. MV.1 ~54ft 3141.114 Usm.1. Us a..

a..

P~

mm 134 13 INasn ,m 13 am

,,,. .m US n.m UISA.aml.,.0llamlU 6* 56mm am 146n lb 015 m. 1 0 4 5 us urn Oem mmtm mm 3E ~.l ImmOiS ~6I MMMI 1445 15*157 ma. lUam .3 6* 26154 am am am am am U

13. 56 5131 U Lam W 115 UsL.UsT A Us im 3665 46*4 46

'1.6.. 6444. ~ ~'1R *56455 am ~1. 5165 14, 53~mm S 1215 311 am. 3I1 am OS LOUs 115 am U~446L22U5*5l22 mm .~U.am 16 41.8 151.053U 22312616 mm bamedd*4 lao. sam ma 15.134 565 13. ~1464 Im 2,6 52146*65.01 a3314 mm Usmm a 654 5.655 U A 215 53 IM 146 a 6 015126 061. 16 1 tin 53 14 446 mm T mm in am 56mm mm 01am3'in U UsM 54.16* am 1* I 16 mm ~ 14 Usd1 224am am 114 I 501 3a. In 106 564*4 mm a.,, ma me mm.. mm..

mm ~ a.~ ~mm.s am ~mma 5166 mm~s mu murams mm

~am am am am am am am U 65 U Il554 5i5 I. mm.aa52.53 A 1514 .m m 0.45 5 ISOZI s a U II6 aIm U 161* Il IA, 5356~ 16 13 W 5.124 am a.amsa.

114mm ad 5-.. 3*4 2*6.1 ~.ft 14.In mm mm.a..& Sm 55, mm mm..am a am am Cm sin 1mm spa. am U13SmUU.U4MM216 mm mm.3~amm 71056 1.aas15sU .sau. .u am am ~d64 I 853 4241512Us.sa.2241 113Me1.a.*4. fraamam.am.,Wa..a..mm5m.a..m.,mbl.2*4e~.14*4.1.

566 ..inam.rn .US 11656 arm am ~wam 1 1~31 *4aa2U.....meU 11*UA.a..Us 1mUs515.ama..am.3..53515Usk3I..*Usmm44~

mm mma.mm~ 4U2m6 22610 165546 11(14 UOSII .604 16 2612 3512Sm.m3U41 14.1)0122.

mm amamamins ¶ IWU 314 mm mm.. mao a. Va.*4.. 03645 I)m.14l a.Sma 10(5

a. 1Jan16 236516*5 211.35 am a641J1 amJaa.3a aW*l40 am am am am am am am mm i mm

.5.2 ma.56smm a 54 lm EN Us am 365*. 46 11am- ... ms Us.in~A 14am.u. mm mm.a.t mm mm mmm 616 044 amIss .a.m. ImAs 20* Us 03*..

inn mm Smab. mail. a.Eain C.0 114Sma 61443 7445 'I, ma ,wm.in ma am am mu miMn maw am am am am mm am am I*~ Oe53 5 16 16 15151 13. am ma l56a. ~ agOem.

mm amm, mm...t a mm mm... L~1. 446.4. 11441.14.

mm mm am mm am talam Irn 44 mm ma. mm lao 0d1 5.45 U 5 am mm ino ,tJm sam**

mm PIn ISo 31(0 54656 046 222 III Cm mm 16 71 4.6 1648 am me mm~ 2*o a.6 013.2 1mm; a..ga rams mm mu n.m am am 18 24163 mm

~a au am am am am am am 14 1.U 1454 Us am 1616 U 64121 114 15.4 *4~ftb 5 4145-. Id ma mm 44a+/- mm~ mmiA. mm mmla.a. mm 55..

mm 53*464 &mm mm.. .6.16 2mm am am ~am I 7151 J..UOSma.65.U1 U8m.Uc4.a.,3. 13m5h..ama.Sm.l1.0*4a.24Us14562*Usmmamam mm mm. mu 6* .me 5126 IU am a...4in~ I 3M 2*U4Imma.U6.U41 11356U.a.a.4'1 amUs0m..am~mmmmmm.m3b56amUsmm1464.

mm mamma in. ,,am mm. mm am am ..4am I 1* lbUUSmasftUsl 123d2122.,..s*.. l4*Us0b444d.mm~5356mmUsfr*42*445-ammst 6146 am me ~ am 36. a.mma ramIla mama maLi Us' WOIWn 1.5146 mm am 11151.3 a.m ,s..lm.u mmoam am am am am am am am 5 Us lm 22122 144 am mm a. 722 1411.222

.u ~

35-. 56

~.,ammmlm.65U1a mm ma siam.. t agm.~ft mama424 mm amlS.L mm mm 535, am 3am lImos an n.am sam. 16 36 UUSma.21.641 14.12146.

5-am. Us 265 456am .6*6 65 liP 36 ~1464. I am l3Ustmmmd1.U41 1236'U,,a..*.. UsUsk1..ams.mmI2*a.444...44.a.s..mbUs.sa64lmm424.mm..

mm in mm ~mm am am. mm as. 61465 ~3. am UUSmUU.64 l1.13Ua1.

mm a43 ~am 156' 6 L.a. SlUm en 16 am 621mm. 30411.120101.

mm mmmm Us uW am mm am am .. am lame.

mm 5-mmmm.. 165 IM5W am inn am 346 6160 I 122.3 25U16mm107111.IVIU, mm 5-amm. UDU LinuS 4am m.56 V.6 Us ~6am In 2233 UIlUsUamSa22l1.152m 6*1 3 am mrn en 16 lISa UU14a.3U41 1511010 mm mm~mm I flU 3SUmU.U~I Wmad1c...in.raa.. 1Us446am1...SbW.514415.&

mm ~bnmamm 4am 2.64 16mm rnn'A UUd1 Sm n. 6.0am 4d5 1015 mm am 215445. mm 36mm. ~1a ~a.s.5 mmV.a 1440 65 *.mamas amom 13112 am laliaM Um6'l) 1613.14 am am am am am am am 151 26*1 1.140 am ama 5444.322 a. 01.113 1122312 ISa mm...... dO.. 5 26 356' Id mm... 064 14. 44.51 1644.414. Sm4. 124 mm ~5~1. p..p mm 5-a64ssa*4, am am am Us s~1.Ms 16 2213 313mSm)1 22322am mm aao-.m.ma am iso U155 2mm 3.3 .4 11456 16 244.4 22135.5..am22U4.14316

SM.5 ~ t.d *441 is~ Se. a- 2Sii~ n.m 5is *5 LiAise - Se. - - - - c ,..we we we we it..amfl

_ a.~a- am Vdt.5 Tame. ame. LamM ydu..M .~

  • Ta CaE tad.~it w55 e.s41 S tea LU. ama .m am sim issama in ii, us. am an am a aim in us ammamita*ittu.

amamama a ui am am 517 5 Lam itO m.m ma,.eg..alsamamnin ama.~. a a am am s.ai a Lam in intL.a.urniwits am 5A54 tArn am 1ZS is.im Sm 58 arnams. Uft14UM meisaise.~ 'U 4 am. - am in am in am amam amm am~amam in a ama sam t.t am am in us a--Se. em asia saw as. am am in am 4.4 at, am am.. am amam. ., is ama.a va.a a- am UP 4.4 MM ist17~ Wb 3mm am a. am MM mm MM MM Imamama U MIII U an -

iA7 La l aIa am SM etVkl Uee.,WlR&r am gw L ftp

- e Llama am1eo Ifl am itO 38 m*rnamm Ui5i54 SM La- itO iU Uit.a.UU&istlSM sew us 3m 18 GM MisiM~IiU3i4 U-am is~a. e.~ Md-. a-a. Tg.) ~5 ~t a- 4M 5W LuG MM Ig.7i SIMM Ugt4 a-am am am am MM MM MM MM ut amamam a a in MN a am MM mi. w aiUtua SiM wiam. am.. U' am sews.. MM4.g weaa wesseft am V~wet am ftP am. am ti7aa MMO 141345 .34g. IMMU sin aI a.,ma iN US? SMTwaMesisuMi3.iTI

-MN MN Ut?

we. am... a- ,a~am.e a-wi am..., am.. ra.)

a- reaM g.e gas Siam.,. Ms.u.4 .saain a-- am an MM tam mm MM as am.ame.am. a N IM USS Ut ma ma uw.tit 116455 vga- am. sE tam. Am.g.I ve.a. ft mama am e..gwet e pJ a- Im* LI. SimM Mu. MN Lit am .. 3m i ii) e.mUa-u.ggsi IIIS.I.asi.e.a. lis.aa55esMmammewaiam....55amam..a..ie.am.ama.

Ca ita simm -a.. an an MM isEim I tit 4~mt2S.ese.g.U4i g.Um.a.is...a~ tgsis41.minamaiam...a.e.amams.am.amam am weIIam u.n mm. use an am se in am g a- a-sm. OASiS 05g. Gig iii am sa in am ama a- am 3am mm. me ssi am SM W.Mi2am..mU41 ttn~M.is..u~. ThSaGM.Mewa.u.iam.u.hewa.igteemamw..am.mewam a- a-ait a m em. letS lit ii asistam in SAC s~in~ins.

a- is' Nm. mm am in ta in in am U- MUam a it am. am am Ii -~ U iam a- tiaSi il.USI. IGaSa IASM NI Mn weams in aatIam..Uusi la4aamm,, ewa. T*a5.nea-eU-.m.amammamewsamvgame.ams..saa.

a- sun am am am am bis in am am sun in we a-.. itim ~E amiss Ts.I US.t Ta.)

we 41MM ami in tan sauw 1)91* Mmii em am GM MM Urn MM MM Tae.a-u.I...in...bGeCa u.n in item ai Siam g awam u.S a-am a-a.a.05.

  • am. a -

iii .. eam

  • am- . is..

$ am S5l is e. 24 5s tat a-a41e.. us am- a "is I am-I.amltm *in'.

Sat a-RE a-a-a- it am. si a. a ktl vlsl a

a-.. amm mm isa-a U ewam- 535mm

'is amIMa-~ iS igamue...hadaa ii A 5it~ Sm is@8 a am an am a am am am mm m U w u a g.m iit.5 .44we4.u A 54N iM isism a gin g.m tEb~. tam *EU..iS am am we amg.a am.s.a am a-suet am NP we aim am em SM lat seMise. SM lit aainwe.siuas.,sw 5s' aim ama am am am isg.fra ItO U IMweainU S.5)S an am ltD am ag.g.a 5W MiMg.W a-4.55V amw...it. G~a. sil Ta.5 saweesam 5551mn tam en mmn N5iMa-Mmi4Stam a-a sam ass anma-nmu.stin.smaai uazeia is it a 11613 aiIm nmi am.aisU c~a I amawama.. MI. ama-am....

I eweamew MM amam~a-.a S samaa-a-a son ama-am....

amaamseam UI. a-a-a-am.a I GitO....5 MN amama-ame.m si am. MM ama-a-ama..

I ama- MM ama-tame....

I ama-I bia5sa-am MM simawia-.....

MM ama-a-ge..

I a-a.a- MM ama-a-am.

S~5mis3isThM lam ama-a-gm

IWIdO1w

¶ dI Sm m I 2~*m

~m 71 LJ

  • m
  • 6 116 1124514 IC
  • I~16 84453 ~

A 316 *16 316 S 3471 16*12 *443 1*461 S.* 36 2*13% ft~ C 3%~

2 6144* 3 ¶16 *145 3 S 11316 14 116 3.13 3 I 6*1646 3 *16 14.13 3 4 3 34*3 3

ENCLOSURE 2 TO OMY-15-053 CERTIFICATION OF FINANCIAL ASSURANCE

CERTIFICATION OF FINANCIAL ASSURANCE NRC Licensee:

Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 72-30) 321 Old Ferry Road Wiscasset, ME 04578-4922 Issued to: U.S. Nuclear Regulatory Commission Certification:

I hereby certify that Maine Yankee Atomic Power Company is the licensee for the Maine Yankee Independent Spent Fuel Storage Installation (Maine Yankee ISFSI) and that I, the undersigned, am authorized to provide this Certification of Financial Assurance with respect to the radiological decommissioning of the Maine Yankee ISFSI.

During the operation of this ISFSI, spent nuclear fuel and Greater than Class C waste will be stored at the Maine Yankee 1SF SI in storage casks licensed under 10 CFR 72. Pursuant to contracts with the Department of Energy the spent fuel and associated casks will ultimately be removed from the ISFSI location, and Maine Yankee will dispose of other radiological waste in accordance with NRC regulations, at which time the Maine Yankee ISFSI will be decommissioned in accordance with NRC regulations.

I further certify that financial assurance in an amount sufficient to fund Maine Yankee ISFSI radiological decommissioning at the time of such decommissioning has been provided, pursuant to 10 CFR 72.30, as described in Enclosure 1 to the letter to which this Certification is attached.

That radiological decommissioning funding assurance is premised on a site-specific decommissioning cost estimate and funding methodology described therein, in the amount of:

Maine Yankee ISFSI $21.6 million (in 2015 dollars, inclusive of contingency)

Carla M. Pizzella Maine Yankee Atomic Pd rer Company -

Vice President, Chief Financial Officer, and Treasurer -,

Phone (860) 267-6426 x304 Corporate Seal Date \ *1t

ENCLOSURE 3 TO OMY-15-053 TOTAL COSTS ASSOCIATED WITH THE HNP ISFSI, INCLUDING COST ESTIMATE FOR MANAGING IRRADIATED FUEL AND GTCC WASTE

Maine Yankee 12222015 2013130? Budget MaineYankeeAtonioPeoenrComanry SpentFeelManagennntand ISF21 Dnem Estimate

-OEC~sanmeal Sumof62060 Sumaf2all Somal201 Sumneoele¶ Bumne2020SanneOOOI25umof202~2 Suofoe2022 S~oaeel02 5wna62025 5umno62226 Suno62027 Sumnol202a 9ame12029Sumoe62010S~onnelOt smonteta3a aunnaof20 SrnetTalteale20132e et5.5sa $ 455.3701 4220947$ 474,522 $ 4L55.270 522,216 2 2 452,271 5220,21 3 502,202 $$ 455.270 022.216 0 2 455,371 520,202 2 5052,216 2 425.754 455,371 $ 5 455,371 54,219 $$ 452,271 522.216 $$ 532,216 $

4552371 592,219 0

$ 422.232 $ 1,52487e2 222016$ 9,126.822 522,216$ 55.O200 $ 522,2106 50222160 505.21$ 0 231,929

.abat.-Sn-Manual 1,943,522$ 6.203,205$ 1.243,20 $ 1.043.922 1,203.922$ 1,843,9060 1,823.922$ 1,84532*62 1.043.922 5 1.543.922 1,243,326$1,943.902 $ 1,843,922$ 1.943,222 $10.43.222 $ 1.23.92,36$ 277.923$

1.,02.,376 2.750.762$ 3.225.704$ 3.225.724 3.025.704 $32025,784 latlrniab Supple. 105,0473 52,125$ 22,025$ 92,125 $ 162,247 3 22,1225 92.025 $ 92[2,12 92,122 $ 92,125 5 0,125 $ 2,0225 92.125 $ 22,025 5 2,122 $ 92.0225 Ila,274$ 113.207 $ 113.074 5 113.274 $ 113.074 52,12352 552.223 $ 552,9223 522.223 $ 552,223 9 052,2232 5029,2 $ *92,922 5523238 0 5529,93 0 52522 $ 552,523 529,923 $ 2359293$ 5529,223 052,222 241.525$

3o22d* Serreos- FuelLeedina - $ - $ - . $ 722301,25

)22asoSaraos-ISF510CPa 3.932.2355 7322282 725.203 $ n4.590 90,727$

305.272$ 219,2728 75348235 424,621 2 205,076 2 205,272 2052372 215,372 0 0.0323.04 $ 215,372 205,272 210,272 215.279 424,221 0 723,8230 2,1092.470

>226ad aauoans- 222-RAiD252 atl1FSl - $ - 3 - $-

. . .. $ -" " $ $ " $ . .. 6,212,2..

17,5222221 Dupaaa Saeraica

-29 P6DDaloISFSl - $ - $ 6 3 - 3 -$

- $- - $ 2- $ - $ . 0 - $ - $727.522$14.el,.32o 6,14.2352, 1,.0229$22 1,022,2229 0,222.2229 1.0802222$ 1.040229$ 1.0802.32$ 1.0222250,2,229$2 0,022,229

$ 0.9222229$0.022229$ 0.002.222 0.020.229$ 1.222291,80229 0 1.08022,229 logulalaryFe,. 225,275$ 225.275$ 225.2752 25.275 5 825,975 9292068$

612.452$ 1.921225e 018.4522 112,4258 118.452 112,452 OIlo45 112,452 $ 118,4,58 116,452 012.402 019.452 108,4528 112,452 112,452 011.4528 161.5342 226,22$

OrancdTotal $ 12761494 $ 12606G7208 9162222361220992282 $ 91992492 $ 8i522263$ etE62r78$ 69r22780$ 96*2r780 $ laal10e8n 6 95622760$ e912172e0 29626278$ 892.21700$ 9242i6 $ 22202337a32$2i316010 $ 0 946123 0 ieeoo26uae Noba6:75 et etmanagae~nt afIrtdiulodfustandGTOC Costes clonnatadastosaa:

$ 004.722,222GrandTotalfSomajbooo

$ (9.013.2021Naon-Rd 0&DISF51 L.25571Rod 022ISF51

$671,217,616Managesrnantallradluled Fuela*d 2722Waste Noloa2:Th~olestofRAD andNsN.RAD 56BoftherSFSlpn201adlodaas auproidedpodhaealunes labalad"Sumaot2203Pand"Sunlot2203T"Isaeorved by esaaua~ngtvalUeofth~eaO*stn espn~osrodsdn E~ondor027y2.5%.

N90o 3: Ti~sSarononC32rles MOYe 2013Approaod0365RoleCaserai thaKnightCostEnginoeelng Seslos 2215RAGendNO2N-Rud 0S700 DoamCostEusnoate

Maine Yankee 321 Old Ferry Road, Wiscasset, Maine 04578 December 16, 2015 OMY- 15-053 Re: 10 CFR 72.4 and 10 CFR 72.30 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-000 1 Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 50-309)

Subject:

Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan Pursuant to the requirements of 10 CFR 72.3 0(c) and 10 CFR 70.4, Maine Yankee Atomic Power Company (Maine Yankee) is providing the three-year update to the Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Funding Plan (DFP). Enclosure 1 updates the Maine Yankee ISFSI decommissioning cost estimate and the cost estimate for the management of irradiated fuel and Greater than Class C Waste submitted with the original Maine Yankee ISFSI DFP on December 17, 2012 (Reference 1), as revised on January 8, 2013 (Reference 2). It includes adjustments to account for changes in costs. The update does not include any adjustments for additional radiological contamination, because the extent of radioactive contamination at the Maine Yankee ISFSI remains unchanged.

10 CFR 72.3 0(c) defines specific events that must be considered in the subsequent updates.

Since the submittal of the original Decommissioning Funding Plan for the ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISF SI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.
4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

In addition, Maine Yankee complies with the requirements of 10 CFR 72.30(b)(1) through (b)(6), as follows.

Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 2 10 CFR 72.30(b)(1) requires the licensee to provide "information on how reasonable assurance will be provided that funds will be available to decommission the ISFSI." Maine Yankee has established an account within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological Decom," that segregates the funds for decommissioning of the ISFSI from the larger balance of funds for ongoing management of irradiated fuel and GTCC waste held in the NDT. Currently, the trust has sufficient funds to meet the revised DCE for the Maine Yankee ISFSI.

10 CER 72.30(b)(2) requires the licensee to provide a detailed cost estimate for decommissioning. Enclosure 1 provides a revised DCE for the Maine Yankee ISFSI that:

1) Utilizes an independent contractor to perform the decommissioning activities in accordance with 10 CFR 72.30O(b)(2)(i); 2) Includes an adequate contingency factor in accordance with 10 CFR 72.30(b)(2)(ii); and 3) Includes the cost of meeting the criteria for unrestricted release in accordance with 10 CFR 72.30(b)(2)(iii). In addition, the revised Maine Yankee ISFSI DCE specifically considered the effects of the events described in 10 CFR 72.30(c) on the costs of decommissioning and the extent of contamination. The revised Maine Yankee ISFSI DCE estimates the total cost to decommission the Maine Yankee ISFSI to be $27.4 million and $28.1 million (in 2015 and 2016 dollars, respectively), inclusive of radiological and non-radiological removal.

10 CFR 72.30(b)(3) requires the licensee to identify and justify the key assumptions contained in the DCE. Enclosure 1 provides the revised DCE for the Maine Yankee ISFSI, including the key assumptions and the justification for their use.

10 CFR 72.30(b)(4) requires the licensee to provide a description of the method of assuring funds for decommissioning from 10 CFR 72.30(e), including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. Maine Yankee will periodically reassess the decommissioning cost estimate in accordance with 10 CFR 72.30(c).

On a periodic basis, Maine Yankee will submit rate cases to Federal Energy Regulatory Commission (FERC) that will include revised cost estimates for decommissioning and the management of irradiated fuel and GTCC waste. If necessary, additional funds may be recovered from the purchasers.

Maine Yankee has successfully litigated a couple of breach of contract damages claims against the Department of Energy (DOE) for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998. A third breach of contract damages claim for the period 2008-20 12 is with the federal court for decision and additional damages claims against the DOE relating to the government's breach of contract are expected to continue as long as the irradiated fuel and GTCC waste remain on site.

Annually, Maine Yankee submits the reports required by 10 CFR 50.75(f)(2),

10 CFR 50.82(a)(8)(v) and 10 CFR 50.82(a)(8)(vii) to establish how it satisfies the obligations defined in those regulations regarding the assurance of decommissioning funding and the status of funding for the management of irradiated fuel.

Maine Yankee Atomic Power Company OMY- 15-053/December 16, 2015/Page 3 10 CFR 72.3 0(b)(5) requires the licensee to define the volume of onsite subsurface material containing residual radioactivity that will require remediation to meet the criteria for license termination. No subsurface material is assumed to require remediation regarding radionuclides.

This is justified because: 1) the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the ISFSI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters; 4) nuclear activation of the Vertical Concrete Casks (VCCs),

VCCs liners, and ISFSI are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent.

10 CFR 72.30(b)(6) requires a certification that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning. Enclosure 2 provides the certification of financial assurance.

In addition, Enclosure 3 provides an estimate of the total costs associated with the Maine Yankee ISFSI for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI through 2033.

A summary of the revised DCE and the cost estimate for the management of irradiated fuel and GTCC waste at the Maine Yankee ISFSI will be incorporated into the Post-Shutdown Decommissioning Activities Report (PSDAR) and the License Termination Plan (LTP).

If you have any questions, please do not hesitate to contact me at (860) 267-6426 x304.

Respectfully, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer

Enclosures:

1. Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation
2. Certification of Financial Assurance
3. Total Costs Associated with the Maine Yankee ISFSI, including Cost Estimate for Managing Irradiated Fuel and GTCC Waste

Maine Yankee Atomic Power Company OMY-15-053/December 16, 2015/Page 4

References:

1. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012 (OMY- 12-073)
2. Letter from C. Pizzella (Maine Yankee) to Document Control Desk (NRC), Revised Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013 (OMY-13-003) cc: D. Dorman, NRC Region I Administrator R. Powell, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager P. 1. Dostie, SNSI, State of Maine J. Hyland, State of Maine

ENCLOSURE 1 TO OMY-15-053 DECOMMISSIONING STUDY OF THE MAINE YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Decommissioning Study of the Maine Yankee Independent Spent Fuel Storage Installation Prepared for Maine Yankee Atomic Power Company Knight Cost Engineering Services, LLC November, 2015

Knight Cost Engineering Services, LICKCS25-20-30Rv0 KCES 2015 - 2015-300Rev. O Table of Contents

1.0 INTRODUCTION

............................................................................... 3 2.0

SUMMARY

...................................................................................... 4 3.0 DECOMMISSIONING COST ESTIMATING APPROACH ............................ 7 4.0 ASSUMPTIONS................................................................................. 8 5.0 SCHEDULE ....................................................................................... 10 6.0 PROJECT MANAGEMENT ....................................... ........................... 12 61 OVERSIGHT STAFF................................................................................. 12 6.2 DECOMMISSIONING GENERAL CONTRACTOR ............................................. 13 6.3 SECURITY ............................................................................................ 13

7.0 REFERENCES

................................................................................... 14 APPENDIX A............................................................................................ 15 Page 2 of 15

Knight Cost Engineering Services, LLCKES25-20-30Rv0 KCES 2015- 2015-300 Rev. O 1.0 INTRODhUCTION The purpose of this study is to identify the costs associated with the decommissioning of the Maine Yankee (MY) Independent Spent Fuel Storage Installation (ISFSI). This estimate includes only the structures, systems and land within the NRC licensed area. The MY ISFSI is located within the site boundary of the former Maine Yankee nuclear power plant in the Town of Wiscasset, Maine. The site is approximately 1200 feet north of the former plant site in an area used as a vehicle parking lot. The NAC-UMS fuel storage and transport canister system chosen by MY is licensed by the NRC for both storage and transportation.

The ISF SI consists of the storage system and concrete storage pads, a Protected Area (PA) for spent fuel storage and a Security/Operations Building for equipment and staff. The PA contains 16, 3 foot thick concrete pads, each 31 feet by 31 feet. There are 64 dry storage casks on the 16 pads, 60 for spent fuel and four for sections of the reactor vessel internals that are classified as Greater Than Class C (GTCC) waste. Each vertical concrete cask has a two and a half-inch steel liner surrounded by 28.3 inches of reinforced concrete.

Page 3 of 15

Knight Cost Engineering Services, LLCKCS21 20-30Rv0 KCES 2015 - 2015-300 Rev. O 2.0

SUMMARY

Decommissioning is the safe removal of a facility or site from service and the reduction of radioactivity to a level that permits either the release of the property for unrestricted use and NRC license termination; or a restricted release of the property and NRC license termination. This estimate includes all costs incurred to release the property for unrestricted use.

On June 17, 2011, the NRC published a final rule amending its regulations to improve decommissioning planning. The rule became effective on December 17, 2012. This rule requires licensees to report additional details in their decommissioning cost estimate. To assist in the implementation of the new rule, the NRC issued NUIREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness."

NUREG-1757 does not apply to licensees under i0CFR Part 50 nor does it eliminate the need to follow Regulatory Guide 1.202 or NUJREG-1713. It does provide additional information to support the development of the cost estimate. This cost estimate was prepared in accordance with the guidelines provided in RG 1.202 and NUREG-1713. In addition, it does take into account the guidelines identified in NUJREG-1757.

NUJREG- 1757 specifies that a contingency of 25% is to be included in the estimate. This estimate takes exception to this contingency level for two reasons. First, the estimate is conservative in that the entire storage pad, concrete overpacks and overpack liners are assumed to be disposed of as potentially contaminated. Second, the MY site has recently been successfully decommissioned, and the land released from the operating license, with the exception of land associated with the ISFSI and laydown area. The lessons learned from that project will be incorporated in the MY ISFSI decommissioning. For this reason it is felt that a 10% contingency is adequate to cover unknown and unplanned occurrences.

The original Decommissioning Funding Plan for the Maine Yankee Independent Spent Fuel Storage Installation (ISFSI) to comply with 10 CFR 72.30(b) was submitted on December 17, 2012, with a revision submitted on January 8, 2013. 10 CFR 72.30(c) defines specific events that must be considered in the subsequent updates. Since the submittal of the original Decommissioning Funding Plan for the Maine Yankee ISFSI in December 2012:

1. No spills of radioactive material producing additional residual radioactivity in onsite subsurface material have occurred.
2. Facility modifications that affected the ISFSI, including those that were implemented within the licensed area, were assessed for impact.
3. There were no changes in authorized possession limits.
4. No active decommissioning has occurred, thus, there have not been any actual remediation costs that exceed the previous cost estimate.

Page 4 of 15

Knight Cost Engineering Services, LLC KCES 2015- 2015-300 Rev. 0 The total cost including contingency is $27.4 million, $21.6 million for radiological removal and

$5.9 million for non-radiological removal. Table 2-1 provides a summary of costs. Cost details are provided in Appendix A TABLE 2-1

SUMMARY

OF COSTS Non-Radiological radiological Total Cost Removal $ Removal $

Grand Total Building $27,423,524 $21,556,946 $5,866,578 Tax on General Contractor $0 $0 $0 General Contractor with contingency $17,757,734 $13,958,910 $3,798,824

$9,665,790 $7,598,036 $2,067,754 Site Costs with contingency

$16,143,394 $12,689,919 $3,453,476 General Contractor Site Costs $8,787,082 $6,907,305 $1,879,777 MY ISFSI $24,930,477 $19,597,224 $5,333,253

$15,126,261 $11,890,375 $3,235,886 PERIOD DEPENDENT COSTS 1.1 MY Site Costs $8,787,082 $6,907,305 $1,879,777 1.1.1 Project Management $4,111,355 1.1.2 Security Staff $2,303,834 1.1.3 Fees $719,678

$565,721 $153,957 1.1.4 Insurance $582,818 $458,139 $124,679 1.1.5 Legal $200,000 $157,215 $42,785 1.1.6 Property Taxes $869,397 $683,411 $185,986

.1.2 General Contractor $6,339,179 $4,983,070 $1,356,109 1.2.1 Decommissioning General Contractor S3,344,685 1.2.2 Waste Packaging Crew $1,062,680 1.2.3 Equipment & Materials $1,931,813 ACTIVITIES $9,804,216 $7,706,849 $2,097,367 1.3 Project Engineering $12,346 $9,705 $2,641 1.3.1 Procedure Development and Review - Offsite $6,173 Preparation of QA and Safety Documents -

1.3.2 Offsite (in parallel with 1.2.1) $6,173 Site Mobilization and General Employee Training (GET) $95,166 1.4 $74,808 $20,358 1.4.1 Site Mobilization $23,364 1.4.2 General Employee Training $65,348 1.4.3 Site Specific Training $6,455 1.5 Site Preparation - Performed by Staff $12,025 $9,452 $2,572 Page 5 of 15

Knight Cost Engineering Services, LLC KCES 2015-2015-300 Rev, O

SUMMARY

OF COSTS, continued 1.5.1 Initial site Survey 1.5.2 Setup work areas

,1.5.3 Decontamination Readiness Review 1.6 Disconnect all utilities to work areas. $6,012 $4,726 $1,286 1.6.1 Electrical $3,006 1.6.2 Ventilation $1,503 1.6.3 Piping $1,503 1.7 Removal inside fences $8,082,872 $7,570,361 $512,511 1.7.1 Remove compacted gravel $371,230 $371,230 1.7.2 Remove VCCs $5,464,765 $5,464,765 $0 1.7.2.1 Exterior Concrete $3,651,744 $0 $0 1.7.2.2 Steel liner $1,813,021 1.7.3 Remove Concrete Pad $2,105,596 $2,105,596 1.7.4 Remove Security Fence $63,016 $63,016

'1.7.5 Remove Light Towers $7/8,265 $78,265 1.8 Removal outside fences $1,539,000 $1,539,000 1.8.1 Security/Operations Building $561,356 $561,356 1.8.2 Remove paved area inside nuisance fence $.86,508 $86,508 1.8.3 Remove nuisance fence $73,685 $73,685 1.8.4 Miscellaneous Pads $79,464 $79,464 1.8.5 Miscellaneous structures $419,709 $419,709 1.8.6 Remove buried utilities $153,213 $153,213 1.8.7 SOB electrical service $8,815 $8,815 1.8.8 Remove road inside licensed area $140,067 $140,067 1.8.9 Remove vehicle barriers $16,184 $16,184 Final Site Survey Structure gone - By DGC 1.9 Staff $25,000 $19,652 $5,348 1.9.1 Prepare Final Status Survey Plan 1.9.2 Soil Sampling 1.9.3 Direct Survey 1.9.4 Sampling Analysis 1.9.5 Prepare Final Status Survey Report 1.10 Orise Site Release Confirmation 1.11 Outside areas $8,712 $8,712 1.11.1 Backfill, grade and seed $8,712 $8,712 1.12 Demolition Crew Demobilization $16,909 $13,292 $3,617 1.13 Final Project Report- Offsite $6,1]73 $4,853 $1,321 Page 6 of 15

Knight Cost Engineering Services, LLCKES21-20530R.0 KCES 2015- 2015-300 Rev. O 3.0 DECOMMISSIONING COST ESTIMATING APPROACH Two types of costs were determined in this estimate: activity costs and level of effort costs. The activity costs were developed utilizing a unit cost factor approach. Site material quantities for concrete, steel and equipment where developed from site specific drawings. Productivity factors were applied to these quantities to determine activity durations. Labor crews were developed and applied to the material quantities to determine labor costs and person-hours. The activity durations were used to develop a project schedule.

The level of effort costs such as equipmenit rental and the General Contractor (GC) staff were developed based on the project schedule duration. A rental equipment file was developed for the construction effort. The GC staff is assumed to be on-site for the duration of the project. The Oversight staff cost is another level of effort cost that. is included in the cost estimate.

Bulk removal of the storage pad and concrete storage casks is assumed to be performed using an excavator with a hydraulic hammer attachment. The steel liner will be segmented utilizing torch cutters. All of this waste will be trucked off-site for processing. This leads to a large disposal volume; however, at a lower rate for bulk processing than for direct burial. In addition, there will be far less characterization and iterative decontamination. Clean structures will be demolished using mechanical means and disposed of at a local landfill.

In addition to the removal labor there is a dedicated waste packaging crew included in this estimate.

This crew will consolidate, package and prepare containers for transportation. The waste packaging crew is estimauted to remain on site for the duration of the project. This crew consists of 2 laborers; 1 Health Physics Technician; 1 Equipment Operator and 1 Foreman.

Page 7 of 15

Knight Cost Engineering Services, LLCKES21-20530Rv0 KCES 2015 - 2015-300 Rev. O 4.0 ASSUMPTIONS Following is a list of assumptions developed by KCES in completing this study. These assumptions are based on the most current decommissioning methodologies and site-specific considerations.

1. Component quantities were developed from actual plant listings.
2. Concrete volumnes were developed from plant drawings.
3. The oversight staff is assumed to be similar in size and configuration as it is currently.
4. The oversight staff positions and costs were supplied by the Company and represent September, 2015 salary and benefit data.
5. Subcontractor base labor rates and fringe benefits were taken directly from the 2015 R. S. Means Heavy Construction Cost Data and adjusted to Maine based on the City Cost Indexes for Bath, ME.
6. Activity labor costs do not include any allowance for delays between activities, nor is there any cost allowance for craft labor retained on-site while waiting for work to become available.
7. All skilled laborers will be supplied locally and hired by the Decommissioning General Contractor (DGC).
8. The cost for Utility personnel assisting the DGC to develop decommissioning activity specifications is included in the Utility Staff costs.
9. The separate DGC staff salaries, including overhead and profit, were determined by KCES.
10. Transportation costs for LLW are included in the bulk disposal rate.
11. The ISFSI Concrete Pad, VCC exterior concrete and VCC liner steel are assumed to be low-level radioactive wastes that will be disposed of at the Waste Control Specialists facility in Texas (a licensed facility) at $0.25 per pound.
12. The following buildings are disposed of as Clean waste in local landfill. A disposal rate of $91.80 per ton has been used in this estimate and is based on information provided in the 2015 R. S. Means Building Construction Cost Data.

Compacted gravel around pads Security Fence Light Towers Security/Operations Building Paved area inside nuisance fence Page 8 of 15

Knight Cost Engineering Services, LIC ES01-21530Rv0 KCES 20!5 - 2015-300 Rev. O Nuisance fence Miscellaneous Pads Miscellaneous structures Buried utilities SOB electrical service Road inside licensed area Vehicle barriers

13. All costs used in these calculations were current on September, 2015.
14. The costs of all required safety analyses and safety measures for the protection of the general public, the environment, and decommissioning workers are included in the cost estimates.
15. It is assumed that all UMS canisters containing both spent fuel and GTCC will have been removed from site prior to the start of decommissioning.
16. Property taxes are included in the estimate at the current cost of $869,397 per year.
17. Fees are included in the estimate at the current cost of $719,678 per year.
18. Insurance costs are included in the estimate at the current cost of $582,818 per year.
19. Legal costs are included in the estimate at the current cost of $200,000 per year.
20. The decommissioning will be performed under the current regulations.
21. Removal of the pad and concrete overpacks will be performed in Tyvek coveralls.

Productivity rates have been adjusted to account for this.

22. The removal of the berm is not included in the estimate.
23. No subsurface material is assumed to require remediation regarding radionuclides. This assumption is justified because: 1)the ISFSI area was confirmed to be clean of radiological contaminants prior to the construction of the 1SF SI; 2) the ISFSI area will be maintained clean of loose radiological contaminants during the storage period; 3) the irradiated fuel and GTCC waste are stored in sealed canisters; 4) nuclear activation of the VCCs, VCCs liners, and ISFSI pad are anticipated; the activation products will remain fixed during the storage period; and 5) if contamination of subsurface material occurs during decommissioning activities, the contamination is expected to remain below the decommissioning criteria of 25 millirem per year Total Effective Dose Equivalent Page 9 of 15

IKnight Cost Engineering Services, LLC KE 2015-2015-300 KCES 05 0530Rv Rev. O 5.0 SCHEDULE A scenario-specific schedule has been developed for estimate.

Activity durations were determined based on the unit cost factor approach. Plant material inventory quantities were developed from site specific material. Unit rates for cost, man hours and schedule hours were applied to the material quantities. From this calculation the removal or decontamination cost, total man hours and total schedule hours were detei'mined for an activity.

The schedule hours are then entered into the schedule to determine project duration. Two work crews are assumed for the concrete pad and concrete overpacks. All other work was assumed to be performed by one crew. Work outside of the security fence will be performed in parallel with the work inside the fence. The total project duration is 17.97 months.

Figure 5-1 provides the detailed decommissioning schedule.

Page 10 of 15

Knight Cost Eri[ineering Services, LLC KCES 2015- 2015-300 Rev. 0 Figure 5-1 Project Schedule

  • I C]* air i use .yi rev i r.u Si -, I

__l_

2-i- a5*8 Eus0'am ay 3

t1C n-dlaiPpi~ay SitellDydITdelgI tdld*! Wb oes at--"

eedraud6 w,* r INgig,S Devesaaaladbvew-Otedays Sb elseds.TtW 8S s ft4*ue b'mewt a m 6day 4ays de1r Idap dayl 1 da 1$. 1114 Thu'1/11114 ThjIl6114 The111411 Woe 112114 Ff1d22/14 Mera 1/27114 We.* 1Wa4.

Wed 1/6*/14 WTu 11131/14 Mn 111611 The 1111114 flu 1/N4/I4 655 1117)14 I

I jj beilt81 8 t we/iitma.lS aye Tim 1/2N14 Wed 1/3144 11I da. 1iae1114S Tee 1111 ml I , I

  • 14 66041*I*Fm IIII I Vee n:.8 0*Tdais PWed1261 Wed 11111 I

beedledd be m 58/ ayeS Tlsi1/'114 Pt 4r/411W St  ::::::-::::::::*.*-~**-*~**~-'**'~-.*.*.-.-.*.-.-..

  • blU 4i* ell~n 60Tday" TIs'Wi261 'Wed6/1--

Stedm, 14,1.U days flwh/23/4 Pit116/4 IIw 21 aeee slaPdllu 48.1$ dais I 741/714 Man 216/14 IRemsee Sbslylala ra 7I days 16.3d Tis 3I/II/j4 Fit 3t148

  • Mtie Gemeeedw lays Tee s Pt 111 w/11
:1 l:1 iUMM* *U1561IUON21t,7 aeys P14111 Tue 6/13/1 M~

0MflatUm C FadWne 64 bcye Tne6/3/4 s we6/7/1 Page 11 of 15

Knight Cost Engineering Services, LLCKES21 20-30Rv0 KCES 2015 - 2015-300 Rev. O 6.0 PROJECT MANAGEMENT There are three components to project management during decommissioning, Oversight Staff (staff), Decommissioning General Contractor Staff (DGC) and Security. The person levels for each are identified below.

6.1 OVERSIGHT STAFF The staff size is assumed to be maintained at the current level and at a similar configuration during the decommissioning. In addition, the staff is augmented with one final status survey resource and one licensing person to assist mnthe decommissioning. The staff will provide DGC oversight as well as maintain license compliance. Table 6-1 provides a summary of this staff.

TABLE 6-1 OVERSIGHT STAFF Staff Number President 1 Cask Relicensing Project Manager1 Workers Concerns Manager 1 Director of Operations I ISFSI Manager 1 ISFSI QA Manager 1 ISFSI RPM I ISFSI Operations Specialist 1 ISFSI Administrator 1 Licensing Specialist 1 FSS Manager 1 ISFSI Technical Specialist1 Assistant Director of Operations 1 Program Manager I Program Manager 1 Program Manager 1 Public/Government Affairs 1 Regulatory Affairs 1 General Counsel1 Licensing EngineerI VP CFO & Treasurer Business Administrator 1 Accounting Manager I Sr. Accountant 1 Sr. Accountant 1 Benefits 1

  • IT Services 1 Security Manager1 28' Page 12 of 15

Knight Cost Engineering Services,. LLC KE 2015-2015-300 KCES 05 0Rv Rev. O 6.2 DECOMMISSIONING GENERAL CONTRACTOR The DGC will be responsible for all of the physical work. The staff will oversee the work crews.,

schedule work and supply HP support. The DOGC will be responsible for finishing the project on time and on budget. Table 6-2 provides a Summary of the DGC staff.

TABLE 6-2 DGC STAFF 2015 Base Man Position Salary. Level Project Superintendent $200,000 1.00 QA Auditor/Inspector $64,000 1.00 Health & Safety Supervisor $89,205 1.00 Packaging/Shipping Specialist $66,522 1.00 Cost Control Accountant $65,071 1.00 Scheduler II $65,000 1.00 Demolition Specialist $56,000 1.00 industrial Safety $67,000 1.00 Engineering Supervisor $113,000 1.00 Project Supervisor $81,000 1.00 Decontamination Tech $35,000 2.00 Instrumentation Tech $42,248 1.00 Tool Crib Attendant $33,976 1.00 14.00 6.3 SECURITY Once spent fuel and G3TCC waste are removed from the site the security force will be significantly reduced. This estimate assumes a force of 13 guards, four supervisors and one manager. This will allow a security person level of 5 guards during work time and two guards all other times. . While this staff level may be high for industrial standards, we have decided to maintain the security staff at conservatively high level. The guard force was assumed to consist of various levels of guards and the rate used has been adjusted accordingly.

Page 13 of 15

Knight Cost Engineering Services, LLCKCS01 21530Rv0 KCES 2015 - 2015-300 Rev. 0 7.0 REFER]ENCES

1. R.S. Means, Inc, Building Construction Cost Data, Kingston, Massachusetts, 2015.
2. Regulatory Guide 1.202, "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors"
3. NUREG-1713, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors"
4. NUREG-1757, "Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping and Timeliness"
5. 10CFR 72.30, Financial Assurance and Recordikeeping for Decommissioning
6. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated December 17, 2012.
7. Letter form Carla Pizella (MY) to Document Control Desk (NRC), Independent Spent Fuel Storage Installation Decommissioning Funding Plan, dated January 8, 2013.

Page 14 of 15

Knight Cost Engineering Services, LICKES21-20-30Rv0 KCES 2015 - 2015-300 Rev. O APPENDIX A Page 15 of 15

iii W.* i. 5 55 i' SI. (55 S S Ws lu0ls 11 an~ms*I.a *mt i55ta~i.5lli m um~ 5am a-.- la saUs UsaOW Usas4 tarn.. tiiw 5-~l iairnn oa

  • unsta i~hl*JS aSjami ma. mm. simmml -

arm mut*

-- a-ll i+i almios sa wliiis 7. 13 -

eta. ii.iiim.

is Dma.~W (5.5W CM 5W. Ma inn mm lasH. Haul 1114.3 i win mm urns ma? sum iU urn mm u.s mm 2,1mm 'a ma mm testis usia 5Mm in taul Minis sum sam tans muss a.tnu us Imum.ill urn mm wins u.N. 271mm Ia urn mm u.s mm &itam in arm mm turns Hams 11143 iM isa mm tans stUns 2It4 in sun m iu.ns ass. ,,tti.u in urn mm inns mis. tiitm Ia 5 mm mm wins sum 3.tlmm its LW& II NIiii awn mm wins SliMe 21,455 its urn mm u.s mu 211455 in urn mm ia.s ma. suisa in m.Tila-irn .it..a mm mas sutn s.iwm in 1 inst mm wins .iu~aa 21169 in an mu aim us. s.nem in

-a-l~l~ win mm tans pins &itsu in ms mm urns urSa suimm in mats mm tens stunt sum in a- at? mm u.s arm s.,tim in mm mm urns aria ..tieu in

~i-i lml u.n wi.ii mm mm wins wins asa slim aiim.

~ii4u an in I*

mns 41 - tim.?. mm tans mm. atisa in awn mm tans s. sitmm us u.s mm usui similE itiss in

.mnim. am.. urn nun ama sa Its, -

5WW* 77.3 is isus'aI. Ua5W CM simat? Unsti u4is mw is mn ties tans use tin wins maui tistis

- a-i-a n.os an utah. ira ans ilitia

,~a.n ii,. u.s asii Sian its. hiSs iii.m mu. tnt ass a.iu

.uan tim gas wine ursa tiut urns a.ni it u25SU4 UisU litaisil tewi' in - aiim mans mUll ia..ta maw Sittlil iii p..

mlisn -- in - am am saYs. aa.m ama -- in - -- maw main am iiA Itat iii Pisittis auwits --

is a- ii,. neens 41s.ts m*is isa mua ,'alrni-~t ill

5. a-Ma W.hta is isis smut am.u uumis Hielas us.

H.-~i -~ SW. Pan item tans am z.iam mita 1.3555 am am aim mu tees mum mm stint. stem tans Hata ama

  • isg i.il aiim stem tans itata hum I ma aim tans mis. han aiim trim aims ma.. as...

SiA win uns 1mm 1.3i55 UhI aim tani siam. 5s.w alit aim tans StiLe ,asm ii aim iim.u inns itiuuli hum mesa nan iins.m is-ala mm-- ~16. tilt

33*15 1.3.5

-ima Waef,*

5 5744 m m ~m 45*425.7i1inJ 253 4 Ii.) 1454 Mi-be-tm-.

  • 4-4,,v .*

3 143 55 twu, idp.4.ma 3 SN U 34.1U Wma-3 f3331 amw a

33 31 Smo N 33 33su

]mlmee.

-- 4hmem.-

-- 5. - mm at v sumN U4N -

GWI- 4 - 1.44 34004 0551 0a45m 34 4534 I 531 5U83 44- Wm 4.. 34 5157 I aa3 345JI 45-4 0*4 - =J4 45 em tw . am 5*5.13 IA 4- 337*4..av 15 33 I 5333 3 Is .m tim 31254 S -~m Sm - 334 N 1 525.5 3*64 acI-a  ! e I 4-*, 0123ee 314 mm 511*53 u ma.. slams, 31.45-15 5525* 55. 34

$1447

  • ~ .4215 rn~ o S 2911 0 4 3453 52543 16.5* N N 516* 521i4 37714 43 5 36 3 13.7 Pm ~ N 4-~m* -a sla s4 a m ISAIS aim?

g44*me 34 a-tWa t mm 5 i 4 11133 33 115.33 33 i4 am 33 4

ails i,.

122 51414555.334513N151i11 30 4 30 133 ails aIls 44 4451 33m1 Otaa. 1 44 a-adS 1.33 $143 5 44beNSS I Sm am 33 33*64 14 ala 33 a¶vs m IA 455551eTS455t5*1 5*6 12 25 sam p.m.

514 mmSt~

14.1 mm' 34 331 05 15.45 C-Me 5,444-55 54 0544355555 1 5~ as wu~~

a r44344~ as pese444-

  • 515544554- as sea-m I 04054.44-5 as 55adsg~

I ~ as sa-I 04.444555 as ssas~a-.

I - 55 wesia-~.g

  • ~ as sa44a-~uam as eta-45a-s 3 4-55145 as 1545,444-3445 I 51517.4. as ~

I 1adIs4- as sasoam 3 4455 35.4 55453 7 L* 45.5 564 3 F~S 45.34 51154 3 4- sau sias 33 '-4

  • 515- 3 51 4 Se k..45ee44-440544454.5 33 Se u 3 15125.33 I-'-- 33 3454 M4 F-4-44.5O 142 a Itkls mm mja C- 44.14. 04545 I 444-44 as as 05~44C-am..s I Mka.4...a, as as wsa-.s.asu I 51253.5534- as as 44a-5545

2824 d 4.3. 3.34 2~ 3332 2824 0 3.272 21*8.

-- - WA - - - - - - Ossa LEAVe - We -

~2 223.7*2 4824MM MUMU 282We ~V3M 82323282 1MMA~ 2~43 -~ ~ £~ L~ 4.3 4.3 33 4.3

~22~ 3M 33 3UF3Mm~23 1 2342*3~

3M 223 143 We2.3M3MM 7 282322 3M 3M 33p3M4~3.

  • ~3M2222We 3Mo~ aM ~

7~2- 3M 3M 3.We2~3M 1 I3M3M23~2.

3M 3M 3.2343333232 3Ma 3M W314i28I~223

'3M.- 3M 2~ 33 W343.~i3.23

¶~ 3M 3M Wm328We434

¶ 1282332We 3M 3M 3822.42833.343.

2 223We 2742M 1 7.*M 214.

2 3232 42342 333 21 3.3 3MW 13. 73. 73.

We. - 17 23323 2332 8.232 flU 2? 3533 2253 p17341* 4 2223w 213 22 24M 3323 2737 7 737273 223 27 23*223 2323 24.13 233*~. -- 32 3M 3 6 2ft323 542312 217.32 IA) 231238272382 4 73 542 233 353 3,23 We 3.531 2353, We- 3M 3M 33223Ao*~

  • 52~223 3M 3.33333123.3.3.

7 22834.We34 3M 3.3 W3We~3M 3M 3M 33 33323428.3.

23338.422 3M 3M 333333288.38.

7 32322 3M 3M w*33~We 3M 33 3332833343.

7 ~We 3M 3M 3333213.233.

2W~I3.28. 3M 3M 333332333.

7 73332sh 3M 3M 33332123.323 2 ~3M..123 3M 3M 332.34213234223 7 23123 3M 213 33 2.34323.3.3.

123233233 3M 3M 333333343.

I 33321 2243 2233 I 743. - um 3234 21.a..

2 ~2 5322 2733 21 -u 6 MM 73 213 23 272.35 213 34 37 743 73 33 2MM8823., 1227.

22.73 27*3 3 3*1 3m 71.2J 823343 * ,3 73O 430 28 213 22.3

  • 23 23 43 24 273 215
  • 3 17137 2421 3 3 3.3
  • 4 24444 2 2232.32 372*21 3*3 235 3 27 334.,. 4334 i *t 34I 4,e 3tlS WeIl

'U 32 M~ 73 3.72 247228332733.122

.1.2Z 32327.#23 3)2 334 0 3211 2*732 33 7 2 2 2 2 22 27.43,222 24428.32 3 3 3 33432 3M*

232.427 24.72232 3 313)44 23

- 3321 ~3L ft 33224 33 33.4. Sm 27J 24 31223 71333 332 723.3 233 aM ~3U2 73 2323 3237233.324347 G.3~32.4~3. Th8.328.542343823473537454138.322.21333..

We 223.54 33 *233.8... 22 7332 MUAI 143.2 33 23 23 23 3M 3M 33 223 73.323 731223 3218. 213mM 3M 3532323 21122)223 32737 232.32 3 27*1531 77.22 38.232 A 2.32 73 3.21 72*27 322*7 7*2.32.2 43238 23 227 22.327 738. 43.22.1 V.3..3fl 2138.7.22 237 232243.8. 33 723233.3 24 24*22 23222 2.3 4253 832*2 3.3 63 73.2 733.57 0.38234 3334 3.3 33 3.3 22282 33.3 7223. 332332 22 2 733.2 32~2 743.2 MU 23 23 33 3M 33 3M

~ 8 2533242 2,2273 3M 23.323 22.3 223*33 2222.343

77) 2322233222 Pd A 73 73 733 2.23 3.2.3 23227 2732.32II 3 2173122 24.73,23 2333 33 #3 33 3.2.32. .27.ft 222222.18. We flat 3.

23 332 23 23 3233 232323 .331 42 233 3M 3~3.7 73 733 7543113333327 71333.3.,.37 177227..8.3..23..24.273747242.21*8.*2A2322*2322282*2

.3 733 133 333.333.2124

Usa mm 464 - lmm1. - lUsa - 3551% 21n.

-- - LOAWS. d... 2*4 - V - VS. - LSA. - - -

Us64 Y~ Y~M lmm*4 ~ ILmm64 1.~ 1*4Us Ca. Us Us lb 1s.Us a~5 ~a 12.4 ~i~A Wam l~

  • W.~24 V*4l. 5*.d~ C*412 Tammi Usm5 1445 ~0Us am ma. 48 515 d1 U lam 365 mm as.aja..m a.,.,. nn I14amm Urn junam. ua.inis In IOU 164 56 1.0U 16.16 15 52116 16014 USA1a I.7A Us.a.3~I14U A In Us.m4a. ad Oil l~ I.1. MV.1 ~54ft 3141.114 Usm.1. Us a..

a..

P~

mm 134 13 INasn ,m 13 am

,,,. .m US n.m UISA.aml.,.0llamlU 6* 56mm am 146n lb 015 m. 1 0 4 5 us urn Oem mmtm mm 3E ~.l ImmOiS ~6I MMMI 1445 15*157 ma. lUam .3 6* 26154 am am am am am U

13. 56 5131 U Lam W 115 UsL.UsT A Us im 3665 46*4 46

'1.6.. 6444. ~ ~'1R *56455 am ~1. 5165 14, 53~mm S 1215 311 am. 3I1 am OS LOUs 115 am U~446L22U5*5l22 mm .~U.am 16 41.8 151.053U 22312616 mm bamedd*4 lao. sam ma 15.134 565 13. ~1464 Im 2,6 52146*65.01 a3314 mm Usmm a 654 5.655 U A 215 53 IM 146 a 6 015126 061. 16 1 tin 53 14 446 mm T mm in am 56mm mm 01am3'in U UsM 54.16* am 1* I 16 mm ~ 14 Usd1 224am am 114 I 501 3a. In 106 564*4 mm a.,, ma me mm.. mm..

mm ~ a.~ ~mm.s am ~mma 5166 mm~s mu murams mm

~am am am am am am am U 65 U Il554 5i5 I. mm.aa52.53 A 1514 .m m 0.45 5 ISOZI s a U II6 aIm U 161* Il IA, 5356~ 16 13 W 5.124 am a.amsa.

114mm ad 5-.. 3*4 2*6.1 ~.ft 14.In mm mm.a..& Sm 55, mm mm..am a am am Cm sin 1mm spa. am U13SmUU.U4MM216 mm mm.3~amm 71056 1.aas15sU .sau. .u am am ~d64 I 853 4241512Us.sa.2241 113Me1.a.*4. fraamam.am.,Wa..a..mm5m.a..m.,mbl.2*4e~.14*4.1.

566 ..inam.rn .US 11656 arm am ~wam 1 1~31 *4aa2U.....meU 11*UA.a..Us 1mUs515.ama..am.3..53515Usk3I..*Usmm44~

mm mma.mm~ 4U2m6 22610 165546 11(14 UOSII .604 16 2612 3512Sm.m3U41 14.1)0122.

mm amamamins ¶ IWU 314 mm mm.. mao a. Va.*4.. 03645 I)m.14l a.Sma 10(5

a. 1Jan16 236516*5 211.35 am a641J1 amJaa.3a aW*l40 am am am am am am am mm i mm

.5.2 ma.56smm a 54 lm EN Us am 365*. 46 11am- ... ms Us.in~A 14am.u. mm mm.a.t mm mm mmm 616 044 amIss .a.m. ImAs 20* Us 03*..

inn mm Smab. mail. a.Eain C.0 114Sma 61443 7445 'I, ma ,wm.in ma am am mu miMn maw am am am am mm am am I*~ Oe53 5 16 16 15151 13. am ma l56a. ~ agOem.

mm amm, mm...t a mm mm... L~1. 446.4. 11441.14.

mm mm am mm am talam Irn 44 mm ma. mm lao 0d1 5.45 U 5 am mm ino ,tJm sam**

mm PIn ISo 31(0 54656 046 222 III Cm mm 16 71 4.6 1648 am me mm~ 2*o a.6 013.2 1mm; a..ga rams mm mu n.m am am 18 24163 mm

~a au am am am am am am 14 1.U 1454 Us am 1616 U 64121 114 15.4 *4~ftb 5 4145-. Id ma mm 44a+/- mm~ mmiA. mm mmla.a. mm 55..

mm 53*464 &mm mm.. .6.16 2mm am am ~am I 7151 J..UOSma.65.U1 U8m.Uc4.a.,3. 13m5h..ama.Sm.l1.0*4a.24Us14562*Usmmamam mm mm. mu 6* .me 5126 IU am a...4in~ I 3M 2*U4Imma.U6.U41 11356U.a.a.4'1 amUs0m..am~mmmmmm.m3b56amUsmm1464.

mm mamma in. ,,am mm. mm am am ..4am I 1* lbUUSmasftUsl 123d2122.,..s*.. l4*Us0b444d.mm~5356mmUsfr*42*445-ammst 6146 am me ~ am 36. a.mma ramIla mama maLi Us' WOIWn 1.5146 mm am 11151.3 a.m ,s..lm.u mmoam am am am am am am am 5 Us lm 22122 144 am mm a. 722 1411.222

.u ~

35-. 56

~.,ammmlm.65U1a mm ma siam.. t agm.~ft mama424 mm amlS.L mm mm 535, am 3am lImos an n.am sam. 16 36 UUSma.21.641 14.12146.

5-am. Us 265 456am .6*6 65 liP 36 ~1464. I am l3Ustmmmd1.U41 1236'U,,a..*.. UsUsk1..ams.mmI2*a.444...44.a.s..mbUs.sa64lmm424.mm..

mm in mm ~mm am am. mm as. 61465 ~3. am UUSmUU.64 l1.13Ua1.

mm a43 ~am 156' 6 L.a. SlUm en 16 am 621mm. 30411.120101.

mm mmmm Us uW am mm am am .. am lame.

mm 5-mmmm.. 165 IM5W am inn am 346 6160 I 122.3 25U16mm107111.IVIU, mm 5-amm. UDU LinuS 4am m.56 V.6 Us ~6am In 2233 UIlUsUamSa22l1.152m 6*1 3 am mrn en 16 lISa UU14a.3U41 1511010 mm mm~mm I flU 3SUmU.U~I Wmad1c...in.raa.. 1Us446am1...SbW.514415.&

mm ~bnmamm 4am 2.64 16mm rnn'A UUd1 Sm n. 6.0am 4d5 1015 mm am 215445. mm 36mm. ~1a ~a.s.5 mmV.a 1440 65 *.mamas amom 13112 am laliaM Um6'l) 1613.14 am am am am am am am 151 26*1 1.140 am ama 5444.322 a. 01.113 1122312 ISa mm...... dO.. 5 26 356' Id mm... 064 14. 44.51 1644.414. Sm4. 124 mm ~5~1. p..p mm 5-a64ssa*4, am am am Us s~1.Ms 16 2213 313mSm)1 22322am mm aao-.m.ma am iso U155 2mm 3.3 .4 11456 16 244.4 22135.5..am22U4.14316

SM.5 ~ t.d *441 is~ Se. a- 2Sii~ n.m 5is *5 LiAise - Se. - - - - c ,..we we we we it..amfl

_ a.~a- am Vdt.5 Tame. ame. LamM ydu..M .~

  • Ta CaE tad.~it w55 e.s41 S tea LU. ama .m am sim issama in ii, us. am an am a aim in us ammamita*ittu.

amamama a ui am am 517 5 Lam itO m.m ma,.eg..alsamamnin ama.~. a a am am s.ai a Lam in intL.a.urniwits am 5A54 tArn am 1ZS is.im Sm 58 arnams. Uft14UM meisaise.~ 'U 4 am. - am in am in am amam amm am~amam in a ama sam t.t am am in us a--Se. em asia saw as. am am in am 4.4 at, am am.. am amam. ., is ama.a va.a a- am UP 4.4 MM ist17~ Wb 3mm am a. am MM mm MM MM Imamama U MIII U an -

iA7 La l aIa am SM etVkl Uee.,WlR&r am gw L ftp

- e Llama am1eo Ifl am itO 38 m*rnamm Ui5i54 SM La- itO iU Uit.a.UU&istlSM sew us 3m 18 GM MisiM~IiU3i4 U-am is~a. e.~ Md-. a-a. Tg.) ~5 ~t a- 4M 5W LuG MM Ig.7i SIMM Ugt4 a-am am am am MM MM MM MM ut amamam a a in MN a am MM mi. w aiUtua SiM wiam. am.. U' am sews.. MM4.g weaa wesseft am V~wet am ftP am. am ti7aa MMO 141345 .34g. IMMU sin aI a.,ma iN US? SMTwaMesisuMi3.iTI

-MN MN Ut?

we. am... a- ,a~am.e a-wi am..., am.. ra.)

a- reaM g.e gas Siam.,. Ms.u.4 .saain a-- am an MM tam mm MM as am.ame.am. a N IM USS Ut ma ma uw.tit 116455 vga- am. sE tam. Am.g.I ve.a. ft mama am e..gwet e pJ a- Im* LI. SimM Mu. MN Lit am .. 3m i ii) e.mUa-u.ggsi IIIS.I.asi.e.a. lis.aa55esMmammewaiam....55amam..a..ie.am.ama.

Ca ita simm -a.. an an MM isEim I tit 4~mt2S.ese.g.U4i g.Um.a.is...a~ tgsis41.minamaiam...a.e.amams.am.amam am weIIam u.n mm. use an am se in am g a- a-sm. OASiS 05g. Gig iii am sa in am ama a- am 3am mm. me ssi am SM W.Mi2am..mU41 ttn~M.is..u~. ThSaGM.Mewa.u.iam.u.hewa.igteemamw..am.mewam a- a-ait a m em. letS lit ii asistam in SAC s~in~ins.

a- is' Nm. mm am in ta in in am U- MUam a it am. am am Ii -~ U iam a- tiaSi il.USI. IGaSa IASM NI Mn weams in aatIam..Uusi la4aamm,, ewa. T*a5.nea-eU-.m.amammamewsamvgame.ams..saa.

a- sun am am am am bis in am am sun in we a-.. itim ~E amiss Ts.I US.t Ta.)

we 41MM ami in tan sauw 1)91* Mmii em am GM MM Urn MM MM Tae.a-u.I...in...bGeCa u.n in item ai Siam g awam u.S a-am a-a.a.05.

  • am. a -

iii .. eam

  • am- . is..

$ am S5l is e. 24 5s tat a-a41e.. us am- a "is I am-I.amltm *in'.

Sat a-RE a-a-a- it am. si a. a ktl vlsl a

a-.. amm mm isa-a U ewam- 535mm

'is amIMa-~ iS igamue...hadaa ii A 5it~ Sm is@8 a am an am a am am am mm m U w u a g.m iit.5 .44we4.u A 54N iM isism a gin g.m tEb~. tam *EU..iS am am we amg.a am.s.a am a-suet am NP we aim am em SM lat seMise. SM lit aainwe.siuas.,sw 5s' aim ama am am am isg.fra ItO U IMweainU S.5)S an am ltD am ag.g.a 5W MiMg.W a-4.55V amw...it. G~a. sil Ta.5 saweesam 5551mn tam en mmn N5iMa-Mmi4Stam a-a sam ass anma-nmu.stin.smaai uazeia is it a 11613 aiIm nmi am.aisU c~a I amawama.. MI. ama-am....

I eweamew MM amam~a-.a S samaa-a-a son ama-am....

amaamseam UI. a-a-a-am.a I GitO....5 MN amama-ame.m si am. MM ama-a-ama..

I ama- MM ama-tame....

I ama-I bia5sa-am MM simawia-.....

MM ama-a-ge..

I a-a.a- MM ama-a-am.

S~5mis3isThM lam ama-a-gm

IWIdO1w

¶ dI Sm m I 2~*m

~m 71 LJ

  • m
  • 6 116 1124514 IC
  • I~16 84453 ~

A 316 *16 316 S 3471 16*12 *443 1*461 S.* 36 2*13% ft~ C 3%~

2 6144* 3 ¶16 *145 3 S 11316 14 116 3.13 3 I 6*1646 3 *16 14.13 3 4 3 34*3 3

ENCLOSURE 2 TO OMY-15-053 CERTIFICATION OF FINANCIAL ASSURANCE

CERTIFICATION OF FINANCIAL ASSURANCE NRC Licensee:

Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License No. DPR-36 (NRC Docket No. 72-30) 321 Old Ferry Road Wiscasset, ME 04578-4922 Issued to: U.S. Nuclear Regulatory Commission Certification:

I hereby certify that Maine Yankee Atomic Power Company is the licensee for the Maine Yankee Independent Spent Fuel Storage Installation (Maine Yankee ISFSI) and that I, the undersigned, am authorized to provide this Certification of Financial Assurance with respect to the radiological decommissioning of the Maine Yankee ISFSI.

During the operation of this ISFSI, spent nuclear fuel and Greater than Class C waste will be stored at the Maine Yankee 1SF SI in storage casks licensed under 10 CFR 72. Pursuant to contracts with the Department of Energy the spent fuel and associated casks will ultimately be removed from the ISFSI location, and Maine Yankee will dispose of other radiological waste in accordance with NRC regulations, at which time the Maine Yankee ISFSI will be decommissioned in accordance with NRC regulations.

I further certify that financial assurance in an amount sufficient to fund Maine Yankee ISFSI radiological decommissioning at the time of such decommissioning has been provided, pursuant to 10 CFR 72.30, as described in Enclosure 1 to the letter to which this Certification is attached.

That radiological decommissioning funding assurance is premised on a site-specific decommissioning cost estimate and funding methodology described therein, in the amount of:

Maine Yankee ISFSI $21.6 million (in 2015 dollars, inclusive of contingency)

Carla M. Pizzella Maine Yankee Atomic Pd rer Company -

Vice President, Chief Financial Officer, and Treasurer -,

Phone (860) 267-6426 x304 Corporate Seal Date \ *1t

ENCLOSURE 3 TO OMY-15-053 TOTAL COSTS ASSOCIATED WITH THE HNP ISFSI, INCLUDING COST ESTIMATE FOR MANAGING IRRADIATED FUEL AND GTCC WASTE

Maine Yankee 12222015 2013130? Budget MaineYankeeAtonioPeoenrComanry SpentFeelManagennntand ISF21 Dnem Estimate

-OEC~sanmeal Sumof62060 Sumaf2all Somal201 Sumneoele¶ Bumne2020SanneOOOI25umof202~2 Suofoe2022 S~oaeel02 5wna62025 5umno62226 Suno62027 Sumnol202a 9ame12029Sumoe62010S~onnelOt smonteta3a aunnaof20 SrnetTalteale20132e et5.5sa $ 455.3701 4220947$ 474,522 $ 4L55.270 522,216 2 2 452,271 5220,21 3 502,202 $$ 455.270 022.216 0 2 455,371 520,202 2 5052,216 2 425.754 455,371 $ 5 455,371 54,219 $$ 452,271 522.216 $$ 532,216 $

4552371 592,219 0

$ 422.232 $ 1,52487e2 222016$ 9,126.822 522,216$ 55.O200 $ 522,2106 50222160 505.21$ 0 231,929

.abat.-Sn-Manual 1,943,522$ 6.203,205$ 1.243,20 $ 1.043.922 1,203.922$ 1,843,9060 1,823.922$ 1,84532*62 1.043.922 5 1.543.922 1,243,326$1,943.902 $ 1,843,922$ 1.943,222 $10.43.222 $ 1.23.92,36$ 277.923$

1.,02.,376 2.750.762$ 3.225.704$ 3.225.724 3.025.704 $32025,784 latlrniab Supple. 105,0473 52,125$ 22,025$ 92,125 $ 162,247 3 22,1225 92.025 $ 92[2,12 92,122 $ 92,125 5 0,125 $ 2,0225 92.125 $ 22,025 5 2,122 $ 92.0225 Ila,274$ 113.207 $ 113.074 5 113.274 $ 113.074 52,12352 552.223 $ 552,9223 522.223 $ 552,223 9 052,2232 5029,2 $ *92,922 5523238 0 5529,93 0 52522 $ 552,523 529,923 $ 2359293$ 5529,223 052,222 241.525$

3o22d* Serreos- FuelLeedina - $ - $ - . $ 722301,25

)22asoSaraos-ISF510CPa 3.932.2355 7322282 725.203 $ n4.590 90,727$

305.272$ 219,2728 75348235 424,621 2 205,076 2 205,272 2052372 215,372 0 0.0323.04 $ 215,372 205,272 210,272 215.279 424,221 0 723,8230 2,1092.470

>226ad aauoans- 222-RAiD252 atl1FSl - $ - 3 - $-

. . .. $ -" " $ $ " $ . .. 6,212,2..

17,5222221 Dupaaa Saeraica

-29 P6DDaloISFSl - $ - $ 6 3 - 3 -$

- $- - $ 2- $ - $ . 0 - $ - $727.522$14.el,.32o 6,14.2352, 1,.0229$22 1,022,2229 0,222.2229 1.0802222$ 1.040229$ 1.0802.32$ 1.0222250,2,229$2 0,022,229

$ 0.9222229$0.022229$ 0.002.222 0.020.229$ 1.222291,80229 0 1.08022,229 logulalaryFe,. 225,275$ 225.275$ 225.2752 25.275 5 825,975 9292068$

612.452$ 1.921225e 018.4522 112,4258 118.452 112,452 OIlo45 112,452 $ 118,4,58 116,452 012.402 019.452 108,4528 112,452 112,452 011.4528 161.5342 226,22$

OrancdTotal $ 12761494 $ 12606G7208 9162222361220992282 $ 91992492 $ 8i522263$ etE62r78$ 69r22780$ 96*2r780 $ laal10e8n 6 95622760$ e912172e0 29626278$ 892.21700$ 9242i6 $ 22202337a32$2i316010 $ 0 946123 0 ieeoo26uae Noba6:75 et etmanagae~nt afIrtdiulodfustandGTOC Costes clonnatadastosaa:

$ 004.722,222GrandTotalfSomajbooo

$ (9.013.2021Naon-Rd 0&DISF51 L.25571Rod 022ISF51

$671,217,616Managesrnantallradluled Fuela*d 2722Waste Noloa2:Th~olestofRAD andNsN.RAD 56BoftherSFSlpn201adlodaas auproidedpodhaealunes labalad"Sumaot2203Pand"Sunlot2203T"Isaeorved by esaaua~ngtvalUeofth~eaO*stn espn~osrodsdn E~ondor027y2.5%.

N90o 3: Ti~sSarononC32rles MOYe 2013Approaod0365RoleCaserai thaKnightCostEnginoeelng Seslos 2215RAGendNO2N-Rud 0S700 DoamCostEusnoate