MONTHYEARCNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) CNL-24-031, Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance2024-03-18018 March 2024 Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 CNL-24-028, Response to Request for Additional Information Regarding Watts Bar Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Watts Bar Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20240102024-03-0808 March 2024 Age-Related Degradation Inspection Report 05000390/2024010 and 05000391/2024010 IR 05000390/20230062024-02-28028 February 2024 Annual Assessment Letter for Watts Bar Nuclear Plant Units 1 and 2 - Report 05000390/2023006 and 05000391/2023006 CNL-24-012, Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance2024-02-28028 February 2024 Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance CNL-24-023, Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 252024-02-20020 February 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 25 ML24009A1712024-02-16016 February 2024 Environmental Assessment and Finding of No Significant Impact Related to an Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods (EPID L-2023-LLA-0039) - Letter ML24019A0722024-02-14014 February 2024 Request for Withholding Information from Public Disclosure IR 05000390/20230042024-02-13013 February 2024 Integrated Inspection Report 05000390/2023004 and 05000391/2023004 and Apparent Violation ML24038A3342024-02-0707 February 2024 Change to South Texas Project Electric Generating Station (Stepgs) Emergency Plan 2024-09-24
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 23, 2012 Mr. Michael D. Skaggs, Senior Vice President, Nuclear Generation Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT, UNIT 2 - REVIEW SCHEDULE DELAY BECAUSE OF COORDINATION ISSUES WITH UNIT 1 LICENSING BASIS
Dear Mr. Skaggs:
By letter dated November 7,2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11307A396), the Nuclear Regulatory Commission (NRC) staff informed Tennessee Valley Authority (TVA) of the need to closely coordinate proposed license amendment requests (LARs) for Watts Bar Nuclear Plant (WBN) Unit 1 with the WBN Unit 2 operating license (OL) review effort. The NRC staff wants to ensure that the submission of proposed LARs do not adversely affect NRC's safety evaluations for WBN Unit 2, which are currently in progress. The NRC staff stressed that it is imperative that TVA ensure that the proposed list of LARs is complete, no additional LARs are planned or necessary, and that TVA adhere to the specified schedule for LAR submittals. The NRC staff also stated that this is necessary to ensure that the NRC staff can complete its review of WBN Unit 2 OL application consistent with TVA's project schedule. To date, only one (to change the dose equivalent iodine value, dated March 8, 2012) of the eight anticipated LARs has been submitted.
On December 6, 2011, during a conference call with representatives from TVA, the NRC staff learned that TVA may need an LAR to change the probable maximum flood (PMF) level in the WBN Unit 1 Updated Final Safety Analysis Report (UFSAR) from 734.9 feet to 738.8 feet. The revised design basis PMF conforms to the calculations prepared to support the FSAR for WBN Unit 2. TVA's initial estimate for submitting an LAR to revise the design basis for hydrology in the UFSAR was the end of January 2012. The date subsequently slipped to February 22, to February 29, and then to March 9,2012. Bye-mail dated March9,2012,Mr. J. Shea (TVA) informed me that TVA will not be able to submit the LAR until additional questions posed by your offsite review committee are addressed.
Staff Requirements Memorandum dated July 25,2007, regarding SECY-07-0096, "Possible Reactivation of Construction and Licensing Activities for the Watts Bar Nuclear Plant Unit 2,"
states:
The Commission supports a licensing review approach that employs the current licensing basis for Unit 1 as the reference basis for the review and licensing of Unit 2.
M. Skaggs -2 The NRC staff has, therefore, used the licensing basis for WBN Unit 1 as the reference for its review of the OL application for WBN Unit 2. However, the staff recognized that the review of the WBN Unit 2 FSAR might identify issues within the licensing basis of WBN Unit 1. Thus, WBN Unit 1's licensing basis must be kept up-to-date to conform to TVA's proposed basis for WBN Unit 2. The staffs review schedule for WBN Unit 2 has been adversely impacted by TVA's lack of timely LAR submittals for WBN Unit 1. Thus, the NRC staff's estimated date for completing the review of the WBN Unit 2 OL application will change, as well as the schedule for related meetings with the NRC Advisory Committee on Reactor Safeguards, due to the delays with TVA's submittal. The staff will revise and inform you of its review schedule after TVA submits the proposed LARs.
If you have any questions, please contact me at (301) 415-2296 or Fred.Lyon@nrc.gov.
Sincerely,
~~~t-Carl F. Lyon, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv
M. Skaggs - 2 The NRC staff has, therefore, used the licensing basis for WBN Unit 1 as the reference for its review of the OL application for WBN Unit 2. However, the staff recognized that the review of the WBN Unit 2 FSAR might identify issues within the licensing basis of WBN Unit 1. Thus, WBN Unit 1's licensing basis must be kept up-to-date to conform to TVA's proposed basis for WBN Unit 2. The staff's review schedule for WBN Unit 2 has been adversely impacted by TVA's lack of timely LAR submittals for WBN Unit 1. Thus, the NRC staff's estimated date for completing the review of the WBN Unit 2 OL application will change, as well as the schedule for related meetings with the NRC Advisory Committee on Reactor Safeguards, due to the delays with TVA's submittal. The staff will revise and inform you of its review schedule after TVA submits the proposed LARs.
If you have any questions, please contact me at (301) 415-2296 or Fred.Lyon@nrc.gov.
Sincerely, IRA by P. Milano forI Carl F. Lyon, Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391 cc: Distribution via Listserv DISTRIBUTION:
LP-WB r/f PUBLIC RidsOgc Resource RidsAcrsAcnw MailCTR Resource RidsRgn2MailCenter Resource SLingam, NRR RidsOpaMaii Resource RidsNrrDorl Resource Rids NrrDorlLpl2-2 Resource RidsNrrLABClayton Resource RidsNrrDorlLp-Wb Resource RidsNrrPMWattsBar1 Resource RidsNrrPMWattsBar2 Resource RHannah, OPA RII RidsNrrDeEmcb Resource ADAMS ACCESSION NUMBER: ML12073A390