MONTHYEARML24304B0512024-10-30030 October 2024 Cycle 26 Core Operating Limits Report IR 05000498/20244022024-10-23023 October 2024 Security Baseline Inspection Report 05000498/2024402 and 05000499/2024402 05000499/LER-2024-003, Containment Isolation Valve Inoperable Resulting in Condition Prohibited by Technical Specification and Prevention of Fulfillment of Safety Function2024-10-22022 October 2024 Containment Isolation Valve Inoperable Resulting in Condition Prohibited by Technical Specification and Prevention of Fulfillment of Safety Function ML24295A0772024-10-21021 October 2024 Licensed Operator Positive Fitness-for-Duty Test 05000499/LER-2024-002, Two Control Room Envelope HVAC Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function2024-10-17017 October 2024 Two Control Room Envelope HVAC Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24290A1162024-10-16016 October 2024 Change to South Texas Project Electric Generating Station (STPEGS) Emergency Plan ML24255A0322024-09-30030 September 2024 The Associated Independent Spent Fuel Storage Installation - Notice of Consideration of Approval of Direct Transfer of Licenses and Opportunity to Request a Hearing (EPID L-2024-LLM-0002) - Letter ML24269A1762024-09-25025 September 2024 Tpdes Permit Renewal Application WQ0001 908000 05000498/LER-2024-004, Loss of Offsite Power Resulting in Unit 1 Automatic Reactor Trip and Actuation of Emergency Diesel Generators and Auxiliary Feedwater Pumps2024-09-19019 September 2024 Loss of Offsite Power Resulting in Unit 1 Automatic Reactor Trip and Actuation of Emergency Diesel Generators and Auxiliary Feedwater Pumps ML24271A3022024-09-18018 September 2024 STP-2024-09 Post-Exam Comments - Redacted ML24274A0902024-09-16016 September 2024 Written Response - EA-24-026 STP Operator - Redacted ML24250A1882024-09-11011 September 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000499/LER-2024-001-01, Supplement to Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators2024-08-29029 August 2024 Supplement to Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators IR 05000498/20243012024-08-27027 August 2024 NRC Initial Operator Licensing Examination Approval 05000498/2024301; 05000499/2024301 IR 05000498/20240052024-08-22022 August 2024 Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2024005 and 05000499/2024005) IR 05000498/20240022024-08-0909 August 2024 Integrated Inspection Report 05000498/2024002 and 05000499/2024002 IR 05000498/20240102024-08-0808 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000498/2024010 and 05000499/2024010 ML24218A1462024-07-26026 July 2024 2. EPA Comments on South Texas Project Exemption Ea/Fonsi ML24207A1782024-07-25025 July 2024 Licensed Operator Positive Fitness-For-Duty Test 05000499/LER-2024-001, Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators2024-07-0202 July 2024 Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators 05000498/LER-2024-003, Condition Prohibited by Technical Specifications and Potential Loss of Safety Function Due to Inoperable Low Head Safety Injection Pump2024-07-0101 July 2024 Condition Prohibited by Technical Specifications and Potential Loss of Safety Function Due to Inoperable Low Head Safety Injection Pump 05000498/LER-2024-002-01, Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function2024-06-27027 June 2024 Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function 05000498/LER-2023-003-01, Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function2024-06-19019 June 2024 Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A2842024-05-15015 May 2024 Independent Spent Fuel Storage Installation Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance ML24137A0882024-05-15015 May 2024 Operator Licensinq Examination Schedule Revision 3 ML24136A2872024-05-15015 May 2024 Submittal of 2024 Nrc/Fema Evaluated Exercise Scenario Manual ML24130A2712024-05-0909 May 2024 Re Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24128A1572024-05-0707 May 2024 Independent Spent Fuel Storage Installation Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance IR 05000498/20240012024-05-0606 May 2024 Integrated Inspection Report 05000498/2024001 & 05000499/2024001 ML24120A3762024-04-29029 April 2024 Annual Dose Report for 2023 ML24116A2282024-04-25025 April 2024 Annual Environmental Operating Report ML24116A3032024-04-25025 April 2024 Operations Quality Assurance Plan Condition Adverse to Quality Definition Change Resulting in a Reduction in Commitment 05000498/LER-2023-004-01, Condition Prohibited by Technical Specifications Due to Inoperable Train of Essential Chilled Water2024-04-25025 April 2024 Condition Prohibited by Technical Specifications Due to Inoperable Train of Essential Chilled Water ML24117A1602024-04-24024 April 2024 2023 Radioactive Effluent Release Report ML24102A2452024-04-23023 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0046 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24113A3122024-04-22022 April 2024 Cycle 24 Core Operating Limits Report ML24097A0072024-04-0606 April 2024 Relief Request Number RR-ENG-4-07 – Request for an Alternative to ASME Code Case N-729-6 for Reactor Vessel Head Penetration 75 05000498/LER-2024-001, Re Two Steam Generator Power Operated Relief Valves (Porvs) Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function2024-04-0101 April 2024 Re Two Steam Generator Power Operated Relief Valves (Porvs) Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24088A3022024-03-28028 March 2024 Financial Assurance for Decommissioning - 2024 Update ML24081A3972024-03-21021 March 2024 Response to Request for Additional Information for Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation NOC-AE-240040, Nuclear Liability Certificates of Insurance2024-03-19019 March 2024 Nuclear Liability Certificates of Insurance ML24080A2902024-03-19019 March 2024 Nuclear Liability Certificates of Insurance ML24066A2002024-03-0606 March 2024 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes ML24079A1312024-03-0505 March 2024 Nuclear Insurance Protection ML24060A1742024-02-28028 February 2024 Submittal of Annual Fitness for Duty Performance Report for 2023 IR 05000498/20230062024-02-28028 February 2024 Annual Assessment Letter for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2023006 and 05000499/2023006) IR 05000498/20240132024-02-27027 February 2024 Design Basis Assurance Inspection (Programs) Commercial Grade Dedication IR 05000498/2024013 and 05000499/2024013 ML24022A2252024-02-20020 February 2024 Issuance of Amendment Nos. 227 and 212 to Authorize the Revision of the Alternative Source Term Dose Calculation ML24050A0082024-02-19019 February 2024 Evidence of Financial Protection 2024-09-30
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 9, 2015 Mr. Dennis L. Koehl President and CEO/CNO STP Nuclear Operating Company South Texas Project P.O. Box 289 Wadsworth, TX 77 483
SUBJECT:
SOUTH TEXAS PROJECT, UNITS 1 AND 2 - RESPONSE REGARDING PHASE 2 STAFFING SUBMITTALS ASSOCIATED WITH NEAR-TERM TASK FORCE RECOMMENDATION 9.3 RELATED TO THE FUKUSHIMA DAl-ICHI NUCLEAR POWER PLANT ACCIDENT (TAC NOS. MF5379 AND MF5380)
Dear Mr. Koehl:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information pursuant to Title 1O of the Code of Federal Regulations ( 10 CFR) Part 50, Section 50.54(f) (hereafter referred to as the 50.54(f) letter), regarding Recommendations 2.1 (seismic and flooding evaluations), 2.3 (seismic and flooding walkdowns), and 9.3 (emergency preparedness communication and staffing) of the Near-Term Task Force (NTTF) review of insights from the Fukushima Dai-ichi accident. With respect to Recommendation 9.3, Enclosure 5 to the NRC's letter requested licensees and holders of construction permits to assess their means to power communications equipment onsite and offsite during a prolonged station blackout (SBO) event and to perform a staffing assessment to determine the staff required to fill all necessary positions in response to a multi-unit event.
The 50.54(f) letter, in part, requested licensee responses pursuant to the provisions of 10 CFR 50.54(f) pertaining to onsite and augmented staff availability to implement the strategies discussed in the emergency plan and plant operating procedures including new staff or functions resulting from the assessment, identified collateral duties, an implementation schedule to perform the assessments, identified modifications, and any changes that have been made or will be made to the emergency plan regarding on-shift or augmented staffing. In addition, NTTF Recommendation 9.3 has a dependency on the implementation of NTTF Recommendation 4.2 (mitigating strategies). As a result of this dependency, licensees responded to the 50.54(f) letter in phases. The Phase 1 staffing assessment requested licensees to evaluate their ability to respond to a multi-unit extended loss of alternating current (ac) power (ELAP) event utilizing existing processes and procedures. The licensee responses to the 50.54(f) letter for Phase 1 staffing assessments for multi-unit sites were received and evaluated by the NRC staff. The NRC staff issued acknowledgement letters to all licensees with multi-unit sites, with the exception of San Onofre Nuclear Generating Station, by April 28, 2014.
D. Koehl Licensees were also requested to submit for NRC staff review a Phase 2 staffing assessment, which provides an assessment of the staffing necessary to perform the functions related to the strategies developed in response to NTTF Recommendation 4.2 and the resulting NRC Order EA-12-049, "Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events [BDBEE]" (ADAMS Accession No. ML12054A736).
Licensees were requested to provide their Phase 2 Staffing Assessments to the NRC no later than four months prior to the beginning of their second refueling outage (as used in the context of NRC Order EA-12-049). By letter dated November 25, 2014 (ADAMS Accession No.
ML14351A156), STP Nuclear Operating Company (the licensee) submitted its Phase 2 staffing assessment for South Texas Project, Units 1 and 2 to the NRC in response to the 50.54(f) letter.
By letter dated July 2, 2015 (ADAMS Accession No. ML15196A038), the licensee submitted a supplement to its initial submittal.
The NRC staff reviewed your Phase 2 staffing assessment and supplemental information in accordance with the assumptions and guidelines of Sections 2.2, 2.3, and 3 of the Nuclear Energy Institute (NEI) guidance document NEI 12-01, "Guideline for Assessing Beyond Design Basis Accident Response Staffing and Communications Capabilities," (ADAMS Accession No.
ML12125A412), which was endorsed by the NRC staff by letter dated May 15, 2012 (ADAMS Accession No. ML12131A043). The NRC staff noted that you assessed your current onsite minimum staffing levels to identify any enhancements needed to respond following a beyond-design-basis large-scale natural event, and to ensure that the strategies contained in the existing emergency plan and plant operating procedures, such as those used in response to a SBO, can be performed by the site staff. Your assessment assumed that a large-scale natural event causes: (1) an ELAP, (2) all units on the site to be affected, and (3) access to the site to be impeded for a minimum of six hours. You also assessed your capability to perform the site specific functions related to the strategies developed in response to Order EA-12-049. You conducted independent reviews and concluded, based on your staffing assessment, that the existing on-shift minimum staff is sufficient to implement the loss of all ac power, multi-unit event response strategies, including those strategies developed to support the requirements of NRC Order EA-12-049, while supporting performance of the required emergency planning duties without unacceptable collateral duties.
The NRC staff reviewed your Phase 2 staffing submittal and confirmed that your existing emergency response resources, as described in your emergency plan, are sufficient to perform the required plant actions and emergency plan functions, and implement the multi-unit event response strategies that were developed in response to Order EA-12-049 without the assignment of collateral duties that would impact the performance of assigned emergency plan functions.
As a result, the NRC staff concludes that your Phase 2 staffing submittal adequately addresses the response strategies needed to respond to a BDBEE using your procedures and guidelines.
The NRC staff will verify the implementation of your staffing capabilities through the inspection program.
D. Koehl If you have any questions regarding this letter, please contact Stephen Philpott at (301) 415-2365 or via email at Stephen.Philpott@nrc.gov.
Sincerely,
/llMZfUd&i Mandy K. Halter, Acting Branch Chief Orders Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499 cc: Distribution via Listserv
ML15231A035 *via email OFFICE NRR/JLD/JOMB/PM NRR/JLD/LA NSIR/DPR/DDEP/NRLB/BC* NRR/JLD/JOMB/BC(A)
NAME SPhilpott Slent A Rivera MHalter DATE 08/25/15 08/24/15 08/31/15 09/09/15