|
---|
Category:Letter
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) ML24304A8492024-10-31031 October 2024 December 2024 Requalification Inspection Notification Letter IR 05000327/20250102024-10-29029 October 2024 Notification of Sequoyah, Units 1 and 2 - Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000327/2025010 and 05000328/2025010 ML24298A1172024-10-24024 October 2024 Cycle 26, 180-Day Steam Generator Tube Inspection Report CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 05000327/LER-2024-001, Reactor Trip Due to a Turbine Trip2024-10-17017 October 2024 Reactor Trip Due to a Turbine Trip ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 05000328/LER-2024-001, Reactor Trip Due to an Electrical Trouble Turbine Trip2024-09-25025 September 2024 Reactor Trip Due to an Electrical Trouble Turbine Trip CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24267A0402024-09-19019 September 2024 Cycle 27 Core Operating Limits Report Revision 0 ML24185A1742024-09-18018 September 2024 Cover Letter - Issuance of Exemption Related to Non-Destructive Examination Compliance Regarding Sequoyah Nuclear Plant Independent Spent Fuel Storage Installation CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24253A0152024-09-0808 September 2024 Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation ML24247A2212024-08-29029 August 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Letter OG-21-160, NEI 03-08 Needed Guidance: PWR Lower Radial Support Clevis Insert X-750 Bolt Inspection Requirements, September 1, 2021 ML24247A1802024-08-28028 August 2024 Application to Revise the Fuel Handling Accident Analysis, to Delete Technical Specification 3.9.4, Containment Penetrations, and to Modify Technical Specification 3.3.6, Containment Ventilation Isolation Instrumentation for Sequoyah Nuclea IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000327/20240052024-08-26026 August 2024 Updated Inspection Plan for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2024005 and 05000328/2024005 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev IR 05000327/20240022024-07-31031 July 2024 Integrated Inspection Report 05000327/2024002 and 05000328/2024002 ML24211A0542024-07-29029 July 2024 Operator License Examination Report ML24211A0572024-07-29029 July 2024 Submittal of Emergency Plan Implementing Procedure Revision ML24211A0412024-07-26026 July 2024 Unit 1 Cycle 26 Refueling Outage - 90-Day Inservice Inspection Summary Report ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24191A4652024-07-0909 July 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24177A0282024-06-25025 June 2024 Emergency Plan Implementing Procedure Revisions ML24176A0222024-06-24024 June 2024 Retraction of Interim Report of a Deviation or Failure to Comply – Transducer Model 8005N ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24145A0852024-05-30030 May 2024 1B-B Diesel Generator Failure - Final Significance Determination Letter ML24145A1052024-05-29029 May 2024 301 Exam Approval Letter ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc 2024-09-08
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 September 30, 2013 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating Licenses Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391
Subject:
Second Progress Update on Improved Flood Mitigation System Project
References:
- 1. Letter from TVA to NRC, "Commitment to Install Improved Flood Mitigation Systems," dated April 16, 2013
- 2. Letter from TVA to NRC, "Progress Update on Improved Flood Mitigation System Project," dated July 1, 2013 By letter dated April 16, 2013, the Tennessee Valley Authority (TVA) committed to install improved flood mitigation systems at the Sequoyah Nuclear Power Plant (SQN), Units 1 and 2, and the Watts Bar Nuclear Plant (WBN), Units 1 and 2 (Reference 1). TVA committed to complete implementation of the improved flood mitigation systems at SQN and WBN by December 31, 2016. TVA also committed to provide periodic written updates regarding progress of the project. During a public meeting on June 27, 2013, TVA briefed the NRC regarding the status of the improved flood mitigation project and provided the first progress update on July 1, 2013 (Reference 2). TVA also committed in the first progress update (Reference 2), to develop a set of major tasks through TVA's engineering design and project controls processes and to discuss these major tasks as part of the periodic written progress updates.
The purpose of this letter is to provide the second written progress update regarding progress of the improved flood mitigation system project consistent with Commitment 2 in of the Reference 1 letter and Commitment 1 in Enclosure 1 of the Reference 2 letter.
Printedon recycledpaper
U.S. Nuclear Regulatory Commission Page 2 September 30, 2013 During the June 27, 2013, public meeting and in the first update (Reference 2), TVA advised the NRC that engineering design and project controls for the project are being developed consistent with TVA's existing design and project management procedures. The Project Status Schedule, provided in Table 1 on page 3 of this letter lists the major tasks associated with-the design and project controls developed to implement the flood mitigation system.
Table 1 will be used to provide the overall status of the improved flood mitigation system project each quarter. The status of the Table 1 tasks from July 1, 2013 to September 20, 2013, is provided below.
" Task 2, Develop Project Plan, and Task 3, Perform Conceptual Design Phase, scheduled completion is revised from September 30, 2013, to October 30, 2013. The following actions have been completed:
- a. Joint project team formed
- b. Project Charter developed and comments are being resolved
- c. Cost estimate and schedule has been developed for the Conceptual Design Phase
- d. Project approval package for the Conceptual Design Phase has been prepared
- e. The Project Approval Board (PAB) has granted authorization to fund the Conceptual Design Phase A plan is being developed for Tasks 2 and 3 to maintain the scheduled completion of Task 4.
- Task 4, Perform Preliminary Design Phase, has begun. For Task 4, the following actions have been completed:
- a. Design Criteria have been approved and issued for SQN and are under review for WBN
- b. Statement of work for the Preliminary Engineering Phase is drafted and is expected to be released to the prospective bidders in October 2013
- c. Procurement strategy has been developed for the Final Engineering and Implementation Phase - Firm Fixed Price Design, Build, and Test The following Task 4 actions are scheduled to be completed between September 21, 2013 and February 27, 2014:
- a. Develop 10% Design Package
- b. Vendor Selection for Design/Build Contract
- c. Detailed Cost and Schedule development
- d. Risk identification and risk mitigation planning
- e. Project Plans (Project Management, Communication, and Risk Management)
National Environmental Policy Act (NEPA) screening
U.S. Nuclear Regulatory Commission Page 3 September 30, 2013 TVA noted in the June 27, 2013, public meeting and in Reference 2, that since issuance of the April 16, 2013 letter, potential design alternatives had emerged for a number of elements of the overall flood mitigation system design as described in Enclosure 1 of Reference 1. To date, progress in the following design areas has been made:
- 1. The SQN FLEX Equipment Storage Building is being designed to include the flood mode equipment.
- 2. For the flood mode equipment, dedicated diesel generators will be procured and installed in lieu of using the FLEX 3 MW diesels for power.
TABLE 1 PROJECT STATUS SCHEDULE (updates shown in bold type)
Scheduled Scheduled Task Start Finish Status
U.S. Nuclear Regulatory Commission Page 4 September 30, 2013 TVA will provide the third quarterly written progress update of the improved flood mitigation system project by December 31, 2013, consistent with Commitment 2 in Enclosure 2 of TVA's letter to NRC dated April 16, 2013.
There are no new regulatory commitments contained in this letter.
Ifyou have questions regarding this update, please contact Kevin Casey at (423) 751-8523.
- Res ully, J .Shea ice President, Nuclear Licensing cc
NRC Regional Administrator - Region II NRR Director - NRC Headquarters NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant, Unit I NRR Project Manager - Watts Bar Nuclear Plant, Unit 2