MONTHYEARML14028A2562014-01-23023 January 2014 Response to Request for Clarifying Information Regarding Steam Generator Tube Inservice Inspection Report for the Fall 2012 Refueling Outage Project stage: Request ML14150A1372014-05-30030 May 2014 Review of the 2012 Steam Generator Tube Inspection Report Project stage: Approval 2014-01-23
[Table View] |
Similar Documents at Surry |
---|
Category:Letter
MONTHYEARIR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 ML23312A1922024-01-18018 January 2024 Issuance of Amendment Nos. 316 & 316 Regarding a Risk Informed Approach for Tornado Classification of the Fuel Handling Trolley Support Structure ML24003A9022024-01-0303 January 2024 Stations, Units 1 and 2, Emergency Plan Revision - Relocation of the Technical Support Center (TSC) - Editorial Correction IR 05000280/20233012023-12-28028 December 2023 NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23352A3692023-12-18018 December 2023 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML23334A2342023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23242A2292023-11-0707 November 2023 Issuance of Amendment Nos. 315 and 315, Regarding Emergency Procedure Relocation of the Technical Support Center ML23200A2622023-11-0202 November 2023 Issuance of Amendment Nos. 314 and 314, Regarding Technical Specification and Spent Fuel Pool Criticality Change IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 ML23286A0372023-10-13013 October 2023 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J ML23285A0922023-10-12012 October 2023 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests ML23277A1172023-10-0303 October 2023 Operator Licensing Examination Approval 05000280/2023301 and 05000281/2023301 ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23244A2352023-09-18018 September 2023 Request to Use a Subsequent Edition of the ASME Code, Section XI ML23230A0012023-09-15015 September 2023 Request to Use a Provision of a Previous Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for Non-Destructive Examinations IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 ML23244A0142023-08-30030 August 2023 Inservice Inspection Owner'S Activity Report IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) ML23226A1862023-08-10010 August 2023 Proposed License Amendment Request - Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML23220A1492023-08-0707 August 2023 Independent Spent Fuel Storage Installation - Submittal of Cask Registrations for Spent Fuel Storage ML23220A1482023-08-0707 August 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Response to Request for Additional Information IR 05000280/20230022023-08-0404 August 2023 Integrated Inspection Report 05000280/2023002 and 05000281/2023002 ML23208A0922023-07-26026 July 2023 Request for Approval of Appendix F of Fleet Report DOM-NAF-2-P Qualification of Framatome ORFEO-GAIA and OORFE-NMGRID CHF Correlations in the Dominion Energy Vipre-D Computer Code Response ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations ML23198A0322023-07-18018 July 2023 Regulatory Audit Report Regarding Review of License Amendment to Modify Emergency Plan Staff Augmentation Times ML23193A9382023-07-18018 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML23173A0602023-07-11011 July 2023 Audit Summary for License Amendment Request Revision of the Emergency Plan to Support Relocation of the Technical Support Center ML23136B1392023-06-29029 June 2023 Issuance of Amendment No. 313 Administrative Changes to Subsequent Renewed Operating Licenses and Technical Specifications ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23152A0432023-06-22022 June 2023 Audit Plan License Amendment Requests to Change Emergency Plan Staff Augmentation Times ML23153A1732023-06-16016 June 2023 Correction to Amendment Nos. 346 & 286 Millstone, 294 & 277 North Anna, 311 & 311 Surry, and 225 Summer to Revise Technical Specifications to Adopt TSTF-554,Rev Reactor Coolant Leakage Requirement ML23163A2352023-06-12012 June 2023 Request to Use a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI, for the SPS Sixth Inservice Inspection (Isi) Intervals and VCSNS Fifth ISI Interval ML23151A6612023-05-31031 May 2023 ES-2.1-1, Surry 2023-301 Corporate Notification Letter (Revised) ML23167B0072023-05-31031 May 2023 Proposed Emergency Plan Revision - Relocation of the Technical Support Center (TSC) Supplemental Information - LOCA Dose Calculation Summary ML23117A0952023-05-10010 May 2023 Audit Plan License Amendment Request to Support Relocation of the Technical Support Center ML23130A3742023-05-10010 May 2023 Request to Delay NRC Intial Licensing Examination 2024-02-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 30, 2014 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
SURRY POWER STATION, UNIT NO.2, REVIEW OF THE 2012 STEAM GENERATOR TUBE INSPECTION REPORT (TAC NOS. MF1968)
~
Dear Mr. Heacock:
Th~ U.S. Nuclear Regulatory Commission (NRC) staff formally reviews all steam generator (SG) inservice inspection summary reports submitted by licensees in accordance with the plant's Technical Specification requirements. By letter dated May 10, 2013 (Agencywide Documents Access Management System (ADAMS) Accession No. ML13149A229), Virginia Electric and Power Company (Dominion), the licensee, submitted information summarizing the results of the steam generator tube inspections performed during the 2012 refueling outage at Surry Power Station (SPS), Unit No.2. The licensee submitted additional information regarding the same inspections on January 23, 2014 (ADAMS Accession No. ML14028A256).
The NRC staff has completed its review of the submittals pertaining to the SPS, Units No.2, SG inspections, and the associated review summary is enclosed. The NRC staff finds that the licensee has provided the information required by the TSs. In addition, the staff did not identify any technical issues that warrant follow-up action at this time. Based on these considerations, the subject TAGs are being closed.
Please contact me at (301) 415-2597, if you have any questions regarding this issue.
Sincerely, Dr. V. Sreenivas, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-281
Enclosure:
As stated cc w/encl: Distribution via Listserv
UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION REVIEW OF THE 2012 STEAM GENERATOR TUBE INSERVICE INSPECTION REPORT VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION, UNITS NO.2 DOCKET NOS. 50-281 By letter dated May 10, 2013 (Agencywide Documents Access Management System (ADAMS)
Accession No. ML13149A229), Virginia Electric and Power Company (Dominion), the licensee, submitted information summarizing the results of the steam generator tube inspections performed 1
during the 2012 refueling outage at Surry Power Station (SPS), Unit No.2. The licensee submitted additional information regarding the same inspections on January 23, 2014 (ADAMS Accession No. ML14028A256).
Surry Power Station, Unit 2 has three Westinghouse model 51 F SGs. Each SG has 3,342 thermally treated Alloy 600 tubes with an outside diameter of 0.875 inches and a nominal wall thickness of 0.050 inches. The tubes are hydraulically expanded for the full depth of the tubesheet at each end. The tubes are supported by stainless steel support plates with quatrefoil-shaped holes. The U-bend region of the tubes installed in rows 1-8 was thermally
- treated after bending in order to reduce stress.
The licensee provided the scope, extent, methods, and results of their SG tube inspections in the documents referenced above. In addition, the licensee described corrective actions (i.e., tube plugging) taken in response to the inspection findings. The tubes in SG A were inspected this outage.
After reviewing the information provided by the licensee, the staff has the following comments/observations:
The licensee indicated that the replacement SGs have operated for 301 .8 effective full power months since the first inservice inspection after installation.
Based on a review of the information provided, the staff concludes that the licensee provided the information required by their Technical Specifications. In addition, the staff concludes that there are no technical issues that warrant follow-up action at this time since the inspections appear to be consistent with the objective of detecting potential tube degradation and the inspection results appearto be consistent with industry operating experience at similarly designed and operated units.
Enclosure
ML14028A256).
The NRC staff has completed its review of the submittals pertaining to the SPS, Units No. 2, SG inspections, and the associated review summary is enclosed. The NRC staff finds that the licensee has provided the information required by the TSs. In addition, the staff did not identify any technical issues that warrant follow-up action at this time. Based on these considerations, the subject TAGs are being closed.
Please contact me at (301) 415-2597, if you have any questions regarding this issue.
Sincerely,
/RAJ Dr. V. Sreenivas, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-281
Enclosure:
As stated cc w/encl: Distribution vfa Listserv DISTRIBUTION:
Public LPL2-1 R/F RidsNrrDeEsgb Resource AJohnson, NRR RidsAcrsAcnw_MaiiCTR Resource RidsNrrLASFigueroa Resource GKulesa, NRR RidsNrrDorllpl2-1 Resource RidsOgcRp Resource KKarwoski, NRR RidsNrrDssStsb Resource RidsNrrPMNorthAnna Resource Rid~Rgn2Mai1Center Resource ADAMS Access1on No.: ML141 5OA137 *B'jy Memo bae t d 02/06/2014 OFFICE LPL2-1/PM LPL2-1/LA DE/ESGB/BC LPL2-1/BC LPL2-1/PM NAME VSreenivas SFigueroa* GKulesa* RPascarelli VSreenivas DATE 05/30/14 05/30/14 02/06/14 05/30/14 05/30/14'