ML18024A402

From kanterella
Revision as of 02:09, 22 October 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Updated Final Safety Analysis Report (Ufsar), Amendment 27, Appendix M - Table of Contents
ML18024A402
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 10/05/2017
From:
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation
Shared Package
ML18018A778 List: ... further results
References
Download: ML18024A402 (3)


Text

BFN-25 APPENDIX M REPORT ON PIPE FAILURES OUTSIDE CONTAINMENT IN THE BROWNS FERRY NUCLEAR PLANT TABLE OF CONTENTS M.1 Introduction ..................................................................................................................................... M.0-1 M.2 Pressure Analyses .......................................................................................................................... M.0-2 M.3 Piping Design Philosophy ............................................................................................................... M.0-6 M.3.1 Piping From Reactor Vessel Through the Anchor Outside the Drywell ............................. M.0-6 M.3.2 Piping From the Anchor Through Turbine Inset or Feedwater Pump Discharge ............... M.0-7 M.4 Breaks Postulated and Loading Effects Considered ....................................................................... M.0-7 M.5 Pipe Rupture Loads ........................................................................................................................ M.0-8 M.5.1 Critical Crack Size Loading ............................................................................................... M.0-9 M.5.2 Jet Expansion Considerations ...........................................................................................M.0-10 M.5.3 Jet Impingement Loads ..................................................................................................... M.0-11 M.5.4 Break Size ......................................................................................................................... M.0-12 M.6 Pipe Break Assumptions, Analysis, and Break Locations ............................................................... M.0-12 M.6.1 Pipe Rupture Analysis ....................................................................................................... M.0-12 M.6.2 Case I - Circumferential Break Postulated at Point 1 ........................................................ M.0-13 M.6.3 Case II - Circumferential Break Postulated at Points 2 and 3 ............................................ M.0-13 M.6.4 Case III - Circumferential Break Postulated at Points 4 and 5 ........................................... M.0-14 M.6.5 Case IV - Longitudinal Break Postulated at Point 1 ........................................................... M.0-14 M.6.6 Case V - Longitudinal Breaks Postulated at and Between Points 2 and 3 ........................ M.0-16 M.6.7 Case VI - Longitudinal Break Postulated at the Elbow in Main Steam Lines (Turbine Building) .............................................................................................................. M.0-16 M.6.8 Case VII - Critical Crack Loading ......................................................................................M.0-18 M.6.9 Additional High Energy Line Break Analysis...................................................................... M.0-19 M.7 Structural Analysis .......................................................................................................................... M.0-22 M.8 Effects on Safety-Related Components and Structures .................................................................. M.0-23 M.9 Additional Work ............................................................................................................................... M.0-25 M.10 Summary and Conclusions ............................................................................................................. M.0-25 M.11 References ...................................................................................................................................... M.0-26 M.0-i

BFN-25 APPENDIX M LIST OF TABLES Table Title M.0-1 Deleted M.0-2 Deleted M.0-ii

BFN-25 LIST OF FIGURES APPENDIX M LIST OF FIGURES Figure Title M.0-1 Pipe Failure Analysis - Main Steam and Feedwater Vault Enclosure M.0-2 Main Steam line Break Accident Mass of Coolant Lost Through Break M.0-3 Jet Loading Model M.0-4 Steam line Break Locations in Steam Vault M.0-5 Feedwater Line Break Locations in Steam Vault M.0-6 Jet Impingement Loading on RCIC Pump Discharge Line M.0-7 Pipe Impact Analytical Model for Worst Pipe Break Inside Turbine Building M.0-iii