09/14/2007 Revised Notice - Date Change of Meeting with Progress Energy Florida to Discuss Status of the Power Uprates at Crystal River, Unit 3
ML072410005
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/29/2007
From: Stewart Bailey
Plant Licensing Branch III-2
To: Boyce T
NRC/NRR/ADRO/DORL/LPLII-2
Bailey S , NRR/DORL,415-1321
References
Download: ML072410005 (6)


Text

August 29, 2007CHANGED MEETING DATEMEMORANDUM TO: Thomas H. Boyce, Chief Plant Licensing Branch II-2

Division of Operating Reactor LicensingFROM: Stewart N. Bailey, Senior Project Manager Plant Licensing Branch

/RA/ Division of Operating Reactor Licensing

SUBJECT:

FORTHCOMING MEETING WITH PROGRESS ENERGY FLORIDA DATE & TIME: Friday, September 7, 2007 Friday, September 14, 2007 9:00 a.m. to 12:00 p.m.LOCATION: U.S. Nuclear Regulatory Commission One White Flint North

11555 Rockville Pike, Room O-4 B6

Rockville, MarylandPURPOSE: To discuss the status of the power uprates at Crystal River Unit 3.

CATEGORY 1:* This is a Category 1 Meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with

the Nuclear Regulatory Commission (NRC) after the business portion, but before the meeting is adjourned.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC LICENSEE T. McGintyD. RoderickP. Infanger T. BoyceD. VarnerP. Rose S. BaileyT. Williams et al.K. Wilson Docket No. 50-302

Enclosure:

Agenda

cc w/encl: See next page CONTACTS: Stewart Bailey, NRRM. Vaaler, NRR 301-415-1321301-415-3178

snb@nrc.gov mgv@nrc.gov

  • Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings" (67 FR 36920), May 28, 2002 AGENDA FOR THE SEPTEMBER 14, 2007, PUBLIC MEETING BETWEEN THE NRC AND PROGRESS ENERGY FLORIDA REGARDING THE STATUS OF POWER UPRATES AT CRYSTAL RIVER UNIT 3 AGENDA:I.Margin Uncertainty Recapture A.License Amendment Request1.Submittals 2.Requests for Additional Informationa.)Response Summary b.)Feedback 3.Technical Specification Changesa.)Rated Thermal Power Definition b.)Treatment of leading-edge flow meter (LEFM) and Input Unavailabilityc.)Current ProposalB.Status of Engineering/Installation Activities1.Configuration Change (LEFM and Flow Straighteners) 2.Completed Engineering Change Packages 3.Preinstallation Testing Progress 4.Installation Status 5.ScheduleII.Extended Power UprateA.Major Task Status1.NSSSa.)License Amendment Request b.)Safety and Transient Analysis c.)Fuels2.Focus Areasa.)Rapid Cooldown b.)Core Flood Line Break c.)Mass and Energy Input Validation d.)Confirmation of Boron Precipitation Mitigation e.)Ultimate Heat Sink Systems3.Turbine Generator 4.Balance of Plant 5.Schedule Enclosure

ML072410005NRC-001OFFICELPLII-2/PMLPLII-2/LALPLII-2/BCNAMESBaileyBClaytonBMozafari foTBoyceDATE08/29/0708/29/0708/29/07

SUBJECT:

FORTHCOMING MEETING ON SEPTEMBER 14, 2007, WITH PROGRESS ENERGY FLORIDA Date: August 29, 2007 DISTRIBUTION

RidsNrrDorlLpl2-2RidsOgcMailCenterRidsRgn2MailCenter RidsOpaMailCenterRidsAcrsAcnwMailCenterRidsNrrAdro RidsNrrLABClaytonRidsNrrPMSBailey RidsNrrDorl PUBLICLPL2-2 R/FT. Liu, NRR K. Clark, RIIS. Campbell, EDOReceptionist (OWFN & TWFN)

PMNS Florida Power CorporationCrystal River Nuclear Plant, Unit 3 cc:

Mr. R. Alexander Glenn Associate General Counsel (MAC-BT15A)

Florida Power Corporation

P.O. Box 14042

St. Petersburg, Florida 33733-4042 Mr. Michael J. Annacone Plant General Manager

Crystal River Nuclear Plant (NA2C)

15760 W. Power Line Street

Crystal River, Florida 34428-6708Mr. Jim Mallay Framatome ANP

1911 North Ft. Myer Drive, Suite 705

Rosslyn, Virginia 22209 Mr. William A. Passetti, Chief Department of Health

Bureau of Radiation Control

2020 Capital Circle, SE, Bin #C21

Tallahassee, Florida 32399-1741 Attorney General Department of Legal Affairs

The Capitol

Tallahassee, Florida 32304 Mr. Craig Fugate, Director Division of Emergency Preparedness

Department of Community Affairs

2740 Centerview Drive

Tallahassee, Florida 32399-2100 Chairman Board of County Commissioners

Citrus County

110 North Apopka Avenue

Inverness, Florida 34450-4245 Mr. Stephen J. Cahill Engineering Manager

Crystal River Nuclear Plant (NA2C)

15760 W. Power Line Street

Crystal River, Florida 34428-6708 Mr. Jon A. Franke Director Site Operations Crystal River Nuclear Plant (NA2C)

15760 W. Power Line Street

Crystal River, Florida 34428-6708 Senior Resident Inspector Crystal River Unit 3

U.S. Nuclear Regulatory Commission

6745 N. Tallahassee Road

Crystal River, Florida 34428 Ms. Phyllis Dixon Manager, Nuclear Assessment

Crystal River Nuclear Plant (NA2C)

15760 W. Power Line Street

Crystal River, Florida 34428-6708 David T. Conley Associate General Counsel II - Legal Dept.

Progress Energy Service Company, LLC

Post Office Box 1551

Raleigh, North Carolina 27602-1551 Mr. Daniel L. Roderick Vice President, Nuclear Projects &

Construction Crystal River Nuclear Plant (SA2C)

15760 W. Power Line Street

Crystal River, Florida 34428-6708 Mr. David Varner Manager, Support Services - Nuclear

Crystal River Nuclear Plant (SA2C)

15760 W. Power Line Street

Crystal River, Florida 34428-6708 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)

ATTN: Supervisor, Licensing

& Regulatory Programs

15760 W. Power Line Street

Crystal River, Florida 34428-6708