Revised Notice - Date Change of Meeting with Progress Energy Florida to Discuss Status of the Power Uprates at Crystal River, Unit 3
ML072410005
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/29/2007
From: Stewart Bailey
Plant Licensing Branch III-2
To: Boyce T
NRC/NRR/ADRO/DORL/LPLII-2
Bailey S , NRR/DORL,415-1321
References
Download: ML072410005 (6)


Text

August 29, 2007 CHANGED MEETING DATE MEMORANDUM TO: Thomas H. Boyce, Chief Plant Licensing Branch II-2 Division of Operating Reactor Licensing FROM: Stewart N. Bailey, Senior Project Manager Plant Licensing Branch /RA/

Division of Operating Reactor Licensing

SUBJECT:

FORTHCOMING MEETING WITH PROGRESS ENERGY FLORIDA DATE & TIME: Friday, September 7, 2007 Friday, September 14, 2007 9:00 a.m. to 12:00 p.m.

LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room O-4 B6 Rockville, Maryland PURPOSE: To discuss the status of the power uprates at Crystal River Unit 3.

CATEGORY 1:* This is a Category 1 Meeting: The public is invited to observe this meeting and will have one or more opportunities to communicate with the Nuclear Regulatory Commission (NRC) after the business portion, but before the meeting is adjourned.

PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC LICENSEE T. McGinty D. Roderick P. Infanger T. Boyce D. Varner P. Rose S. Bailey T. Williams et al. K. Wilson Docket No. 50-302

Enclosure:

Agenda cc w/encl: See next page CONTACTS: Stewart Bailey, NRR M. Vaaler, NRR 301-415-1321 301-415-3178 snb@nrc.gov mgv@nrc.gov

  • Commission's Policy Statement on Enhancing Public Participation in NRC Meetings (67 FR 36920), May 28, 2002

AGENDA FOR THE SEPTEMBER 14, 2007, PUBLIC MEETING BETWEEN THE NRC AND PROGRESS ENERGY FLORIDA REGARDING THE STATUS OF POWER UPRATES AT CRYSTAL RIVER UNIT 3 AGENDA:

I. Margin Uncertainty Recapture A. License Amendment Request

1. Submittals
2. Requests for Additional Information a.) Response Summary b.) Feedback 3.Technical Specification Changes a.) Rated Thermal Power Definition b.) Treatment of leading-edge flow meter (LEFM) and Input Unavailability c.) Current Proposal B. Status of Engineering/Installation Activities
1. Configuration Change (LEFM and Flow Straighteners)
2. Completed Engineering Change Packages
3. Preinstallation Testing Progress
4. Installation Status
5. Schedule II. Extended Power Uprate A. Major Task Status
1. NSSS a.) License Amendment Request b.) Safety and Transient Analysis c.) Fuels
2. Focus Areas a.) Rapid Cooldown b.) Core Flood Line Break c.) Mass and Energy Input Validation d.) Confirmation of Boron Precipitation Mitigation e.) Ultimate Heat Sink Systems
3. Turbine Generator
4. Balance of Plant
5. Schedule Enclosure

ML072410005 NRC-001 OFFICE LPLII-2/PM LPLII-2/LA LPLII-2/BC NAME SBailey BClayton BMozafari fo TBoyce DATE 08/29/07 08/29/07 08/29/07

SUBJECT:

FORTHCOMING MEETING ON SEPTEMBER 14, 2007, WITH PROGRESS ENERGY FLORIDA Date: August 29, 2007 DISTRIBUTION:

RidsNrrDorlLpl2-2 RidsOgcMailCenter RidsRgn2MailCenter RidsOpaMailCenter RidsAcrsAcnwMailCenter RidsNrrAdro RidsNrrLABClayton RidsNrrPMSBailey RidsNrrDorl PUBLIC LPL2-2 R/F T. Liu, NRR K. Clark, RII S. Campbell, EDO Receptionist (OWFN & TWFN)

PMNS

Florida Power Corporation Crystal River Nuclear Plant, Unit 3 cc:

Mr. R. Alexander Glenn Director Site Operations Associate General Counsel (MAC-BT15A) Crystal River Nuclear Plant (NA2C)

Florida Power Corporation 15760 W. Power Line Street P.O. Box 14042 Crystal River, Florida 34428-6708 St. Petersburg, Florida 33733-4042 Senior Resident Inspector Mr. Michael J. Annacone Crystal River Unit 3 Plant General Manager U.S. Nuclear Regulatory Commission Crystal River Nuclear Plant (NA2C) 6745 N. Tallahassee Road 15760 W. Power Line Street Crystal River, Florida 34428 Crystal River, Florida 34428-6708 Ms. Phyllis Dixon Mr. Jim Mallay Manager, Nuclear Assessment Framatome ANP Crystal River Nuclear Plant (NA2C) 1911 North Ft. Myer Drive, Suite 705 15760 W. Power Line Street Rosslyn, Virginia 22209 Crystal River, Florida 34428-6708 Mr. William A. Passetti, Chief David T. Conley Department of Health Associate General Counsel II - Legal Dept.

Bureau of Radiation Control Progress Energy Service Company, LLC 2020 Capital Circle, SE, Bin #C21 Post Office Box 1551 Tallahassee, Florida 32399-1741 Raleigh, North Carolina 27602-1551 Attorney General Mr. Daniel L. Roderick Department of Legal Affairs Vice President, Nuclear Projects &

The Capitol Construction Tallahassee, Florida 32304 Crystal River Nuclear Plant (SA2C) 15760 W. Power Line Street Mr. Craig Fugate, Director Crystal River, Florida 34428-6708 Division of Emergency Preparedness Department of Community Affairs Mr. David Varner 2740 Centerview Drive Manager, Support Services - Nuclear Tallahassee, Florida 32399-2100 Crystal River Nuclear Plant (SA2C) 15760 W. Power Line Street Chairman Crystal River, Florida 34428-6708 Board of County Commissioners Citrus County Mr. Dale E. Young, Vice President 110 North Apopka Avenue Crystal River Nuclear Plant (NA1B)

Inverness, Florida 34450-4245 ATTN: Supervisor, Licensing

& Regulatory Programs Mr. Stephen J. Cahill 15760 W. Power Line Street Engineering Manager Crystal River, Florida 34428-6708 Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. Jon A. Franke