05000482/FIN-2017003-04
From kanterella
Revision as of 22:19, 16 November 2017 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Finding | |
---|---|
Title | Failure to Verify Equipment or Systems are Capable of Performing Their Intended Design Function Following Maintenance |
Description | The inspectors reviewed a Green, self-revealed non-cited violation of Technical Specification 5.4.1.a for the licensees failure to ensure that maintenance that can affect the performance of safety-related equipment was properly pre-planned and performed in accordance with written procedures, documented, instructions, or drawings appropriate to the circumstances. Specifically, the licensee failed to verify that the wiring in the transformer 7 primary differential protective relay was landed on the correct termination point, and as a result, the station experienced an unplanned loss of normal offsite power to bus NB01, the train A Class 1E electrical bus.Description. On November 16, 2016, at approximately 9:09 p.m., a fault occurred that isolated the east switchyard bus from the train A safety-related 4160 volt alternating current bus NB01, while the Wolf Creek Nuclear Generating Station was in Mode 5 with the reactor coolant system filled and a bubble in the pressurizer. During refueling outage 21, a modification to transformer 7 allowed the offsite power through transformer 7 to bus NB01 to be fed from either the east or west switchyard busses through two different breakers (345-80 or 345-90). After the loss of the east switchyard bus, the second breaker unexpectedly tripped, which resulted in a loss of offsite power to NB01. An undervoltage condition was detected on bus NB01, which caused the train A emergency diesel generator to start and power bus NB01 as designed. All other systems functioned as expected. Westar, the substation owner, determined that the initial fault was caused by a mouse on the 13-4 circuit at Wolf Creek. The 13-4 relay and breaker cleared the fault and coordinated with all upstream devices. Approximately 5.5 seconds after the initial fault, a second fault occurred in transformer 6. The transformer 7 digital differential relay scheme provides a standard configuration with primary and secondary protective relays, each with the capability of isolating transformer 7. Troubleshooting activities focused on the reason why the primary relay tripped and the secondary relay did not trip. Westar technicians identified a jumper on the transformer 7 primary differential relay current transformer circuit that had been improperly landed. The jumper was designed to run from the neutral circuit of one current transformer to the neutral circuit of the other. However, Westar Energy technicians had incorrectly landed the jumper from the neutral of the first current transformer onto the C phase of the other. This allowed current from the transformer 6 fault event to be detected in the transformer 7 primary differential relay circuit.The inspectors reviewed the cause evaluation completed by the licensee, whichdetermined that the direct cause of this event was the wiring in the transformer 7 primary differential protective relay was landed on the incorrect termination point. This cause is supported by the fact that this incorrect termination allowed additional current to be introduced onto the C phase relay circuit, which initiated the trip circuit actuation.The inspectors also reviewed corrective actions associated with the root cause evaluation for the unplanned plant shutdown, loss of offsite power, and Notification of Unusual Event declaration that occurred on January 13, 2012. An Augmented Inspection Team was chartered to review the circumstances surrounding the loss of offsite power event and Notification of Unusual Event declarationan issue of Yellow safety significance was identified. The event from January 13, 2012, involved equipment owned by Wolf Creek (startup transformer XMR01), with work being performed by Wolf Creek contractors. The November 16, 2016, event involved equipment owned by Westar (transformer 7). While inspectors acknowledge that the two events from January 13, 2012, and November 16, 2016, are not exactly the same, the inspectors noted that they are similar in that they both involved the modification of current transformer wiring associated with transformers that provide power to train A and B engineered safety function transformers (XNB01 and XNB02, respectively), which supply train A and B Class 1E electrical busses NB01 and NB02, respectively. The inspectors did not determine that the 2012 event actions were causal to the 2016 event; however, the inspectors noted similarities between the identified causes. Procedure AP 21C-001, Wolf Creek Substation, establishes responsibilities and defines necessary interfaces and communications for the operational control, coordination and maintenance necessary to ensure Wolf Creek Substation protection, safety and reliability. The inspectors reviewed the licensees assessment associated with the 2016 event and concluded that the substation work control process requirements in procedure AP 21C-001 were not adequately met. Specifically, step 6.2.5.1 states, in part, that following preventive or corrective maintenance work, appropriate post-maintenance inspections, checks, and/or testing shall be performed to verify that affected equipment or systems (primary and secondary differential relay circuitry) are capable of performing their intended design function.The wiring error on the primary differential protective relay was corrected and its functionality was verified. The secondary differential protective relay wiring was also verified to be correct. The east switchyard bus, transformer 7, and its differential relays were all restored to service. The licensee documented the event in LER 2016-002-00 and Condition Reports 109467 and 116849. The licensee also updated procedure AP 21C-001 to include additional detail and steps that require work instructions for post maintenance testing of current transformer wiring to ensure independent verification of wiring terminations.Analysis. The licensees failure to verify that the primary and secondary differential relay circuitry is capable of performing its intended design function following maintenance was a performance deficiency. The performance deficiency was more than minor because it affected the design control attribute of the Mitigating Systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, the licensee failed to verify that the wiring terminations for the primary differential protective relay for transformer 7 were installed correctly, leading to the isolation of transformer 7, resulting in an unplanned loss of offsite power to NB01, the train A Class 1E electrical bus. The inspectors evaluated the finding using Exhibit 3, "Mitigating SystemsScreening Questions," of Inspection Manual Chapter 0609, Appendix G, Attachment 1, "Shutdown Operations Significance Determination Process Phase I Initial Screening and Characterization of Finding," and Appendix G, "Shutdown Operations Significance Determination Process," both issued May 9, 2014. The inspectors determined this finding is a deficiency affecting the design or qualification of a mitigating SSC, and the SSC maintained its operability or functionality. Therefore, the inspectors determined the fi nding was of very low safety significance (Green). The inspectors determined that the finding has a human performance cross-cutting aspect in the area of resources because leaders did not ensure that personnel, equipment, procedures, and other resources are available and adequate to support nuclear safety. Specifically, leaders did not ensure adequate procedures were available to support successful work performance including necessary standards for verifying wiring circuitry terminations such that the loss of power to the NB01 Class 1E electrical bus would not have occurred. This issue is indicative of current performance because the issue occurred in the last three years [H.1]. |
Site: | Wolf Creek |
---|---|
Report | IR 05000482/2017003 Section 4OA3 |
Date counted | Sep 30, 2017 (2017Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | D Dodson F Thomas T Farina P Jayroe E Ruesch N Taylor |
Violation of: | Technical Specification - Procedures |
CCA | H.1, Resources |
INPO aspect | LA.1 |
' | |
Finding - Wolf Creek - IR 05000482/2017003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Wolf Creek) @ 2017Q3
Self-Identified List (Wolf Creek)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||