|
---|
Category:Preliminary Safety Analysis Report (PSAR)
MONTHYEARML15258A3692015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 01 - the Facility ML15258A5322015-08-27027 August 2015 Enclosure 1, Attachment 1 - Preliminary Safety Analysis Report Changes Markups ML15258A5332015-08-27027 August 2015 Enclosure 1 - Update to the Evaluation of Aircraft Hazard and the Evaluation of Chemical Hazards Provided in the Preliminary Safety Analysis Report ML15258A5972015-08-27027 August 2015 Enclosure 2, Attachment 2 - Preliminary Safety Analysis Report Changes (Markup) ML15258A3892015-08-27027 August 2015 Shine Medical Technologies V. 0 - PSAR Master Table of Contents ML15258A4302015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.5.2-006 Through 19.5.2-009 ML15258A4292015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.5.2-001 Through 19.5.2-005 ML15258A4282015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.4.1-001 Through 19.4.13-001 ML15258A4262015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.4-001 Through 19.3.4-008 ML15258A4242015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.3-001 Through 19.3.3-007 ML15258A4232015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.2-001 Through 19.3.2-036 ML15258A4222015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.1-007 Through 19.3.1-009 ML15258A4202015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.2.1-001 Through 19.2.3-001 ML15258A4182015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.07 - References ML15258A4172015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.06 - Conclusions ML15258A4162015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.05 - Alternatives ML15258A4152015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.04 - Impacts of Proposed Construction, Operations, and Decommissioning ML15258A4142015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.03 - Description of the Affected Environment ML15258A4132015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.02 - Proposed Action ML15258A4122015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.01 - Introduction to the Environmental Report ML15258A4192015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Environmental Review ML15258A4112015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 12 - Figure 12.1-001 ML15258A4102015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 11 - Figures 11.1-001 and 11.1-003 ML15258A4092015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 09 - Figures 9b.2-001 Through 9b.7-008 ML15258A4082015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 09 - Figures 9a2.1-001 Through 9a2.7-001 ML15258A4072015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 08 - Figure 8a2.2-001 ML15258A4062015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 08 - Figure 8a2.1-001 ML15258A4052015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 07 - Figure 7b.2-001 ML15258A4032015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 05 - Figures 5a2.1-001 Through 5a2.4-001 ML15258A3702015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Site Characteristics ML15258A3902015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 01 - Figures 1.3-001 Through 1.3-006 ML15258A3912015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.1-001 Through 2.1-026 ML15258A4042015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 07 - Figures 7a2.1-001 Through 7a2.6-002 ML15258A3922015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.2-001 Through 2.2-002 ML15258A3932015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.3-001 Through 2.3-036 ML15258A3982015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.5-007 Through 2.5-023 ML15258A3712015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 03 - Design of Structures, Systems, and Components ML15258A3722015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 04 - Irradiation Unit and Radioisotope Production Facility Description ML15258A3732015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 05 - Cooling Systems ML15258A3742015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 06 - Engineered Safety Features ML15258A3752015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 07 - Instrument and Control Systems ML15258A3782015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 08 - Electrical Power Systems ML15258A3802015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 10 - Experimental Facilities ML15258A4022015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 04 - Figures 4b.3-001 Through 4b.4-007 ML15258A4002015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 04 - Figures 4a2.1-001 Through 4a2.8-002 ML15258A3792015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 09 - Auxiliary Systems ML15258A3992015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 03 - Figures 3.4-001 Through 3.4-014 ML15258A3882015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 18 - Highly Enriched to Low Enriched Uranium Conversion ML15258A3872015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 17 - Decommissioning and Possession-Only License Amendments ML15258A3852015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 15 - Financial Qualifications 2015-08-27
[Table view] Category:License-Application for Construction Permit DKT 50
MONTHYEARML22279A9512022-10-0606 October 2022 Shine Technologies, LLC Request to Amend Construction Permit No. CPMIF-001 ML22091A0932022-04-0101 April 2022 Shine Technologies, LLC Request to Amend Construction Permit No. CPMIF-001 ML21232A6202021-08-20020 August 2021 Shine Medical Technologies, LLC Request to Amend Construction Permit No. CPMIF-001 - Response to Request for Additional Information ML21119A1682021-04-29029 April 2021 Enclosure 2: Request to Amend Construction Permit No. CPMIF-001 ML18347A2152018-12-11011 December 2018 Shine Medical Technologies - Application for Order Approving Indirect Transfer of Control of Construction Permit and Conforming Administrative Construction Permit Amendment ML15247A0672015-09-0202 September 2015 Shine Medical Technologies, Inc. Application for Construction Permit Response to Request for Additional Information ML15258A3692015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 01 - the Facility ML15258A4302015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.5.2-006 Through 19.5.2-009 ML15258A4292015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.5.2-001 Through 19.5.2-005 ML15258A4282015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.4.1-001 Through 19.4.13-001 ML15258A4262015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.4-001 Through 19.3.4-008 ML15258A4242015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.3-001 Through 19.3.3-007 ML15258A4232015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.2-001 Through 19.3.2-036 ML15258A4222015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.3.1-007 Through 19.3.1-009 ML15258A4202015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Figures 19.2.1-001 Through 19.2.3-001 ML15258A4182015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.07 - References ML15258A4172015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.06 - Conclusions ML15258A4162015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.05 - Alternatives ML15258A4152015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.04 - Impacts of Proposed Construction, Operations, and Decommissioning ML15258A4142015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.03 - Description of the Affected Environment ML15258A4132015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.02 - Proposed Action ML15258A4122015-08-27027 August 2015 Shine Medical Technologies V. 0 - Section 19.01 - Introduction to the Environmental Report ML15258A4192015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 19 - Environmental Review ML15258A4112015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 12 - Figure 12.1-001 ML15258A4102015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 11 - Figures 11.1-001 and 11.1-003 ML15258A4092015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 09 - Figures 9b.2-001 Through 9b.7-008 ML15258A4082015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 09 - Figures 9a2.1-001 Through 9a2.7-001 ML15258A4072015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 08 - Figure 8a2.2-001 ML15258A4062015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 08 - Figure 8a2.1-001 ML15258A4042015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 07 - Figures 7a2.1-001 Through 7a2.6-002 ML15258A3892015-08-27027 August 2015 Shine Medical Technologies V. 0 - PSAR Master Table of Contents ML15258A3702015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Site Characteristics ML15258A3902015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 01 - Figures 1.3-001 Through 1.3-006 ML15258A3912015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.1-001 Through 2.1-026 ML15258A3922015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.2-001 Through 2.2-002 ML15258A3932015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.3-001 Through 2.3-036 ML15258A3982015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 02 - Figures 2.5-007 Through 2.5-023 ML15258A3712015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 03 - Design of Structures, Systems, and Components ML15258A3722015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 04 - Irradiation Unit and Radioisotope Production Facility Description ML15258A3732015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 05 - Cooling Systems ML15258A3742015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 06 - Engineered Safety Features ML15258A3752015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 07 - Instrument and Control Systems ML15258A3782015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 08 - Electrical Power Systems ML15258A3792015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 09 - Auxiliary Systems ML15258A3812015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 11 - Radiation Protection Program and Waste Management ML15258A4052015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 07 - Figure 7b.2-001 ML15258A4032015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 05 - Figures 5a2.1-001 Through 5a2.4-001 ML15258A4022015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 04 - Figures 4b.3-001 Through 4b.4-007 ML15258A4002015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 04 - Figures 4a2.1-001 Through 4a2.8-002 ML15258A3992015-08-27027 August 2015 Shine Medical Technologies V. 0 - Chapter 03 - Figures 3.4-001 Through 3.4-014 2022-04-01
[Table view] |
Text
Figure 8a2.1 One-Line Diagram - Normal Electrical Power Supply System NOTES:1. BREAKERS DROP OUT (TRIP) ON LOSS OF POWER TO THE BUS AND CAN BE MANUALLY CLOSED SELECTIVELY AFTER SDG RESTORES POWER TO THE BUSES.2. SDG AND AUTOMATIC TRANSFER EQUIPMENT LOCATED IN SEPARATE BUILDING.
- 3. RESPECTIVE 480V AC SWGR BUS A OR B POWERS THE SDG BUSES DURING NORMAL OPERATION. ON LOSS OF OFF-SITE POWER, BOTH AC SWGR A AND B WILL BE CONNECTED AS NEEDED.4. ON LOSS OF OFF-SITE POWER SDG WILL START. AFTER RATED VOLTAGE AND FREQUENCY ARE ESTABLISHED AT THE SDG BUS, BREAKER FEEDS TO OTHER FACILITY LOADS WILL BE MANUALLY CONNECTED AS NEEDED.5. LOAD BREAKERS EQUIPPED WITH SOFT STARTERS.6. SDG - STANDBY DIESEL GENERATOR7. FIRE PUMP CONTROLLER BOX PER NFPA 20 AND IS LOCATED IN SIGHT OF FIRE PUMP ROOM.480V-208Y/120V75 kVA3PHDISTRIBUTION PANEL FOR TCAP 1, 2, 3 & 4CHILLER 1FACILITY 480V AC PLANT SWGR A208Y/120V 200A3PH, 4W12kV-480Y/277V2000 kVA 3PHTRANSFORMER OUTDOOR TYPE12kV UTILITY FEEDER CABLE BUSUTILITY INTERFACEZONE 1 EXHAUSTFAN A ZONE 2 EXHAUSTFAN A OUTDOOR NC M480V-208Y/120V75 kVA 3PHDISTRIBUTION PANEL FOR TCAP 5, 6, 7 & 8CHILLER 3 FACILITY 480V AC PLANT SWGR B208Y/120V 200A 3PH, 4W12kV-480Y/277V 2000 kVA3PHTRANSFORMER OUTDOOR TYPE12kV UTILITY FEEDERCABLE BUSUTILITY INTERFACEZONE 2 EXHAUSTFAN B(STANDBY)OUTDOOR NC M480VLATER kW 3PH, 4W NC NOBATTERYCHARGER ABATTERYCHARGER BNCNC NO NOPLUG-INPORTABLE DG FACILITY 480V AC SDG BUS A AT SWGR ROOM NOTE 3 NOTE 3 NCNOTE 4 LOCATED INSDG BUILDINGUPS VOLTAGEREGULATINGXFMR ASSEMBLY BUPS VOLTAGEREGULATINGXFMR ASSEMBLY A NC NC NC NCTO 480V AC MCC A1TO 480V ACMCC A2TO 480V AC MCC B1TO 480V ACMCC B2TO 480V ACSDG MCC B125 HP200 HP100 HP 200 HP100 HPSDGCHILLER 4 200 HPCHILLER 2200 HPEMERGENCYLIGHTINGPANELZONE 1EXHAUST FAN B(STANDBY)125 HP NCTO 480V ACSDG MCC A NCEMERGENCYLIGHTINGPANEL FACILITY 480V AC SDG BUS B AT SWGR ROOM NO OUTDOOR LOAD BANKFOR SDGTESTING NO NOFROM 480V AC SUPPLY SDG MCC A FIRE PUMP 200 HPFIRE PUMP ROOM(LOCATED OUTSIDE FACILITY)FIRE PUMPCONTROLLER BOX (NOTE 7) Chapter 8 - Electrical Power Systems Normal Electrical Power Systems SHINE Medical Technologies Rev. 0 Figure 8a2.1 One-Line Diagram - Normal Electrical Power Supply System NOTES:1. BREAKERS DROP OUT (TRIP) ON LOSS OF POWER TO THE BUS AND CAN BE MANUALLY CLOSED SELECTIVELY AFTER SDG RESTORES POWER TO THE BUSES.2. SDG AND AUTOMATIC TRANSFER EQUIPMENT LOCATED IN SEPARATE BUILDING.
- 3. RESPECTIVE 480V AC SWGR BUS A OR B POWERS THE SDG BUSES DURING NORMAL OPERATION. ON LOSS OF OFF-SITE POWER, BOTH AC SWGR A AND B WILL BE CONNECTED AS NEEDED.4. ON LOSS OF OFF-SITE POWER SDG WILL START. AFTER RATED VOLTAGE AND FREQUENCY ARE ESTABLISHED AT THE SDG BUS, BREAKER FEEDS TO OTHER FACILITY LOADS WILL BE MANUALLY CONNECTED AS NEEDED.5. LOAD BREAKERS EQUIPPED WITH SOFT STARTERS.6. SDG - STANDBY DIESEL GENERATOR7. FIRE PUMP CONTROLLER BOX PER NFPA 20 AND IS LOCATED IN SIGHT OF FIRE PUMP ROOM.480V-208Y/120V75 kVA3PHDISTRIBUTION PANEL FOR TCAP 1, 2, 3 & 4CHILLER 1FACILITY 480V AC PLANT SWGR A208Y/120V 200A3PH, 4W12kV-480Y/277V2000 kVA 3PHTRANSFORMER OUTDOOR TYPE12kV UTILITY FEEDER CABLE BUSUTILITY INTERFACEZONE 1 EXHAUSTFAN A ZONE 2 EXHAUSTFAN A OUTDOOR NC M480V-208Y/120V75 kVA 3PHDISTRIBUTION PANEL FOR TCAP 5, 6, 7 & 8CHILLER 3 FACILITY 480V AC PLANT SWGR B208Y/120V 200A 3PH, 4W12kV-480Y/277V 2000 kVA3PHTRANSFORMER OUTDOOR TYPE12kV UTILITY FEEDERCABLE BUSUTILITY INTERFACEZONE 2 EXHAUSTFAN B(STANDBY)OUTDOOR NC M480VLATER kW 3PH, 4W NC NOBATTERYCHARGER ABATTERYCHARGER BNCNC NO NOPLUG-INPORTABLE DG FACILITY 480V AC SDG BUS A AT SWGR ROOM NOTE 3 NOTE 3 NCNOTE 4 LOCATED INSDG BUILDINGUPS VOLTAGEREGULATINGXFMR ASSEMBLY BUPS VOLTAGEREGULATINGXFMR ASSEMBLY A NC NC NC NCTO 480V AC MCC A1TO 480V ACMCC A2TO 480V AC MCC B1TO 480V ACMCC B2TO 480V ACSDG MCC B125 HP200 HP100 HP 200 HP100 HPSDGCHILLER 4 200 HPCHILLER 2200 HPEMERGENCYLIGHTINGPANELZONE 1EXHAUST FAN B(STANDBY)125 HP NCTO 480V ACSDG MCC A NCEMERGENCYLIGHTINGPANEL FACILITY 480V AC SDG BUS B AT SWGR ROOM NO OUTDOOR LOAD BANKFOR SDGTESTING NO NOFROM 480V AC SUPPLY SDG MCC A FIRE PUMP 200 HPFIRE PUMP ROOM(LOCATED OUTSIDE FACILITY)FIRE PUMPCONTROLLER BOX (NOTE 7) Chapter 8 - Electrical Power Systems Normal Electrical Power Systems SHINE Medical Technologies Rev. 0