(Nei), Request for Endorsement of Seismic Evaluation Guidance: Spent Fuel Pool Integrity Evaluation (EPRI 3002009564)
ML17031A171
Person / Time
Site: Nuclear Energy Institute
Issue date: 01/31/2017
From: Mauer A N
Nuclear Energy Institute
To: Franovich M X
Japan Lessons-Learned Division
Vega F G, NRR/JLD, 415-1617
Shared Package
ML17031A169 List:
References
Download: ML17031A171 (2)


Text

ANDREW N. MAUER Senior Project Manager, Risk Assessment 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8018 anm@nei.org nei.org January 31, 2017 Mr. Michael Franovich Director, Japan Lessons-Learned Division Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Request for Endorsement of Seismic Evaluation Guidance: Spent Fuel Pool Integrity Evaluation (EPRI 3002009564) Project Number: 689

Dear Mr. Franovich:

This letter provides a link to the Seismic Evaluation Guidance: Spent Fuel Pool Integrity Evaluation (EPRI 3002009564) for U.S. Nuclear Regulatory Commission (NRC) review and endorsement. The NRC-endorsed Seismic Evaluation Guidance: Screening, Prioritization and Implementation Details (SPID) for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1:Seismic (EPRI 1025287) provides guidance for conducting sewhich requested that licensees and holders of construction permits under 10 CFR Part 50 reevaluate the seismic hazards at their sites against present-day NRC requirements and guidance. letter, which asks that plants reevaluate the seismic hazards at their sites against present-day NRC requirements and guidance. Section 7 of EPRI 1025287 provides guidance for performing an evaluation of the spent fuel pool (SFP) that considers all seismically induced failures that can lead to draining of the SFP. The evaluations provided in EPRI 3002009564 supplement the SFP evaluation guidance in EPRI 1025287 and show that SFPs can retain adequate water inventory for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> provided the plant meets a limited set of parameters. This report provides SFP seismic evaluation guidance for the structural and non-structural aspects of SFP integrity. Separate guidance is provided for plants in which the ground motion response spectrum (GMRS) peak spectral acceleration is less than or equal to 0.8g, and for plants in which the GMRS peak spectral acceleration is greater than 0.8g. A key conclusion of the report is that the seismic induced SFP inventory losses are modest and that the majority of inventory losses over 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> are due to boil off.

Mr. Michael Franovich January 31, 2017 Page 2 This report provides criteria, which will enable plants to confirm that their plant parameters are enveloped by those considered in this evaluation. Based upon the NRC letter to power reactor licensees dated October 27, 2015, the plants required to perform a spent fuel pool evaluation which have a GMRS peak spectral acceleration >0.8g, will submit a response consistent with Section 4.3 of EPRI 3002009564 by December 31, 2017. Please utilize the following link to retrieve the report. If you have any questions, please contact me. Sincerely, Andrew N. Mauer c: Gregory Bowman, NRR/JLD/PPSD/HMB, NRC