MONTHYEARML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 NL-24-0237, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0240, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0166, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 NL-24-0157, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint NL-24-0144, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 IR 05000321/20230062024-02-28028 February 2024 Annual Assessment Letter Edwin I. Hatch Nuclear Plant Units 1 and 2 - Nrc Inspection Report 05000321/2023006 and 05000366/2023006 NL-24-0067, 10 CFR 72.48(d)(2) Biennial Report2024-02-26026 February 2024 10 CFR 72.48(d)(2) Biennial Report NL-24-0051, License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-02-20020 February 2024 License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers IR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. IR 05000321/20233012024-01-17017 January 2024 – NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) 2024-09-09
[Table view] |
Text
Southern Nuclear Operating Company, Inc, 1e* 205992 500( April 24, 2009 SOUTHERN'\
COMPANY Ellergr to St'rt't' lour World' Docket No.: 50-366 NL-09-0577 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant -Unit 2 GNF-Ziron Lead Test Assemblies Ladies and Gentlemen:
This letter provides an information report describing the two (2) GE14 bundles with GNF-Ziron fuel cladding contained in lead test assemblies (L TAs) loaded into the Plant Hatch-Unit 2 core during the twentieth refueling outage (2R20). Also enclosed in this report is information related to the applicability of NRC-approved methods used to analyze the assemblies, the objective of the lead test assembly program, and measurements to be performed as part of the test program. This letter contains no NRC commitments.
If additional information is required, please contact R. D. Baker at 205-992-7367.
Sincerely, M. J. Ajluni Manager, Nuclear Licensing MJAlPAH/daj
Enclosure:
Information Report Description of Lead Test Assemblies Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. D. R. Madison, Vice President
-Hatch Ms. P. M. Marino, Vice President
-Engineering RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. R. E. Martin, NRR Project Manager -Hatch Mr. J. A. Hickey, Senior Resident Inspector
-Hatch
Edwin I. Hatch Nuclear Plant - Unit 2 GNF-Ziron Lead Test Assemblies Enclosure Information Report Description of Lead Test Assemblies Enclosure Plant Hatch GNF-Ziron LTAs Information Report Description of Lead Test Assemblies Page 1 of 2 Two lead test assemblies (LTAs), with selected fuel rods (~30 rod in each assembly) fabricated from GNF-Ziron cladding material, will be loaded into Plant Hatch Unit 2 during reload 20 for Cycle 21, with planned operation through Cycles 22 and 23. The LTAs also incorporate water rods manufactured from GNF-Ziron material. These GNF-supplied fuel assemblies are standard GE14 fuel assemblies with the exception of the cladding material and water rod material. GNF-Ziron is a zirconium-based alloy with composition very similar to the industry standard Zircaloy-2 but with increased iron content. The dimensions and processing of all assembly components are identical to the standard GE14 assemblies.
GE14 fuel is licensed according to criteria and requirements specified in GESTAR II (General Electric Standard Application For Reactor Fuel, NEDE-24011-P-A), as reported in the GE14 compliance report (GE14 Compliance With Amendment 22 of NEDE- 24011-P-A, NEDC-32868P, Rev. 2). The GE14 compliance report states that the GE14 fuel cladding and water rods are made of Zircaloy-2.
Because the composition of GNF-Ziron falls outside of the ASTM-specification ranges for Zircaloy-2, the current GE14 compliance report does not cover the use of GNF-Ziron for reload applications. Specific approval from the NRC on the use of GNF-Ziron as cladding material is therefore required before the alloy can be deployed in reload quantities; in addition, an amendment to the GE14 compliance report will be needed. GNF is in the process of preparing a Licensing Topical Report to seek NRC approval for the use of GNF-Ziron as cladding material. In
the absence of specific approval from the NRC, Reference 1 discusses how LTAs could be loaded provided LTAs are analyzed with approved methods. Accordingly, the two GE14 GNF-Ziron LTAs are being loaded into Plant Hatch Unit 2 per provisions in 10 CFR Part 50, Section 50.59. However, 10 CFR Part 50, Section 50.46 and Appendix K specifically address cladding material made from Zircaloy or Zirlo. As GNF-Ziron is not a Zircaloy, an exemption to the requirements of 10 CFR Part 50, Section 50.46 and Appendix K was submitted to the NRC (Reference 2). A more detailed description of GNF-Ziron is given in Reference 3, which forms one of the attachments in the exemption request (Reference 2).
Applicability of GESTAR-II Methods and Exemptions From Requirements of 10 CFR Part 50, Section 50.46 and Appendix K The key properties of GNF-Ziron are described in Reference 4. A discussion on the applicability of approved methods to GNF-Ziron cladding is given in Reference 3. In particular, the impact of GNF-Ziron on thermal-mechanical evaluations is given in Reference 5, with the conclusion that GNF-Ziron behavior can be adequately modeled by the existing GNF methods; hence, no impact on thermal-mechanical licensing limits is expected. The application of selected GNF-Ziron fuel rods in the two GE14 LTAs is therefore consistent with "As long as the analysis of the LTAs using approved methods meets the approved criteria, it would be concluded that no unreviewed safety question exists" as discussed in Reference 1.
Enclosure Plant Hatch GNF-Ziron LTAs Information Report Description of Lead Test Assemblies Page 2 of 2 In support of the Reference 2 application for exemption from 10 CFR Part 50, Section 50.46 and Appendix K requirements to use zircaloy fuel cladding, information on the high temperature oxidation behavior of GNF-Ziron pertaining to postulated loss-of coolant accident (LOCA) considerations is provided in Reference 3. The exemption request was approved by the NRC on Nov 7, 2008 (Reference 6).
Objective of LTA Program The objective of the LTA program at Plant Hatch is to obtain operational experience with GNF-Ziron. The performance of GNF-Ziron under normal operating conditions is expected to be similar to that of Zircaloy-2. The LTA
program will provide confirmation on the GNF-Ziron performance.
Outline of Measurements Since obtaining operational experience with GNF-Ziron is the objective of the Hatch LTA program, poolside inspections (e.g., visual, eddy current liftoff, and profilometry) will be conducted on selected rods.
References
- 1. NRC Letter, "Lead Test Assembly Licensing," T. A. Ippolito (NRC) to R. E.
Engel, September 23, 1981. 2. SNC Letter to NRC, "Edwin I. Hatch Nuclear Plant - Unit 2 Submittal of Additional Information to Support Proposed Exemption to 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow Ziron Fuel Cladding," September 22, 2008, ML082681156. 3. "Technical Basis Supporting GNF-Ziron Lead Test Assembly Introduction into the Hatch Nuclear Plant" in License support letter for GNF-Ziron LTA at Hatch, eDRFsection 0000-0079-7396, Rev. 4, as attachment in Reference 2. 4. "Properties of GNF-Ziron" in Proprietary and Non-Proprietary versions of GNF-Ziron Properties and TM Assessment, eDRFsection 0000-0087-8749, Rev. 2, ML082250038. 5. "Impact of GNF-Ziron Cladding on Thermal-Mechanical Licensing Limits" in Proprietary and Non-Proprietary versions of GNF-Ziron Properties and TM Assessment, eDRFsection 0000-0087-8749, Rev. 2., ML082250037. 6. NRC Letter, "Edwin I. Hatch Nuclear Plant, Unit No 2- Exemptions from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K (TAC No.
MD8356)," R. E. Martin to D. H. Jones, November 7, 2008, ML082950149.