Relief, Relief Requests Nos. RR-89-60 and IR-2-44 Requesting for Alternatives to the 10-Year Reactor Vessel Examinations Requirements (TAC Nos. MD1719 and MD1720)
ML070740465
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 05/01/2007
From: Chernoff H K
NRC/NRR/ADRO/DORL/LPLI-2
To: Christian D A
Dominion Nuclear Connecticut
nerses V, NRR//DORL, 415-1484
References
IR-2-44, RR-89-60, TAC MD1719, TAC MD1720
Download: ML070740465 (7)


Text

May 1, 2007Mr. David A. ChristianSr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - RELIEF REQUESTSNOS. RR-89-60 AND IR-2-44 REQUESTING FOR ALTERNATIVES TO THE 10-YEAR REACTOR VESSEL EXAMINATIONS REQUIREMENTS (TAC NOS. MD1719 AND MD1720)

Dear Mr. Christian:

By letter dated May 11, 2006, [Agency Documents Access and Management System (ADAMS)accession number ML061530137] Dominion Nuclear Connecticut, Inc. (DNC) submitted to the U.S. Nuclear Regulatory Commission (NRC), Relief Requests RR-89-60 and IR-2-44 for approval to use alternatives to the examination requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI at the Millstone Power Station, Unit Nos. 2 and 3. Specifically, DNC requests the use of Performance Demonstration Initiative (PDI) qualified procedures for the performance of the ultrasonic testing examination of the reactor pressure vessel shell-to-flange weld in accordance with ASME Code,Section XI, Division I,1995 Edition,1996 Addenda, Appendix VIII, Supplements 4 and 6. Therelief is requested pursuant to Title 10 of the Code of Federal Regulations (10 CFR),Section 50.55a(a)(3)(i).Based upon the review of the information you provided, the NRC concluded that the proposedalternative provides reasonable assurance of satisfactory ultrasonic testing examination of thereactor pressure vessel shell-to-flange weld that are performed from the vessel side of the weld, and the NRC finds that the use PDI qualified procedures as an alternative provides an acceptable level of quality and safety. Therefore, pursuant to 10 CFR 50.55a(a)(3)(i), your proposed alternative is authorized. The NRC staff's Safety Evaluation is enclosed. If you have any questions, please contact the project manager, John Hughey at (301) 415-3204.Sincerely,/ra/Harold K. Chernoff, Chief Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-336, 50-423

Enclosure:

As stated cc: See next page

ML070740465*By memo datedNRR-028OFFICELPL1-2/PMLPL1-2/LALPL1-2/PMCPNB/BCOGC (NLO)LPLI-2/BCNAMEVNersesCSolaJHugheyTChan*DRothHChernoffDATE3/22/073/20/074/27/07 2/14/0704/25/075/1/07 Millstone Power Station, Unit Nos. 2 and 3 cc:

Lillian M. Cuoco, EsquireSenior Counsel Dominion Resources Services, Inc.

Building 475, 5 th Floor Rope Ferry Road Waterford, CT 06385Edward L. Wilds, Jr., Ph.D.Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127Regional Administrator, Region IU.S. Nuclear Regulatory Commission

475 Allendale Road King of Prussia, PA 19406First SelectmenTown of Waterford 15 Rope Ferry Road Waterford, CT 06385Charles Brinkman, DirectorWashington Operations Nuclear Services Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852Senior Resident InspectorMillstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357Mr. J. W. "Bill" Sheehan Co-Chair NEAC 19 Laurel Crest Drive Waterford, CT 06385Ms. Nancy Burton147 Cross Highway Redding Ridge, CT 00870Mr. Evan W. WoollacottCo-Chair Nuclear Energy Advisory Council 128 Terry's Plain Road Simsbury, CT 06070Mr. Joseph RoyDirector of Operations Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056Mr. David W. DodsonLicensing Supervisor Dominion Nuclear Connecticut, Inc.

Building 475, 5 th FloorRoper Ferry Road Waterford, CT 06385Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.

Building 475, 5 th FloorRope Ferry Road Waterford, CT 06385 Mr. Chris L. FunderburkDirector, Nuclear Licensing and Operations Support Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 EnclosureSAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATIONRELIEF REQUESTS NOS. RR-89-60 AND IR-2-44MILLSTONE POWER STATION, UNIT NOS. 2 AND 3DOMINION NUCLEAR CONNECTICUT, INC.DOCKET NUMBERS 50-336 AND 50-42

31.0 INTRODUCTION

By letter dated May 11, 2006, Dominion Nuclear Connecticut, Inc. (DNC) submitted to theU.S. Nuclear Regulatory Commission (NRC), a request for approval to use alternatives to the examination requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI at the Millstone Power Station, Unit Nos. 2 and 3 (MPS2 and MPS3). Specifically, DNC requests the use of Performance Demonstration Initiative (PDI) qualified procedures for the performance of the ultrasonic testing examination of the reactor pressure vessel shell-to-flange weld in accordance with ASME Code,Section XI, Division I,1995 Edition,1996 Addenda, Appendix VIII, Supplements 4 and 6. The relief isrequested pursuant to Title 10 of the Code of Federal Regulations (10 CFR),Section 50.55a(a)(3)(i).

2.0REGULATORY EVALUATION

The inservice inspection (ISI) of the ASME Code Class 1, 2, and 3 components is to beperformed in accordance with Section XI of the ASME Code and applicable edition and addenda as required by 10 CFR 50.55a(g), except where specific written relief has been granted by NRC pursuant to 10 CFR 50.55a(g)(6)(i). 10 CFR 50.55a(a)(3) states in part that alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if the licensee demonstrates that: (i) the proposed alternatives would provide an acceptable level of quality and safety, or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (includingsupports) shall meet the requirements, except the design and access provisions and the pre-service examination requirements, set forth in the ASME Code,Section XI, "Rules for ISI of Nuclear Power Plant Components," to the extent practical within the limitations of design, geometry, and materials of construction of the components. The regulations require that inservice examination of components and system pressure tests conducted during the first 10-year interval and subsequent intervals comply with the requirements in the latest edition and addenda of Section XI of the ASME Code incorporated by reference in 10 CFR 50.55a(b) twelve months prior to the start of the 120-month interval, subject to the limitations and modifications listed therein. The ISI Code of record for the third 10-year ISI interval for MPS2and the second 10-year ISI interval for MPS3 is the 1989 Edition of the ASME Code,Section XI. In addition, 10 CFR 50.55a(g)(6)(ii)(C)(2) requires that licensees using the 1989 Edition or earlier editions must implement the 1995 Edition with the 1996 Addenda of Appendix VIII and the supplements to Appendix VIII of Section XI of the ASME Code.3.0EVALUATION FOR RELIEF REQUEST NOS. RR-89-60 AND IR-2-443.1Components for Which Relief is RequestedASME Code Class 1, Item B1.30, Reactor Pressure Vessel (RPV) Shell-to-Flange weldsidentified as:Millstone 2:Weld FS-1Millstone 3:Weld 101-1213.2Code RequirementsThe 1989 Edition of ASME Code,Section XI, Appendix I, Subparagraph I-2110, requires thatultrasonic testing (UT) of RPV shell-to-flange welds be conducted in accordance with Article 4 of ASME Code,Section V, supplemented by the requirements of Table I-2000-1. In addition, Regulatory Guide (RG) 1.150, Revision 1, "Ultrasonic Testing of Reactor Vessel Welds During Preservice and Inservice Examinations," serves as guidance for UT examination of RPV welds.3.3 Licensee's Proposed Alternative and Basis for UseDuring the upcoming 10-year RPV vessel examinations, the licensee proposes to performultrasonic examinations of the RPV shell-to-flange welds using procedures, personnel, and equipment that have been demonstrated and qualified in accordance with ASME Section XI, 1995 Edition with 1996 Addenda, Appendix VIII, Supplements 4 and 6 as amended by 10 CFR50.55a. The examination will be performed automated as qualified in accordance with ASME Code,Section XI, 1995 Edition with 1996 Addenda, Appendix VIII, Supplement s 4 and 6 asamended by 10 CFR 50.55a and the PDI Program. Since the subject examinations will be performed from a single side due to the weld configuration, all procedures, personnel, and equipment will be qualified for single side access for examination of these welds.Appendix VIII requirements were developed and adopted to ensure the effectiveness ofultrasonic examinations within the nuclear industry by means of a rigorous, item specific performance demonstration containing flaws of various sizes, locations, and orientations. The performance demonstration process has established with a high degree of confidence, the capability of personnel, procedures, and equipment to detect and characterize flaws that could be detrimental to the structural integrity of the RPV. The PDI approach has demonstrated that for detection and characterization of flaws in the RPV the ultrasonic examination techniques are equal to or surpass the requirements of the ASME Code,Section V, Article 4 ultrasonic examination requirements. The licensee finds that though Appendix VIII is not required for the RPV shell-to-flange weldexamination, the use of Appendix VIII, Supplements 4 and 6 criteria for detection and sizing offlaws in the subject welds will be equal to or exceed the requirements of ASME Code,Section V, Article 4 and the guidance in RG 1.150. 3.4NRC Staff Evaluation The ASME Code requires that ultrasonic examination of shell-to-flange welds in vessels greaterthan 2 inches in thickness be conducted in accordance with Article 4 of the ASME Code,Section V, as supplemented by requirements in Table I-2000-1. ASME Code,Section V, Article 4 provides a prescriptive process for qualifying UT procedures and performing examinations. The licensee instead proposes to use procedures and personnel qualified in accordance with performance-based criteria listed in the 1995 Edition, 1996 Addenda of the ASME Code,Section XI, Appendix VIII, Supplements 4 and 6 as implemented by the industry'sPDI program. These performance-based methods are currently required by 10 CFR 50.55a for examination of all other RPV shell welds (having replaced the Article 4 techniques).Amplitude-based sizing techniques such as the prescriptive UT procedures that comply with therequirements of Article 4 of ASME Code,Section V, are based on the amplitude of the returned signal and correlating that amplitude with an equivalent machined reflector such as a notch or a side-drilled hole. However, correlation between defect size and amplitude has been poor.

This is not unexpected given the number of variables from the material, equipment and defect itself. The material has potential velocity and microstructure variations, and the equipment has potential amplitude variations due to the type of pulser, frequency band, cabling, and other inherent electrical parameters. Perhaps the biggest variable is the defect itself. Ultrasonic examination is highly sensitive to defect orientation. Also, transparency, roughness, curvature, and location play a role in the ability to detect and size defects. In addition, conventional amplitude-based ultrasonics is particularly unreliable for vertical defects.When prescriptive UT procedures that comply with the requirements of Article 4 of ASME Code,Section V, were used in round robin tests containing real flaws in RPV mockups, and the results statistically analyzed according to the screening criteria of ASME Code,Section XI, Appendix VIII, the procedures proved to be less effective than ex aminations that utilizeAppendix VIII, Supplements 4 and 6, qualified procedures. Performance-based UT is generallyapplied with higher sensitivity, which increases the probability of detecting a flaw when compared to prescriptive Section V, Article 4 requirements. Also, flaw sizing is more accurately determined with the time-based tip diffraction criteria used by performance-based ultrasonics than with the less accurate amplitude criteria for prescriptive Section V, Article 4 requirement.

Procedures, equipment, and personnel qualified through the PDI program have demonstrated their skill level to detect flaws common to nuclear power plants and have shown high probability of detection levels. This has resulted in an increased reliability of inspections for weldconfigurations subject to the requirements of Appendix VIII.The licensee states that the examination, using automated equipment, will be performed byprocedures qualified in accordance with ASME Code,Section XI, 1995 Edition with 1996 Addenda, Appendix VIII, Supplements 4 and 6 as amended by 10 CFR 50.55a and the PDIprogram. Due to the weld configuration the examination will be performed from a single side.

Therefore, all procedures, personnel, and equipment will be qualified for single-sided access for examination of the subject welds. 3.5SummaryThe NRC staff finds that the use of UT procedures and personnel qualified to the 1995 Editionwith 1996 Addenda of Section XI of the ASME Code, Appendix VIII, Supplement 4 and 6, asmodified by 10 CFR 50.55a by demonstration through the PDI program for the RPV shell-to-flange weld, provides equivalent or better examination results than those obtained from ASME Code,Section V requirements and RG 1.150 recommendations. Therefore, based on the above analysis, the staff considers that an acceptable level of quality and safety will be maintained when using the licensee's proposed alternative examination.

4.0 CONCLUSION

The NRC staff concludes that the proposed alternative with PDI qualified procedures andpersonnel applied from the RPV shell surface along with the improved capabilities as discussed above will provide equivalent or better examination results than those realized from the ASME Code,Section V, requirements and RG 1.150 recommendations and, therefore, will provide an acceptable level of quality and safety. Therefore, pursuant to 10 CFR 50.55a(a)(3)(i), the NRC authorizes the proposed alternative for the remainder of the third 10-year ISI interval at MPS2 and the second 10-year ISI interval at MPS3.All other ASME Code,Section XI requirements for which relief was not specifically requestedand approved in this, or previous, relief requests remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.Principal Contributor: A. Keim Date: May 1, 2007