ML16357A151

From kanterella
Revision as of 01:20, 2 February 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Revision 18 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance
ML16357A151
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 09/19/2016
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML16357A167 List:
References
Download: ML16357A151 (2)


Text

LGS UFSAR

CHAPTER 17 17-i REV. 13, SEPTEMBER 2006 CHAPTER 17 - QUALITY ASSURANCE

TABLE OF CONTENTS 17.1 QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION

17.2 QUALITY ASSURANCE DURING THE OPERATIONS PHASE

APPENDIX 17.2B - Deleted.

APPENDIX 17.2.I - Deleted.

APPENDIX 17.2.II - Deleted.

LGS UFSAR CHAPTER 17 17.2-1 REV. 13, SEPTEMBER 2006 CHAPTER 17 - QUALITY ASSURANCE

17.1 QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION

This section is not applicable to the LGS UFSAR.

17.2 QUALITY ASSURANCE DURING THE OPERATIONS PHASE

The licensee is responsible for the operation and maintenance of Limerick Generating Station (LGS). These activities are presently conducted in accordance with the NRC approved Quality

Assurance Topical Report (QATR) which descr ibes the formal and comprehensive control methods established to assure compliance with 10CFR50, Appendix B.

The QATR describes how the Quality Assurance Pr ogram is to be functionally implemented with due regard to the safety and health of the public and the personnel on site. The LGS Quality

Assurance Program as described by the QA TR is incorporated herein by reference.