 Issue dateFromTitleProject stage
ML08170029412 June 2008Tennessee Valley Authority
Langley D
Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Response to ACRS Conclusions and Recommendations Regarding Containment Overpressure CreditOther
ML08172007816 June 2008Tennessee Valley Authority
Langley D
(BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Schedule Regarding EPUOther
ML08175008016 June 2008Tennessee Valley Authority
Langley D
Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 15 Group 4 and Round 17 Request for Additional Information (RAI)Request
ML08175008116 June 2008Tennessee Valley Authority
Structural Integrity Associates
Encl. 6, Calculation Package 0006982.301, Extended Power Uprate Main Steam Line Strain Gage Vibration Monitoring, and Encl. 7, Response to Round 15 Group 4 and Round 17 Request for Additional InformationRequest
ML0817602959 April 2008Tennessee Valley Authority
Langley D
Units 1, 2, & 3 - Technical Specifications Changes TS-431 and TS-418 - Extended Power Uprate - Confirmation of Commitment CompletionsOther
ML08203061610 July 2008Tennessee Valley AuthorityTVA Presentation Slides for the July 10, 2008 Meeting on COPMeeting
ML08204006522 July 2008Ellen Brown
NRC/NRR/ADRO/DORL/LPLII-2
Summary of with Tennessee Valley Authority, Regarding Containment Overpressure Portion of the Extended Power Uprate ReviewOther
ML08205046218 July 2008Tennessee Valley AuthorityBrown Ferry Units 1, 2, and 3 - Non-Proprietary - Slides from July 18, 2008 TVA PresentationOther
ML0820702906 August 2008Ellen Brown
Plant Licensing Branch III-2
Summary of 7/9/08 Meeting with TVA to Discuss Upcoming Power Uprate ACRS PresentationMeeting
ML08210042525 July 2008Tennessee Valley Authority
West R
Technical Specifications Change TS-431, Proposed Extended Power Uprate (EPU) Fuels License ConditionOther
ML08227075812 August 2008Ellen Brown
Plant Licensing Branch II
Public RAI - Request for Additional Information for Extended Power Uprate - Round 19 (TAC Nos. MD5262 and MD5263) (TS-431 and TS-418)RAI
ML08233018715 August 2008Tennessee Valley Authority
Emens J
Units 2 and 3 - Technical Specifications (TS) Change TS-418- Extended Power Uprate (EPU) - Partial Response to Round 18 Request for Additional Information (RAI)Request
ML08234000212 August 2008Ellen Brown
Plant Licensing Branch II
Public Letter - Request for Additional Information for Extended Power Uprate - Round 19 (TAC Nos. MD5262 and MD5263) (TS-431 and TS-418)RAI
ML0824901692 September 2008Tennessee Valley Authority
Langley D
Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Response to Round 19 Request for Additional Information (RAI)Request
ML08259070916 September 2008Ellen Brown
Plant Licensing Branch II
Public Letter - Request for Additional Information for Extended Power Uprate - Round 20 (TAC Nos. MD5262, MD5263, and MD5264) (TS-431 and TS-418)RAI
ML08260000316 September 2008Ellen Brown
Plant Licensing Branch II
Public RAI - Request for Additional Information for Extended Power Uprate - Round 20 (TAC MD5262, MD5263, and MD5264) (TS-431 and TS-418)RAI
ML08269001619 September 2008Tennessee Valley Authority
Langley D
Specifications (TS) Change TS-418 - Extended Power Uprate (EPU) - Supplemental Response to Request for Additional Information (RAI) Round 3 & 18 & Response to Round 20 Fuels Methods RAIsSupplement
ML08276058317 November 2008Ellen Brown
Plant Licensing Branch II
Summary of July 18, 2008, Meeting with Tennessee Valley Authority Regarding Steam Dryer Portion of the Extended Power Uprate ReviewMeeting
ML0828104703 October 2008Tennessee Valley Authority
Langley D
Technical Specifications (TS) Change TS-431 - Extended Power Uprate (EPU) - Unit 1 Large Transient Testing (Ltt)Other
ML0828104713 October 2008Tennessee Valley Authority
Langley D
Technical Specification Changes TS-431 & TS-418 Extended Power Uprate - Supplemental Response to Round 19 Request for Additional Information & Response to Rounds 20 and 21 RAISupplement
ML0828200389 October 2008Ellen Brown
Plant Licensing Branch II
Brown Ferry, Units 1, 2 and 3, Request for Additional Information for Extended Power Uprate-Round 21 (TS-431 and TS-418)RAI
ML08289020614 October 2008Tennessee Valley AuthorityTVA Slides - EPU - Summary of October 14, 2008, Meeting with Tennessee Valley Authority Regarding Steam Dryer Portion of the Extended Power Uprate ReviewMeeting
ML08296022717 October 2008Tennessee Valley Authority
Brandon M
Technical Specifications Change TS-418 - Extended Power Uprate - Response to Round 21 Request for Additional Information on Channel BowRequest
ML0830302202 December 2008Ellen Brown
Plant Licensing Branch II
Summary of October 14, 2008, Meeting with Tennessee Valley Authority Regarding Steam Dryer Portion of the Extended Power Uprate Review (TAC Nos. MD5262 and MD5263)Meeting
ML0831000036 November 2008Ellen Brown
Plant Licensing Branch II
Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear PlantWithholding Request Acceptance
ML0831002416 November 2008Ellen Brown
Plant Licensing Branch II
Request for Withholding Information from Public DisclosureWithholding Request Acceptance
ML08312004512 November 2008Ellen Brown
Plant Licensing Branch II
Request for Additional Information for Extended Power Uprate - Round 22 (TAC Nos. MD5262 and MD5263) (TS-431 and TS-418)RAI
ML08312030731 October 2008Tennessee Valley Authority
Brandon M
Technical Specifications (TS) Changes TS-418 and TS-431, Extended Power Uprate (EPU) - Supplemental Response to Round 19 Request for Additional Information & Response to Round 22 Rai'S Regarding Steam DryersSupplement
ML08312030830 October 2008Structural Integrity Associates
Kok S
Calculation Package 0006982.304, Extended Power Uprate Main Steam Line Strain Gauge Vibration Monitoring.Other
ML08315042417 November 2008Ellen Brown
Plant Licensing Branch II
Request for Withholding Information from Public Disclosure for Browns Ferry Nuclear PlantWithholding Request Acceptance
ML08324022414 November 2008Tennessee Valley Authority
Brandon M
Technical Specifications Changes TS-431 & TS-418 - Extended Power Uprate (EPU) - Correction to Schedule Letter Regarding EPUOther
ML08325008314 November 2008Tennessee Valley Authority
Brandon M
(BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-418 and TS-431 - Extended Power Uprate (EPU) - Steam Dryer ReportsOther
ML08325011414 November 2008Tennessee Valley Authority
Emens J
(BFN) - Units 1, 2, & 3 - Technical Specifications (TS) Changes TS-418 & TS-431 - Extended Power Uprate (EPU) - Supplemental Response to Rounds 19 and 22 Request for Additional Information (RAI) Regarding Steam Dryers.Supplement
ML0834600218 December 2008Tennessee Valley Authority
Godwin F
Technical Specifications Changes TS-418 and TS-431 - Extended Power Uprate - Response to Request for Additional Information Regarding Withholding Information from Public DisclosureResponse to RAI
ML08353061915 December 2008Tennessee Valley Authority
Godwin F
Technical Specifications Change TS-431 - Extended Power Uprate - Response to Round 22 Request for Additional Information - Unit 1 Large Transient Testing (Ltt) -Request
ML0901307181 April 2009Division of Operating Reactor Licensing
Giitter J
Schedule Update for the Extended Power Uprate Amendment Requests (TAC Nos. MD5262 and MD5263) (TS-431 and TS-418)Other
ML0902203939 January 2009Tennessee Valley Authority
Godwin F
Technical Specifications Changes TS-418 and TS-431 - Extended Power Uprate - Response to Round 23 Request for Additional Information (RAI) Regarding Steam Dryer Analysis SubmodelingRequest
ML09023011216 January 2009Tennessee Valley Authority
Godwin F
Technical Specifications (TS) Changes TS-418 and TS-431 - Extended Power Uprate (EPU) - Response to Round 23 Request for Additional Information (RAI) Regarding Steam Dryer Signal ProcessingRequest
ML09027045123 January 2009Tennessee Valley Authority
Godwin F
(Bfn), Units 1, 2 and 3 - Technical Specifications (TS) Changes TS-418 and TS-431 - Extended Power Uprate (EPU) - Response to Round 23 Request for Additional Information (RAI) EMCB.203/164 Regarding Steam Dryer SignalRequest
ML09034052830 January 2009Gardner R
AREVA NP
Generic Implications of Issue Identified During an NRC Audit of Calculations Supporting an Extended Power Uprate SubmittalOther
ML09051017418 February 2009Tennessee Valley Authority
Godwin F
Technical Specifications Changes TS-418 and TS-431 - Extended Power Uprate - Response to Round 23 Request for Additional Information EMCB.204/168 Regarding Steam Dryer AnalysesRequest
ML09058019324 February 2009Tennessee Valley Authority
Godwin F
Technical Specifications Change TS-431 - Extended Power Uprate - Response to Round 23 Request for Additional Information - Large Transient TestingRequest
ML09071070523 March 2009Ellen Brown
Plant Licensing Branch II
Summary of Meeting with Tennessee Valley Authority (TVA) to Discuss Proposed Extended Power Uprate (EPU) Analyses RevisionMeeting
ML09071076826 February 2009Tennessee Valley AuthorityPresentation Slides: February 26, 2009 Meeting with the Tennessee Valley Authority (TVA) to Discuss Proposed Extended Power Uprate (EPU) Analyses RevisionMeeting
ML09071080723 March 2009Office of Nuclear Reactor RegulationSubmittal of Request for Additional Information from ACRS to NRC on Transmittal of ACRS Members' Concerns Regarding Containment Overpressure Credit for Browns Ferry Extended Power Uprate.RAI
ML09072095112 March 2009Tennessee Valley Authority
West R
Brown Ferry Nuclear Plant (Bfn), Units 1, 2, and 3, Technical Specifications (TS) Changes TS-431 and TS-418 - Extended Power Uprate (EPU) - Results of Revised Analyses for Short-Term Loss-of-Coolant Accident (LOCA) and Appendix R Regarding.Other
ML09076063011 March 2009Tennessee Valley Authority
West R
(BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Changes TS-418 and TS-431 - Extended Power Uprate (EPU) - Steam Dryer Analyses Additional InformationOther
ML09091035027 March 2009Tennessee Valley Authority
West R
Technical Specifications Change TS-431 - Extended Power Uprate - Response to Request for Additional Information - SRXB-78Response to RAI
ML09100028322 April 2009Ellen Brown
Plant Licensing Branch II
Public Letter and RAI - Request for Additional Information for Extended Power Uprate-Round 23 (TAC Nos. MD5262 and MD5263) (TS-431 and TS-418)RAI
ML0910002913 April 2009Tennessee Valley Authority
West R
(BFN) - Unit 1 - Technical Specifications (TS) Change TS-431 - Extended Power Uprate (EPU) - Response to Round 23 Request for Additional Information (RAI) EMCB.205 and EMCB.206Request