MONTHYEARML24232A1812024-08-19019 August 2024 Summer_2024-04_RP Information Request ML24190A0412024-07-0505 July 2024 Notification of Inspection and Request for Information ML24170A3892024-06-18018 June 2024 NRR E-mail Capture - Acceptance Review for VC Summer Containment Tendon Relief Request (L-2024-LLR-0035) ML24165A1912024-06-13013 June 2024 003 Radiation Safety Baseline Inspection Information Request ML24156A0022024-06-0303 June 2024 VC Summer SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Eric Carr ML24129A0722024-05-0808 May 2024 VC Summer SLRA - Requests for Confirmation of Information - Set 1 - Email from Marieliz Johnson to Eric Carr ML24075A1872024-03-15015 March 2024 NRR E-mail Capture - Draft RAIs for Alternative Request RR-5-V2 (L-2023-LLR-0068) ML24067A0672024-03-0707 March 2024 NRR E-mail Capture - Draft RAIs for Inverter CT License Amendment Request TS 3.8.3.1, Onsite Power Distribution - Operating, (L-2023-LLA-0157) ML24061A1892024-03-0101 March 2024 NRR E-mail Capture - Request for Additional Information (RAI) for VC Summer Inverter License Amendment Request (LAR) to Revise the Emergency Plan ML24052A0102024-02-16016 February 2024 NRR E-mail Capture - Draft RAIs for Emergency Plan (EP) Changes License Amendment Request (LAR) (L-2023-LLA-0083) ML24026A2802024-01-25025 January 2024 Acceptance Review for Virgil C. Summer Relief Requests RR-5-V1, RR-5-V2, and RR-5-V3 (EPIDs L-2023-LLR-0067, L-2023-LLR-0068, and L-2023-LLR-0069) (Email) ML23270B8712023-09-27027 September 2023 NRR E-mail Capture - Draft RAIs for License Amendment Request (LAR) to Revise the Virgil C. Summer Nuclear Station (VCSNS) Unit 1 Emergency Plan (L-2023-LLA-0083) ML23193A9552023-07-12012 July 2023 NRR E-mail Capture - Acceptance Review for VC Summer and Surry Relief Request (L-2023-LLR-0029) ML23186A1392023-07-0505 July 2023 NRR E-mail Capture - Acceptance Review for VC Summer Emergency Plan (EP) License Amendment Request (LAR) (L-2023-LLA-0083) ML23131A1492023-05-10010 May 2023 2023 V.C. Summer Commercial Grade Dedication Inspection Information Request ML23044A3392023-02-13013 February 2023 NRR E-mail Capture - Acceptance Review for Change to Reactor Vessel Surveillance Capsule Schedule (L-2023-LLL-0002) ML23027A0122023-01-26026 January 2023 002 Radiation Safety Baseline Inspection Information Request ML23026A0152023-01-23023 January 2023 NRR E-mail Capture - Feb 14, 2023 Public Meeting with the Dominion Energy to Discuss a Planned Emergency Preparedness Submittal to Relocate the Emergency Operations Facility for the VC Summer Power Station - Dominion Slides ML22263A0502022-09-19019 September 2022 NRR E-mail Capture - Draft Request for Additional Information for Proposed Alternative Request RR-4-26 Extension of Steam Generator Primary Inlet Nozzle Dissimilar Metal Weld Inspection Interval V.C. Summer Unit 1 ML22194A9422022-07-13013 July 2022 NRC 50.59 Inspection (IP 71111.17T) Information Request ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22173A0292022-06-17017 June 2022 NRR E-mail Capture - Acceptance Review for Summer to Defer Weld Examinations (L-2022-LLR-0052) ML22139A2302022-05-19019 May 2022 NRR E-mail Capture - Acceptance Review for Summer TS 4.6.2.1.d LAR (L-2022-LLR-0060) ML22139A2322022-05-19019 May 2022 NRR E-mail Capture - Acceptance Review for Summer TSTF-491 LAR (L-2022-LLR-0059) ML22084A4052022-03-25025 March 2022 NRR E-mail Capture - Acceptance Review for Summer Dissimilar Metal Weld Inspection Interval (L-2022-LLR-0033) ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21333A1892021-11-29029 November 2021 NRR E-mail Capture - Draft RAI for Summer LAR Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5b, (TSTF-425) ML21253A1352021-09-0808 September 2021 Document Request for VC Summer Nuclear Station - Radiation Protection Inspection - Inspection Report 2021-04 ML21197A0432021-07-15015 July 2021 VCS ISI 2021004 RFI - Combined ML21187A1242021-06-28028 June 2021 10CFR Part 21 Update - Deviation Identified in the Bolting Utilized to Maintain Seismic Qualification ML21173A1782021-06-22022 June 2021 NRR E-mail Capture - Acceptance Review - Summer LAR Unit Staff Qualification Relocation TS to Quality Assurance Program Description (QAPD) ML21145A0222021-05-24024 May 2021 003 Radiation Safety Baseline Inspection Information Request ML21131A0402021-05-11011 May 2021 NRR E-mail Capture - V.C. Summer, Unit 1 - Final RAI for the Spring 2020 RFO Sgtir Review ML21125A1942021-05-0505 May 2021 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit 1 - Acceptance Review (L-2021-LLA-0064) ML21020A0562021-01-20020 January 2021 Email Capture Upcoming V.C. Summer POV Inspection (IP71111.21N.02) Information Request ML20342A1822020-12-0707 December 2020 NRR E-mail Capture - Final RAI for Summer LAR - TS 3.6.4 ML20342A3822020-12-0707 December 2020 NRR E-mail Capture - Final RAIs for Summer Fs LOCA LAR ML20321A2112020-11-16016 November 2020 NRR E-mail Capture - Summer, Unit 1 - Final RAIs for the SG Tube Inspection Report Review ML20316A0122020-11-0404 November 2020 NRR E-mail Capture - V.C. Summer Nuclear Station, Unit 1 - Acceptance Review (L-2020-LLR-0141) ML20302A2032020-10-28028 October 2020 NRR E-mail Capture - V.C. Summer Nuclear Station, Unit 1 - Acceptance Review (L-2020-LLR-0141) ML20260H4262020-09-0303 September 2020 NRR E-mail Capture - Acceptance Review for Fleet Relief Request for Code Case N-885 ML20178A5892020-06-26026 June 2020 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit 1 - Acceptance Review of the Fsloca LAR (L-2020-LLA-0124) ML20178A5912020-06-23023 June 2020 NRR E-mail Capture - VC Summer Unit Alternate Request RR-4-21 ML20178A5932020-06-23023 June 2020 NRR E-mail Capture - VC Summer Unit Alternate Request RR-4-19 ML20149K4262020-05-21021 May 2020 NRR E-mail Capture - V. C. Summer, Unit 1 - Acceptance of License Amendment Request (LAR-20-142) Related to TS 3.6.4, Containment Isolation Valves (L-2020-LLA-0092) ML19218A3742019-08-0606 August 2019 NRR E-mail Capture - Virgil C. Summer, Unit 1 -Acceptance of Relief Request (RR-4-20), Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML19214A2732019-08-0202 August 2019 NRR E-mail Capture - Virgil C. Summer, Unit 1 - Acceptance of License Amendment Request to Change Company Name ML19211D5102019-07-30030 July 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 (Supplement to PRA RAI 03) ML19179A1262019-06-27027 June 2019 NRR E-mail Capture - Virgil C. Summer Nuclear Station, Unit No. 1 - Request for Additional Information LAR-16-01490 NFPA-805 Program Revisions ML19155A2752019-06-0404 June 2019 VC Summer 2019003 Rad Safety Inspection Document Request 2024-08-19
[Table view] |
Text
1 NRR-PMDAPEm Resource From: Orenak, Michael Sent: Saturday, January 14, 2017 10:27 AM To:jgarza@scana.com; bthompson@scana.com Cc:Williams, Shawn
Subject:
Verbal Authorization for Relief Request RR-4-11 John, Below is the script for the verbal authorization of relief request RR-4-11 that was provided at approximately 10:10 am EDT on 1/14/2017 by David Alley and Michael Markley. Please le t me or Shawn Williams know if you have any further questions. As I stated during the call, a written relief request authorization will be issued within 150 days from today.
Mike VERBAL AUTHORIZATION FOR RELIEF REQUEST RR-4-11 TEMPORARY ACCEPTANCE OF FLAW S IN SERVICE WATER PIPING VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 DOCKET NO. 50-395 JANUARY 14, 2017 Technical Evaluation read by David Alley, Chief of the Component Performance, Non-Destructive Examination, and Testing Branch, NRR
By letter dated January 13, 2017, South Carolina Electric and Gas Company (the licensee) requested relief from the requirements of the American Society of Mechanic al Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI, IWA-4000, at Virgil C. Summer Nuclear Station Unit 1.
Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z)(2), the licensee submitted Relief Request RR-4-11 to propose an alternative flaw evaluation to that of ASME Code Case N-513-3 "Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping,Section XI, Division 1," to disposition a pin hole leak in lieu of performing an ASME Code repair of the 8-inch , ASME Code Class 3 service water system piping.
On January 11, 2017, the licensee discovered a small pin hole leak on the weld neck flange of valve XVB03121A-SW on the "A" emergency diesel generator heat exchanger discharge of the service water system piping. At the time, the licensee reported a leak rate of 1 milliliter per minute. The licensee derived an allowable leak rate of 11.5 gallons per minute based on a 0.375-inch diameter hole. The allowable leak rate is sufficiently low so as to not to cha llenge the structural integrity of the piping, affect the required safety function of the pipe, or create issues associated with water spray or flooding. The licensee calculated that the degradation is acceptable as long as the average thickness of remaining ma terial outside of the pin hole is greater than 0.02 inches within a diameter of 1.5 inch es of the pin hole. The licensee stated that it will 2 perform required augmented inspections per Code Case N-513-3, including monitoring the leak rate daily, ultrasonic testing every 30 days to monitor flaw growth, and extent of condition inspections.
The NRC staff finds that there is a sufficient margin in terms of flaw size and leak rate with respect to the acceptable limits. Based on indepe ndent calculations, the NRC staff dete rmines that the subject pipe has sufficient fracture toughness to maintain the structur al integrity of the subject piping until the April 2017 refueling outage (RF23).
The NRC finds that the licensee has demonstrated th at Relief Request RR-4-11 will provide reasonable assurance that the structural integrity of the subject service water piping and its intended safety function will be maintained.
Authorization read by Michael Markley, Chief of the Plant Licensing Branch II-1, NRR
As Chief of the Plant Licensing Branch II-1, Office of Nuclear Reactor Regulation, I concur with the conclusions of the Component Performance, Non-Destructive Examination, and Testing Branch.
The NRC staff concludes that the proposed alternative pr ovides a reasonable assurance of structural integrity of the subject service water piping. The NRC staff fi nds that complying with IWA-4000 of the ASME Code,Section XI, would result in hardship or unusual difficu lty without a compensating increase in the level of quality and safety. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(2). Therefore, as of January 14, 2017, the NRC authorizes the use of Relief Request RR-4-11 at Virgil C. Summer Nuclear Station Unit 1 until the end of the April 2017 refueling outage (RF23), or exceeding the temporary acceptance criteria of Code Case N-513-3 and the relief request, whic hever occurs first.
All other requirements in ASME Code,Section XI, for wh ich relief was not specifically requested and approved in this relief request remain applic able, including third-party review by the Authorized Nuclear Inservice Inspector.
This verbal authorization does not preclude the NRC staff from asking additional clarification questions regarding the Relief Request while preparin g subsequent written safety evaluation.
Hearing Identifier: NRR_PMDA Email Number: 3269 Mail Envelope Properties (1484407608173.15618)
Subject:
Verbal Authorization for Relief Request RR-4-11 Sent Date: 1/14/2017 10:26:47 AM Received Date: 1/14/2017 10:26:48 AM From: Orenak, Michael Created By: Michael.Orenak@nrc.gov Recipients: "Williams, Shawn" <Sha wn.Williams@nrc.gov> Tracking Status: None "jgarza@scana.com" <jgarza@scana.com>
Tracking Status: None "bthompson@scana.com" <bthompson@scana.com> Tracking Status: None
Post Office: nrc.gov Files Size Date & Time MESSAGE 4660 1/14/2017 10:26:48 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: