MONTHYEARML24250A1882024-09-11011 September 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal ML24249A3372024-09-0404 September 2024 Inservice Inspection Summary Report - 2RE23 ML24242A1632024-08-29029 August 2024 Supplement to Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators IR 05000498/20243012024-08-27027 August 2024 NRC Initial Operator Licensing Examination Approval 05000498/2024301; 05000499/2024301 IR 05000498/20240052024-08-22022 August 2024 Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2024005 and 05000499/2024005) IR 05000498/20240022024-08-0909 August 2024 Integrated Inspection Report 05000498/2024002 and 05000499/2024002 IR 05000498/20240102024-08-0808 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000498/2024010 and 05000499/2024010 NOC-AE-240040, Application for Order Consenting to Direct Transfer of Licenses2024-07-31031 July 2024 Application for Order Consenting to Direct Transfer of Licenses ML24218A1462024-07-26026 July 2024 2. EPA Comments on South Texas Project Exemption Ea/Fonsi ML24207A1782024-07-25025 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24184C0832024-07-0202 July 2024 Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators ML24183A1742024-07-0101 July 2024 Condition Prohibited by Technical Specifications and Potential Loss of Safety Function Due to Inoperable Low Head Safety Injection Pump ML24179A3412024-06-27027 June 2024 Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24171A0112024-06-19019 June 2024 Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function IR 05000498/20244042024-06-0303 June 2024 Cyber Security Inspection Report 05000498/2024404 (Cover Letter) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24137A0882024-05-15015 May 2024 Operator Licensinq Examination Schedule Revision 3 NOC-AE-240040, Operator Licensinq Examination Schedule Revision 32024-05-15015 May 2024 Operator Licensinq Examination Schedule Revision 3 ML24136A2872024-05-15015 May 2024 Submittal of 2024 Nrc/Fema Evaluated Exercise Scenario Manual ML24136A2842024-05-15015 May 2024 Independent Spent Fuel Storage Installation Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance ML24130A2712024-05-0909 May 2024 Re Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24128A1572024-05-0707 May 2024 Independent Spent Fuel Storage Installation Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance IR 05000498/20240012024-05-0606 May 2024 Integrated Inspection Report 05000498/2024001 & 05000499/2024001 NOC-AE-240040, Annual Dose Report for 20232024-04-29029 April 2024 Annual Dose Report for 2023 ML24120A3762024-04-29029 April 2024 Annual Dose Report for 2023 ML24116A3032024-04-25025 April 2024 Operations Quality Assurance Plan Condition Adverse to Quality Definition Change Resulting in a Reduction in Commitment ML24116A3172024-04-25025 April 2024 Condition Prohibited by Technical Specifications Due to Inoperable Train of Essential Chilled Water ML24116A2282024-04-25025 April 2024 Annual Environmental Operating Report ML24117A1602024-04-24024 April 2024 2023 Radioactive Effluent Release Report ML24102A2452024-04-23023 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0046 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24113A3122024-04-22022 April 2024 Cycle 24 Core Operating Limits Report ML24097A0072024-04-0606 April 2024 Relief Request Number RR-ENG-4-07 – Request for an Alternative to ASME Code Case N-729-6 for Reactor Vessel Head Penetration 75 ML24092A1902024-04-0101 April 2024 Re Two Steam Generator Power Operated Relief Valves (Porvs) Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function NOC-AE-240040, Financial Assurance for Decommissioning - 2024 Update2024-03-28028 March 2024 Financial Assurance for Decommissioning - 2024 Update ML24088A3022024-03-28028 March 2024 Financial Assurance for Decommissioning - 2024 Update ML24080A2902024-03-19019 March 2024 Nuclear Liability Certificates of Insurance ML24066A2002024-03-0606 March 2024 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes ML24079A1312024-03-0505 March 2024 Nuclear Insurance Protection IR 05000498/20230062024-02-28028 February 2024 Annual Assessment Letter for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2023006 and 05000499/2023006) ML24060A1742024-02-28028 February 2024 Submittal of Annual Fitness for Duty Performance Report for 2023 IR 05000498/20240132024-02-27027 February 2024 Design Basis Assurance Inspection (Programs) Commercial Grade Dedication IR 05000498/2024013 and 05000499/2024013 ML24022A2252024-02-20020 February 2024 Issuance of Amendment Nos. 227 and 212 to Authorize the Revision of the Alternative Source Term Dose Calculation ML24050A0082024-02-19019 February 2024 Evidence of Financial Protection ML24045A0922024-02-16016 February 2024 Response to STP FOF Move Letter (2024) ML24017A2972024-02-15015 February 2024 Project Manager Assignment ML24039A1112024-02-0808 February 2024 Operator Licensing Examination Schedule Revision 2 ML24039A1602024-02-0808 February 2024 Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation NOC-AE-240040, Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation2024-02-0808 February 2024 Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation ML24038A3342024-02-0707 February 2024 Change to South Texas Project Electric Generating Station (Stepgs) Emergency Plan ML24033A3002024-02-0707 February 2024 Summary of Regulatory Audit Regarding a Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections 2024-09-04
[Table view] |
See also: IR 05000498/2018301
Text
October 10, 2018
Mr. G. T. Powell
President and CEO
STP Nuclear Operating Company
P.O. Box 289
Wadsworth, TX 77483
SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION
- NRC INITIAL OPERATOR LICENSING EXAMINATION APPROVAL
05000498/2018301 AND 05000499/2018301
Dear Mr. Powell
- The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at South Texas Project Electric Generating Station, Units 1 and 2
. The U.S. Nuclear Regulatory Commission (NRC) has approved the subject examinations, and you may administer the written examination, in accordance
with Revision 11 of NUREG
-1021, "Operator Licensing Examination Standards for Power Reactors," on November 7, 2018. The NRC staff will administer the operating tests during the week of October 2 2, 2018. The list of applicants approved to take the examination has been provided to Adrian Culver , Initial Training Supervisor
. The examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility.
Based on this review, I have concluded that
the examination meets the guidelines of NUREG
-1021 for content, operational, and discrimination validity.
By administering this examination, you also agree that it meets NUREG-1021 guidelines and is appropriate for measuring the qualifications of licensed operator applicants at your facility.
If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 817
-200-1159.
G.T. Powell
2 Please contact your Chief Examiner, John Kirkla
nd , at 817-200-1 771, if you have any questions
or identify any errors or changes in the license level (reactor operator
or senior reactor operator) or type of examination (partial or
complete written examination
or operating test, or both) specified for each applicant
approved to take the examination
. Sincerely, /RA/ Vincent G. Gaddy, Chief Operations Branch
Division of Reactor Safety
Docket Nos. 50
-498; 50-499 License Nos. NPF
-76; NPF-80
G.T. Powell
3 SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION
- NRC INITIAL OPERATOR LICENSING EXAMINATION APPROVAL 05000498/2018301 AND 05000499/2018301
- DATED OCTOBER 10, 2018
DISTRIBUTION:
KKennedy, RA
SMorris, DRA
AVegel, DRP
MHay, DRP MShaffer, DRS
RLantz, DRS
DCylkowski, RC
NTaylor, DRP
DProulx, DRP
JMelfi, DRP
ECombs, DRP
FSanchez, DRP
JChoate, DRP
LReyna, DRP
CCook, RIV/OEDO
VDricks, ORA
JWeil, OCA
LRegner, NRR
AMoreno, RIV/CAO
BMaier, RSLO
GMiller, IPAT
PJayroe, IPAT
MHerrera, DRMA
ADAMS ACCESSION
NUMBER: ML18283A080
X SUNSI Review
ADAMS: Non-Publicly Available
X Non-Sensitive Keyword: By: JCK X Yes No X Publicly Available
Sensitive OFFICE OB:SOE OB:BC NAME JKirkland VGaddy SIGNATURE /RA/ /RA/ DATE 10/10/18 10/10/18 OFFICIAL RECORD COPY