Schedule for Response to Reactor Vessel Inspection Program Request for Additional Information (RAI) 2-1
ML14087A219
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 03/28/2014
From: Davison K
Northern States Power Co, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-PI-14-030, TAC MF0052, TAC MF0053
Download: ML14087A219 (2)


Text

'(l Xcel Energy MAR 2 8 2014 U S Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Units 1 and 2 Dockets 50-282 and 50-306 Renewed License Nos. DPR-42 and DPR-60 L-PI-14-030 Schedule for Response to Reactor Vessel Inspection Program Request for Additional Information (RAI) 2-1 for the Prairie Island Nuclear Generating Plant (PINGP) (TAC Nos. MF0052 and MF0053) By letter dated October 1, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12276A041), Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy (hereafter "NSPM"), submitted an aging management program (AMP) for the reactor vessel internals (RVI) at PINGP, Units 1 and 2. Letters dated March 7, 2013 (ML13067A284), March 22, 2013 (ML13084A378) and October 8, 2013 (ML13284A081

), provided additional AMP information, including responses to all NRC RAis except for RAI 2-1. Pursuant to a teleconference with the NRC Staff on August 27, 2013, NSPM agreed to provide the response to RAI 2-1 at a later date when industry-wide resolution of the issues becomes available.

Pursuant to a teleconference with the NRC Staff on January 29, 2014, NSPM by this letter provides a written milestone schedule for the response to RAI 2-1. The vendor performing the material reviews for the response to RAI 2-1 will provide their deliverable to NSPM by September 30, 2014; NSPM will submit the response to RAI 2-1 to the NRC by October 24, 2014. If there are any questions or if additional information is needed, please contact Mr. Dale Vincent, P.E., at 651-267-1736.

1717 Wakonade Drive East

651.388.1121 Document Control Desk Page 2 Summary of Commitments This contains no new commitments no revisions to existing commitments. ;:#£ MAR 2 8 2014 Kevin Davison Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company -Minnesota cc: Administrator, Region Ill, USNRC Project Manager, PINGP, USNRC Resident Inspector, PINGP, USNRC