{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532
-4352  September 3, 2013 Ms. Karen Fili Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota
2807 West County Road 75 Monticello, MN  55362
-9637 
==SUBJECT:==
MONTICELLO NUCLEAR GENERATING PLANT REQUEST FOR WAIVER OF EXPERIENCE REQUIREMENT FOR INITIAL LICENSE EXAMINATION
==Dear Ms. Fili:==
In a letter (L
-MT-13-045) dated June 20, 2013, your staff requested an eligibility waiver for Mr. A. Herrmann for the June 2015 initial operator license examination. Your staff requested a waiver of one month of the six months responsible nuclear power plant experience at the plant for which the applicant seeks a license. The Region III Operations Branch has reviewed Mr. Herrmann's work experience at Monticello Nuclear Generating Plant and his prior experience at the Point Beach Nuclear Plant in accordance with the Operator Licensing Examination Standards for Power Reactors, NUREG-1021, ES-202 D.2.a(1), and agree that Mr. Herrmann meets all requirements to take the 2015 NRC initial license examination with the exception of the required six months responsible power plant experience at the Monticello Nuclear Generating Plant. When Mr. Herrmann submits his application for the license, please have Mr. Herrmann request the experience waiver on his application and, in accordance with NUREG-1021, Section D.1.i(1) "Routine Waivers," the waiver will be granted at that time. Mr. Herrmann will be required to complete the one month of responsible power plant experience before an operator license can be issued after satisfactory performance on the operator license examination. When Mr. Herrmann's power plant experience requirement is satisfied, it will need to be documented in a manner comparable to Mr. Herrmann's original license application and signed by the Plant Vice President or the designated alternate.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents
K. Fili      Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room)
. Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No.
50-263 License No. DPR
-22  cc: Distribution via ListServ TM K. Fili      Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room)
. Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No.
50-263 License No. DPR-22  cc: Distribution via ListServ TM  DISTRIBUTION
: Vivian Campbell RidsNrrDorlLpl3
-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Anne Boland Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak John McHale
DOCUMENT NAME:  Ltr 090313 Monticello Req for Waiver DRM.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII  RIII  RIII  RIII  NAME DMcneil:bl HPeterson DATE 08/29/13 09/03/13  OFFICIAL RECORD COPY}}

Revision as of 08:40, 4 July 2018

Ltr 090313 Monticello Request for Waiver - Drm
ML13246A471
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 09/03/2013
From: Hironori Peterson
Operations Branch III
To: Fili K D
Northern States Power Co
Dell McNeil
References
Download: ML13246A471 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532

-4352 September 3, 2013 Ms. Karen Fili Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota

2807 West County Road 75 Monticello, MN 55362

-9637

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT REQUEST FOR WAIVER OF EXPERIENCE REQUIREMENT FOR INITIAL LICENSE EXAMINATION

Dear Ms. Fili:

In a letter (L

-MT-13-045) dated June 20, 2013, your staff requested an eligibility waiver for Mr. A. Herrmann for the June 2015 initial operator license examination. Your staff requested a waiver of one month of the six months responsible nuclear power plant experience at the plant for which the applicant seeks a license. The Region III Operations Branch has reviewed Mr. Herrmann's work experience at Monticello Nuclear Generating Plant and his prior experience at the Point Beach Nuclear Plant in accordance with the Operator Licensing Examination Standards for Power Reactors, NUREG-1021, ES-202 D.2.a(1), and agree that Mr. Herrmann meets all requirements to take the 2015 NRC initial license examination with the exception of the required six months responsible power plant experience at the Monticello Nuclear Generating Plant. When Mr. Herrmann submits his application for the license, please have Mr. Herrmann request the experience waiver on his application and, in accordance with NUREG-1021, Section D.1.i(1) "Routine Waivers," the waiver will be granted at that time. Mr. Herrmann will be required to complete the one month of responsible power plant experience before an operator license can be issued after satisfactory performance on the operator license examination. When Mr. Herrmann's power plant experience requirement is satisfied, it will need to be documented in a manner comparable to Mr. Herrmann's original license application and signed by the Plant Vice President or the designated alternate.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents

K. Fili Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room)

. Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No.

50-263 License No. DPR

-22 cc: Distribution via ListServ TM K. Fili Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room)

. Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No.

50-263 License No. DPR-22 cc: Distribution via ListServ TM DISTRIBUTION

Vivian Campbell RidsNrrDorlLpl3

-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Anne Boland Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak John McHale

DOCUMENT NAME: Ltr 090313 Monticello Req for Waiver DRM.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME DMcneil:bl HPeterson DATE 08/29/13 09/03/13 OFFICIAL RECORD COPY