NL-17-1201, Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:J. J. Hutto                40 Inverness Center Parkway Regulatory Affairs Director Post Office Box 1295 Birmingham, AL 35242 205 992 5872     tel 205 992 7601     fax jjhutto@southernco.com July 11, 2017 Docket Nos.: 50-424                                                               NL-17-1201 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Vogtle Electric Generating Plant Units 1 & 2 Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report Ladies and Gentlemen:
{{#Wiki_filter:40 Inverness Center Parkway Post Office Box 1295 Birmingham, AL 35242 205 992 5872 tel 205 992 7601 fax jjhutto@southernco.com J. J. Hutto Regulatory Affairs Director July 11, 2017 Docket Nos.:
By letter dated April 21, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17116A096), Southern Nuclear Operating Company (SNC) submitted a technical report for approval for Vogtle Electric Generating Plant, Units 1 and 2. In addition, the letter provided a supplemental response to Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors" (ADAMS Accession No. ML042360586) that supersedes previous responses. The technical report contains a risk-informed methodology to evaluate debris effects, except for vessel fiber limits.
50-424 NL-17-1201 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Vogtle Electric Generating Plant Units 1 & 2 Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report Ladies and Gentlemen:
By letter dated June 26, 2017, (ADAMS Accession No. ML17166A433), the Nuclear Regulatory Commission (NRC) staff requested information regarding the seismic probabilistic risk assessment peer review. The Enclosure provides the SNC response to the NRC request. In addition, the NRC staff asked SNC to confirm the scope of the requested technical report review. To clarify, SNC requests NRC review and approval of Enclosures 1 - 5 from the April 21, 2017 technical report. While SNCs intent is that the Enclosures can be separated for review by the appropriate NRC branch, they are intertwined such that NRC approval of all five is necessary for SNCs final resolution of Generic Letter (GL) 2004-02.
By {{letter dated|date=April 21, 2017|text=letter dated April 21, 2017}} (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17116A096), Southern Nuclear Operating Company (SNC) submitted a technical report for approval for Vogtle Electric Generating Plant, Units 1 and 2. In addition, the letter provided a supplemental response to Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors" (ADAMS Accession No. ML042360586) that supersedes previous responses. The technical report contains a risk-informed methodology to evaluate debris effects, except for vessel fiber limits.
This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at 205.992.7369.
By {{letter dated|date=June 26, 2017|text=letter dated June 26, 2017}}, (ADAMS Accession No. ML17166A433), the Nuclear Regulatory Commission (NRC) staff requested information regarding the seismic probabilistic risk assessment peer review. The Enclosure provides the SNC response to the NRC request. In addition, the NRC staff asked SNC to confirm the scope of the requested technical report review. To clarify, SNC requests NRC review and approval of Enclosures 1 - 5 from the April 21, 2017 technical report. While SNCs intent is that the Enclosures can be separated for review by the appropriate NRC branch, they are intertwined such that NRC approval of all five is necessary for SNCs final resolution of Generic Letter (GL) 2004-02.
This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at 205.992.7369.  


U. S. Nuclear Regulatory Commission NL-17-1201 Page2 Mr. J. J. Hutto states he is Regulatory Affairs Director of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and, to the best of his knowledge and belief, the facts set forth in this letter are true.
U. S. Nuclear Regulatory Commission NL-17-1201 Page2 Mr. J. J. Hutto states he is Regulatory Affairs Director of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and, to the best of his knowledge and belief, the facts set forth in this letter are true.
Respectfully submitted, J. J. Hutto Regulatory Affairs Director JJH/RMJ Swam to   ~nd subscribed before me this 11_ day of~"--\~                           12017, otary Public
Respectfully submitted, J. J. Hutto Regulatory Affairs Director JJH/RMJ
                                                    ~~~~~~~~*-~~--~~
: 12017, Swam to ~nd subscribed before me this 11_ day of~"--\\~  
MICHEllE l GRAVES tQ * ~\)\'0 Notary PubNc               ~
~~~~~~~~*-~~--~~
My commission expires: ( \
otary Public My commission expires: (\\
* Alabama State at large         ~
* tQ * ~\\)\\ '0 MICHEllE l GRAVES Notary PubNc Alabama State at large  
~
~  


==Enclosure:==
==Enclosure:==
SNC Response to NRC Request Regarding Risk-Informed Methodology cc:   Regional Administrator, Region II NRR Project Manager- Vogtle 1 & 2 Senior Resident Inspector- Vogtle 1 & 2 State of Georgia Environmental Protection Division RType: CVC7000
SNC Response to NRC Request Regarding Risk-Informed Methodology cc:
Regional Administrator, Region II NRR Project Manager-Vogtle 1 & 2 Senior Resident Inspector-Vogtle 1 & 2 State of Georgia Environmental Protection Division RType: CVC7000  


Vogtle Electric Generating Plant Units 1 & 2 Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report Enclosure SNC Response to NRC Request Regarding Risk-Informed Methodology
Vogtle Electric Generating Plant Units 1 & 2 Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report Enclosure SNC Response to NRC Request Regarding Risk-Informed Methodology


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology NRC Information Request:
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-1 NRC Information Request:
Regulatory Guide 1.200, Rev. 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities (ADAMS Accession No. ML090410014) describes an approach for determining whether the technical adequacy of a PRA is sufficient to provide confidence in the results; it also describes information the NRC staff expects to be included in risk-informed submittals. As discussed in the guide, a risk informed submittal should contain discussions concerning peer review. If the peer review is not performed against the established standards, then information needs to be included in the submittal demonstrating that the different criteria used are consistent with the established standards. The risk-informed methodology described in the technical report should include the following:
Regulatory Guide 1.200, Rev. 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities (ADAMS Accession No. ML090410014) describes an approach for determining whether the technical adequacy of a PRA is sufficient to provide confidence in the results; it also describes information the NRC staff expects to be included in risk-informed submittals. As discussed in the guide, a risk informed submittal should contain discussions concerning peer review. If the peer review is not performed against the established standards, then information needs to be included in the submittal demonstrating that the different criteria used are consistent with the established standards. The risk-informed methodology described in the technical report should include the following:
x     Description demonstrating that the criteria in ASME/ANS RA-Sb-2013 (Addendum B), which is not an established endorsed standard, are consistent with the ASME/ANS RA-Sa-2009 (Addendum A), which is an established endorsed standard, for the seismic probabilistic risk assessment peer review facts and observations.
x Description demonstrating that the criteria in ASME/ANS RA-Sb-2013 (Addendum B), which is not an established endorsed standard, are consistent with the ASME/ANS RA-Sa-2009 (Addendum A), which is an established endorsed standard, for the seismic probabilistic risk assessment peer review facts and observations.
x     If the different criteria are not consistent with the established endorsed standard, an explanation demonstrating that the analogous Addendum A supporting requirements have been met.
x If the different criteria are not consistent with the established endorsed standard, an explanation demonstrating that the analogous Addendum A supporting requirements have been met.
SNC Response:
SNC Response:
Regulatory Guide 1.200, Revision 2.0 endorses ASME/ANS RA-Sa-2009 (Addendum A) but, as noted in an NRC letter to ASME, does not endorse PRA Standard ASME/ANS RA-Sb-2013 (Addendum B). The Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle) Seismic Probabilistic Risk Assessment (SPRA) peer review was performed using the SPRA requirements in Addendum B.
Regulatory Guide 1.200, Revision 2.0 endorses ASME/ANS RA-Sa-2009 (Addendum A) but, as noted in an NRC letter to ASME, does not endorse PRA Standard ASME/ANS RA-Sb-2013 (Addendum B). The Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle) Seismic Probabilistic Risk Assessment (SPRA) peer review was performed using the SPRA requirements in Addendum B.
Because the peer review was not performed against the NRC endorsed standard, information demonstrating that any different criteria used are consistent with the NRC endorsed standard is provided here. The following discussion addresses the differences relative to establishing the technical capability of the Vogtle SPRA.
Because the peer review was not performed against the NRC endorsed standard, information demonstrating that any different criteria used are consistent with the NRC endorsed standard is provided here. The following discussion addresses the differences relative to establishing the technical capability of the Vogtle SPRA.
The ASME/ANS PRA Standard Part 5 requirements for at-power seismic PRA (in all versions of the PRA Standard) are organized into the following three major technical elements:
The ASME/ANS PRA Standard Part 5 requirements for at-power seismic PRA (in all versions of the PRA Standard) are organized into the following three major technical elements:
x     Seismic hazard analysis (technical element SHA) x     Seismic fragility analysis (technical element SFR), and x     Seismic plant-response modeling (technical element SPR)
x Seismic hazard analysis (technical element SHA) x Seismic fragility analysis (technical element SFR), and x
Each technical element contains several high level requirements (HLR) and associated supporting requirements (SR). The following three tables (Table 1 for SHA, Table 2 for SFR and Table 3 for SPR) provide SR by SR comparisons between Addendum A and Addendum B of the ASME/ANS PRA Standard. Differences between SR wordings are denoted in the following tables using bold type. Changes in the HLRs between Addendum A and Addendum B are denoted using strikethrough text. The comparison assessment focuses on capability category II (CCII); as such, SR text not related to CCII is not included in the following E-1
Seismic plant-response modeling (technical element SPR)
Each technical element contains several high level requirements (HLR) and associated supporting requirements (SR). The following three tables (Table 1 for SHA, Table 2 for SFR and Table 3 for SPR) provide SR by SR comparisons between Addendum A and Addendum B of the ASME/ANS PRA Standard. Differences between SR wordings are denoted in the following tables using bold type. Changes in the HLRs between Addendum A and Addendum B are denoted using strikethrough text. The comparison assessment focuses on capability category II (CCII); as such, SR text not related to CCII is not included in the following  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology tables. This comparison assessment is performed by SR and not by HLR; peer reviewers assess technical quality by reviewing SRs (HLRs are not assigned technical capabilities). The following assessment conclusion categories are used in the SR comparison assessment:
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-2 tables. This comparison assessment is performed by SR and not by HLR; peer reviewers assess technical quality by reviewing SRs (HLRs are not assigned technical capabilities). The following assessment conclusion categories are used in the SR comparison assessment:
x     Addendum B Assessment Equates to Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are the same or effectively the same (i.e., re-wording that is for clarity and consistency and not intended to change the intent). This conclusion category is also used in cases where the wording differences are related to moving the requirements to another SR. In certain SRs the qualifier for a specific capability category range is assigned to indicate the focus on capability category II when there are differences in other capability categories. A peer reviewer using Addendum A or Addendum B would come to the same technical capability assessment on these topics.
x Addendum B Assessment Equates to Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are the same or effectively the same (i.e., re-wording that is for clarity and consistency and not intended to change the intent). This conclusion category is also used in cases where the wording differences are related to moving the requirements to another SR. In certain SRs the qualifier for a specific capability category range is assigned to indicate the focus on capability category II when there are differences in other capability categories. A peer reviewer using Addendum A or Addendum B would come to the same technical capability assessment on these topics.
x     Addendum B Envelopes Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are different and the requirements of Addendum B envelope that of Addendum A (i.e., if the analysis meets Addendum B CCII then by definition it meets Addendum A CCII or higher). A peer reviewer using Addendum B would assess a technical capability on these topics that would be equal to or greater than what would be determined if Addendum A were used in the review.
x Addendum B Envelopes Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are different and the requirements of Addendum B envelope that of Addendum A (i.e., if the analysis meets Addendum B CCII then by definition it meets Addendum A CCII or higher). A peer reviewer using Addendum B would assess a technical capability on these topics that would be equal to or greater than what would be determined if Addendum A were used in the review.
x     Vogtle Conforms to Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are different, or some of the requirements of Addendum A no longer exist in Addendum B, yet the analysis performed and documented in the Vogtle analysis conforms to the requirements of Addendum A as well as Addendum B.
x Vogtle Conforms to Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are different, or some of the requirements of Addendum A no longer exist in Addendum B, yet the analysis performed and documented in the Vogtle analysis conforms to the requirements of Addendum A as well as Addendum B.
x     Vogtle Conforms to Accepted Current Practices: This conclusion category is used when the SR wording of Addendum A and Addendum B are different; or some of the requirements of Addendum A no longer exist in Addendum B because they were removed from the Standard as confusing or judged too specific how-to. For the one SR where this conclusion category applies, Vogtle does not follow some of the specifics of the Addendum A SR requirements but Vogtle does conform to accepted current practices.
x Vogtle Conforms to Accepted Current Practices: This conclusion category is used when the SR wording of Addendum A and Addendum B are different; or some of the requirements of Addendum A no longer exist in Addendum B because they were removed from the Standard as confusing or judged too specific how-to. For the one SR where this conclusion category applies, Vogtle does not follow some of the specifics of the Addendum A SR requirements but Vogtle does conform to accepted current practices.
While the Vogtle SPRA was peer reviewed against the ASME/ANS RA-Sb-2013 (Addendum B) requirements, the tables that follow demonstrate that most of the supporting requirements in Addendum B are consistent with the supporting requirements in ASME/ANS RA-Sa-2009 (Addendum A). For the few supporting requirements where differences are noted in the tables, the Vogtle SPRA model and documentation meet the analogous Addendum A supporting requirements. Therefore, the Vogtle SPRA meets the technical adequacy requirements of Regulatory Guide 1.200, Revision 2 and is of sufficient quality and level of detail to support the risk informed approach for GSI-191.
While the Vogtle SPRA was peer reviewed against the ASME/ANS RA-Sb-2013 (Addendum B) requirements, the tables that follow demonstrate that most of the supporting requirements in Addendum B are consistent with the supporting requirements in ASME/ANS RA-Sa-2009 (Addendum A). For the few supporting requirements where differences are noted in the tables, the Vogtle SPRA model and documentation meet the analogous Addendum A supporting requirements. Therefore, the Vogtle SPRA meets the technical adequacy requirements of Regulatory Guide 1.200, Revision 2 and is of sufficient quality and level of detail to support the risk informed approach for GSI-191.
E-2


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category Capability Category Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-3 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                          II                      III HLR-SHA-A: The frequency of earthquakes at the site shall be based on a site-specific probabilistic seismic hazard analysis (existing or new) that reflects the composite distribution of the informed technical community. The level of analysis shall be determined based on the intended application and on site-specific complexity.
Capability Category I
SHA-A1 ASME/ANS <not printed here; not In performing the probabilistic seismic hazard Addendum B Assessment Equates to RA-Sa-      focus of this              analysis (PSHA), BASE it on, and MAKE it       Addendum A 2009        assessment>                consist of, the collection and evaluation of available information and data, evaluation of   The wording for this SR is the same for the uncertainties in each element of the       Addendum A and Addendum B.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
PSHA, and a defined process and documentation to make the PSHA traceable.
HLR-SHA-A: The frequency of earthquakes at the site shall be based on a site-specific probabilistic seismic hazard analysis (existing or new) that reflects the composite distribution of the informed technical community. The level of analysis shall be determined based on the intended application and on site-specific complexity.
ASME/ANS Identical to                   Identical to Addendum A RA-Sb-      Addendum A 2013 SHA-A2 ASME/ANS As the parameter to characterize both hazard <not printed here; not Addendum B CC1-III Assessment Equates RA-Sa-      and fragilities, USE the spectral accelerations, focus of this            to Addendum A CCI-II 2009        or the average spectral acceleration over a           assessment>
SHA-A1 ASME/ANS RA-Sa-2009
selected band of frequencies, or peak ground                               In response to EPRI 2011 comment, acceleration.                                                              Addendum B removed the CCIII ASME/ANS Identical to Addendum A for CC I/II                                            requirements. The Addendum B SR equates RA-Sb-                                                                                  to Addendum A CCI-II.
<not printed here; not focus of this assessment>
2013 SHA-A3 ASME/ANS In the selection of frequencies to determine spectral                               Addendum B Assessment Equates to RA-Sa-      accelerations or average spectral acceleration, CAPTURE the               Addendum A 2009        frequencies of those structures, systems, or components, or a combination thereof that are significant in the PRA results and           Addendum B changed action verbs to be insights.                                                                  consistent with accepted verb usage across ASME/ANS     If spectral   acceleration or average   spectral acceleration over a   SRs, and also made minor changes in RA-Sb-      band of frequencies is used, INCLUDE the response frequencies of wordings. This wording edit does not change 2013        SSCs that are significant in the PRA results and insights.                 the capability category requirements of this SR.
In performing the probabilistic seismic hazard analysis (PSHA), BASE it on, and MAKE it consist of, the collection and evaluation of available information and data, evaluation of the uncertainties in each element of the PSHA, and a defined process and documentation to make the PSHA traceable.
E-3
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
ASME/ANS RA-Sb-2013 Identical to Addendum A Identical to Addendum A SHA-A2 ASME/ANS RA-Sa-2009 As the parameter to characterize both hazard and fragilities, USE the spectral accelerations, or the average spectral acceleration over a selected band of frequencies, or peak ground acceleration.
<not printed here; not focus of this assessment>
Addendum B CC1-III Assessment Equates to Addendum A CCI-II In response to EPRI 2011 comment, Addendum B removed the CCIII requirements. The Addendum B SR equates to Addendum A CCI-II.
ASME/ANS RA-Sb-2013 Identical to Addendum A for CC I/II SHA-A3 ASME/ANS RA-Sa-2009 In the selection of frequencies to determine spectral accelerations or average spectral acceleration, CAPTURE the frequencies of those structures, systems, or components, or a combination thereof that are significant in the PRA results and insights.
Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs, and also made minor changes in wordings. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013 If spectral acceleration or average spectral acceleration over a band of frequencies is used, INCLUDE the response frequencies of SSCs that are significant in the PRA results and insights.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category Capability Category Capability Category SR                                                                                                  Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-4 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                        II                      III SHA-A4 ASME/ANS In developing the probabilistic seismic hazard analysis results,                 Addendum B Assessment Equates to RA-Sa-        whether they are characterized by spectral accelerations, peak ground Addendum A 2009          accelerations, or both, EXTEND them to large-enough values (consistent with the physical data and interpretations) so that the   Addendum B added the phrase "for use in truncation does not produce unstable final numerical results, such as accident sequence quantification". This core damage frequency, and the delineation and ranking of seismic-     wording edit does not change the capability initiated sequences are not affected.                                  category requirements of this SR.
Capability Category I
ASME/ANS In developing the probabilistic seismic hazard analysis results for use RA-Sb-        in accident sequence quantification, whether they are characterized 2013          by spectral accelerations, peak ground accelerations, or both, EXTEND them to large-enough values (consistent with the physical data and interpretations) so that the truncation does not produce unstable final numerical results, such as core damage frequency, and the delineation and ranking of seismic-initiated sequences are not affected.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SHA-A5 ASME/ANS SPECIFY a lower-bound magnitude (or probabilistically defined                     Addendum B Assessment Equates to RA-Sa-        characterization of magnitudes based on a damage parameter) for       Addendum A 2009          use in the hazard analysis, such that earthquakes of magnitude less than this value are not expected to cause significant damage to the   The wording for this SR is the same for engineered structures or equipment.                                    Addendum A and Addendum B.
SHA-A4 ASME/ANS RA-Sa-2009 In developing the probabilistic seismic hazard analysis results, whether they are characterized by spectral accelerations, peak ground accelerations, or both, EXTEND them to large-enough values (consistent with the physical data and interpretations) so that the truncation does not produce unstable final numerical results, such as core damage frequency, and the delineation and ranking of seismic-initiated sequences are not affected.
ASME/ANS Identical to Addendum A RA-Sb-2013 HLR-SHA-B: To provide inputs to the probabilistic seismic hazard analysis, a comprehensive up-to-date database including geological, seismological, and geophysical data; local site topography; and surficial geologic and geotechnical site properties shall be compiled. A catalog of historical, instrumental, and paleoseismicity information shall also be compiled.
Addendum B Assessment Equates to Addendum A Addendum B added the phrase "for use in accident sequence quantification". This wording edit does not change the capability category requirements of this SR.
SHA-B1 ASME/ANS In performing the probabilistic seismic hazard <not printed here; not Addendum B Assessment Equates to RA-Sa-        analysis (PSHA), BASE it on available or           focus of this      Addendum A 2009          developed geological, seismological,               assessment>
ASME/ANS RA-Sb-2013 In developing the probabilistic seismic hazard analysis results for use in accident sequence quantification, whether they are characterized by spectral accelerations, peak ground accelerations, or both, EXTEND them to large-enough values (consistent with the physical data and interpretations) so that the truncation does not produce unstable final numerical results, such as core damage frequency, and the delineation and ranking of seismic-initiated sequences are not affected.
geophysical, and geotechnical data that                               Addendum B changed action verbs to be reflect the current state of the knowledge and                         consistent with accepted verb usage across that are used by experts/analysts to develop                           SRs. This wording edit does not change the E-4
SHA-A5 ASME/ANS RA-Sa-2009 SPECIFY a lower-bound magnitude (or probabilistically defined characterization of magnitudes based on a damage parameter) for use in the hazard analysis, such that earthquakes of magnitude less than this value are not expected to cause significant damage to the engineered structures or equipment.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
ASME/ANS RA-Sb-2013 Identical to Addendum A HLR-SHA-B: To provide inputs to the probabilistic seismic hazard analysis, a comprehensive up-to-date database including geological, seismological, and geophysical data; local site topography; and surficial geologic and geotechnical site properties shall be compiled. A catalog of historical, instrumental, and paleoseismicity information shall also be compiled.
SHA-B1 ASME/ANS RA-Sa-2009 In performing the probabilistic seismic hazard analysis (PSHA), BASE it on available or developed geological, seismological, geophysical, and geotechnical data that reflect the current state of the knowledge and that are used by experts/analysts to develop  
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category Capability Category             Capability Category SR                                                                                                  Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-5 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                I                        II                        III interpretations and inputs to the PSHA.                                     capability category requirements of this SR.
Capability Category I
ASME/ANS In performing the probabilistic seismic hazard <not printed here; not RA-Sb-      analysis (PSHA), USE available or developed focus of this 2013        geological, seismological, geophysical, and         assessment>
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) interpretations and inputs to the PSHA.
geotechnical data that reflect the current state of the knowledge and that are used by experts/analysts to develop interpretations and inputs to the PSHA.
capability category requirements of this SR.
SHA-B2   ASME/ANS ENSURE that the database and information                 <not printed here; not Addendum B Assessment Equates to RA-Sa-      used are adequate to characterize all credible focus of this                Addendum A 2009        seismic sources that may contribute                 assessment>
ASME/ANS RA-Sb-2013 In performing the probabilistic seismic hazard analysis (PSHA), USE available or developed geological, seismological, geophysical, and geotechnical data that reflect the current state of the knowledge and that are used by experts/analysts to develop interpretations and inputs to the PSHA.
significantly to the frequency of occurrence of                             The wording for this SR is the same for vibratory ground motion at the site,                                       Addendum A and Addendum B for CCI and considering regional attenuation of ground                                 CCII.
<not printed here; not focus of this assessment>
motions and local site effects. If the existing probabilistic seismic hazard analysis (PSHA) studies are to be used in the seismic PRA, ENSURE that any new data or interpretations that could affect the PSHA are adequately incorporated in the existing data and analysis.
SHA-B2 ASME/ANS RA-Sa-2009 ENSURE that the database and information used are adequate to characterize all credible seismic sources that may contribute significantly to the frequency of occurrence of vibratory ground motion at the site, considering regional attenuation of ground motions and local site effects. If the existing probabilistic seismic hazard analysis (PSHA) studies are to be used in the seismic PRA, ENSURE that any new data or interpretations that could affect the PSHA are adequately incorporated in the existing data and analysis.
ASME/ANS Identical to Addendum A                                 <not printed here; not RA-Sb-                                                            focus of this 2013                                                              assessment>
<not printed here; not focus of this assessment>
SHA-B3   ASME/ANS <not printed here; not As a part of data collection, COMPILE a                 Vogtle Conforms to Addendum A RA-Sa-      focus of this            catalog of historically reported, geologically 2009        assessment>              identified, and instrumentally recorded           A catalog of historically reported, geologically earthquakes. USE reference [5-30]                 identified, and instrumentally recorded E-5
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B for CCI and CCII.
ASME/ANS RA-Sb-2013 Identical to Addendum A
<not printed here; not focus of this assessment>
SHA-B3 ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
As a part of data collection, COMPILE a catalog of historically reported, geologically identified, and instrumentally recorded earthquakes. USE reference [5-30]
Vogtle Conforms to Addendum A A catalog of historically reported, geologically identified, and instrumentally recorded  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard       Capability Category       Capability Category Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-6 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                    I                      II                      III requirements or equivalent.                   earthquakes for the entire CEUS was ASME/ANS INCLUDE an appropriate existing catalog of              <not printed here; not compiled by the 2012 CEUS SSC report.
Capability Category I
RA-Sb-        historically reported earthquakes,                focus of this          Following a SSHAC Level 3 process, the 2013          instrumentally recorded earthquakes, and          assessment>            CEUS SSC report is a robust evaluation of earthquakes reported through geological                                  available information on historical seismicity, investigations. USE reference [5-30]                                    paleoseismic data on large-magnitude requirements or equivalent.                                              recurrence rates, and state-of-the-knowledge of earthquake seismic sources as considered in the informed technical community.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) requirements or equivalent.
earthquakes for the entire CEUS was compiled by the 2012 CEUS SSC report.
Following a SSHAC Level 3 process, the CEUS SSC report is a robust evaluation of available information on historical seismicity, paleoseismic data on large-magnitude recurrence rates, and state-of-the-knowledge of earthquake seismic sources as considered in the informed technical community.
The 2012 CEUS SSC catalog followed a SSHAC Level 3 process and is applicable for risk informed applications. Compiling a new catalog will not be as rigorous as the SSHAC Level 3 process. The Addenda B SR requirement is appropriate for CC-II.
The 2012 CEUS SSC catalog followed a SSHAC Level 3 process and is applicable for risk informed applications. Compiling a new catalog will not be as rigorous as the SSHAC Level 3 process. The Addenda B SR requirement is appropriate for CC-II.
The 2012 CEUS SSC report used an earthquake catalog which extended through 2008. Recent earthquake activity in the vicinity of the Vogtle site was assessed for its impact on hazard. The study was based on a temporal update of the earthquake catalog from 2009 through February 2016. The assessment concluded that the 2012 CEUS SSC report seismicity parameters are appropriate for evaluation of seismic hazard at Vogtle. Based on this, the Vogtle PSHA that was performed conforms to Addendum A.
The 2012 CEUS SSC report used an earthquake catalog which extended through 2008. Recent earthquake activity in the vicinity of the Vogtle site was assessed for its impact on hazard. The study was based on a temporal update of the earthquake catalog from 2009 through February 2016. The assessment concluded that the 2012 CEUS SSC report seismicity parameters are appropriate for evaluation of seismic hazard at Vogtle. Based on this, the Vogtle PSHA that was performed conforms to Addendum A.
ASME/ANS RA-Sb-2013 INCLUDE an appropriate existing catalog of historically reported earthquakes, instrumentally recorded earthquakes, and earthquakes reported through geological investigations. USE reference [5-30]
requirements or equivalent.
<not printed here; not focus of this assessment>
HLR-SHA-C: To account for the frequency of occurrence of seismic ground motions in the site region, the probabilistic seismic hazard analysis shall examine all credible sources of potentially damaging earthquakes.
HLR-SHA-C: To account for the frequency of occurrence of seismic ground motions in the site region, the probabilistic seismic hazard analysis shall examine all credible sources of potentially damaging earthquakes.
E-6


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category Capability Category Capability Category SR                                                                                              Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-7 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                I                      II                        III SHA-C1   ASME/ANS In the probabilistic seismic hazard analysis, EXAMINE all potential         Addendum B Assessment Envelopes RA-Sa-      sources of earthquakes that affect the probabilistic hazard at the     Addendum A 2009        site. BASE the identification and characterization of seismic sources on regional and site geological and geophysical data,           Addendum B added additional clarifications historical and instrumental seismicity data, the regional stress field, and requirements into the text of this SR, and and geological evidence of prehistoric earthquakes.                    also Addendum B changed action verbs to be ASME/ANS In the probabilistic seismic hazard analysis, EVALUATE sources of           consistent with accepted verb usage across RA-Sb-      earthquakes that have the potential to contribute significantly to     SRs. The Addendum B SR wording 2013        the probabilistic hazard at the site. IDENTIFY and                     envelopes that of Addendum A.
Capability Category I
CHARACTERIZE seismic sources taking into account previous compilations of seismic sources, based on regional and site geological and geophysical data, historical and instrumental seismicity data, and geological evidence of prehistoric earthquakes.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SHA-C2   ASME/ANS ENSURE that any expert elicitation process used to characterize the         Addendum B Assessment Equates to RA-Sa-      seismic sources is compatible with the level of analysis discussed in   Addendum A 2009        Requirement HA-A, and FOLLOW a structured approach.
SHA-C1 ASME/ANS RA-Sa-2009 In the probabilistic seismic hazard analysis, EXAMINE all potential sources of earthquakes that affect the probabilistic hazard at the site. BASE the identification and characterization of seismic sources on regional and site geological and geophysical data, historical and instrumental seismicity data, the regional stress field, and geological evidence of prehistoric earthquakes.
ASME/ANS ENSURE that any expert elicitation process used to characterize the         Addendum B changed action verbs to be RA-Sb-      seismic sources is compatible with the level of analysis discussed in   consistent with accepted verb usage across 2013        Requirement HLR-SHA-A, and USE a structured approach.                  SRs. This wording edit does not change the capability category requirements of this SR.
Addendum B Assessment Envelopes Addendum A Addendum B added additional clarifications and requirements into the text of this SR, and also Addendum B changed action verbs to be consistent with accepted verb usage across SRs. The Addendum B SR wording envelopes that of Addendum A.
SHA-C3   ASME/ANS <not printed here; not       The seismic sources are characterized by       Vogtle Conforms to Addendum A RA-Sa-      focus of this            source location and geometry, maximum 2009        assessment>              earthquake magnitude, and earthquake           Addenda B added additional clarification into recurrence. INCLUDE the aleatory and          the text of this SR, and also added a clause epistemic uncertainties explicitly in these    "where significant" at the end. The Addenda characterizations.                            B SR requirement is appropriate for CC-II.
ASME/ANS RA-Sb-2013 In the probabilistic seismic hazard analysis, EVALUATE sources of earthquakes that have the potential to contribute significantly to the probabilistic hazard at the site. IDENTIFY and CHARACTERIZE seismic sources taking into account previous compilations of seismic sources, based on regional and site geological and geophysical data, historical and instrumental seismicity data, and geological evidence of prehistoric earthquakes.
Under the SSHAC Level 3 process the aleatory and epistemic uncertainties in E-7
SHA-C2 ASME/ANS RA-Sa-2009 ENSURE that any expert elicitation process used to characterize the seismic sources is compatible with the level of analysis discussed in Requirement HA-A, and FOLLOW a structured approach.
Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013 ENSURE that any expert elicitation process used to characterize the seismic sources is compatible with the level of analysis discussed in Requirement HLR-SHA-A, and USE a structured approach.
SHA-C3 ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
The seismic sources are characterized by source location and geometry, maximum earthquake magnitude, and earthquake recurrence. INCLUDE the aleatory and epistemic uncertainties explicitly in these characterizations.
Vogtle Conforms to Addendum A Addenda B added additional clarification into the text of this SR, and also added a clause "where significant" at the end. The Addenda B SR requirement is appropriate for CC-II.
Under the SSHAC Level 3 process the aleatory and epistemic uncertainties in  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category     Capability Category Capability Category SR                                                                                              Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-8 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                I                      II                    III ASME/ANS <not printed here; not     The seismic sources are characterized by     seismic sources are characterized for source RA-Sb-      focus of this          alternative source representation and        location and geometry, magnitude, and 2013        assessment>            source geometry, maximum earthquake          activity rate. Logic trees to account for the magnitude, and earthquake recurrence.        epistemic uncertainty were developed as part INCLUDE the aleatory and epistemic            of the SSHAC Level 3 methodology uncertainties explicitly in these            implemented in the CEUS SSC report. The characterizations, where significant.        aleatory uncertainty was also accounted for in the PSHA framework of the Vogtle PSHA.
Capability Category I
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
The seismic sources are characterized by alternative source representation and source geometry, maximum earthquake magnitude, and earthquake recurrence.
INCLUDE the aleatory and epistemic uncertainties explicitly in these characterizations, where significant.
seismic sources are characterized for source location and geometry, magnitude, and activity rate. Logic trees to account for the epistemic uncertainty were developed as part of the SSHAC Level 3 methodology implemented in the CEUS SSC report. The aleatory uncertainty was also accounted for in the PSHA framework of the Vogtle PSHA.
For seismic sources representing repeated large magnitude earthquakes (RLMEs),
For seismic sources representing repeated large magnitude earthquakes (RLMEs),
uncertainties in location and geometry, magnitude model, activity rate, and maximum magnitude were explicitly included in the characterization. For background sources, uncertainty in geometry was represented with alternative sets of area sources, uncertainties in recurrence rates were represented with alternative rates, and uncertainties in maximum magnitude were represented with distributions of values. These uncertainties were documented in the 2012 CEUS SSC report and were included in the Vogtle PSHA.
uncertainties in location and geometry, magnitude model, activity rate, and maximum magnitude were explicitly included in the characterization. For background sources, uncertainty in geometry was represented with alternative sets of area sources, uncertainties in recurrence rates were represented with alternative rates, and uncertainties in maximum magnitude were represented with distributions of values. These uncertainties were documented in the 2012 CEUS SSC report and were included in the Vogtle PSHA.
Based on this, the Vogtle PSHA that was performed conforms to Addendum A.
Based on this, the Vogtle PSHA that was performed conforms to Addendum A.
SHA-C4   ASME/ANS If an existing probabilistic seismic hazard analysis study is used,       Addendum B Assessment Equates to RA-Sa-      SHOW that any seismic sources that were previously unknown or         Addendum A 2009        uncharacterized are not significant, or INCLUDE them in a revision of the hazard estimates.                                                 Addendum B added additional clarifications and modified the sentence structure to ASME/ANS If an existing seismic source model is used, DEMONSTRATE that any         highlight the seismic source model aspect of RA-Sb-      new seismic sources that have been identified or were                 the PSHA. In addition, Addendum B changed 2013        uncharacterized when the existing models were developed are not       action verbs to be consistent with accepted E-8
SHA-C4 ASME/ANS RA-Sa-2009 If an existing probabilistic seismic hazard analysis study is used, SHOW that any seismic sources that were previously unknown or uncharacterized are not significant, or INCLUDE them in a revision of the hazard estimates.
Addendum B Assessment Equates to Addendum A Addendum B added additional clarifications and modified the sentence structure to highlight the seismic source model aspect of the PSHA. In addition, Addendum B changed action verbs to be consistent with accepted ASME/ANS RA-Sb-2013 If an existing seismic source model is used, DEMONSTRATE that any new seismic sources that have been identified or were uncharacterized when the existing models were developed are not  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category Capability Category Capability Category SR                                                                                                  Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-9 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                        II                      III significant, or INCLUDE them in the update of the hazard estimates.       verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
Capability Category I
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) significant, or INCLUDE them in the update of the hazard estimates.
verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
HLR-SHA-D: The probabilistic seismic hazard analysis shall examine mechanisms influencing vibratory ground motion that can occur at a site given the occurrence of an earthquake of a certain type (e.g., strike slip, normal, reverse) and magnitude, and at a certain location.
HLR-SHA-D: The probabilistic seismic hazard analysis shall examine mechanisms influencing vibratory ground motion that can occur at a site given the occurrence of an earthquake of a certain type (e.g., strike slip, normal, reverse) and magnitude, and at a certain location.
Uncertainties shall be addressed in characterizing the ground motion propagation.
Uncertainties shall be addressed in characterizing the ground motion propagation.
SHA-D1 ASME/ANS ACCOUNT in the probabilistic seismic hazard analysis for                           Addendum B Assessment Equates to RA-Sa-        (a) credible mechanisms governing estimates of vibratory ground           Addendum A 2009          motion that can occur at a site (b) regional and site-specific geological, geophysical, and               Addendum B changed action verbs to be geotechnical data and historical and instrumental seismicity data         consistent with accepted verb usage across (including strong motion data)                                             SRs. In addition, Addendum B modified item (c) current attenuation models in the ground motion estimates             (b) by removing requirements that were ASME/ANS In the vibratory ground motion analysis, INCLUDE                                redundant with SHA-B1. This wording edit RA-Sb-         (a) credible mechanisms governing estimates of vibratory ground           does not change the capability category 2013          motion that can occur at a site                                           requirements of this SR.
SHA-D1 ASME/ANS RA-Sa-2009 ACCOUNT in the probabilistic seismic hazard analysis for (a) credible mechanisms governing estimates of vibratory ground motion that can occur at a site (b) regional and site-specific geological, geophysical, and geotechnical data and historical and instrumental seismicity data (including strong motion data)
(b) available historical and instrumental seismicity data (including strong motion data)
(c) current attenuation models in the ground motion estimates Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. In addition, Addendum B modified item (b) by removing requirements that were redundant with SHA-B1. This wording edit does not change the capability category requirements of this SR.
(c) current attenuation models for the ground motion estimates SHA-D2 ASME/ANS ENSURE that any expert elicitation process used to characterize the                 Addendum B Assessment Envelopes RA-Sa-        ground motion is compatible with the level of analysis discussed in       Addendum A 2009          Requirement SHA-A, and FOLLOW a structured approach.
ASME/ANS RA-Sb-2013 In the vibratory ground motion analysis, INCLUDE (a) credible mechanisms governing estimates of vibratory ground motion that can occur at a site (b) available historical and instrumental seismicity data (including strong motion data)
ASME/ANS ENSURE that any expert elicitation process used to characterize the             Addendum B added additional requirements RA-Sb-        ground motion or any other elements of the ground motion                   into the text of this SR, and also Addendum B 2013          analysis is compatible with the level of analysis discussed in             changed action verbs to be consistent with Requirement HLR-SHA-A, and USE a structured approach.                      accepted verb usage across SRs. The Addendum B SR wording envelopes that of Addendum A.
(c) current attenuation models for the ground motion estimates SHA-D2 ASME/ANS RA-Sa-2009 ENSURE that any expert elicitation process used to characterize the ground motion is compatible with the level of analysis discussed in Requirement SHA-A, and FOLLOW a structured approach.
SHA-D3 ASME/ANS <not printed here; not ADDRESS both the aleatory and epistemic                     Addendum B Assessment Envelopes RA-Sa-        focus of this            uncertainties in the ground motion               Addendum A 2009          assessment>              characterization in accordance with the level of analysis identified for Requirement SHA-A. Addendum B changed action verbs to be E-9
Addendum B Assessment Envelopes Addendum A Addendum B added additional requirements into the text of this SR, and also Addendum B changed action verbs to be consistent with accepted verb usage across SRs. The Addendum B SR wording envelopes that of Addendum A.
ASME/ANS RA-Sb-2013 ENSURE that any expert elicitation process used to characterize the ground motion or any other elements of the ground motion analysis is compatible with the level of analysis discussed in Requirement HLR-SHA-A, and USE a structured approach.
SHA-D3 ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
ADDRESS both the aleatory and epistemic uncertainties in the ground motion characterization in accordance with the level of analysis identified for Requirement SHA-A.
Addendum B Assessment Envelopes Addendum A Addendum B changed action verbs to be  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category     Capability Category Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-10 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                I                        II                        III ASME/ANS <not printed here; not       INCLUDE both the aleatory and epistemic             consistent with accepted verb usage across RA-Sb-      focus of this            uncertainties separately in the ground motion      SRs, and also Addendum B added additional 2013        assessment>              characterization in accordance with the level      requirement on handling aleatory and of analysis identified for Requirement HLR-        epistemic uncertainties separately. The SHA-A.                                              Addendum B SR wording envelopes that of Addendum A.
Capability Category I
SHA-D4   ASME/ANS If an existing probabilistic seismic hazard analysis study is used,             Addendum B Assessment Equates to RA-Sa-      SHOW that any ground motion models or new information that were             Addendum A 2009        previously unused or unknown are not significant, or INCLUDE them in a revision of the hazard estimates.                                       Addendum B added additional clarifications ASME/ANS If existing ground motion models are used, DEMONSTRATE that                      and modified the sentence structure to RA-Sb-      new information not previously used or which was unknown when the            highlight the ground motion model aspect of 2013        existing models were developed would not significantly affect the            the PSHA. In addition, Addendum B changed PSHA results, or INCLUDE it in the update of the hazard estimates.          action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
INCLUDE both the aleatory and epistemic uncertainties separately in the ground motion characterization in accordance with the level of analysis identified for Requirement HLR-SHA-A.
consistent with accepted verb usage across SRs, and also Addendum B added additional requirement on handling aleatory and epistemic uncertainties separately. The Addendum B SR wording envelopes that of Addendum A.
SHA-D4 ASME/ANS RA-Sa-2009 If an existing probabilistic seismic hazard analysis study is used, SHOW that any ground motion models or new information that were previously unused or unknown are not significant, or INCLUDE them in a revision of the hazard estimates.
Addendum B Assessment Equates to Addendum A Addendum B added additional clarifications and modified the sentence structure to highlight the ground motion model aspect of the PSHA. In addition, Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013 If existing ground motion models are used, DEMONSTRATE that new information not previously used or which was unknown when the existing models were developed would not significantly affect the PSHA results, or INCLUDE it in the update of the hazard estimates.
HLR-SHA-E: The probabilistic seismic hazard analysis shall account for the effects of local site response.
HLR-SHA-E: The probabilistic seismic hazard analysis shall account for the effects of local site response.
SHA-E1 ASME/ANS <not printed here; not ACCOUNT in the probabilistic seismic                         Addendum B Assessment Equates to RA-Sa-      focus of this            hazard analysis for the effects of site             Addendum A 2009        assessment>              topography, surficial geologic deposits, and site geotechnical properties on ground             Addendum B changed action verbs to be motions at the site.                                consistent with accepted verb usage across ASME/ANS <not printed here; not In the probabilistic seismic hazard                      SRs. This wording edit does not change the RA-Sb-       focus of this           analysis, INCLUDE the effects of site               capability category requirements of this SR.
SHA-E1 ASME/ANS RA-Sa-2009
2013        assessment>              topography, surficial geologic deposits, and site geotechnical properties on ground motions at the site.
<not printed here; not focus of this assessment>
SHA-E2 ASME/ANS <not printed here; not ADDRESS both the aleatory and epistemic                     Addendum B Assessment Equates to RA-Sa-      focus of this            uncertainties in the local site response           Addendum A 2009        assessment>              analysis.
ACCOUNT in the probabilistic seismic hazard analysis for the effects of site topography, surficial geologic deposits, and site geotechnical properties on ground motions at the site.
E-10
Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
In the probabilistic seismic hazard analysis, INCLUDE the effects of site topography, surficial geologic deposits, and site geotechnical properties on ground motions at the site.
SHA-E2 ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
ADDRESS both the aleatory and epistemic uncertainties in the local site response analysis.
Addendum B Assessment Equates to Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category       Capability Category Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-11 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                        II                        III ASME/ANS <not printed here; not       INCLUDE both the aleatory and epistemic         Addendum B changed action verbs to be RA-Sb-      focus of this            uncertainties in the local site response        consistent with accepted verb usage across 2013        assessment>              analysis.                                        SRs. This wording edit does not change the capability category requirements of this SR.
Capability Category I
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
INCLUDE both the aleatory and epistemic uncertainties in the local site response analysis.
Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
HLR-SHA-F: Uncertainties in each step of the hazard analysis shall be propagated and displayed in the final quantification of hazard estimates for the site.
HLR-SHA-F: Uncertainties in each step of the hazard analysis shall be propagated and displayed in the final quantification of hazard estimates for the site.
Addendum A only: The results shall include fractile hazard curves, median and mean hazard curves, and uniform hazard response spectra. For certain applications, the probabilistic seismic hazard analysis shall include seismic source deaggregation and magnitude-distance deaggregation SHA-F1 ASME/ANS <not printed here; not In the final quantification of the seismic                     Addendum B Assessment Equates to RA-Sa-      focus of this            hazard, INCLUDE and DISPLAY the                 Addendum A 2009        assessment>              propagation of both aleatory and epistemic uncertainties.                                   In response to NRC 2012 comment on ASME/ANS <not printed here; not In the final quantification of the seismic              Addendum B ballot that said the wording of RA-Sb-      focus of this            hazard, INCLUDE uncertainties through a          this SR was vague, Addendum B revised the 2013        assessment>              family of hazard curves.                        wording to be clear that CCI is Mean only and that CCII-III is a family of hazard curves. This wording edit does not change the capability category requirements of this SR.
Addendum A only: The results shall include fractile hazard curves, median and mean hazard curves, and uniform hazard response spectra. For certain applications, the probabilistic seismic hazard analysis shall include seismic source deaggregation and magnitude-distance deaggregation SHA-F1 ASME/ANS RA-Sa-2009
SHA-F2 ASME/ANS In the probabilistic seismic hazard analysis, INCLUDE appropriate                     Addendum B Assessment Equates to RA-Sa-      sensitivity studies and inter mediate results to identify factors that are Addendum A 2009        important to the site hazard and that make the analysis traceable.
<not printed here; not focus of this assessment>
ASME/ANS Identical to Addendum A                                                       The wording for this SR is the same for RA-Sb-                                                                                  Addendum A and Addendum B.
In the final quantification of the seismic hazard, INCLUDE and DISPLAY the propagation of both aleatory and epistemic uncertainties.
2013 E-11
Addendum B Assessment Equates to Addendum A In response to NRC 2012 comment on Addendum B ballot that said the wording of this SR was vague, Addendum B revised the wording to be clear that CCI is Mean only and that CCII-III is a family of hazard curves. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
In the final quantification of the seismic hazard, INCLUDE uncertainties through a family of hazard curves.
SHA-F2 ASME/ANS RA-Sa-2009 In the probabilistic seismic hazard analysis, INCLUDE appropriate sensitivity studies and inter mediate results to identify factors that are important to the site hazard and that make the analysis traceable.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
ASME/ANS RA-Sb-2013 Identical to Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category   Capability Category       Capability Category SR                                                                                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-12 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                I                        II                      III SHA-F3   ASME/ANS <not printed here; not     DEVELOP the               <not printed here; not Addendum B Assessment Equates to RA-Sa-      focus of this          following results as a    focus of this          Addendum A 2009        assessment>            part of the              assessment>
Capability Category I
quantification                                  Addendum B changed action verbs to be process, compatible                              consistent with accepted verb usage across with needs for the                              SRs, and also Addendum B added additional level of analysis                                clarification on the phrase "quantification determined in (HLR-                              process" by modifying it to "hazard SHA-A):                                          quantification process". This wording edit (a) fractile and mean                          does not change the capability category hazard curves for                                requirements of this SR.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
each ground motion parameter considered in the probabilistic seismic hazard analysis (b) fractile and mean uniform hazard response spectrum ASME/ANS <not printed here; not     CALCULATE the            <not printed here; not RA-Sb-      focus of this         following results as a   focus of this 2013        assessment>            part of the hazard       assessment>
SHA-F3 ASME/ANS RA-Sa-2009
quantification process, compatible with needs for the level of analysis determined in Requirement HLR-SHA-A:
<not printed here; not focus of this assessment>
DEVELOP the following results as a part of the quantification process, compatible with needs for the level of analysis determined in (HLR-SHA-A):
(a) fractile and mean hazard curves for each ground motion parameter considered in the probabilistic seismic hazard analysis (b) fractile and mean uniform hazard response spectrum
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs, and also Addendum B added additional clarification on the phrase "quantification process" by modifying it to "hazard quantification process". This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
CALCULATE the following results as a part of the hazard quantification process, compatible with needs for the level of analysis determined in Requirement HLR-SHA-A:
 
<not printed here; not focus of this assessment>
HLR-SHA-G:
HLR-SHA-G:
Addendum A: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account the E-12
Addendum A: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account the  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard       Capability Category Capability Category Capability Category SR                                                                                                      Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-13 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                          II                      III contributions of deaggregated magnitude-distance results of the probabilistic seismic hazard analysis. Broad-band, smooth spectral shapes, such as those presented in NUREG/CR-0098 [5-5] (for lower seismicity sites such as most of those east of the U.S. Rocky Mountains) are also acceptable if they are shown to be appropriate for the site. The use of existing uniform hazard response spectra (UHSs) is acceptable unless evidence comes to light that would challenge these uniform hazard spectral shapes.
Capability Category I
Reg Guide 1.200 Rev2 Clarification: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account the contributions of deaggregated magnitude-distance results of the probabilistic seismic hazard analysis. Broad-band, smooth spectral shapes, ... that would challenge these uniform hazard spectral shapes.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) contributions of deaggregated magnitude-distance results of the probabilistic seismic hazard analysis. Broad-band, smooth spectral shapes, such as those presented in NUREG/CR-0098 [5-5] (for lower seismicity sites such as most of those east of the U.S. Rocky Mountains) are also acceptable if they are shown to be appropriate for the site. The use of existing uniform hazard response spectra (UHSs) is acceptable unless evidence comes to light that would challenge these uniform hazard spectral shapes.
Reg Guide 1.200 Rev2 Clarification: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account the contributions of deaggregated magnitude-distance results of the probabilistic seismic hazard analysis. Broad-band, smooth spectral shapes,... that would challenge these uniform hazard spectral shapes.
Addendum B: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account results of the probabilistic seismic hazard analysis.
Addendum B: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account results of the probabilistic seismic hazard analysis.
SHA-G1 ASME/ANS <not printed here; not BASE the response                       <not printed here; not Addendum B Assessment Equates to RA-Sa-        focus of this              spectral shape used      focus of this          Addendum A 2009          assessment>                in the seismic PRA      assessment>
SHA-G1 ASME/ANS RA-Sa-2009
on site-specific                                Addendum B deleted the last sentence of this evaluations                                    SR to make the language more concise and performed for the                              remove redundancy. In addition, Addendum probabilistic                                  B changed the action verb to be consistent seismic hazard                                  with accepted verb usage across SRs. This analysis. REFLECT                              wording edit does not change the capability or BOUND the site-                              category requirements of this SR.
<not printed here; not focus of this assessment>
specific considerations.
BASE the response spectral shape used in the seismic PRA on site-specific evaluations performed for the probabilistic seismic hazard analysis. REFLECT or BOUND the site-specific considerations.
ASME/ANS <not printed here; not ENSURE that the                     <not printed here; not RA-Sb-        focus of this              spectral shape used     focus of this 2013          assessment>                in the seismic PRA       assessment>
<not printed here; not focus of this assessment>
uses site-specific evaluations performed for the PSHA.
Addendum B Assessment Equates to Addendum A Addendum B deleted the last sentence of this SR to make the language more concise and remove redundancy. In addition, Addendum B changed the action verb to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
ENSURE that the spectral shape used in the seismic PRA uses site-specific evaluations performed for the PSHA.
<not printed here; not focus of this assessment>
HLR-SHA-H: When use is made of an existing study for probabilistic seismic hazard analysis purposes, it shall be confirmed that the basic data and interpretations are still valid in light of established current information [Addendum A only: the study meets the requirements outlined in A through G above, and the study is suitable for the intended application.]
HLR-SHA-H: When use is made of an existing study for probabilistic seismic hazard analysis purposes, it shall be confirmed that the basic data and interpretations are still valid in light of established current information [Addendum A only: the study meets the requirements outlined in A through G above, and the study is suitable for the intended application.]
Reg Guide 1.200 Rev 2 Clarification: When use ... for the intended application. It shall be confirmed that basic data and interpretations E-13
Reg Guide 1.200 Rev 2 Clarification: When use... for the intended application. It shall be confirmed that basic data and interpretations  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard       Capability Category Capability Category Capability Category SR                                                                                                      Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-14 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                        II                      III from an existing study are valid.
Capability Category I
SHA-H1 ASME/ANS <not printed here; not Use of existing                         <not printed here; not Addendum B Assessment Envelopes RA-Sa-          focus of this           studies allowed.         focus of this            Addendum A 2009            assessment>                                        assessment>
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) from an existing study are valid.
ASME/ANS CONFIRM that the basic data and interpretations for any existing Addendum B added additional clarifications RA-Sb-          studies used remain valid in light of established current                   and requirements into the text of this SR. The 2013            information, consistent with the Requirements HLR-SHA-A                     Addendum B SR wording envelopes that of through HLR-SHA-G, and DESCRIBE the bases and methodology Addendum A.
SHA-H1 ASME/ANS RA-Sa-2009
used.
<not printed here; not focus of this assessment>
Use of existing studies allowed.
<not printed here; not focus of this assessment>
Addendum B Assessment Envelopes Addendum A Addendum B added additional clarifications and requirements into the text of this SR. The Addendum B SR wording envelopes that of Addendum A.
ASME/ANS RA-Sb-2013 CONFIRM that the basic data and interpretations for any existing studies used remain valid in light of established current information, consistent with the Requirements HLR-SHA-A through HLR-SHA-G, and DESCRIBE the bases and methodology used.
HLR-SHA-I: A screening analysis shall be performed to assess whether, in addition to the vibratory ground motion, other seismic hazards, such as fault displacement, landslide, soil liquefaction, or soil settlement, need to be included in the seismic PRA [Addendum A only: for the specific application. If so, the seismic PRA shall address the effect of these hazards through assessment of the frequency of hazard occurrence or the magnitude of hazard consequences, or both.]
HLR-SHA-I: A screening analysis shall be performed to assess whether, in addition to the vibratory ground motion, other seismic hazards, such as fault displacement, landslide, soil liquefaction, or soil settlement, need to be included in the seismic PRA [Addendum A only: for the specific application. If so, the seismic PRA shall address the effect of these hazards through assessment of the frequency of hazard occurrence or the magnitude of hazard consequences, or both.]
Reg Guide 1.200 Rev 2 Clarification: A screening analysis ... or the magnitude of hazard consequences, or both. The hazard analysis shall include hazards other than vibratory ground motion if necessary.
Reg Guide 1.200 Rev 2 Clarification: A screening analysis... or the magnitude of hazard consequences, or both. The hazard analysis shall include hazards other than vibratory ground motion if necessary.
SHA-I1     ASME/ANS (There are no supporting requirements here.)                                       Addendum B Assessment Envelopes RA-Sa-                                                                                      Addendum A 2009 ASME/ANS DOCUMENT the bases and methodology used for any screening                          There are no supporting requirements for RA-Sb-          out of the seismic hazards other than vibratory ground motion.              HLR-SHA-I in Addendum A. Since the HLRs 2013                                                                                        only say do something and the SRs establish what needs to be done, the addition of SRs in Addendum B establishes new requirements beyond Addendum A.
SHA-I1 ASME/ANS RA-Sa-2009 (There are no supporting requirements here.)
SHA-I2     ASME/ANS no SHA-I2 in Addendum A                                                           Addendum B Assessment Envelopes RA-Sa-                                                                                      Addendum A 2009 ASME/ANS For those hazards not screened out, INCLUDE their effect                          There are no supporting requirements for RA-Sb-          through assessment of the frequency of hazard occurrence and                HLR-SHA-I in Addendum A. Since the HLRs 2013            the magnitude of hazard consequences.                                      only say do something and the SRs establish what needs to be done, the addition of SRs in Addendum B establishes new E-14
Addendum B Assessment Envelopes Addendum A There are no supporting requirements for HLR-SHA-I in Addendum A. Since the HLRs only say do something and the SRs establish what needs to be done, the addition of SRs in Addendum B establishes new requirements beyond Addendum A.
ASME/ANS RA-Sb-2013 DOCUMENT the bases and methodology used for any screening out of the seismic hazards other than vibratory ground motion.
SHA-I2 ASME/ANS RA-Sa-2009 no SHA-I2 in Addendum A Addendum B Assessment Envelopes Addendum A There are no supporting requirements for HLR-SHA-I in Addendum A. Since the HLRs only say do something and the SRs establish what needs to be done, the addition of SRs in Addendum B establishes new ASME/ANS RA-Sb-2013 For those hazards not screened out, INCLUDE their effect through assessment of the frequency of hazard occurrence and the magnitude of hazard consequences.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA Standard     Capability Category       Capability Category     Capability Category SR                                                                                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-15 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.
Rev.                  I                        II                        III requirements beyond Addendum A.
Capability Category I
HLR-SHA-J: Documentation of the probabilistic seismic hazard analysis shall be consistent with the applicable supporting requirements SHA-J1   ASME/ANS DOCUMENT the probabilistic seismic hazard analysis in a manner               Addendum B Assessment Equates to RA-Sa-      that facilitates PRA applications, upgrades, and peer review.           Addendum A 2009 ASME/ANS Identical to Addendum A                                                     The wording for this SR is the same for RA-Sb-                                                                                Addendum A and Addendum B.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) requirements beyond Addendum A.
2013 SHA-J2   ASME/ANS DOCUMENT the process used in the probabilistic seismic hazard               Addendum B Assessment Equates to RA-Sa-      analysis. For example, this documentation is typically consistent with   Addendum A 2009        reference [5-28] and includes a description of:
HLR-SHA-J: Documentation of the probabilistic seismic hazard analysis shall be consistent with the applicable supporting requirements SHA-J1 ASME/ANS RA-Sa-2009 DOCUMENT the probabilistic seismic hazard analysis in a manner that facilitates PRA applications, upgrades, and peer review.
(a) the specific methods used for source characterization and ground     The wording for this SR is the same for motion characterization,                                                 Addendum A and Addendum B.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
(b) the scientific interpretations that are the basis for the inputs and results, and (c) if an existing PSHA is used, documentation to ensure that it is adequate to meet the spirit of the requirements herein.
ASME/ANS RA-Sb-2013 Identical to Addendum A SHA-J2 ASME/ANS RA-Sa-2009 DOCUMENT the process used in the probabilistic seismic hazard analysis. For example, this documentation is typically consistent with reference [5-28] and includes a description of:
ASME/ANS Identical to Addendum A RA-Sb-2013 SHA-J3   ASME/ANS DOCUMENT the sources of model uncertainty and related                       Addendum B Assessment Equates to RA-Sa-      assumptions associated with the probabilistic seismic hazard analysis. Addendum A 2009 ASME/ANS Identical to Addendum A                                                     The wording for this SR is the same for RA-Sb-                                                                                Addendum A and Addendum B.
(a) the specific methods used for source characterization and ground motion characterization, (b) the scientific interpretations that are the basis for the inputs and results, and (c) if an existing PSHA is used, documentation to ensure that it is adequate to meet the spirit of the requirements herein.
2013 E-15
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
ASME/ANS RA-Sb-2013 Identical to Addendum A SHA-J3 ASME/ANS RA-Sa-2009 DOCUMENT the sources of model uncertainty and related assumptions associated with the probabilistic seismic hazard analysis.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
ASME/ANS RA-Sb-2013 Identical to Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                                  Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-16 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                      II                      III HLR-SFR-A:
Capability Category I
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
HLR-SFR-A:
Addendum A: The seismic-fragility evaluation shall be performed to estimate seismic fragilities of SSCs whose failure may contribute to core damage or large early release, or both.
Addendum A: The seismic-fragility evaluation shall be performed to estimate seismic fragilities of SSCs whose failure may contribute to core damage or large early release, or both.
Addendum B: The seismic-fragility evaluation shall be performed to estimate plant-specific, realistic seismic fragilities of structures, or systems, or components, or a combination thereof whose failure may contribute to core damage or large early release, or both.
Addendum B: The seismic-fragility evaluation shall be performed to estimate plant-specific, realistic seismic fragilities of structures, or systems, or components, or a combination thereof whose failure may contribute to core damage or large early release, or both.
SFR-A1 ASME/ANS DEVELOP seismic fragilities for all those structures, systems, or                   Addendum B Assessment Equates to RA-Sa-        components, or a combination thereof identified by the systems             Addendum A 2009          analysis (see Requirement SPR-D1).
SFR-A1 ASME/ANS RA-Sa-2009 DEVELOP seismic fragilities for all those structures, systems, or components, or a combination thereof identified by the systems analysis (see Requirement SPR-D1).
ASME/ANS CALCULATE seismic fragilities for SSCs identified by the systems                The changes from Addendum A to RA-Sb-        analysis (see Requirement SPR-D1).                                        Addendum B for this SR included the 2013                                                                                    replacement of "DEVELOP" with "CALCULATE." The change implements a more precise action verb. These wording edits do not change capability category requirements of this SR. The elimination of the phrase a combination thereof does not change the requirements, since it is redundant to other SRs requiring consideration of seismic correlation.
Addendum B Assessment Equates to Addendum A The changes from Addendum A to Addendum B for this SR included the replacement of "DEVELOP" with "CALCULATE." The change implements a more precise action verb. These wording edits do not change capability category requirements of this SR. The elimination of the phrase a combination thereof does not change the requirements, since it is redundant to other SRs requiring consideration of seismic correlation.
SFR-A2 ASME/ANS <not printed here; not BASE the seismic                   <not printed here; not Addendum B Assessment Equates to RA-Sa-        focus of this          fragilities on plant-    focus of this            Addendum A 2009          assessment>            specific data, and        assessment>
ASME/ANS RA-Sb-2013 CALCULATE seismic fragilities for SSCs identified by the systems analysis (see Requirement SPR-D1).
ENSURE that they                                    The changes from Addendum A to are realistic (median                              Addendum B involve the replacement of with uncertainties).                                "BASE" with the more precise action verb Generic data (e.g.,                                "CALCULATE" and the replacement of fragility test data,                                "conservative" with "applicable" in the last generic seismic                                    sentence with respect to the use of generic qualification test data,                            fragility data. The latter change precludes and earthquake                                      confusion due to a contradiction, as the experience data)                                    requirement states first that realistic fragilities E-16
SFR-A2 ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
BASE the seismic fragilities on plant-specific data, and ENSURE that they are realistic (median with uncertainties).
Generic data (e.g.,
fragility test data, generic seismic qualification test data, and earthquake experience data)
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A The changes from Addendum A to Addendum B involve the replacement of "BASE" with the more precise action verb "CALCULATE" and the replacement of "conservative" with "applicable" in the last sentence with respect to the use of generic fragility data. The latter change precludes confusion due to a contradiction, as the requirement states first that realistic fragilities


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category     Capability Category SR                                                                                              Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-17 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                I                    II                      III MAY be used for                                 are required but then the use of generic data screening of certain                             is to be conservative. In the context of the structures, systems,                             requirement, the use of "applicable" is correct or components, or a                             and does not change the capability category combination thereof                             requirements of this SR.
Capability Category I
and for calculating their seismic fragilities by applying the requirements under (HLR-SFR-F),
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
MAY be used for screening of certain structures, systems, or components, or a combination thereof and for calculating their seismic fragilities by applying the requirements under (HLR-SFR-F),
which permits use of such generic data under specified conditions. However, DEMONSTRATE that any use of such generic data is conservative.
which permits use of such generic data under specified conditions. However, DEMONSTRATE that any use of such generic data is conservative.
ASME/ANS <not printed here; not   CALCULATE the            <not printed here; not RA-Sb-      focus of this       seismic fragilities       focus of this 2013        assessment>          based on plant-           assessment>
are required but then the use of generic data is to be conservative. In the context of the requirement, the use of "applicable" is correct and does not change the capability category requirements of this SR.
specific data, and ENSURE that they are realistic (median with uncertainties).
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
CALCULATE the seismic fragilities based on plant-specific data, and ENSURE that they are realistic (median with uncertainties).
Generic data (e.g.,
Generic data (e.g.,
fragility test data, generic seismic qualification test data, and earthquake experience data) may be used for screening E-17
fragility test data, generic seismic qualification test data, and earthquake experience data) may be used for screening
<not printed here; not focus of this assessment>


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category     Capability Category     Capability Category SR                                                                                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-18 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                      II                      III of certain SSCs and for calculating their seismic fragilities by applying the Requirement HLR-SFR-F, which permits use of such generic data under specified conditions. However, DEMONSTRATE that any use of such generic data is applicable.
Capability Category I
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) of certain SSCs and for calculating their seismic fragilities by applying the Requirement HLR-SFR-F, which permits use of such generic data under specified conditions. However, DEMONSTRATE that any use of such generic data is applicable.
HLR-SFR-B: If screening of high-seismic-capacity components is performed, the basis for the screening shall be fully described.
HLR-SFR-B: If screening of high-seismic-capacity components is performed, the basis for the screening shall be fully described.
SFR-B1   ASME/ANS If screening of high-seismic-capacity                 <not printed here; not Addendum B Assessment Equates to RA-Sa-      components is performed, DESCRIBE fully           focus of this          Addendum A 2009        the basis for screening and supporting           assessment>
SFR-B1 ASME/ANS RA-Sa-2009 If screening of high-seismic-capacity components is performed, DESCRIBE fully the basis for screening and supporting documents. For example, it is acceptable to apply guidance given in EPRI NP-6041-SL, Rev. 1, and NUREG/CR-4334 to screen out components with high seismic capacity.
documents. For example, it is acceptable to                             Addendum B removes the sentence citing apply guidance given in EPRI NP-6041-SL,                                 NP-6041-SL and NUREG/CR-4334 as Rev. 1, and NUREG/CR-4334 to screen out                                  examples of screening bases and replaces components with high seismic capacity.                                  the action verb "CHOOSE" with the more However, CHOOSE the screening level high                                precise verb "SELECT." These wording edits enough that the contribution to core damage                              are non-substantive and do not change frequency and large early release frequency                              capability category requirements of this SR.
However, CHOOSE the screening level high enough that the contribution to core damage frequency and large early release frequency from the screened-out components is not significant.
from the screened-out components is not significant.
<not printed here; not focus of this assessment>
E-18
Addendum B Assessment Equates to Addendum A Addendum B removes the sentence citing NP-6041-SL and NUREG/CR-4334 as examples of screening bases and replaces the action verb "CHOOSE" with the more precise verb "SELECT." These wording edits are non-substantive and do not change capability category requirements of this SR.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                              Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-19 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                I                      II                      III ASME/ANS If screening of high-seismic-capacity               <not printed here; not RA-Sb-      components is performed, DESCRIBE the           focus of this 2013        basis for screening and the supporting           assessment>
Capability Category I
documents and SELECT the screening level high enough that the contribution to core damage frequency and large early release frequency from the screened-out components is not significant.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SFR-B2   ASME/ANS ASSESS and DOCUMENT the applicability of the screening                     Addendum B Assessment Equates to RA-Sa-      criteria given in EPRI NP-6041-SL, Rev. 1 [5-3] and NUREG/CR-           Addendum A 2009        4334 [5-4] for the specific plant and specific equipment.
ASME/ANS RA-Sb-2013 If screening of high-seismic-capacity components is performed, DESCRIBE the basis for screening and the supporting documents and SELECT the screening level high enough that the contribution to core damage frequency and large early release frequency from the screened-out components is not significant.
Addendum B deleted this SR. The clarifying ASME/ANS No SFR-B2 in Addendum B                                                    non-mandatory footnote for SFR-B1, which RA-Sb-                                                                              remains unchanged from Addendum A to 2013                                                                                Addendum B, reiterates that NP-6041-SL and NUREG/CR-4334 "may be used" and are not mandatory. SFR-B2 in Addendum A states the applicability of NP-6041-SL and NUREG/CR-4334 shall be assessed and documented. However, if NP-6041-SL and NUREG/CR-4334 are applied for screening, SFR-B1 in both Addendum A and Addendum B state that the basis for use shall be described and documentation is addressed under SFR-G2. Therefore, SFR-B2 is redundant and its removal does not change the requirements of the standard.
<not printed here; not focus of this assessment>
HLR-SFR-C: The seismic-fragility evaluation shall be based on seismic response that the SSCs experience at their failure levels E-19
SFR-B2 ASME/ANS RA-Sa-2009 ASSESS and DOCUMENT the applicability of the screening criteria given in EPRI NP-6041-SL, Rev. 1 [5-3] and NUREG/CR-4334 [5-4] for the specific plant and specific equipment.
Addendum B Assessment Equates to Addendum A Addendum B deleted this SR. The clarifying non-mandatory footnote for SFR-B1, which remains unchanged from Addendum A to Addendum B, reiterates that NP-6041-SL and NUREG/CR-4334 "may be used" and are not mandatory. SFR-B2 in Addendum A states the applicability of NP-6041-SL and NUREG/CR-4334 shall be assessed and documented. However, if NP-6041-SL and NUREG/CR-4334 are applied for screening, SFR-B1 in both Addendum A and Addendum B state that the basis for use shall be described and documentation is addressed under SFR-G2. Therefore, SFR-B2 is redundant and its removal does not change the requirements of the standard.
ASME/ANS RA-Sb-2013 No SFR-B2 in Addendum B HLR-SFR-C: The seismic-fragility evaluation shall be based on seismic response that the SSCs experience at their failure levels


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category         Capability Category SR                                                                                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-20 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                I                        II                      III SFR-C1   ASME/ANS ESTIMATE the seismic responses that the               <not printed here; not Addendum B Assessment Envelopes RA-Sa-      components experience at their failure levels     focus of this          Addendum A 2009        on a realistic basis using site-specific         assessment>
Capability Category I
earthquake response spectra in three                                     The two changes from Addendum A to orthogonal directions, anchored to a ground                              Addendum B involve the deletion of "site-motion parameter such as peak ground                                    specific" prior to "earthquake response acceleration or average spectral acceleration                            spectra" in the first sentence and deletion of over a given frequency band. ENSURE that                                "reflects" in the last sentence. Removal of the spectral shape used reflects or bounds                              "site-specific" prior to earthquake response the site-specific conditions.                                            spectra is inconsequential as bounding by ASME/ANS ESTIMATE the seismic responses that the              <not printed here; not site-specific conditions by definition renders RA-Sb-      components experience at their failure levels    focus of this          the earthquake response spectra site-2013        using input earthquake response spectra in        assessment>            specific. Removal of "reflects" renders three orthogonal directions, anchored to a                              Addendum B as more precise since the ground motion parameter such as peak                                    properties must "bound" site-specific ground acceleration or average spectral                                  conditions and not merely "reflect."
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
acceleration over a given frequency band, and ENSURE that the spectral shape used bounds the site-specific conditions.
SFR-C1 ASME/ANS RA-Sa-2009 ESTIMATE the seismic responses that the components experience at their failure levels on a realistic basis using site-specific earthquake response spectra in three orthogonal directions, anchored to a ground motion parameter such as peak ground acceleration or average spectral acceleration over a given frequency band. ENSURE that the spectral shape used reflects or bounds the site-specific conditions.
SFR-C2   ASME/ANS If probabilistic response analysis is performed       <not printed here; not Addendum B Assessment Envelopes RA-Sa-      to obtain realistic structural loads and floor   focus of this          Addendum A 2009        response spectra, ENSURE that the number         assessment>
<not printed here; not focus of this assessment>
of simulations done (e.g., Monte Carlo                                   The changes from Addendum A to simulation and Latin Hypercube Sampling) is                             Addendum B are to implement the approved large enough to obtain stable median and                                action verb "ACCOUNT" to the more precise 85% nonexceedance responses. ACCOUNT                                    verb "INCLUDE" and to eliminate "realistic" in for the entire spectrum of input ground motion                          the first sentence prior to "structural loads levels displayed in the seismic hazard curves.                          and floor response spectra." The qualifier E-20
Addendum B Assessment Envelopes Addendum A The two changes from Addendum A to Addendum B involve the deletion of "site-specific" prior to "earthquake response spectra" in the first sentence and deletion of "reflects" in the last sentence. Removal of "site-specific" prior to earthquake response spectra is inconsequential as bounding by site-specific conditions by definition renders the earthquake response spectra site-specific. Removal of "reflects" renders Addendum B as more precise since the properties must "bound" site-specific conditions and not merely "reflect."
ASME/ANS RA-Sb-2013 ESTIMATE the seismic responses that the components experience at their failure levels using input earthquake response spectra in three orthogonal directions, anchored to a ground motion parameter such as peak ground acceleration or average spectral acceleration over a given frequency band, and ENSURE that the spectral shape used bounds the site-specific conditions.
<not printed here; not focus of this assessment>
SFR-C2 ASME/ANS RA-Sa-2009 If probabilistic response analysis is performed to obtain realistic structural loads and floor response spectra, ENSURE that the number of simulations done (e.g., Monte Carlo simulation and Latin Hypercube Sampling) is large enough to obtain stable median and 85% nonexceedance responses. ACCOUNT for the entire spectrum of input ground motion levels displayed in the seismic hazard curves.
<not printed here; not focus of this assessment>
Addendum B Assessment Envelopes Addendum A The changes from Addendum A to Addendum B are to implement the approved action verb "ACCOUNT" to the more precise verb "INCLUDE" and to eliminate "realistic" in the first sentence prior to "structural loads and floor response spectra." The qualifier  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category           Capability Category SR                                                                                                  Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-21 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                I                        II                      III ASME/ANS If probabilistic response analysis is performed         <not printed here; not realistic is removed to avoid confusion as it is RA-Sb-      to obtain structural loads and floor response       focus of this          unnecessary in the context of applying 2013        spectra, ENSURE that the number of                 assessment>            probabilistic response analysis to determine simulations done (e.g., Monte Carlo                                       structural loads and response spectra.
Capability Category I
simulation and Latin Hypercube Sampling) is large enough to obtain stable median and 85% nonexceedance responses. INCLUDE the entire spectrum of input ground motion levels displayed in the seismic hazard curves.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SFR-C3   ASME/ANS If scaling of existing design response analysis         <not printed here; not Vogtle Conforms to Addendum A RA-Sa-      is used, JUSTIFY it based on the adequacy of       focus of this 2009        structural models, foundation characteristics,     assessment>           The change from Addendum A to Addendum and similarity of input ground motion.                                    B involved the deletion of the word "design" ASME/ANS If scaling of existing response analysis is            <not printed here; not from "existing design response analysis."
ASME/ANS RA-Sb-2013 If probabilistic response analysis is performed to obtain structural loads and floor response spectra, ENSURE that the number of simulations done (e.g., Monte Carlo simulation and Latin Hypercube Sampling) is large enough to obtain stable median and 85% nonexceedance responses. INCLUDE the entire spectrum of input ground motion levels displayed in the seismic hazard curves.
RA-Sb-      used, JUSTIFY it based on the adequacy of          focus of this          However, Plant Vogtle did not perform scaling 2013        structural models, foundation characteristics,      assessment>            of any existing response analysis, and and similarity of input ground motion.                                    therefore the change is irrelevant and Vogtle conforms to Addendum A.
<not printed here; not focus of this assessment>
SFR-C4    ASME/ANS When the design response analysis models               <not printed here; not Addendum B Assessment Equates to RA-Sa-       are judged not to be realistic and state of the     focus of this          Addendum A 2009        art, or when the design input ground motion is     assessment>
realistic is removed to avoid confusion as it is unnecessary in the context of applying probabilistic response analysis to determine structural loads and response spectra.
significantly different from the site-specific                             Similar to SFR-C3, Addendum B in SFR-C4 input motion, PERFORM new analysis to                                      eliminates "design" from "existing design obtain realistic structural loads and floor                                response analysis" in the first sentence and response spectra.                                                          adds the "for use in the seismic PRA" to the ASME/ANS When the existing response analysis models             <not printed here; not last sentence. The judgement of existing RA-Sb-       are judged not to be realistic and state of the     focus of this          response analysis models as unrealistic and 2013        art, or when the design input ground motion is     assessment>            not state of the art as stated in Addendum B significantly different from the site-specific                             would include the judgement of existing input motion, PERFORM new analysis to                                     design response analyses; therefore this obtain realistic structural loads and floor                               change is non-substantive. The addition of response spectra for use in the seismic PRA.                               "for use in the seismic PRA" is for clarification E-21
SFR-C3 ASME/ANS RA-Sa-2009 If scaling of existing design response analysis is used, JUSTIFY it based on the adequacy of structural models, foundation characteristics, and similarity of input ground motion.
<not printed here; not focus of this assessment>
Vogtle Conforms to Addendum A The change from Addendum A to Addendum B involved the deletion of the word "design" from "existing design response analysis."
However, Plant Vogtle did not perform scaling of any existing response analysis, and therefore the change is irrelevant and Vogtle conforms to Addendum A.
ASME/ANS RA-Sb-2013 If scaling of existing response analysis is used, JUSTIFY it based on the adequacy of structural models, foundation characteristics, and similarity of input ground motion.
<not printed here; not focus of this assessment>
SFR-C4 ASME/ANS RA-Sa-2009 When the design response analysis models are judged not to be realistic and state of the art, or when the design input ground motion is significantly different from the site-specific input motion, PERFORM new analysis to obtain realistic structural loads and floor response spectra.
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A Similar to SFR-C3, Addendum B in SFR-C4 eliminates "design" from "existing design response analysis" in the first sentence and adds the "for use in the seismic PRA" to the last sentence. The judgement of existing response analysis models as unrealistic and not state of the art as stated in Addendum B would include the judgement of existing design response analyses; therefore this change is non-substantive. The addition of "for use in the seismic PRA" is for clarification ASME/ANS RA-Sb-2013 When the existing response analysis models are judged not to be realistic and state of the art, or when the design input ground motion is significantly different from the site-specific input motion, PERFORM new analysis to obtain realistic structural loads and floor response spectra for use in the seismic PRA.
<not printed here; not focus of this assessment>


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category       Capability Category   Capability Category SR                                                                                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-22 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                        II                    III and also non-substantive.
Capability Category I
SFR-C5   ASME/ANS If median-centered response analysis is               <not printed here; not Addendum B Assessment Equates to RA-Sa-      performed, ESTIMATE the median response           focus of this          Addendum A 2009        (i.e., structural loads and floor response       assessment>
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) and also non-substantive.
spectra) and variability in the response using                           The wording for this SR is the same for established methods.                                                    Addendum A and Addendum B.
SFR-C5 ASME/ANS RA-Sa-2009 If median-centered response analysis is performed, ESTIMATE the median response (i.e., structural loads and floor response spectra) and variability in the response using established methods.
ASME/ANS Identical to Addendum A                               <not printed here; not RA-Sb-                                                        focus of this 2013                                                          assessment>
<not printed here; not focus of this assessment>
SFR-C6   ASME/ANS When soil-structure interaction (SSI) analysis       <not printed here; not Vogtle Conforms to Accepted Current RA-Sa-      is conducted, ENSURE that it is median           focus of this          Practices 2009        centered using median properties, at soil         assessment>
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
strain levels corresponding to the input                                 The changes in SFR-C6 involved the ground motions that dominate the seismically                             replacement of "ACCOUNT for" with the more induced core damage frequency. ACCOUNT                                   precise action verb "INCLUDE", the non-for the uncertainties in the SSI analysis by                             substantive replacement of "dominate" with varying the low strain soil shear modulus                               "contribute most" for PRA standard between the median value times (1 + Cv)                                 consistency, and the removal of how to and the median value divided by (1 + Cv),                               perform SSI uncertainty analysis.
ASME/ANS RA-Sb-2013 Identical to Addendum A
where Cv is a factor that accounts for uncertainties in the SSI analysis and soil                               The SSI uncertainty analysis method properties. If adequate soil investigation                               presented in Addendum A is derived from data are available, ESTABLISH the mean                                  ASCE 4-98 (as indicated by the non-and standard deviation of the low strain                                mandatory Note 5). Section 3.3.1.7 of ASCE shear modulus for every soil layer. Then                                4-98 states that the use of (1 + Cv) to vary ESTABLISH the value of Cv so that it will                                low strain soil shear moduli is an acceptable cover the mean plus or minus one                                        method in lieu of probabilistic evaluation, standard deviation for every layer. The                                  which Section C.3.3.1.7 further states is the E-22
<not printed here; not focus of this assessment>
SFR-C6 ASME/ANS RA-Sa-2009 When soil-structure interaction (SSI) analysis is conducted, ENSURE that it is median centered using median properties, at soil strain levels corresponding to the input ground motions that dominate the seismically induced core damage frequency. ACCOUNT for the uncertainties in the SSI analysis by varying the low strain soil shear modulus between the median value times (1 + Cv) and the median value divided by (1 + Cv),
where Cv is a factor that accounts for uncertainties in the SSI analysis and soil properties. If adequate soil investigation data are available, ESTABLISH the mean and standard deviation of the low strain shear modulus for every soil layer. Then ESTABLISH the value of Cv so that it will cover the mean plus or minus one standard deviation for every layer. The
<not printed here; not focus of this assessment>
Vogtle Conforms to Accepted Current Practices The changes in SFR-C6 involved the replacement of "ACCOUNT for" with the more precise action verb "INCLUDE", the non-substantive replacement of "dominate" with "contribute most" for PRA standard consistency, and the removal of how to perform SSI uncertainty analysis.
The SSI uncertainty analysis method presented in Addendum A is derived from ASCE 4-98 (as indicated by the non-mandatory Note 5). Section 3.3.1.7 of ASCE 4-98 states that the use of (1 + Cv) to vary low strain soil shear moduli is an acceptable method in lieu of probabilistic evaluation, which Section C.3.3.1.7 further states is the  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category           Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-23 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                    I                      II                      III minimum value of Cv is 0-5. When                                         preferred approach.
Capability Category I
insufficient data are available to address uncertainties in soil properties, ENSURE                                 Plant Vogtle accounted for uncertainties in that Cv is taken as no less than 1.0.                                     the SSI analysis by applying strain-compatible soil properties derived from probabilistic evaluation via the PSHA. Use of the ASCE 4-98 alternate approach using (1 +
Capability Category II Capability Category III Basis for Assessment (CC-II Focus) minimum value of Cv is 0-5. When insufficient data are available to address uncertainties in soil properties, ENSURE that Cv is taken as no less than 1.0.
preferred approach.
Plant Vogtle accounted for uncertainties in the SSI analysis by applying strain-compatible soil properties derived from probabilistic evaluation via the PSHA. Use of the ASCE 4-98 alternate approach using (1 +
Cv) would render overly conservative and unrealistic response analysis results, which would invalidate other SRs. Therefore, the Addendum B assessment is considered appropriate.
Cv) would render overly conservative and unrealistic response analysis results, which would invalidate other SRs. Therefore, the Addendum B assessment is considered appropriate.
ASME/ANS When soil-structure interaction (SSI) analysis         <not printed here; not RA-Sb-        is conducted, ENSURE that it is median             focus of this 2013          centered using median properties, at soil         assessment>
ASME/ANS RA-Sb-2013 When soil-structure interaction (SSI) analysis is conducted, ENSURE that it is median centered using median properties, at soil strain levels corresponding to the input ground motions that contribute most to the seismically induced core damage frequency.
strain levels corresponding to the input ground motions that contribute most to the seismically induced core damage frequency.
INCLUDE the uncertainties in the SSI analysis.
INCLUDE the uncertainties in the SSI analysis.
<not printed here; not focus of this assessment>
HLR-SFR-D: The seismic-fragility evaluation shall be performed for critical failure modes of SSCs such as structural failure modes and functional failure modes identified through the review of plant design documents, supplemented as needed by earthquake experience data, fragility test data, generic qualification test data, and a walkdown.
HLR-SFR-D: The seismic-fragility evaluation shall be performed for critical failure modes of SSCs such as structural failure modes and functional failure modes identified through the review of plant design documents, supplemented as needed by earthquake experience data, fragility test data, generic qualification test data, and a walkdown.
SFR-D1 ASME/ANS IDENTIFY realistic failure modes of structures and equipment that                     Addendum B Assessment Envelopes RA-Sa-        interfere with the operability of equipment during or after the           Addendum A 2009          earthquake through a review of the plant design documents and the walkdown.                                                                 The change from Addendum A to Addendum E-23
SFR-D1 ASME/ANS RA-Sa-2009 IDENTIFY realistic failure modes of structures and equipment that interfere with the operability of equipment during or after the earthquake through a review of the plant design documents and the walkdown.
Addendum B Assessment Envelopes Addendum A The change from Addendum A to Addendum  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                                  Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-24 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                I                        II                      III ASME/ANS IDENTIFY realistic failure modes of structures ( e.g., sliding,             B involved the move of example failure RA-Sb-        overturning, yielding, and excessive drift), equipment (e.g.,           modes from SFR-D2 to SFR-D1.
Capability Category I
2013          anchorage failure, impact with adjacent equipment or structures, bracing failure, and functional failure), and soil (e.g., liquefaction, slope instability, and excessive differential settlement) that interfere with the operability of equipment during or after the earthquake, through a review of the plant design documents and the walkdown.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SFR-D2     ASME/ANS EXAMINE all relevant failure modes of structures (e.g., sliding,             Addendum B Assessment Envelopes RA-Sa-        overturning, yielding, and excessive drift), equipment (e.g.,           Addendum A 2009          anchorage failure, impact with adjacent equipment or structures, bracing failure, and functional failure), and soil (i.e., liquefaction, The changes from Addendum A to slope instability, and excessive differential settlement), and         Addendum B for this SR involved the EVALUATE fragilities for critical failure modes.                        aforementioned move of example failure ASME/ANS EVALUATE all relevant failure modes identified in Requirement                modes to SFR-D1 and change in wording RA-Sb-        SFR-D1, and EVALUATE fragilities for critical failure modes.            from "EXAMINE all relevant failure modes of 2013                                                                                  structures..." to "EVALUATE relevant failure modes identified in SFR-D1." The latter change implements a more precise action verb in addition to providing more specificity for the evaluation of failure modes.
ASME/ANS RA-Sb-2013 IDENTIFY realistic failure modes of structures ( e.g., sliding, overturning, yielding, and excessive drift), equipment (e.g.,
anchorage failure, impact with adjacent equipment or structures, bracing failure, and functional failure), and soil (e.g., liquefaction, slope instability, and excessive differential settlement) that interfere with the operability of equipment during or after the earthquake, through a review of the plant design documents and the walkdown.
B involved the move of example failure modes from SFR-D2 to SFR-D1.
SFR-D2 ASME/ANS RA-Sa-2009 EXAMINE all relevant failure modes of structures (e.g., sliding, overturning, yielding, and excessive drift), equipment (e.g.,
anchorage failure, impact with adjacent equipment or structures, bracing failure, and functional failure), and soil (i.e., liquefaction, slope instability, and excessive differential settlement), and EVALUATE fragilities for critical failure modes.
Addendum B Assessment Envelopes Addendum A The changes from Addendum A to Addendum B for this SR involved the aforementioned move of example failure modes to SFR-D1 and change in wording from "EXAMINE all relevant failure modes of structures..." to "EVALUATE relevant failure modes identified in SFR-D1." The latter change implements a more precise action verb in addition to providing more specificity for the evaluation of failure modes.
ASME/ANS RA-Sb-2013 EVALUATE all relevant failure modes identified in Requirement SFR-D1, and EVALUATE fragilities for critical failure modes.
HLR-SFR-E: The seismic-fragility evaluation shall incorporate the findings of a detailed walkdown of the plant focusing on the anchorage, lateral seismic support, and potential systems interactions.
HLR-SFR-E: The seismic-fragility evaluation shall incorporate the findings of a detailed walkdown of the plant focusing on the anchorage, lateral seismic support, and potential systems interactions.
SFR-E1     ASME/ANS CONDUCT a detailed walkdown of the plant, focusing on equipment             Addendum B Assessment Equates to RA-Sa-        anchorage, lateral seismic support, spatial interactions, and potential Addendum A 2009          systems interactions (both structural and functional interactions).
SFR-E1 ASME/ANS RA-Sa-2009 CONDUCT a detailed walkdown of the plant, focusing on equipment anchorage, lateral seismic support, spatial interactions, and potential systems interactions (both structural and functional interactions).
The wording for this SR is the same for ASME/ANS Identical to Addendum A                                                      Addendum A and Addendum B.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
RA-Sb-2013 E-24
ASME/ANS RA-Sb-2013 Identical to Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                            Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-25 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                    II                      III SFR-E2   ASME/ANS     DOCUMENT the walkdown procedures, walkdown team composition           Addendum B Assessment Equates to RA-Sa-      and its members qualifications, walkdown observations, and           Addendum A 2009        conclusions.
Capability Category I
ASME/ANS    Identical to Addendum A                                               The wording for this SR is the same for RA-Sb-                                                                            Addendum A and Addendum B.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
2013 SFR-E3   ASME/ANS     If components are screened out during or following the walkdown,     Addendum B Assessment Envelopes RA-Sa-      DOCUMENT anchorage calculations and PROVIDE the basis                 Addendum A 2009        justifying such a screening.
SFR-E2 ASME/ANS RA-Sa-2009 DOCUMENT the walkdown procedures, walkdown team composition and its members qualifications, walkdown observations, and conclusions.
The change implemented from Addendum A ASME/ANS If components are screened out during or following the walkdown,         to Addendum B involves increased RA-Sb-      DOCUMENT the basis, including any anchorage calculations that         requirement to not only document anchorage 2013        justify such a screening.                                            screening but all screening (e.g. including functional or component structure).
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
SFR-E4   ASME/ANS During the walkdown, FOCUS on the potential for seismically induced       Addendum B Assessment Envelopes RA-Sa-      fire and flooding.                                                    Addendum A 2009 ASME/ANS During the walkdown, EVALUATE the potential for seismically              The change from Addendum A to Addendum RA-Sb-      induced fire and flooding by focusing on the issues described in      B involved changing "FOCUS" into the more 2013        NUREG-1407 [5-7].                                                    precise action verb "EVALUATE" in addition to adding specific criteria pertaining to NUREG-1407.
ASME/ANS RA-Sb-2013 Identical to Addendum A SFR-E3 ASME/ANS RA-Sa-2009 If components are screened out during or following the walkdown, DOCUMENT anchorage calculations and PROVIDE the basis justifying such a screening.
SFR-E5   ASME/ANS During the walkdown, EXAMINE potential sources of interaction (e.g.,     Addendum B Assessment Equates to RA-Sa-      II/I issues, impact between cabinets, masonry walls, flammable and   Addendum A 2009        combustion sources, flooding, and spray) and consequences of such interactions on equipment contained in the systems model.             The change from Addendum A to Addendum B for this SR involved the replacement of ASME/ANS During the walkdown, EVALUATE potential sources of interaction "EXAMINE" with "EVALUATE." The action RA-Sb-       (e.g., II/I issues, impact between cabinets, masonry walls, flammable verb change was made to be consistent with 2013        and combustion sources, flooding, and spray) and consequences of accepted verb usage across SRs. These such interactions on equipment contained in the systems model.
Addendum B Assessment Envelopes Addendum A The change implemented from Addendum A to Addendum B involves increased requirement to not only document anchorage screening but all screening (e.g. including functional or component structure).
wording edits do not change capability category requirements of this SR..
ASME/ANS RA-Sb-2013 If components are screened out during or following the walkdown, DOCUMENT the basis, including any anchorage calculations that justify such a screening.
E-25
SFR-E4 ASME/ANS RA-Sa-2009 During the walkdown, FOCUS on the potential for seismically induced fire and flooding.
Addendum B Assessment Envelopes Addendum A The change from Addendum A to Addendum B involved changing "FOCUS" into the more precise action verb "EVALUATE" in addition to adding specific criteria pertaining to NUREG-1407.
ASME/ANS RA-Sb-2013 During the walkdown, EVALUATE the potential for seismically induced fire and flooding by focusing on the issues described in NUREG-1407 [5-7].
SFR-E5 ASME/ANS RA-Sa-2009 During the walkdown, EXAMINE potential sources of interaction (e.g.,
II/I issues, impact between cabinets, masonry walls, flammable and combustion sources, flooding, and spray) and consequences of such interactions on equipment contained in the systems model.
Addendum B Assessment Equates to Addendum A The change from Addendum A to Addendum B for this SR involved the replacement of "EXAMINE" with "EVALUATE." The action verb change was made to be consistent with accepted verb usage across SRs. These wording edits do not change capability category requirements of this SR..
ASME/ANS RA-Sb-2013 During the walkdown, EVALUATE potential sources of interaction (e.g., II/I issues, impact between cabinets, masonry walls, flammable and combustion sources, flooding, and spray) and consequences of such interactions on equipment contained in the systems model.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard   Capability Category Capability Category Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-26 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                        II                      III HLR-SFR-F: The calculation of seismic-fragility parameters such as median capacity and variabilities shall be based on plant-specific data or, if necessary, on earthquake experience data, fragility test data, and generic qualification test data. Use of such generic data shall be justified.
Capability Category I
SFR-F1     ASME/ANS BASE component seismic-fragility parameters           <not printed here; not    Addendum B Assessment Envelopes RA-Sa-      such as median capacity and variabilities           focus of this            Addendum A 2009        (logarithmic standard deviations reflecting         assessment>
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
randomness and uncertainty) on plant-specific                                 Addendum B changes the action verb from data supplemented as appropriate by                                          "BASE" to the more precise and restrictive earthquake experience data, fragility test                                    verb "CALCULATE" in keeping with the data, and generic qualification test data.                                    approved action verb list and adds more specificity to the use of sources beyond plant-ASME/ANS CALCULATE component seismic-fragility                  <not printed here; not    specific data, including the provision to justify RA-Sb-     parameters such as median capacity and             focus of this            the appropriateness of generic fragility data.
HLR-SFR-F: The calculation of seismic-fragility parameters such as median capacity and variabilities shall be based on plant-specific data or, if necessary, on earthquake experience data, fragility test data, and generic qualification test data. Use of such generic data shall be justified.
2013        variabilities (logarithmic standard deviations     assessment>
SFR-F1 ASME/ANS RA-Sa-2009 BASE component seismic-fragility parameters such as median capacity and variabilities (logarithmic standard deviations reflecting randomness and uncertainty) on plant-specific data supplemented as appropriate by earthquake experience data, fragility test data, and generic qualification test data.
reflecting randomness and uncertainty) based on plant-specific data or, if necessary, on earthquake experience data, fragility test data, and generic qualification test data.
<not printed here; not focus of this assessment>
Addendum B Assessment Envelopes Addendum A Addendum B changes the action verb from "BASE" to the more precise and restrictive verb "CALCULATE" in keeping with the approved action verb list and adds more specificity to the use of sources beyond plant-specific data, including the provision to justify the appropriateness of generic fragility data.
ASME/ANS RA-Sb-2013 CALCULATE component seismic-fragility parameters such as median capacity and variabilities (logarithmic standard deviations reflecting randomness and uncertainty) based on plant-specific data or, if necessary, on earthquake experience data, fragility test data, and generic qualification test data.
Exception: JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.
Exception: JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.
SFR-F2     ASME/ANS For all structures, or systems, or components,         <not printed here; not    Addendum B Assessment Equates to RA-Sa-      or a combination thereof (SSCs) that appear         focus of this            Addendum A 2009        in the dominant accident cut sets, ENSURE           assessment>
<not printed here; not focus of this assessment>
that they have site-specific fragility                                       Addendum B changes the use of "dominant parameters that are derived based on plant-                                   accident cut sets" in Addendum A to specific information, such as anchoring and                                   "significant accident sequences." This installation of the component or structure and                               wording edit is for consistency with the plant-specific material test data. Exception:                                 convention used elsewhere in the PRA JUSTIFY the use of generic fragility for any                                 standard to be software neutral and does SSC as being appropriate for the plant.                                       not change the capability category E-26
SFR-F2 ASME/ANS RA-Sa-2009 For all structures, or systems, or components, or a combination thereof (SSCs) that appear in the dominant accident cut sets, ENSURE that they have site-specific fragility parameters that are derived based on plant-specific information, such as anchoring and installation of the component or structure and plant-specific material test data. Exception:
JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A Addendum B changes the use of "dominant accident cut sets" in Addendum A to "significant accident sequences." This wording edit is for consistency with the convention used elsewhere in the PRA standard to be software neutral and does not change the capability category  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                                    Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-27 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                I                          II                      III ASME/ANS For all SSCs that appear in the significant               <not printed here; not requirements of this SR.
Capability Category I
RA-Sb-      accident sequences, ENSURE that they have focus of this 2013        site-specific fragility parameters that are           assessment>
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
derived based on plant-specific information, such as anchoring and installation of the component or structure and plant-specific material test data. Exception: JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.
ASME/ANS RA-Sb-2013 For all SSCs that appear in the significant accident sequences, ENSURE that they have site-specific fragility parameters that are derived based on plant-specific information, such as anchoring and installation of the component or structure and plant-specific material test data. Exception: JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.
SFR-F3   ASME/ANS <not printed here; not DEVELOP seismic fragilities for relays                   Addendum B Assessment Equates to RA-Sa-      focus of this              identified to be essential and that are included Addendum A 2009        assessment>                in the systems-analysis model.
<not printed here; not focus of this assessment>
The change from Addendum A to Addendum ASME/ANS <not printed here; not          CALCULATE seismic fragilities for relays        B for this SR was the replacement of RA-Sb-      focus of this              identified to be essential and that are included "DEVELOP" with "CALCULATE." The action 2013        assessment>                in the systems-analysis model.                  verb change was made to be consistent with accepted verb usage across SRs. These wording edits do not change capability category requirements of this SR.
requirements of this SR.
SFR-F4   ASME/ANS DEVELOP seismic fragilities for structures, or systems, or                       Addendum B Assessment Equates to RA-Sa-      components, or a combination thereof that are identified in the             Addendum A 2009        systems model as playing a role in the large early release frequency part of the seismic PRA. (See Requirements SPR-A1 and SPR-A3.)               The changes from Addendum A to ASME/ANS CALCULATE seismic fragilities for SSCs that are identified in the                Addendum B for this SR included the RA-Sb-      systems model as playing a role in the large early release frequency        replacement of "DEVELOP" with 2013        part of the seismic PRA. (See Requirements SPR-A1 and SPR-A3.)              "CALCULATE." The action verb change was made to be consistent with accepted verb usage across SRs. Also, SSC abbreviation used instead. These wording edits do not change capability category requirements of this SR.
SFR-F3 ASME/ANS RA-Sa-2009
E-27
<not printed here; not focus of this assessment>
DEVELOP seismic fragilities for relays identified to be essential and that are included in the systems-analysis model.
Addendum B Assessment Equates to Addendum A The change from Addendum A to Addendum B for this SR was the replacement of "DEVELOP" with "CALCULATE." The action verb change was made to be consistent with accepted verb usage across SRs. These wording edits do not change capability category requirements of this SR.
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
CALCULATE seismic fragilities for relays identified to be essential and that are included in the systems-analysis model.
SFR-F4 ASME/ANS RA-Sa-2009 DEVELOP seismic fragilities for structures, or systems, or components, or a combination thereof that are identified in the systems model as playing a role in the large early release frequency part of the seismic PRA. (See Requirements SPR-A1 and SPR-A3.)
Addendum B Assessment Equates to Addendum A The changes from Addendum A to Addendum B for this SR included the replacement of "DEVELOP" with "CALCULATE." The action verb change was made to be consistent with accepted verb usage across SRs. Also, SSC abbreviation used instead. These wording edits do not change capability category requirements of this SR.
ASME/ANS RA-Sb-2013 CALCULATE seismic fragilities for SSCs that are identified in the systems model as playing a role in the large early release frequency part of the seismic PRA. (See Requirements SPR-A1 and SPR-A3.)


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-28 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                          II                    III HLR-SFR-G: Documentation of the seismic-fragility evaluation shall be consistent with the applicable supporting requirements.
Capability Category I
SFR-G1   ASME/ANS     DOCUMENT the seismic fragility analysis in a manner that facilitates     Addendum B Assessment Equates to RA-Sa-      PRA applications, upgrades, and peer review.                             Addendum A 2009 ASME/ANS    Identical to Addendum A                                                   The wording for this SR is the same for RA-Sb-                                                                                Addendum A and Addendum B.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
2013 SFR-G2   ASME/ANS     DOCUMENT the process used in the seismic-fragility analysis. For         Addendum B Assessment Equates to RA-Sa-      example, this typically includes a description of                         Addendum A 2009          (a) The methodologies used to quantify the seismic fragilities of structures, or systems, or components, or a combination thereof,         The only change in this SR is related to use together with key assumptions                                             of "structures, systems, and components" (b) The seismic fragilities of structures, or systems, or components,   versus its acronym "SSC." This change is or a combination thereof (SSC) fragility values that includes the        considered editorial and does not change the method of seismic qualification, the dominant failure mode(s), the       capability category requirements of this SR.
HLR-SFR-G: Documentation of the seismic-fragility evaluation shall be consistent with the applicable supporting requirements.
source of information, and the location of the component (c) The fragility parameter values (i.e., median acceleration capacity, Br and Bu) and the technical bases for them for each analyzed SSC, and (d) the different elements of seismic-fragility analysis, such as (1) the seismic response analysis (2) the screening steps (3) the walkdown (4) the review of design documents (5) the identification of critical failure modes for each SSC, and (6) the calculation of fragility parameter values for each SSC modeled E-28
SFR-G1 ASME/ANS RA-Sa-2009 DOCUMENT the seismic fragility analysis in a manner that facilitates PRA applications, upgrades, and peer review.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
ASME/ANS RA-Sb-2013 Identical to Addendum A SFR-G2 ASME/ANS RA-Sa-2009 DOCUMENT the process used in the seismic-fragility analysis. For example, this typically includes a description of (a) The methodologies used to quantify the seismic fragilities of structures, or systems, or components, or a combination thereof, together with key assumptions (b) The seismic fragilities of structures, or systems, or components, or a combination thereof (SSC) fragility values that includes the method of seismic qualification, the dominant failure mode(s), the source of information, and the location of the component (c) The fragility parameter values (i.e., median acceleration capacity, Br and Bu) and the technical bases for them for each analyzed SSC, and (d) the different elements of seismic-fragility analysis, such as (1) the seismic response analysis (2) the screening steps (3) the walkdown (4) the review of design documents (5) the identification of critical failure modes for each SSC, and (6) the calculation of fragility parameter values for each SSC modeled Addendum B Assessment Equates to Addendum A The only change in this SR is related to use of "structures, systems, and components" versus its acronym "SSC." This change is considered editorial and does not change the capability category requirements of this SR.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR Standard     Capability Category Capability Category Capability Category SR                                                                                              Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-29 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.
Rev.                  I                          II                    III ASME/ANS DOCUMENT the process used in the seismic-fragility analysis. For RA-Sb-      example, this typically includes a description of 2013          (a) the methodologies used to quantify the seismic fragilities of SSCs, together with key assumptions (b) the SSC fragility values that includes the method of seismic qualification, the dominant failure mode(s), the source of information, and the location of the component (c) the fragility parameter values (i.e., median acceleration capacity, Br and Bu) and the technical bases for them for each analyzed SSC, and (d) the different elements of seismic-fragility analysis, such as (1) the seismic response analysis (2) the screening steps (3) the walkdown (4) the review of design documents (5) the identification of critical failure modes for each SSC, and (6) the calculation of fragility parameter values for each SSC modeled SFR-G3   ASME/ANS DOCUMENT the sources of model uncertainty and related                       Vogtle Conforms to Addendum A RA-Sa-      assumptions associated with the seismic fragility analysis.
Capability Category I
2009                                                                                  Addendum B deleted this SR. However, the Plant Vogtle 1&2 SPRA documentation ASME/ANS Deleted.                                                                    describes in detail the sources of model RA-Sb-                                                                                uncertainty and related assumptions 2013                                                                                  associated with the seismic fragility analysis.
Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
ASME/ANS RA-Sb-2013 DOCUMENT the process used in the seismic-fragility analysis. For example, this typically includes a description of (a) the methodologies used to quantify the seismic fragilities of SSCs, together with key assumptions (b) the SSC fragility values that includes the method of seismic qualification, the dominant failure mode(s), the source of information, and the location of the component (c) the fragility parameter values (i.e., median acceleration capacity, Br and Bu) and the technical bases for them for each analyzed SSC, and (d) the different elements of seismic-fragility analysis, such as (1) the seismic response analysis (2) the screening steps (3) the walkdown (4) the review of design documents (5) the identification of critical failure modes for each SSC, and (6) the calculation of fragility parameter values for each SSC modeled SFR-G3 ASME/ANS RA-Sa-2009 DOCUMENT the sources of model uncertainty and related assumptions associated with the seismic fragility analysis.
Vogtle Conforms to Addendum A Addendum B deleted this SR. However, the Plant Vogtle 1&2 SPRA documentation describes in detail the sources of model uncertainty and related assumptions associated with the seismic fragility analysis.
Therefore, the Vogtle SPRA conforms to Addendum A.
Therefore, the Vogtle SPRA conforms to Addendum A.
E-29
ASME/ANS RA-Sb-2013 Deleted.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard         Capability                                         Capability SR                                            Capability Category II                                Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-30 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                        Category III HLR-SPR-A: The seismic-PRA systems model shall include seismic-caused initiating events and other failures including seismic-induced SSC failures, non-seismic-induced unavailabilities, and human errors, that give rise to significant accident sequences and/or significant accident progression sequences.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SPR-A1 ASME/ANS ENSURE that earthquake-caused initiating events that give rise to                   Addendum B Assessment Equates to RA-Sa-      significant accident sequences and/or significant accident progression Addendum A 2009        sequences are included in the seismic-PRA system model using a systematic process.                                                         The wording for this SR is the same for Addendum A and Addendum B. A minor ASME/ANS Identical to Addendum A                                                        clarification (i.e., very low magnitude RA-Sb-                                                                                  earthquakes can be excluded from the 2013                                                                                    quantification process) was added in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.
HLR-SPR-A: The seismic-PRA systems model shall include seismic-caused initiating events and other failures including seismic-induced SSC failures, non-seismic-induced unavailabilities, and human errors, that give rise to significant accident sequences and/or significant accident progression sequences.
SPR-A2     ASME/ANS     In the initiating-event selection process, DEVELOP a hierarchy to           Addendum B Assessment Equates to RA-Sa-      ensure that every earthquake greater than a certain defined size           Addendum A 2009        produces a plant shutdown within the systems model.
SPR-A1 ASME/ANS RA-Sa-2009 ENSURE that earthquake-caused initiating events that give rise to significant accident sequences and/or significant accident progression sequences are included in the seismic-PRA system model using a systematic process.
ASME/ANS    Identical to Addendum A                                                     The wording for this SR is the same for RA-Sb-                                                                                  Addendum A and Addendum B. A minor 2013                                                                                    clarification (i.e., event ordering by consequence severity) was added in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. A minor clarification (i.e., very low magnitude earthquakes can be excluded from the quantification process) was added in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.
SPR-A3     ASME/ANS USE the event trees and fault trees from the internal-event at-power           Addendum B Assessment Equates to RA-Sa-      PRA model as the basis for the seismic event trees.                         Addendum A 2009 E-30
ASME/ANS RA-Sb-2013 Identical to Addendum A SPR-A2 ASME/ANS RA-Sa-2009 In the initiating-event selection process, DEVELOP a hierarchy to ensure that every earthquake greater than a certain defined size produces a plant shutdown within the systems model.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. A minor clarification (i.e., event ordering by consequence severity) was added in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013 Identical to Addendum A SPR-A3 ASME/ANS RA-Sa-2009 USE the event trees and fault trees from the internal-event at-power PRA model as the basis for the seismic event trees.
Addendum B Assessment Equates to Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                         Capability SR                                              Capability Category II                            Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-31 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                        Category III ASME/ANS USE the accident sequences and the systems logic model from                   Some of the terms in this SR were changed RA-Sb-        the at-power, internal-event PRA model as the basis for the seismic-     in Addendum B so that they would not be less 2013          PRA model.                                                              specific to a certain type of PRA modeling software. These term clarifications do not change the capability category requirements of this SR.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SPR-A4   ASME/ANS This supporting requirement is new to Addendum B and not                     Addendum B Assessment Equates to (Add. B)  RA-Sb-        included in Addendum A.                                                 Addendum A 2013          Under special circumstances based on the judgment of the analyst, DEVELOP an ad hoc systems model tailored especially to the               Addendum B added this SR to recognize that seismic-PRA configurations or issues being modeled, instead of           some utilities may build a separate stand-starting with the internal-events model and adapting it, as in           alone SPRA as opposed to adding seismic Requirement SPR-A3. If this approach is used, ENSURE that the           aspects into an existing internal events PRA resulting model is consistent with the internal-events systems model     (as described by SPR-A3). This new SR regarding plant response and the cause-effect relationships of the      ensures that the technical capability of the failures.                                                                base modeling would be consistent with the internal events technical capability requirements. For Vogtle, this specific SR is not applicable because the Vogtle 1&2 SPRA is built upon the internal events PRA per SR SPR-A3 and thus the Vogtle SPRA conforms to Addendum A.
ASME/ANS RA-Sb-2013 USE the accident sequences and the systems logic model from the at-power, internal-event PRA model as the basis for the seismic-PRA model.
SPR-A4   ASME/ANS SPR-A4 of Addendum A:                                                         Addendum B Assessment Equates to (Add. A)  RA-Sa-        ENSURE that the PRA systems models reflect earthquake-caused             Addendum A SPR-A5    2009          failures and nonseismically induced unavailabilities and human errors (Add. B)                that give rise to significant accident sequences or significant accident The wording for this SR is the same for progression sequences.                                                  Addendum A and Addendum B.
Some of the terms in this SR were changed in Addendum B so that they would not be less specific to a certain type of PRA modeling software. These term clarifications do not change the capability category requirements of this SR.
ASME/ANS SPR-A5 of Addendum B is identical to SPR-A4 of Addendum A.                   Miscellaneous edits were made in Addendum RA-Sb-        There is no change in the supporting requirement from                   B to the clarifying non-mandatory footnote for 2013          Addendum A to Addendum B, except that the insertion of a new             this SR; this footnote adjustment does not SPR-A4 in Addendum B changes the number for this                         change the capability category requirements E-31
SPR-A4 (Add. B)
ASME/ANS RA-Sb-2013 This supporting requirement is new to Addendum B and not included in Addendum A.
Under special circumstances based on the judgment of the analyst, DEVELOP an ad hoc systems model tailored especially to the seismic-PRA configurations or issues being modeled, instead of starting with the internal-events model and adapting it, as in Requirement SPR-A3. If this approach is used, ENSURE that the resulting model is consistent with the internal-events systems model regarding plant response and the cause-effect relationships of the failures.
Addendum B Assessment Equates to Addendum A Addendum B added this SR to recognize that some utilities may build a separate stand-alone SPRA as opposed to adding seismic aspects into an existing internal events PRA (as described by SPR-A3). This new SR ensures that the technical capability of the base modeling would be consistent with the internal events technical capability requirements. For Vogtle, this specific SR is not applicable because the Vogtle 1&2 SPRA is built upon the internal events PRA per SR SPR-A3 and thus the Vogtle SPRA conforms to Addendum A.
SPR-A4 (Add. A)
SPR-A5 (Add. B)
ASME/ANS RA-Sa-2009 SPR-A4 of Addendum A:
ENSURE that the PRA systems models reflect earthquake-caused failures and nonseismically induced unavailabilities and human errors that give rise to significant accident sequences or significant accident progression sequences.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.
Miscellaneous edits were made in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements ASME/ANS RA-Sb-2013 SPR-A5 of Addendum B is identical to SPR-A4 of Addendum A.
There is no change in the supporting requirement from Addendum A to Addendum B, except that the insertion of a new SPR-A4 in Addendum B changes the number for this  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                       Capability SR                                              Capability Category II                        Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-32 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                      Category III requirement.                                                         of this SR.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus) requirement.
of this SR.
HLR-SPR-B: The seismic-PRA systems model shall be adapted to incorporate seismic-analysis aspects that are different from corresponding aspects found in the at-power, internal-events PRA systems model.
HLR-SPR-B: The seismic-PRA systems model shall be adapted to incorporate seismic-analysis aspects that are different from corresponding aspects found in the at-power, internal-events PRA systems model.
SPR-B1     ASME/ANS In each of the following aspects of the seismic-PRA systems-analysis     Vogtle Conforms to Addendum A RA-Sa-        work, SATISFY the corresponding requirements in Part 2, except 2009          where they are not applicable or where this Part includes additional Addendum B removed the last sentence of requirements. DEVELOP a defined basis to support the claimed         this SR in response to an EPRI 2011 nonapplicability of any exceptions. The aspects governed by this     comment on the Addendum B ballot. The last requirement are                                                      sentence was removed in Addendum B (a) initiating-event analysis                                      because it was determined to be confusing as (b) accident-sequence analysis                                      wells as inappropriate specificity to require all (c) success-criteria analysis                                      new aspects in the SPRA to meet the exact (d) systems analysis                                                same CCs of Part 2 SRs. In addition, (e) data analysis                                                  Addendum B changed the action verb to be (f) human-reliability analysis                                      consistent with accepted verb usage across (g) use of expert judgment                                          SRs. The Addendum B SR requirement When the Part 2 requirements are used, FOLLOW the Capability        clarifications are appropriate. Regardless, Category designations in Part 2, and for consistency USE the        the Plant Vogtle 1&2 SPRA builds upon the same Capability Category in this analysis.                          internal events PRA and uses the same E-32
SPR-B1 ASME/ANS RA-Sa-2009 In each of the following aspects of the seismic-PRA systems-analysis work, SATISFY the corresponding requirements in Part 2, except where they are not applicable or where this Part includes additional requirements. DEVELOP a defined basis to support the claimed nonapplicability of any exceptions. The aspects governed by this requirement are (a) initiating-event analysis (b) accident-sequence analysis (c) success-criteria analysis (d) systems analysis (e) data analysis (f) human-reliability analysis (g) use of expert judgment When the Part 2 requirements are used, FOLLOW the Capability Category designations in Part 2, and for consistency USE the same Capability Category in this analysis.
Vogtle Conforms to Addendum A Addendum B removed the last sentence of this SR in response to an EPRI 2011 comment on the Addendum B ballot. The last sentence was removed in Addendum B because it was determined to be confusing as wells as inappropriate specificity to require all new aspects in the SPRA to meet the exact same CCs of Part 2 SRs. In addition, Addendum B changed the action verb to be consistent with accepted verb usage across SRs. The Addendum B SR requirement clarifications are appropriate. Regardless, the Plant Vogtle 1&2 SPRA builds upon the internal events PRA and uses the same  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                       Capability SR                                              Capability Category II                        Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-33 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                      Category III ASME/ANS In each of the following aspects of the seismic-PRA systems-analysis       general methodologies as used for Part 2 RA-Sb-        work, SATISFY the corresponding requirements in Part 2, except       where applicable; therefore, the Vogtle SPRA 2013          where they are not applicable or where this Part includes additional conforms to Addendum A.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
requirements. SPECIFY a basis to support the claimed nonapplicability of any exceptions. The aspects governed by this requirement are (a) initiating-event analysis (b) accident-sequence analysis (c) success-criteria analysis (d) systems analysis (e) data analysis (f) human-reliability analysis (g) use of expert judgment SPR-B2   ASME/ANS In the human reliability analysis (HRA) aspect, EXAMINE                   Addendum B Assessment Envelopes RA-Sa-        additional post earthquake stresses that can increase the             Addendum A 2009          likelihood of human errors or inattention, compared to the likelihood assigned in the internal-events HRA when the same         In response to an EPRI 2011 comment on the activities are undertaken in no earthquake accident sequences.       Addendum B ballot, Addendum B added CCI-Whether or not increases in error probabilities are used, JUSTIFY     II and CCIII capability differentiation as well the basis for this decision about what error rates to use.           as the requirement to include the seismic ASME/ANS INCLUDE the following seismic impacts on                <not printed here; HEP impacts on the internal events based RA-Sb-       performance-shaping factors (PSFs) for the not focus of this          HEPs, not simply to Examine them. It also 2013          control room and ex-control room post-             assessment>        expanded on the considerations to initiator actions as appropriate to the                               emphasize PSFs beyond just stress. The human reliability analysis (HRA)                                     Addendum B SR wording envelopes that of methodology used:                                                     Addendum A.
ASME/ANS RA-Sb-2013 In each of the following aspects of the seismic-PRA systems-analysis work, SATISFY the corresponding requirements in Part 2, except where they are not applicable or where this Part includes additional requirements. SPECIFY a basis to support the claimed nonapplicability of any exceptions. The aspects governed by this requirement are (a) initiating-event analysis (b) accident-sequence analysis (c) success-criteria analysis (d) systems analysis (e) data analysis (f) human-reliability analysis (g) use of expert judgment general methodologies as used for Part 2 where applicable; therefore, the Vogtle SPRA conforms to Addendum A.
(a) additional post-earthquake workload and stress that can increase the likelihood of human errors or inattention E-33
SPR-B2 ASME/ANS RA-Sa-2009 In the human reliability analysis (HRA) aspect, EXAMINE additional post earthquake stresses that can increase the likelihood of human errors or inattention, compared to the likelihood assigned in the internal-events HRA when the same activities are undertaken in no earthquake accident sequences.
Whether or not increases in error probabilities are used, JUSTIFY the basis for this decision about what error rates to use.
Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added CCI-II and CCIII capability differentiation as well as the requirement to include the seismic HEP impacts on the internal events based HEPs, not simply to Examine them. It also expanded on the considerations to emphasize PSFs beyond just stress. The Addendum B SR wording envelopes that of Addendum A.
ASME/ANS RA-Sb-2013 INCLUDE the following seismic impacts on performance-shaping factors (PSFs) for the control room and ex-control room post-initiator actions as appropriate to the human reliability analysis (HRA) methodology used:
(a) additional post-earthquake workload and stress that can increase the likelihood of human errors or inattention
<not printed here; not focus of this assessment>


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                         Capability SR                                            Capability Category II                            Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-34 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                        Category III (b) seismic failures that impact access (c) cue availability SPR-B3   ASME/ANS SPR-B3 of Addendum A:                                                       Addendum B Assessment Equates to (Add. A)  RA-Sa-        If any screening is performed, PERFORM it using defined criteria       Addendum A SPR-      2009          that are documented in the PRA.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
B4a                                                                                            Addendum B changed the sentence structure ASME/ANS SPR-B4a of Addendum B:
(b) seismic failures that impact access (c) cue availability SPR-B3 (Add. A)
(Add. B)                                                                                      to correct awkward wording and to use RA-Sb-        If screening out on the basis of seismic capacity is performed in accepted verb. This wording edit does not 2013          the systems model, SPECIFY the screening criterion.
SPR-B4a (Add. B)
change the capability category requirements of this SR.
ASME/ANS RA-Sa-2009 SPR-B3 of Addendum A:
SPR-B4    ASME/ANS SPR-B4 of Addendum A:                                   <not printed here; Addendum B Assessment Equates to (Add. A)  RA-Sa-        PERFORM an analysis of seismic-caused               not focus of this  Addendum A SPR-B3    2009          dependencies and correlations in a way so that assessment>
If any screening is performed, PERFORM it using defined criteria that are documented in the PRA.
(Add. B)                any screening of SSCs appropriately accounts                           Addendum B deleted the phrase for those dependencies and correlations.                               "dependencies and" because they are USE bounding or generic correlation values                            redundant to the "correlation" term so as to and PROVIDE the basis for such use.                                    avoid reviewer potential confusion. This ASME/ANS SPR-B3 of Addendum B:                                    <not printed here; wording edit does not change the capability RA-Sb-       PERFORM an analysis of seismic-caused               not focus of this  category requirements of this SR.
Addendum B Assessment Equates to Addendum A Addendum B changed the sentence structure to correct awkward wording and to use accepted verb. This wording edit does not change the capability category requirements of this SR.
2013          dependencies and correlations in a way so that assessment>
ASME/ANS RA-Sb-2013 SPR-B4a of Addendum B:
any screening of SSCs appropriately accounts for those correlations.
If screening out on the basis of seismic capacity is performed in the systems model, SPECIFY the screening criterion.
SPR-B4 (Add. A)
SPR-B3 (Add. B)
ASME/ANS RA-Sa-2009 SPR-B4 of Addendum A:
PERFORM an analysis of seismic-caused dependencies and correlations in a way so that any screening of SSCs appropriately accounts for those dependencies and correlations.
USE bounding or generic correlation values and PROVIDE the basis for such use.
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A Addendum B deleted the phrase "dependencies and" because they are redundant to the "correlation" term so as to avoid reviewer potential confusion. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013 SPR-B3 of Addendum B:
PERFORM an analysis of seismic-caused dependencies and correlations in a way so that any screening of SSCs appropriately accounts for those correlations.
USE bounding or generic correlation values and PROVIDE the basis for such use.
USE bounding or generic correlation values and PROVIDE the basis for such use.
SPR-B5   ASME/ANS SPR-B5 of Addendum A:                                                       Addendum B Assessment Equates to (Add. A)  RA-Sa-        ENSURE that any screening of human-error basic events and non-         Addendum A 2009          seismic-failure basic events does not significantly affect the PRAs results.                                                               Addendum B deleted this SR because it is ASME/ANS No SR of Addendum B directly matches with SPR-B5 of                        redundant to SR SPR-A5, which already RA-Sb-        Addendum A                                                            requires modeling of operator actions that 2013                                                                                contribute to significant accident sequences.
<not printed here; not focus of this assessment>
E-34
SPR-B5 (Add. A)
ASME/ANS RA-Sa-2009 SPR-B5 of Addendum A:
ENSURE that any screening of human-error basic events and non-seismic-failure basic events does not significantly affect the PRAs results.
Addendum B Assessment Equates to Addendum A Addendum B deleted this SR because it is redundant to SR SPR-A5, which already requires modeling of operator actions that contribute to significant accident sequences.
ASME/ANS RA-Sb-2013 No SR of Addendum B directly matches with SPR-B5 of Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                       Capability SR                                          Capability Category II                              Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-35 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.          Category I                                        Category III Also, it is redundant in part to SR SPR-E3, which requires validation that any screening does not impact the results. Finally, Vogtle did not screen out any human-error or non-seismic events that were in the FPIE model and would propagate through seismic accident sequences, and so conforms to Addendum A.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SPR-     ASME/ANS Not included in Addendum A.                                                 Addendum B Assessment Envelopes B4b      RA-Sa-                                                                                Addendum A 2009 This SR is new for Addendum B to ensure ASME/ANS SPR-B4b of Addendum B:                                                      that recoveries added to the SPRA (i.e., not RA-Sb-        If post-earthquake recovery actions are included in the systems        already included in the internal events PRA) 2013          model, INCLUDE them on a documented basis.                              are assessed for appropriateness.
Also, it is redundant in part to SR SPR-E3, which requires validation that any screening does not impact the results. Finally, Vogtle did not screen out any human-error or non-seismic events that were in the FPIE model and would propagate through seismic accident sequences, and so conforms to Addendum A.
SPR-B4b ASME/ANS RA-Sa-2009 Not included in Addendum A.
Addendum B Assessment Envelopes Addendum A This SR is new for Addendum B to ensure that recoveries added to the SPRA (i.e., not already included in the internal events PRA) are assessed for appropriateness.
Addendum B envelopes Addendum A with respect to this SR.
Addendum B envelopes Addendum A with respect to this SR.
SPR-B6    ASME/ANS <not printed here;          SPR-B6 of Addendum A:                           Addendum B Assessment Envelopes (Add. A) RA-Sa-       not focus of this     EXAMINE the effects of the chatter of relays     Addendum A SPR-B4    2009          assessment>            and similar devices.
ASME/ANS RA-Sb-2013 SPR-B4b of Addendum B:
(Add. B)                                                                                        In response to an EPRI 2011 comment on the ASME/ANS SPR-B4 of Addendum B:                                                        Addendum B ballot, Addendum B added the RA-Sb-        INCLUDE the effects of the chatter of relays and similar devices in the requirement to include the effects of relay 2013          systems model.                                                          chatter in the model, not simply to examine them. The differentiation for "low ruggedness relays" is deleted in Addendum B because the issue of chatter fragility is addressed in SFR SRs. The Addendum B SR wording envelopes that of Addendum A.
If post-earthquake recovery actions are included in the systems model, INCLUDE them on a documented basis.
E-35
SPR-B6 (Add. A)
SPR-B4 (Add. B)
ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
SPR-B6 of Addendum A:
EXAMINE the effects of the chatter of relays and similar devices.
Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added the requirement to include the effects of relay chatter in the model, not simply to examine them. The differentiation for "low ruggedness relays" is deleted in Addendum B because the issue of chatter fragility is addressed in SFR SRs. The Addendum B SR wording envelopes that of Addendum A.
ASME/ANS RA-Sb-2013 SPR-B4 of Addendum B:
INCLUDE the effects of the chatter of relays and similar devices in the systems model.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                       Capability SR                                            Capability Category II                            Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-36 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.           Category I                                        Category III SPR-B7    ASME/ANS SPR-B7 of Addendum A:                                                       Addendum B Assessment Equates to (Add. A)  RA-Sa-        In the systems-analysis models, for each basic event that represents a Addendum A SPR-B5    2009          seismically caused failure, INCLUDE the complementary success (Add. B)                state where applicable to a particular SSC.                           Addendum B revised the wording of this SR to include a capability category distinction to explicitly model fragility complements for risk significant fragilities for CCI-II and for all modeled fragilities for CCIII. The Vogtle 1&2 SPRA uses the SPRA CAFTA suite of codes ASME/ANS SPR-B5 of Addendum B:                                   <not printed here;  with the ACUBE module addressing the RA-Sb-        In the systems-analysis models, for each           not focus of this  fragility complement modeling and so meets 2013          basic event that represents a significant         assessment>        the intent of both Addenda A and B since the seismically caused failure, INCLUDE the                                quantification accounts mathematically for the complementary success state where                                   success states.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
applicable to a particular SSC, and SPECIFY the criteria used for the term significant in this activity.
SPR-B7 (Add. A)
SPR-B8   ASME/ANS SPR-B8 of Addendum A:                                                       Addendum B Assessment Equates to (Add. A)  RA-Sa-        EXAMINE the possibility that a large earthquake can cause damage       Addendum A SPR-B6    2009          that blocks personnel access to safety equipment or controls, thereby (Add. B)                inhibiting operator actions that might otherwise be credited.         Addendum B changed the action verb to be ASME/ANS SPR-B6 of Addendum B:                                                       consistent with accepted verb usage across RA-Sb-        EVALUATE the possibility that a large earthquake can cause damage     SRs. This wording edit does not change the 2013          that blocks personnel access to safety equipment or controls, thereby capability category requirements of this SR.
SPR-B5 (Add. B)
inhibiting operator actions that might otherwise be credited.
ASME/ANS RA-Sa-2009 SPR-B7 of Addendum A:
E-36
In the systems-analysis models, for each basic event that represents a seismically caused failure, INCLUDE the complementary success state where applicable to a particular SSC.
Addendum B Assessment Equates to Addendum A Addendum B revised the wording of this SR to include a capability category distinction to explicitly model fragility complements for risk significant fragilities for CCI-II and for all modeled fragilities for CCIII. The Vogtle 1&2 SPRA uses the SPRA CAFTA suite of codes with the ACUBE module addressing the fragility complement modeling and so meets the intent of both Addenda A and B since the quantification accounts mathematically for the success states.
ASME/ANS RA-Sb-2013 SPR-B5 of Addendum B:
In the systems-analysis models, for each basic event that represents a significant seismically caused failure, INCLUDE the complementary success state where applicable to a particular SSC, and SPECIFY the criteria used for the term significant in this activity.
<not printed here; not focus of this assessment>
SPR-B8 (Add. A)
SPR-B6 (Add. B)
ASME/ANS RA-Sa-2009 SPR-B8 of Addendum A:
EXAMINE the possibility that a large earthquake can cause damage that blocks personnel access to safety equipment or controls, thereby inhibiting operator actions that might otherwise be credited.
Addendum B Assessment Equates to Addendum A Addendum B changed the action verb to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.
ASME/ANS RA-Sb-2013 SPR-B6 of Addendum B:
EVALUATE the possibility that a large earthquake can cause damage that blocks personnel access to safety equipment or controls, thereby inhibiting operator actions that might otherwise be credited.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                     Capability SR                                          Capability Category II                          Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-37 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.           Category I                                      Category III SPR-B9    ASME/ANS <not printed here;         SPR-B9 of Addendum A:                       Addendum B CCII Assessment Equates to (Add. A)  RA-Sa-        not focus of this    EXAMINE the likelihood that system           Addendum A CCII-III SPR-B7    2009          assessment>          recoveries modeled in the internal-events (Add. B)                                      PRA may be more complex or even not         In response to an EPRI 2011 comment on the possible after a large earthquake, and      Addendum B ballot, Addendum B added ADJUST the recovery models accordingly.      three capability differentiations. CCII requirements are effectively the same for Addendum A and Addendum B. The Addendum B SR adds the clarification that generic and/or conservative recovery values are acceptable. The Addendum B SR CCII ASME/ANS <not printed here;        SPR-B7 of Addendum <not printed here; wording effectively equates to Addendum A RA-Sb-        not focus of this    B:                        not focus of this CCII-III given the state of practice at the time 2013          assessment>          EVALUATE the              assessment>
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
(i.e., detailed plant-specific system recovery likelihood that system probability calculations were not typical recoveries modeled in practice at the time of Addendum A).
SPR-B9 (Add. A)
the internal-events PRA may be more complex or even not possible after a large earthquake, and ADJUST the recovery models accordingly. It is acceptable to use generic or conservative recovery values.
SPR-B7 (Add. B)
SPR-     ASME/ANS SPR-B10 of Addendum A:                                                 Addendum B Assessment Envelopes B10      RA-Sa-        EXAMINE the effect of including an earthquake-caused small-       Addendum A (Add. A)  2009          small loss-of-coolant accident as an additional fault within each SPR-B8                  sequence in the seismic-PRA model.                                 Addendum B added differentiation of E-37
ASME/ANS RA-Sa-2009
<not printed here; not focus of this assessment>
SPR-B9 of Addendum A:
EXAMINE the likelihood that system recoveries modeled in the internal-events PRA may be more complex or even not possible after a large earthquake, and ADJUST the recovery models accordingly.
Addendum B CCII Assessment Equates to Addendum A CCII-III In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added three capability differentiations. CCII requirements are effectively the same for Addendum A and Addendum B. The Addendum B SR adds the clarification that generic and/or conservative recovery values are acceptable. The Addendum B SR CCII wording effectively equates to Addendum A CCII-III given the state of practice at the time (i.e., detailed plant-specific system recovery probability calculations were not typical practice at the time of Addendum A).
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
SPR-B7 of Addendum B:
EVALUATE the likelihood that system recoveries modeled in the internal-events PRA may be more complex or even not possible after a large earthquake, and ADJUST the recovery models accordingly. It is acceptable to use generic or conservative recovery values.
<not printed here; not focus of this assessment>
SPR-B10 (Add. A)
SPR-B8 ASME/ANS RA-Sa-2009 SPR-B10 of Addendum A:
EXAMINE the effect of including an earthquake-caused small-small loss-of-coolant accident as an additional fault within each sequence in the seismic-PRA model.
Addendum B Assessment Envelopes Addendum A Addendum B added differentiation of  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                     Capability SR                                          Capability Category II                          Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-38 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                      Category III (Add. B) ASME/ANS SPR-B8 of Addendum B:                                 <not printed here; capability requirements to this SR that require RA-Sb-        ASSUME the existence of an earthquake-          not focus of this  modeling incorporation into the SPRA (if the 2013          caused very small loss-of-coolant              assessment>        topic requires it for a specific plant) whereas accident in the seismic-PRA accident                                the EXAMINE verb in Addendum A did not sequences and system modeling, unless it                            require incorporation into the SPRA (i.e., it is demonstrated that such a LOCA can be                              could be done as a sensitivity study). The excluded, based on a walkdown or on                                  Addendum B SR wording envelopes that of another examination of the possible                                  Addendum A.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
sources of such a LOCA.
(Add. B)
SPR-     ASME/ANS SPR-B11 of Addendum A:                                                   Addendum B Assessment Envelopes B11      RA-Sa-        In the seismic PRA walkdown, INCLUDE the potential for               Addendum A (Add. A)  2009          seismically induced fires and flooding following the guidance SPR-B9                  given in NUREG-1407.                                                 In response to an EPRI 2011 comment on the (Add. B)  ASME/ANS SPR-B9 of Addendum B:                                                    Addendum B ballot, Addendum B added the RA-Sb-        If the seismic PRA walkdown (see Requirement SFR-E4)                requirement to include risk significant 2013          identifies the potential for seismically induced fires and flooding, scenarios into the SPRA models as opposed INCLUDE potential significant contributions to accident              to only including them in the walkdown.
ASME/ANS RA-Sb-2013 SPR-B8 of Addendum B:
sequences in the systems model.                                      Reference to NUREG-1407 was removed in Addendum B because this SR refers to SFR-E4 for input and SFR-E4 already includes the reference to NUREG-1407. The Addendum B SR wording envelopes that of Addendum A.
ASSUME the existence of an earthquake-caused very small loss-of-coolant accident in the seismic-PRA accident sequences and system modeling, unless it is demonstrated that such a LOCA can be excluded, based on a walkdown or on another examination of the possible sources of such a LOCA.
<not printed here; not focus of this assessment>
capability requirements to this SR that require modeling incorporation into the SPRA (if the topic requires it for a specific plant) whereas the EXAMINE verb in Addendum A did not require incorporation into the SPRA (i.e., it could be done as a sensitivity study). The Addendum B SR wording envelopes that of Addendum A.
SPR-B11 (Add. A)
SPR-B9 (Add. B)
ASME/ANS RA-Sa-2009 SPR-B11 of Addendum A:
In the seismic PRA walkdown, INCLUDE the potential for seismically induced fires and flooding following the guidance given in NUREG-1407.
Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added the requirement to include risk significant scenarios into the SPRA models as opposed to only including them in the walkdown.
Reference to NUREG-1407 was removed in Addendum B because this SR refers to SFR-E4 for input and SFR-E4 already includes the reference to NUREG-1407. The Addendum B SR wording envelopes that of Addendum A.
ASME/ANS RA-Sb-2013 SPR-B9 of Addendum B:
If the seismic PRA walkdown (see Requirement SFR-E4) identifies the potential for seismically induced fires and flooding, INCLUDE potential significant contributions to accident sequences in the systems model.
HLR-SPR-C: The seismic-PRA systems model shall reflect the as-built and as-operated plant being analyzed.
HLR-SPR-C: The seismic-PRA systems model shall reflect the as-built and as-operated plant being analyzed.
SPR-C1   ASME/ANS To ensure that the systems-analysis model reflects the as-built, as-     Addendum B Assessment Equates to RA-Sa-        operated plant, JUSTIFY any conservatisms or other distortions       Addendum A 2009          introduced by demonstrating that the seismic-PRAs validity for applications is maintained.                                         Addendum B changed the last clause of this E-38
SPR-C1 ASME/ANS RA-Sa-2009 To ensure that the systems-analysis model reflects the as-built, as-operated plant, JUSTIFY any conservatisms or other distortions introduced by demonstrating that the seismic-PRAs validity for applications is maintained.
Addendum B Assessment Equates to Addendum A Addendum B changed the last clause of this  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard             Capability                                       Capability SR                                              Capability Category II                            Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-39 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.              Category I                                      Category III ASME/ANS To ensure that the systems-analysis model reflects the as-built, as-         SR because the wording was awkward. This RA-Sb-        operated plant, JUSTIFY any conservatisms or other distortions that     wording refinement does not change the 2013          do not adequately reflect the as-built, as-operated plant.             capability category requirements of this SR.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
ASME/ANS RA-Sb-2013 To ensure that the systems-analysis model reflects the as-built, as-operated plant, JUSTIFY any conservatisms or other distortions that do not adequately reflect the as-built, as-operated plant.
SR because the wording was awkward. This wording refinement does not change the capability category requirements of this SR.
HLR-SPR-D: The list of SSCs selected for seismic-fragility analysis shall include the SSCs that participate in accident sequences included in the seismic-PRA systems model.
HLR-SPR-D: The list of SSCs selected for seismic-fragility analysis shall include the SSCs that participate in accident sequences included in the seismic-PRA systems model.
SPR-D1 ASME/ANS USE the seismic PRA systems model as the basis for developing the                 Addendum B Assessment Envelopes RA-Sa-        seismic equipment list, which is the list of all SSCs to be             Addendum A 2009          considered by the subsequent seismic-fragility evaluation task.
SPR-D1 ASME/ANS RA-Sa-2009 USE the seismic PRA systems model as the basis for developing the seismic equipment list, which is the list of all SSCs to be considered by the subsequent seismic-fragility evaluation task.
ASME/ANS USE the PRA systems model as the basis for developing the seismic             Addendum B added additional clarifications RA-Sb-        equipment list to support the fragility analysis of 5-2.2. INCLUDE     and requirements into the text of this SR.
Addendum B Assessment Envelopes Addendum A Addendum B added additional clarifications and requirements into the text of this SR.
2013          structures and passive components that may not be present in           The Addendum B SR wording envelopes that the internal-events model but that require consideration in the         of Addendum A.
The Addendum B SR wording envelopes that of Addendum A.
seismic PRA. SUPPLEMENT the list based on the review of industry seismic-PRA seismic equipment lists (SELs), if available.
ASME/ANS RA-Sb-2013 USE the PRA systems model as the basis for developing the seismic equipment list to support the fragility analysis of 5-2.2. INCLUDE structures and passive components that may not be present in the internal-events model but that require consideration in the seismic PRA. SUPPLEMENT the list based on the review of industry seismic-PRA seismic equipment lists (SELs), if available.
HLR-SPR-E: The analysis to quantify core damage frequency and large early release frequency shall appropriately integrate the seismic hazard, the seismic fragilities, and the systems-analysis aspects SPR-E1     ASME/ANS       In the quantification of core damage frequency and large early release Addendum B Assessment Equates to RA-Sa-        frequency, PERFORM the integration using the seismic hazard,           Addendum A 2009          fragility, and systems analyses.
HLR-SPR-E: The analysis to quantify core damage frequency and large early release frequency shall appropriately integrate the seismic hazard, the seismic fragilities, and the systems-analysis aspects SPR-E1 ASME/ANS RA-Sa-2009 In the quantification of core damage frequency and large early release frequency, PERFORM the integration using the seismic hazard, fragility, and systems analyses.
ASME/ANS      Identical to Addendum A                                                 The wording for this SR is the same for RA-Sb-                                                                                Addendum A and Addendum B. Minor edits 2013                                                                                  were made in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. Minor edits were made in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.
E-39
ASME/ANS RA-Sb-2013 Identical to Addendum A


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                         Capability SR                                              Capability Category II                            Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-40 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                          Category III SPR-E2   ASME/ANS <not printed here;             In quantifying core damage frequency and       Addendum B Assessment Envelopes RA-Sa-        not focus of this        large early release frequency, PERFORM the     Addendum A 2009          assessment>              quantification on a cut-set-by-cut set or accident-sequence-by-accident-sequence         Addendum B revised this SR to back-basis (or for defined groups of these), as well reference to Part 2 requirements for the as on a comprehensive/integrated basis.         accident sequence quantification. This edit ASME/ANS PERFORM seismic-sequence quantification in accordance with the                was made for consistency across the Std RA-Sb-        applicable requirements described in 2-2.7.                              Parts to refer back to Part 2 SRs where 2013                                                                                    applicable. The wording edit in Addendum B to this SR expands the capability category requirements beyond the requirements of Addendum A by incorporating many more SRs.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
SPR-E3   ASME/ANS In the analysis, USE the quantification process to ensure that any             Addendum B Assessment Equates to RA-Sa-        screening of SSCs does not affect the results, taking into account       Addendum A 2009          the various uncertainties.
SPR-E2 ASME/ANS RA-Sa-2009
In addition to minor wording changes, ASME/ANS USE the quantification process to confirm and support the                      Addendum B revised this SR to remove the RA-Sb-        screening of SSCs (refer to Requirement SFR-B1).                          clause regarding consideration of 2013                                                                                    uncertainties. The use of the phrase "confirm and support" allows for the analyst to determine the best way to validate the screening, whereas Addendum A went beyond "what to do" into "how to do it." The end result is the same.
<not printed here; not focus of this assessment>
SPR-E4   ASME/ANS In the integration/quantification analysis,               <not printed here;  Addendum B Assessment Equates to RA-Sa-        ACCOUNT for all significant dependencies and         not focus of this  Addendum A 2009          correlations that affect the results.                 assessment>
In quantifying core damage frequency and large early release frequency, PERFORM the quantification on a cut-set-by-cut set or accident-sequence-by-accident-sequence basis (or for defined groups of these), as well as on a comprehensive/integrated basis.
It is acceptable to use generic correlation                               Addendum B changed action verbs to be values. If used, PROVIDE the basis for such                               consistent with accepted verb usage across E-40
Addendum B Assessment Envelopes Addendum A Addendum B revised this SR to back-reference to Part 2 requirements for the accident sequence quantification. This edit was made for consistency across the Std Parts to refer back to Part 2 SRs where applicable. The wording edit in Addendum B to this SR expands the capability category requirements beyond the requirements of Addendum A by incorporating many more SRs.
ASME/ANS RA-Sb-2013 PERFORM seismic-sequence quantification in accordance with the applicable requirements described in 2-2.7.
SPR-E3 ASME/ANS RA-Sa-2009 In the analysis, USE the quantification process to ensure that any screening of SSCs does not affect the results, taking into account the various uncertainties.
Addendum B Assessment Equates to Addendum A In addition to minor wording changes, Addendum B revised this SR to remove the clause regarding consideration of uncertainties. The use of the phrase "confirm and support" allows for the analyst to determine the best way to validate the screening, whereas Addendum A went beyond "what to do" into "how to do it." The end result is the same.
ASME/ANS RA-Sb-2013 USE the quantification process to confirm and support the screening of SSCs (refer to Requirement SFR-B1).
SPR-E4 ASME/ANS RA-Sa-2009 In the integration/quantification analysis, ACCOUNT for all significant dependencies and correlations that affect the results.
It is acceptable to use generic correlation values. If used, PROVIDE the basis for such  
<not printed here; not focus of this assessment>
Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                       Capability SR                                            Capability Category II                          Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-41 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.            Category I                                        Category III use.                                                                   SRs, and also deleted the redundant "dependencies" term. These wording edits do not change capability category requirements of this SR.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus) use.
ASME/ANS In the integration/quantification analysis,             <not printed here; RA-Sb-        INCLUDE the significant correlations that affect   not focus of this 2013          the results.                                       assessment>
SRs, and also deleted the redundant "dependencies" term. These wording edits do not change capability category requirements of this SR.
ASME/ANS RA-Sb-2013 In the integration/quantification analysis, INCLUDE the significant correlations that affect the results.
It is acceptable to use generic correlation values. If used, SPECIFY the basis for such use.
It is acceptable to use generic correlation values. If used, SPECIFY the basis for such use.
SPR-E5   ASME/ANS <not printed here;           Identical to Addendum B CCII except           Addendum B CCII Assessment Equates to RA-Sa-        not focus of this        Addendum A uses ACCOUNT verb.                Addendum A CCII-III 2009          assessment>
<not printed here; not focus of this assessment>
Addendum B changed action verbs to be ASME/ANS <not printed here;            In the                    <not printed here; consistent with accepted verb usage across RA-Sb-        not focus of this        integration/quantification not focus of this SRs. Three Capability Category distinctions 2013          assessment>              analysis, INCLUDE in      assessment>
SPR-E5 ASME/ANS RA-Sa-2009
are instituted for Addendum B (Addendum B the uncertainties in core CCII corresponds to Addendum A CCII-III).
<not printed here; not focus of this assessment>
damage frequency and These edits do not change the CCII capability large early release category requirements of this SR.
Identical to Addendum B CCII except Addendum A uses ACCOUNT verb.
frequency results that arise from each of the several inputs (the seismic hazard, the seismic fragilities, and the systems-analysis aspects).
Addendum B CCII Assessment Equates to Addendum A CCII-III Addendum B changed action verbs to be consistent with accepted verb usage across SRs. Three Capability Category distinctions are instituted for Addendum B (Addendum B CCII corresponds to Addendum A CCII-III).
E-41
These edits do not change the CCII capability category requirements of this SR.
ASME/ANS RA-Sb-2013
<not printed here; not focus of this assessment>
In the integration/quantification analysis, INCLUDE in the uncertainties in core damage frequency and large early release frequency results that arise from each of the several inputs (the seismic hazard, the seismic fragilities, and the systems-analysis aspects).
<not printed here; not focus of this assessment>


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard           Capability                                       Capability SR                                          Capability Category II                          Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-42 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.          Category I                                      Category III SPR-E6   ASME/ANS PERFORM appropriate sensitivity studies to illuminate the sensitivity     Addendum B Assessment Envelopes (Add. A)  RA-Sa-        of the core damage frequency and large early release frequency       Addendum A 2009          results to the assumptions used about dependencies and correlations.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
In response to an EPRI 2011 comment on the ASME/ANS Deleted in Addendum B                                                    Addendum B ballot, Addendum B deleted this RA-Sb-                                                                            SR because performance of sensitivity 2013                                                                              studies is already addressed by another SR through the new back-reference to meeting the Part 2 quantification requirements (see SPR-E2), which includes the requirement to conduct appropriate sensitivity studies to address sources of uncertainty. This new back-reference implies requirements well beyond just sensitivity to correlations, and so the Addendum B approach envelopes Addendum A, even with this deletion. The Vogtle 1&2 SPRA documentation includes a sensitivity case related to seismic fragility correlation modeling.
SPR-E6 (Add. A)
SPR-E6   ASME/ANS     New Requirement in Addendum B.                                       Addendum B Assessment Envelopes (Add. B)  RA-Sa-                                                                            Addendum A 2009 ASME/ANS     In the analysis of LERF, SATISFY the LERF requirements in 2-2.8,     Addendum B added this SR to back-RA-Sb-        where applicable.                                                   reference to Part 2 requirements for the 2013          Note 6 - Those aspects of LERF analysis that are common to internal- LERF analysis. This new SR was added for events PRA and seismic PRA are referred to here. Also, the           consistency across the Std Parts to refer discussion of LERF analysis in the last four paragraphs of 5-1.3 is back to Part 2 SRs where applicable. The E-42
ASME/ANS RA-Sa-2009 PERFORM appropriate sensitivity studies to illuminate the sensitivity of the core damage frequency and large early release frequency results to the assumptions used about dependencies and correlations.
Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B deleted this SR because performance of sensitivity studies is already addressed by another SR through the new back-reference to meeting the Part 2 quantification requirements (see SPR-E2), which includes the requirement to conduct appropriate sensitivity studies to address sources of uncertainty. This new back-reference implies requirements well beyond just sensitivity to correlations, and so the Addendum B approach envelopes Addendum A, even with this deletion. The Vogtle 1&2 SPRA documentation includes a sensitivity case related to seismic fragility correlation modeling.
ASME/ANS RA-Sb-2013 Deleted in Addendum B SPR-E6 (Add. B)
ASME/ANS RA-Sa-2009 New Requirement in Addendum B.
Addendum B Assessment Envelopes Addendum A Addendum B added this SR to back-reference to Part 2 requirements for the LERF analysis. This new SR was added for consistency across the Std Parts to refer back to Part 2 SRs where applicable. The ASME/ANS RA-Sb-2013 In the analysis of LERF, SATISFY the LERF requirements in 2-2.8, where applicable.
Note 6 - Those aspects of LERF analysis that are common to internal-events PRA and seismic PRA are referred to here. Also, the discussion of LERF analysis in the last four paragraphs of 5-1.3 is  


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard         Capability                                         Capability SR                                              Capability Category II                          Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-43 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.          Category I                                        Category III broadly applicable and should be referred to as background             Addendum B SR wording envelopes that of information.                                                          Addendum A given that Addendum A did not specifically cite this LERF back-referencing to Part 2.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus) broadly applicable and should be referred to as background information.
Addendum B SR wording envelopes that of Addendum A given that Addendum A did not specifically cite this LERF back-referencing to Part 2.
HLR-SPR-F: The seismic-PRA analysis shall be documented in a manner that facilitates applying the PRA and updating it, and that enables peer review.
HLR-SPR-F: The seismic-PRA analysis shall be documented in a manner that facilitates applying the PRA and updating it, and that enables peer review.
SPR-F1 ASME/ANS DOCUMENT the seismic plant response analysis and quantification in Addendum B Assessment Equates to RA-Sa-      a manner that facilitates PRA applications, upgrades, and peer review. Addendum A 2009 The wording for this SR is the same for Addendum A and Addendum B. Addendum B edited the non-mandatory footnote for this ASME/ANS Identical to Addendum A                                                  SR. This footnote edit does not change the RA-Sb-                                                                            capability category requirements of this SR.
SPR-F1 ASME/ANS RA-Sa-2009 DOCUMENT the seismic plant response analysis and quantification in a manner that facilitates PRA applications, upgrades, and peer review.
2013 SPR-F2 ASME/ANS DOCUMENT the process used in the seismic plant response analysis             Addendum B Assessment Equates to RA-Sa-      and quantification. For example, this documentation typically includes Addendum A 2009        a description of:
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. Addendum B edited the non-mandatory footnote for this SR. This footnote edit does not change the capability category requirements of this SR.
(a) the specific adaptations made in the internal events PRA model to Addendum B moved the non-mandatory list produce the seismic-PRA model, and their motivation, and               of examples to the associated non-mandatory (b) the major outputs of a seismic PRA, such as mean core damage     footnote. This edit does not change the frequency (CDF), mean large early release frequency (LERF),           capability category requirements of this SR.
ASME/ANS RA-Sb-2013 Identical to Addendum A SPR-F2 ASME/ANS RA-Sa-2009 DOCUMENT the process used in the seismic plant response analysis and quantification. For example, this documentation typically includes a description of:
(a) the specific adaptations made in the internal events PRA model to produce the seismic-PRA model, and their motivation, and (b) the major outputs of a seismic PRA, such as mean core damage frequency (CDF), mean large early release frequency (LERF),
uncertainty distributions on CDF and LERF, results of sensitivity studies, significant risk contributors, and so on, are examples of the PRA results that are generally documented.
uncertainty distributions on CDF and LERF, results of sensitivity studies, significant risk contributors, and so on, are examples of the PRA results that are generally documented.
ASME/ANS DOCUMENT the process used in the seismic plant response analysis RA-Sb-      and quantification.
Addendum B Assessment Equates to Addendum A Addendum B moved the non-mandatory list of examples to the associated non-mandatory footnote. This edit does not change the capability category requirements of this SR.
2013 E-43
ASME/ANS RA-Sb-2013 DOCUMENT the process used in the seismic plant response analysis and quantification.


Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR Standard         Capability                                     Capability SR                                        Capability Category II                          Basis for Assessment (CC-II Focus)
Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-44 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.
Rev.          Category I                                      Category III SPR-F3   ASME/ANS DOCUMENT the sources of model uncertainty and related                 Addendum B Assessment Equates to RA-Sa-        assumptions associated with the seismic plant response model     Addendum A 2009          development.
Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)
The wording for this SR is the same for Addendum A and Addendum B. Addendum ASME/ANS Identical to Addendum A.
SPR-F3 ASME/ANS RA-Sa-2009 DOCUMENT the sources of model uncertainty and related assumptions associated with the seismic plant response model development.
A had a missing non-mandatory footnote (not RA-Sb-all uncertainties need to be assigned a 2013 numerical distribution in the documentation) that was re-inserted in Addendum B. This footnote does not change the capability category requirements of this SR.
Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. Addendum A had a missing non-mandatory footnote (not all uncertainties need to be assigned a numerical distribution in the documentation) that was re-inserted in Addendum B. This footnote does not change the capability category requirements of this SR.
E-44}}
ASME/ANS RA-Sb-2013 Identical to Addendum A.}}

Latest revision as of 18:04, 8 January 2025

Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report
ML17192A245
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/11/2017
From: Hutto J
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-17-1201
Download: ML17192A245 (47)


Text

40 Inverness Center Parkway Post Office Box 1295 Birmingham, AL 35242 205 992 5872 tel 205 992 7601 fax jjhutto@southernco.com J. J. Hutto Regulatory Affairs Director July 11, 2017 Docket Nos.:

50-424 NL-17-1201 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Vogtle Electric Generating Plant Units 1 & 2 Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report Ladies and Gentlemen:

By letter dated April 21, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17116A096), Southern Nuclear Operating Company (SNC) submitted a technical report for approval for Vogtle Electric Generating Plant, Units 1 and 2. In addition, the letter provided a supplemental response to Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors" (ADAMS Accession No. ML042360586) that supersedes previous responses. The technical report contains a risk-informed methodology to evaluate debris effects, except for vessel fiber limits.

By letter dated June 26, 2017, (ADAMS Accession No. ML17166A433), the Nuclear Regulatory Commission (NRC) staff requested information regarding the seismic probabilistic risk assessment peer review. The Enclosure provides the SNC response to the NRC request. In addition, the NRC staff asked SNC to confirm the scope of the requested technical report review. To clarify, SNC requests NRC review and approval of Enclosures 1 - 5 from the April 21, 2017 technical report. While SNCs intent is that the Enclosures can be separated for review by the appropriate NRC branch, they are intertwined such that NRC approval of all five is necessary for SNCs final resolution of Generic Letter (GL) 2004-02.

This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at 205.992.7369.

U. S. Nuclear Regulatory Commission NL-17-1201 Page2 Mr. J. J. Hutto states he is Regulatory Affairs Director of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and, to the best of his knowledge and belief, the facts set forth in this letter are true.

Respectfully submitted, J. J. Hutto Regulatory Affairs Director JJH/RMJ

12017, Swam to ~nd subscribed before me this 11_ day of~"--\\~

~~~~~~~~*-~~--~~

otary Public My commission expires: (\\

  • tQ * ~\\)\\ '0 MICHEllE l GRAVES Notary PubNc Alabama State at large

~

~

Enclosure:

SNC Response to NRC Request Regarding Risk-Informed Methodology cc:

Regional Administrator, Region II NRR Project Manager-Vogtle 1 & 2 Senior Resident Inspector-Vogtle 1 & 2 State of Georgia Environmental Protection Division RType: CVC7000

Vogtle Electric Generating Plant Units 1 & 2 Response to Supplemental Information Needed for Acceptance of Systematic Risk-Informed Assessment of Debris Technical Report Enclosure SNC Response to NRC Request Regarding Risk-Informed Methodology

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-1 NRC Information Request:

Regulatory Guide 1.200, Rev. 2, An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk-Informed Activities (ADAMS Accession No. ML090410014) describes an approach for determining whether the technical adequacy of a PRA is sufficient to provide confidence in the results; it also describes information the NRC staff expects to be included in risk-informed submittals. As discussed in the guide, a risk informed submittal should contain discussions concerning peer review. If the peer review is not performed against the established standards, then information needs to be included in the submittal demonstrating that the different criteria used are consistent with the established standards. The risk-informed methodology described in the technical report should include the following:

x Description demonstrating that the criteria in ASME/ANS RA-Sb-2013 (Addendum B), which is not an established endorsed standard, are consistent with the ASME/ANS RA-Sa-2009 (Addendum A), which is an established endorsed standard, for the seismic probabilistic risk assessment peer review facts and observations.

x If the different criteria are not consistent with the established endorsed standard, an explanation demonstrating that the analogous Addendum A supporting requirements have been met.

SNC Response:

Regulatory Guide 1.200, Revision 2.0 endorses ASME/ANS RA-Sa-2009 (Addendum A) but, as noted in an NRC letter to ASME, does not endorse PRA Standard ASME/ANS RA-Sb-2013 (Addendum B). The Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle) Seismic Probabilistic Risk Assessment (SPRA) peer review was performed using the SPRA requirements in Addendum B.

Because the peer review was not performed against the NRC endorsed standard, information demonstrating that any different criteria used are consistent with the NRC endorsed standard is provided here. The following discussion addresses the differences relative to establishing the technical capability of the Vogtle SPRA.

The ASME/ANS PRA Standard Part 5 requirements for at-power seismic PRA (in all versions of the PRA Standard) are organized into the following three major technical elements:

x Seismic hazard analysis (technical element SHA) x Seismic fragility analysis (technical element SFR), and x

Seismic plant-response modeling (technical element SPR)

Each technical element contains several high level requirements (HLR) and associated supporting requirements (SR). The following three tables (Table 1 for SHA, Table 2 for SFR and Table 3 for SPR) provide SR by SR comparisons between Addendum A and Addendum B of the ASME/ANS PRA Standard. Differences between SR wordings are denoted in the following tables using bold type. Changes in the HLRs between Addendum A and Addendum B are denoted using strikethrough text. The comparison assessment focuses on capability category II (CCII); as such, SR text not related to CCII is not included in the following

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-2 tables. This comparison assessment is performed by SR and not by HLR; peer reviewers assess technical quality by reviewing SRs (HLRs are not assigned technical capabilities). The following assessment conclusion categories are used in the SR comparison assessment:

x Addendum B Assessment Equates to Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are the same or effectively the same (i.e., re-wording that is for clarity and consistency and not intended to change the intent). This conclusion category is also used in cases where the wording differences are related to moving the requirements to another SR. In certain SRs the qualifier for a specific capability category range is assigned to indicate the focus on capability category II when there are differences in other capability categories. A peer reviewer using Addendum A or Addendum B would come to the same technical capability assessment on these topics.

x Addendum B Envelopes Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are different and the requirements of Addendum B envelope that of Addendum A (i.e., if the analysis meets Addendum B CCII then by definition it meets Addendum A CCII or higher). A peer reviewer using Addendum B would assess a technical capability on these topics that would be equal to or greater than what would be determined if Addendum A were used in the review.

x Vogtle Conforms to Addendum A: This conclusion category is used when the SR wording of Addendum A and Addendum B are different, or some of the requirements of Addendum A no longer exist in Addendum B, yet the analysis performed and documented in the Vogtle analysis conforms to the requirements of Addendum A as well as Addendum B.

x Vogtle Conforms to Accepted Current Practices: This conclusion category is used when the SR wording of Addendum A and Addendum B are different; or some of the requirements of Addendum A no longer exist in Addendum B because they were removed from the Standard as confusing or judged too specific how-to. For the one SR where this conclusion category applies, Vogtle does not follow some of the specifics of the Addendum A SR requirements but Vogtle does conform to accepted current practices.

While the Vogtle SPRA was peer reviewed against the ASME/ANS RA-Sb-2013 (Addendum B) requirements, the tables that follow demonstrate that most of the supporting requirements in Addendum B are consistent with the supporting requirements in ASME/ANS RA-Sa-2009 (Addendum A). For the few supporting requirements where differences are noted in the tables, the Vogtle SPRA model and documentation meet the analogous Addendum A supporting requirements. Therefore, the Vogtle SPRA meets the technical adequacy requirements of Regulatory Guide 1.200, Revision 2 and is of sufficient quality and level of detail to support the risk informed approach for GSI-191.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-3 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

HLR-SHA-A: The frequency of earthquakes at the site shall be based on a site-specific probabilistic seismic hazard analysis (existing or new) that reflects the composite distribution of the informed technical community. The level of analysis shall be determined based on the intended application and on site-specific complexity.

SHA-A1 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

In performing the probabilistic seismic hazard analysis (PSHA), BASE it on, and MAKE it consist of, the collection and evaluation of available information and data, evaluation of the uncertainties in each element of the PSHA, and a defined process and documentation to make the PSHA traceable.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A Identical to Addendum A SHA-A2 ASME/ANS RA-Sa-2009 As the parameter to characterize both hazard and fragilities, USE the spectral accelerations, or the average spectral acceleration over a selected band of frequencies, or peak ground acceleration.

<not printed here; not focus of this assessment>

Addendum B CC1-III Assessment Equates to Addendum A CCI-II In response to EPRI 2011 comment, Addendum B removed the CCIII requirements. The Addendum B SR equates to Addendum A CCI-II.

ASME/ANS RA-Sb-2013 Identical to Addendum A for CC I/II SHA-A3 ASME/ANS RA-Sa-2009 In the selection of frequencies to determine spectral accelerations or average spectral acceleration, CAPTURE the frequencies of those structures, systems, or components, or a combination thereof that are significant in the PRA results and insights.

Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs, and also made minor changes in wordings. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 If spectral acceleration or average spectral acceleration over a band of frequencies is used, INCLUDE the response frequencies of SSCs that are significant in the PRA results and insights.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-4 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SHA-A4 ASME/ANS RA-Sa-2009 In developing the probabilistic seismic hazard analysis results, whether they are characterized by spectral accelerations, peak ground accelerations, or both, EXTEND them to large-enough values (consistent with the physical data and interpretations) so that the truncation does not produce unstable final numerical results, such as core damage frequency, and the delineation and ranking of seismic-initiated sequences are not affected.

Addendum B Assessment Equates to Addendum A Addendum B added the phrase "for use in accident sequence quantification". This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 In developing the probabilistic seismic hazard analysis results for use in accident sequence quantification, whether they are characterized by spectral accelerations, peak ground accelerations, or both, EXTEND them to large-enough values (consistent with the physical data and interpretations) so that the truncation does not produce unstable final numerical results, such as core damage frequency, and the delineation and ranking of seismic-initiated sequences are not affected.

SHA-A5 ASME/ANS RA-Sa-2009 SPECIFY a lower-bound magnitude (or probabilistically defined characterization of magnitudes based on a damage parameter) for use in the hazard analysis, such that earthquakes of magnitude less than this value are not expected to cause significant damage to the engineered structures or equipment.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A HLR-SHA-B: To provide inputs to the probabilistic seismic hazard analysis, a comprehensive up-to-date database including geological, seismological, and geophysical data; local site topography; and surficial geologic and geotechnical site properties shall be compiled. A catalog of historical, instrumental, and paleoseismicity information shall also be compiled.

SHA-B1 ASME/ANS RA-Sa-2009 In performing the probabilistic seismic hazard analysis (PSHA), BASE it on available or developed geological, seismological, geophysical, and geotechnical data that reflect the current state of the knowledge and that are used by experts/analysts to develop

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-5 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) interpretations and inputs to the PSHA.

capability category requirements of this SR.

ASME/ANS RA-Sb-2013 In performing the probabilistic seismic hazard analysis (PSHA), USE available or developed geological, seismological, geophysical, and geotechnical data that reflect the current state of the knowledge and that are used by experts/analysts to develop interpretations and inputs to the PSHA.

<not printed here; not focus of this assessment>

SHA-B2 ASME/ANS RA-Sa-2009 ENSURE that the database and information used are adequate to characterize all credible seismic sources that may contribute significantly to the frequency of occurrence of vibratory ground motion at the site, considering regional attenuation of ground motions and local site effects. If the existing probabilistic seismic hazard analysis (PSHA) studies are to be used in the seismic PRA, ENSURE that any new data or interpretations that could affect the PSHA are adequately incorporated in the existing data and analysis.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B for CCI and CCII.

ASME/ANS RA-Sb-2013 Identical to Addendum A

<not printed here; not focus of this assessment>

SHA-B3 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

As a part of data collection, COMPILE a catalog of historically reported, geologically identified, and instrumentally recorded earthquakes. USE reference [5-30]

Vogtle Conforms to Addendum A A catalog of historically reported, geologically identified, and instrumentally recorded

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-6 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) requirements or equivalent.

earthquakes for the entire CEUS was compiled by the 2012 CEUS SSC report.

Following a SSHAC Level 3 process, the CEUS SSC report is a robust evaluation of available information on historical seismicity, paleoseismic data on large-magnitude recurrence rates, and state-of-the-knowledge of earthquake seismic sources as considered in the informed technical community.

The 2012 CEUS SSC catalog followed a SSHAC Level 3 process and is applicable for risk informed applications. Compiling a new catalog will not be as rigorous as the SSHAC Level 3 process. The Addenda B SR requirement is appropriate for CC-II.

The 2012 CEUS SSC report used an earthquake catalog which extended through 2008. Recent earthquake activity in the vicinity of the Vogtle site was assessed for its impact on hazard. The study was based on a temporal update of the earthquake catalog from 2009 through February 2016. The assessment concluded that the 2012 CEUS SSC report seismicity parameters are appropriate for evaluation of seismic hazard at Vogtle. Based on this, the Vogtle PSHA that was performed conforms to Addendum A.

ASME/ANS RA-Sb-2013 INCLUDE an appropriate existing catalog of historically reported earthquakes, instrumentally recorded earthquakes, and earthquakes reported through geological investigations. USE reference [5-30]

requirements or equivalent.

<not printed here; not focus of this assessment>

HLR-SHA-C: To account for the frequency of occurrence of seismic ground motions in the site region, the probabilistic seismic hazard analysis shall examine all credible sources of potentially damaging earthquakes.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-7 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SHA-C1 ASME/ANS RA-Sa-2009 In the probabilistic seismic hazard analysis, EXAMINE all potential sources of earthquakes that affect the probabilistic hazard at the site. BASE the identification and characterization of seismic sources on regional and site geological and geophysical data, historical and instrumental seismicity data, the regional stress field, and geological evidence of prehistoric earthquakes.

Addendum B Assessment Envelopes Addendum A Addendum B added additional clarifications and requirements into the text of this SR, and also Addendum B changed action verbs to be consistent with accepted verb usage across SRs. The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 In the probabilistic seismic hazard analysis, EVALUATE sources of earthquakes that have the potential to contribute significantly to the probabilistic hazard at the site. IDENTIFY and CHARACTERIZE seismic sources taking into account previous compilations of seismic sources, based on regional and site geological and geophysical data, historical and instrumental seismicity data, and geological evidence of prehistoric earthquakes.

SHA-C2 ASME/ANS RA-Sa-2009 ENSURE that any expert elicitation process used to characterize the seismic sources is compatible with the level of analysis discussed in Requirement HA-A, and FOLLOW a structured approach.

Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 ENSURE that any expert elicitation process used to characterize the seismic sources is compatible with the level of analysis discussed in Requirement HLR-SHA-A, and USE a structured approach.

SHA-C3 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

The seismic sources are characterized by source location and geometry, maximum earthquake magnitude, and earthquake recurrence. INCLUDE the aleatory and epistemic uncertainties explicitly in these characterizations.

Vogtle Conforms to Addendum A Addenda B added additional clarification into the text of this SR, and also added a clause "where significant" at the end. The Addenda B SR requirement is appropriate for CC-II.

Under the SSHAC Level 3 process the aleatory and epistemic uncertainties in

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-8 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

The seismic sources are characterized by alternative source representation and source geometry, maximum earthquake magnitude, and earthquake recurrence.

INCLUDE the aleatory and epistemic uncertainties explicitly in these characterizations, where significant.

seismic sources are characterized for source location and geometry, magnitude, and activity rate. Logic trees to account for the epistemic uncertainty were developed as part of the SSHAC Level 3 methodology implemented in the CEUS SSC report. The aleatory uncertainty was also accounted for in the PSHA framework of the Vogtle PSHA.

For seismic sources representing repeated large magnitude earthquakes (RLMEs),

uncertainties in location and geometry, magnitude model, activity rate, and maximum magnitude were explicitly included in the characterization. For background sources, uncertainty in geometry was represented with alternative sets of area sources, uncertainties in recurrence rates were represented with alternative rates, and uncertainties in maximum magnitude were represented with distributions of values. These uncertainties were documented in the 2012 CEUS SSC report and were included in the Vogtle PSHA.

Based on this, the Vogtle PSHA that was performed conforms to Addendum A.

SHA-C4 ASME/ANS RA-Sa-2009 If an existing probabilistic seismic hazard analysis study is used, SHOW that any seismic sources that were previously unknown or uncharacterized are not significant, or INCLUDE them in a revision of the hazard estimates.

Addendum B Assessment Equates to Addendum A Addendum B added additional clarifications and modified the sentence structure to highlight the seismic source model aspect of the PSHA. In addition, Addendum B changed action verbs to be consistent with accepted ASME/ANS RA-Sb-2013 If an existing seismic source model is used, DEMONSTRATE that any new seismic sources that have been identified or were uncharacterized when the existing models were developed are not

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-9 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) significant, or INCLUDE them in the update of the hazard estimates.

verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

HLR-SHA-D: The probabilistic seismic hazard analysis shall examine mechanisms influencing vibratory ground motion that can occur at a site given the occurrence of an earthquake of a certain type (e.g., strike slip, normal, reverse) and magnitude, and at a certain location.

Uncertainties shall be addressed in characterizing the ground motion propagation.

SHA-D1 ASME/ANS RA-Sa-2009 ACCOUNT in the probabilistic seismic hazard analysis for (a) credible mechanisms governing estimates of vibratory ground motion that can occur at a site (b) regional and site-specific geological, geophysical, and geotechnical data and historical and instrumental seismicity data (including strong motion data)

(c) current attenuation models in the ground motion estimates Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. In addition, Addendum B modified item (b) by removing requirements that were redundant with SHA-B1. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 In the vibratory ground motion analysis, INCLUDE (a) credible mechanisms governing estimates of vibratory ground motion that can occur at a site (b) available historical and instrumental seismicity data (including strong motion data)

(c) current attenuation models for the ground motion estimates SHA-D2 ASME/ANS RA-Sa-2009 ENSURE that any expert elicitation process used to characterize the ground motion is compatible with the level of analysis discussed in Requirement SHA-A, and FOLLOW a structured approach.

Addendum B Assessment Envelopes Addendum A Addendum B added additional requirements into the text of this SR, and also Addendum B changed action verbs to be consistent with accepted verb usage across SRs. The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 ENSURE that any expert elicitation process used to characterize the ground motion or any other elements of the ground motion analysis is compatible with the level of analysis discussed in Requirement HLR-SHA-A, and USE a structured approach.

SHA-D3 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

ADDRESS both the aleatory and epistemic uncertainties in the ground motion characterization in accordance with the level of analysis identified for Requirement SHA-A.

Addendum B Assessment Envelopes Addendum A Addendum B changed action verbs to be

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-10 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

INCLUDE both the aleatory and epistemic uncertainties separately in the ground motion characterization in accordance with the level of analysis identified for Requirement HLR-SHA-A.

consistent with accepted verb usage across SRs, and also Addendum B added additional requirement on handling aleatory and epistemic uncertainties separately. The Addendum B SR wording envelopes that of Addendum A.

SHA-D4 ASME/ANS RA-Sa-2009 If an existing probabilistic seismic hazard analysis study is used, SHOW that any ground motion models or new information that were previously unused or unknown are not significant, or INCLUDE them in a revision of the hazard estimates.

Addendum B Assessment Equates to Addendum A Addendum B added additional clarifications and modified the sentence structure to highlight the ground motion model aspect of the PSHA. In addition, Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 If existing ground motion models are used, DEMONSTRATE that new information not previously used or which was unknown when the existing models were developed would not significantly affect the PSHA results, or INCLUDE it in the update of the hazard estimates.

HLR-SHA-E: The probabilistic seismic hazard analysis shall account for the effects of local site response.

SHA-E1 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

ACCOUNT in the probabilistic seismic hazard analysis for the effects of site topography, surficial geologic deposits, and site geotechnical properties on ground motions at the site.

Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

In the probabilistic seismic hazard analysis, INCLUDE the effects of site topography, surficial geologic deposits, and site geotechnical properties on ground motions at the site.

SHA-E2 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

ADDRESS both the aleatory and epistemic uncertainties in the local site response analysis.

Addendum B Assessment Equates to Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-11 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

INCLUDE both the aleatory and epistemic uncertainties in the local site response analysis.

Addendum B changed action verbs to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

HLR-SHA-F: Uncertainties in each step of the hazard analysis shall be propagated and displayed in the final quantification of hazard estimates for the site.

Addendum A only: The results shall include fractile hazard curves, median and mean hazard curves, and uniform hazard response spectra. For certain applications, the probabilistic seismic hazard analysis shall include seismic source deaggregation and magnitude-distance deaggregation SHA-F1 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

In the final quantification of the seismic hazard, INCLUDE and DISPLAY the propagation of both aleatory and epistemic uncertainties.

Addendum B Assessment Equates to Addendum A In response to NRC 2012 comment on Addendum B ballot that said the wording of this SR was vague, Addendum B revised the wording to be clear that CCI is Mean only and that CCII-III is a family of hazard curves. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

In the final quantification of the seismic hazard, INCLUDE uncertainties through a family of hazard curves.

SHA-F2 ASME/ANS RA-Sa-2009 In the probabilistic seismic hazard analysis, INCLUDE appropriate sensitivity studies and inter mediate results to identify factors that are important to the site hazard and that make the analysis traceable.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-12 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SHA-F3 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

DEVELOP the following results as a part of the quantification process, compatible with needs for the level of analysis determined in (HLR-SHA-A):

(a) fractile and mean hazard curves for each ground motion parameter considered in the probabilistic seismic hazard analysis (b) fractile and mean uniform hazard response spectrum

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across SRs, and also Addendum B added additional clarification on the phrase "quantification process" by modifying it to "hazard quantification process". This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

CALCULATE the following results as a part of the hazard quantification process, compatible with needs for the level of analysis determined in Requirement HLR-SHA-A:

<not printed here; not focus of this assessment>

HLR-SHA-G:

Addendum A: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account the

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-13 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) contributions of deaggregated magnitude-distance results of the probabilistic seismic hazard analysis. Broad-band, smooth spectral shapes, such as those presented in NUREG/CR-0098 [5-5] (for lower seismicity sites such as most of those east of the U.S. Rocky Mountains) are also acceptable if they are shown to be appropriate for the site. The use of existing uniform hazard response spectra (UHSs) is acceptable unless evidence comes to light that would challenge these uniform hazard spectral shapes.

Reg Guide 1.200 Rev2 Clarification: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account the contributions of deaggregated magnitude-distance results of the probabilistic seismic hazard analysis. Broad-band, smooth spectral shapes,... that would challenge these uniform hazard spectral shapes.

Addendum B: For further use in the seismic PRA, the spectral shape shall be based on a site-specific evaluation taking into account results of the probabilistic seismic hazard analysis.

SHA-G1 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

BASE the response spectral shape used in the seismic PRA on site-specific evaluations performed for the probabilistic seismic hazard analysis. REFLECT or BOUND the site-specific considerations.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B deleted the last sentence of this SR to make the language more concise and remove redundancy. In addition, Addendum B changed the action verb to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

ENSURE that the spectral shape used in the seismic PRA uses site-specific evaluations performed for the PSHA.

<not printed here; not focus of this assessment>

HLR-SHA-H: When use is made of an existing study for probabilistic seismic hazard analysis purposes, it shall be confirmed that the basic data and interpretations are still valid in light of established current information [Addendum A only: the study meets the requirements outlined in A through G above, and the study is suitable for the intended application.]

Reg Guide 1.200 Rev 2 Clarification: When use... for the intended application. It shall be confirmed that basic data and interpretations

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-14 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) from an existing study are valid.

SHA-H1 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

Use of existing studies allowed.

<not printed here; not focus of this assessment>

Addendum B Assessment Envelopes Addendum A Addendum B added additional clarifications and requirements into the text of this SR. The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 CONFIRM that the basic data and interpretations for any existing studies used remain valid in light of established current information, consistent with the Requirements HLR-SHA-A through HLR-SHA-G, and DESCRIBE the bases and methodology used.

HLR-SHA-I: A screening analysis shall be performed to assess whether, in addition to the vibratory ground motion, other seismic hazards, such as fault displacement, landslide, soil liquefaction, or soil settlement, need to be included in the seismic PRA [Addendum A only: for the specific application. If so, the seismic PRA shall address the effect of these hazards through assessment of the frequency of hazard occurrence or the magnitude of hazard consequences, or both.]

Reg Guide 1.200 Rev 2 Clarification: A screening analysis... or the magnitude of hazard consequences, or both. The hazard analysis shall include hazards other than vibratory ground motion if necessary.

SHA-I1 ASME/ANS RA-Sa-2009 (There are no supporting requirements here.)

Addendum B Assessment Envelopes Addendum A There are no supporting requirements for HLR-SHA-I in Addendum A. Since the HLRs only say do something and the SRs establish what needs to be done, the addition of SRs in Addendum B establishes new requirements beyond Addendum A.

ASME/ANS RA-Sb-2013 DOCUMENT the bases and methodology used for any screening out of the seismic hazards other than vibratory ground motion.

SHA-I2 ASME/ANS RA-Sa-2009 no SHA-I2 in Addendum A Addendum B Assessment Envelopes Addendum A There are no supporting requirements for HLR-SHA-I in Addendum A. Since the HLRs only say do something and the SRs establish what needs to be done, the addition of SRs in Addendum B establishes new ASME/ANS RA-Sb-2013 For those hazards not screened out, INCLUDE their effect through assessment of the frequency of hazard occurrence and the magnitude of hazard consequences.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-15 Table 1: Comparison of Supporting Requirements of Addendum A and Addendum B for SHA SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) requirements beyond Addendum A.

HLR-SHA-J: Documentation of the probabilistic seismic hazard analysis shall be consistent with the applicable supporting requirements SHA-J1 ASME/ANS RA-Sa-2009 DOCUMENT the probabilistic seismic hazard analysis in a manner that facilitates PRA applications, upgrades, and peer review.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A SHA-J2 ASME/ANS RA-Sa-2009 DOCUMENT the process used in the probabilistic seismic hazard analysis. For example, this documentation is typically consistent with reference [5-28] and includes a description of:

(a) the specific methods used for source characterization and ground motion characterization, (b) the scientific interpretations that are the basis for the inputs and results, and (c) if an existing PSHA is used, documentation to ensure that it is adequate to meet the spirit of the requirements herein.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A SHA-J3 ASME/ANS RA-Sa-2009 DOCUMENT the sources of model uncertainty and related assumptions associated with the probabilistic seismic hazard analysis.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-16 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

HLR-SFR-A:

Addendum A: The seismic-fragility evaluation shall be performed to estimate seismic fragilities of SSCs whose failure may contribute to core damage or large early release, or both.

Addendum B: The seismic-fragility evaluation shall be performed to estimate plant-specific, realistic seismic fragilities of structures, or systems, or components, or a combination thereof whose failure may contribute to core damage or large early release, or both.

SFR-A1 ASME/ANS RA-Sa-2009 DEVELOP seismic fragilities for all those structures, systems, or components, or a combination thereof identified by the systems analysis (see Requirement SPR-D1).

Addendum B Assessment Equates to Addendum A The changes from Addendum A to Addendum B for this SR included the replacement of "DEVELOP" with "CALCULATE." The change implements a more precise action verb. These wording edits do not change capability category requirements of this SR. The elimination of the phrase a combination thereof does not change the requirements, since it is redundant to other SRs requiring consideration of seismic correlation.

ASME/ANS RA-Sb-2013 CALCULATE seismic fragilities for SSCs identified by the systems analysis (see Requirement SPR-D1).

SFR-A2 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

BASE the seismic fragilities on plant-specific data, and ENSURE that they are realistic (median with uncertainties).

Generic data (e.g.,

fragility test data, generic seismic qualification test data, and earthquake experience data)

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A The changes from Addendum A to Addendum B involve the replacement of "BASE" with the more precise action verb "CALCULATE" and the replacement of "conservative" with "applicable" in the last sentence with respect to the use of generic fragility data. The latter change precludes confusion due to a contradiction, as the requirement states first that realistic fragilities

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-17 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

MAY be used for screening of certain structures, systems, or components, or a combination thereof and for calculating their seismic fragilities by applying the requirements under (HLR-SFR-F),

which permits use of such generic data under specified conditions. However, DEMONSTRATE that any use of such generic data is conservative.

are required but then the use of generic data is to be conservative. In the context of the requirement, the use of "applicable" is correct and does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

CALCULATE the seismic fragilities based on plant-specific data, and ENSURE that they are realistic (median with uncertainties).

Generic data (e.g.,

fragility test data, generic seismic qualification test data, and earthquake experience data) may be used for screening

<not printed here; not focus of this assessment>

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-18 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) of certain SSCs and for calculating their seismic fragilities by applying the Requirement HLR-SFR-F, which permits use of such generic data under specified conditions. However, DEMONSTRATE that any use of such generic data is applicable.

HLR-SFR-B: If screening of high-seismic-capacity components is performed, the basis for the screening shall be fully described.

SFR-B1 ASME/ANS RA-Sa-2009 If screening of high-seismic-capacity components is performed, DESCRIBE fully the basis for screening and supporting documents. For example, it is acceptable to apply guidance given in EPRI NP-6041-SL, Rev. 1, and NUREG/CR-4334 to screen out components with high seismic capacity.

However, CHOOSE the screening level high enough that the contribution to core damage frequency and large early release frequency from the screened-out components is not significant.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B removes the sentence citing NP-6041-SL and NUREG/CR-4334 as examples of screening bases and replaces the action verb "CHOOSE" with the more precise verb "SELECT." These wording edits are non-substantive and do not change capability category requirements of this SR.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-19 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 If screening of high-seismic-capacity components is performed, DESCRIBE the basis for screening and the supporting documents and SELECT the screening level high enough that the contribution to core damage frequency and large early release frequency from the screened-out components is not significant.

<not printed here; not focus of this assessment>

SFR-B2 ASME/ANS RA-Sa-2009 ASSESS and DOCUMENT the applicability of the screening criteria given in EPRI NP-6041-SL, Rev. 1 [5-3] and NUREG/CR-4334 [5-4] for the specific plant and specific equipment.

Addendum B Assessment Equates to Addendum A Addendum B deleted this SR. The clarifying non-mandatory footnote for SFR-B1, which remains unchanged from Addendum A to Addendum B, reiterates that NP-6041-SL and NUREG/CR-4334 "may be used" and are not mandatory. SFR-B2 in Addendum A states the applicability of NP-6041-SL and NUREG/CR-4334 shall be assessed and documented. However, if NP-6041-SL and NUREG/CR-4334 are applied for screening, SFR-B1 in both Addendum A and Addendum B state that the basis for use shall be described and documentation is addressed under SFR-G2. Therefore, SFR-B2 is redundant and its removal does not change the requirements of the standard.

ASME/ANS RA-Sb-2013 No SFR-B2 in Addendum B HLR-SFR-C: The seismic-fragility evaluation shall be based on seismic response that the SSCs experience at their failure levels

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-20 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SFR-C1 ASME/ANS RA-Sa-2009 ESTIMATE the seismic responses that the components experience at their failure levels on a realistic basis using site-specific earthquake response spectra in three orthogonal directions, anchored to a ground motion parameter such as peak ground acceleration or average spectral acceleration over a given frequency band. ENSURE that the spectral shape used reflects or bounds the site-specific conditions.

<not printed here; not focus of this assessment>

Addendum B Assessment Envelopes Addendum A The two changes from Addendum A to Addendum B involve the deletion of "site-specific" prior to "earthquake response spectra" in the first sentence and deletion of "reflects" in the last sentence. Removal of "site-specific" prior to earthquake response spectra is inconsequential as bounding by site-specific conditions by definition renders the earthquake response spectra site-specific. Removal of "reflects" renders Addendum B as more precise since the properties must "bound" site-specific conditions and not merely "reflect."

ASME/ANS RA-Sb-2013 ESTIMATE the seismic responses that the components experience at their failure levels using input earthquake response spectra in three orthogonal directions, anchored to a ground motion parameter such as peak ground acceleration or average spectral acceleration over a given frequency band, and ENSURE that the spectral shape used bounds the site-specific conditions.

<not printed here; not focus of this assessment>

SFR-C2 ASME/ANS RA-Sa-2009 If probabilistic response analysis is performed to obtain realistic structural loads and floor response spectra, ENSURE that the number of simulations done (e.g., Monte Carlo simulation and Latin Hypercube Sampling) is large enough to obtain stable median and 85% nonexceedance responses. ACCOUNT for the entire spectrum of input ground motion levels displayed in the seismic hazard curves.

<not printed here; not focus of this assessment>

Addendum B Assessment Envelopes Addendum A The changes from Addendum A to Addendum B are to implement the approved action verb "ACCOUNT" to the more precise verb "INCLUDE" and to eliminate "realistic" in the first sentence prior to "structural loads and floor response spectra." The qualifier

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-21 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 If probabilistic response analysis is performed to obtain structural loads and floor response spectra, ENSURE that the number of simulations done (e.g., Monte Carlo simulation and Latin Hypercube Sampling) is large enough to obtain stable median and 85% nonexceedance responses. INCLUDE the entire spectrum of input ground motion levels displayed in the seismic hazard curves.

<not printed here; not focus of this assessment>

realistic is removed to avoid confusion as it is unnecessary in the context of applying probabilistic response analysis to determine structural loads and response spectra.

SFR-C3 ASME/ANS RA-Sa-2009 If scaling of existing design response analysis is used, JUSTIFY it based on the adequacy of structural models, foundation characteristics, and similarity of input ground motion.

<not printed here; not focus of this assessment>

Vogtle Conforms to Addendum A The change from Addendum A to Addendum B involved the deletion of the word "design" from "existing design response analysis."

However, Plant Vogtle did not perform scaling of any existing response analysis, and therefore the change is irrelevant and Vogtle conforms to Addendum A.

ASME/ANS RA-Sb-2013 If scaling of existing response analysis is used, JUSTIFY it based on the adequacy of structural models, foundation characteristics, and similarity of input ground motion.

<not printed here; not focus of this assessment>

SFR-C4 ASME/ANS RA-Sa-2009 When the design response analysis models are judged not to be realistic and state of the art, or when the design input ground motion is significantly different from the site-specific input motion, PERFORM new analysis to obtain realistic structural loads and floor response spectra.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Similar to SFR-C3, Addendum B in SFR-C4 eliminates "design" from "existing design response analysis" in the first sentence and adds the "for use in the seismic PRA" to the last sentence. The judgement of existing response analysis models as unrealistic and not state of the art as stated in Addendum B would include the judgement of existing design response analyses; therefore this change is non-substantive. The addition of "for use in the seismic PRA" is for clarification ASME/ANS RA-Sb-2013 When the existing response analysis models are judged not to be realistic and state of the art, or when the design input ground motion is significantly different from the site-specific input motion, PERFORM new analysis to obtain realistic structural loads and floor response spectra for use in the seismic PRA.

<not printed here; not focus of this assessment>

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-22 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) and also non-substantive.

SFR-C5 ASME/ANS RA-Sa-2009 If median-centered response analysis is performed, ESTIMATE the median response (i.e., structural loads and floor response spectra) and variability in the response using established methods.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A

<not printed here; not focus of this assessment>

SFR-C6 ASME/ANS RA-Sa-2009 When soil-structure interaction (SSI) analysis is conducted, ENSURE that it is median centered using median properties, at soil strain levels corresponding to the input ground motions that dominate the seismically induced core damage frequency. ACCOUNT for the uncertainties in the SSI analysis by varying the low strain soil shear modulus between the median value times (1 + Cv) and the median value divided by (1 + Cv),

where Cv is a factor that accounts for uncertainties in the SSI analysis and soil properties. If adequate soil investigation data are available, ESTABLISH the mean and standard deviation of the low strain shear modulus for every soil layer. Then ESTABLISH the value of Cv so that it will cover the mean plus or minus one standard deviation for every layer. The

<not printed here; not focus of this assessment>

Vogtle Conforms to Accepted Current Practices The changes in SFR-C6 involved the replacement of "ACCOUNT for" with the more precise action verb "INCLUDE", the non-substantive replacement of "dominate" with "contribute most" for PRA standard consistency, and the removal of how to perform SSI uncertainty analysis.

The SSI uncertainty analysis method presented in Addendum A is derived from ASCE 4-98 (as indicated by the non-mandatory Note 5). Section 3.3.1.7 of ASCE 4-98 states that the use of (1 + Cv) to vary low strain soil shear moduli is an acceptable method in lieu of probabilistic evaluation, which Section C.3.3.1.7 further states is the

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-23 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus) minimum value of Cv is 0-5. When insufficient data are available to address uncertainties in soil properties, ENSURE that Cv is taken as no less than 1.0.

preferred approach.

Plant Vogtle accounted for uncertainties in the SSI analysis by applying strain-compatible soil properties derived from probabilistic evaluation via the PSHA. Use of the ASCE 4-98 alternate approach using (1 +

Cv) would render overly conservative and unrealistic response analysis results, which would invalidate other SRs. Therefore, the Addendum B assessment is considered appropriate.

ASME/ANS RA-Sb-2013 When soil-structure interaction (SSI) analysis is conducted, ENSURE that it is median centered using median properties, at soil strain levels corresponding to the input ground motions that contribute most to the seismically induced core damage frequency.

INCLUDE the uncertainties in the SSI analysis.

<not printed here; not focus of this assessment>

HLR-SFR-D: The seismic-fragility evaluation shall be performed for critical failure modes of SSCs such as structural failure modes and functional failure modes identified through the review of plant design documents, supplemented as needed by earthquake experience data, fragility test data, generic qualification test data, and a walkdown.

SFR-D1 ASME/ANS RA-Sa-2009 IDENTIFY realistic failure modes of structures and equipment that interfere with the operability of equipment during or after the earthquake through a review of the plant design documents and the walkdown.

Addendum B Assessment Envelopes Addendum A The change from Addendum A to Addendum

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-24 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 IDENTIFY realistic failure modes of structures ( e.g., sliding, overturning, yielding, and excessive drift), equipment (e.g.,

anchorage failure, impact with adjacent equipment or structures, bracing failure, and functional failure), and soil (e.g., liquefaction, slope instability, and excessive differential settlement) that interfere with the operability of equipment during or after the earthquake, through a review of the plant design documents and the walkdown.

B involved the move of example failure modes from SFR-D2 to SFR-D1.

SFR-D2 ASME/ANS RA-Sa-2009 EXAMINE all relevant failure modes of structures (e.g., sliding, overturning, yielding, and excessive drift), equipment (e.g.,

anchorage failure, impact with adjacent equipment or structures, bracing failure, and functional failure), and soil (i.e., liquefaction, slope instability, and excessive differential settlement), and EVALUATE fragilities for critical failure modes.

Addendum B Assessment Envelopes Addendum A The changes from Addendum A to Addendum B for this SR involved the aforementioned move of example failure modes to SFR-D1 and change in wording from "EXAMINE all relevant failure modes of structures..." to "EVALUATE relevant failure modes identified in SFR-D1." The latter change implements a more precise action verb in addition to providing more specificity for the evaluation of failure modes.

ASME/ANS RA-Sb-2013 EVALUATE all relevant failure modes identified in Requirement SFR-D1, and EVALUATE fragilities for critical failure modes.

HLR-SFR-E: The seismic-fragility evaluation shall incorporate the findings of a detailed walkdown of the plant focusing on the anchorage, lateral seismic support, and potential systems interactions.

SFR-E1 ASME/ANS RA-Sa-2009 CONDUCT a detailed walkdown of the plant, focusing on equipment anchorage, lateral seismic support, spatial interactions, and potential systems interactions (both structural and functional interactions).

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-25 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SFR-E2 ASME/ANS RA-Sa-2009 DOCUMENT the walkdown procedures, walkdown team composition and its members qualifications, walkdown observations, and conclusions.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A SFR-E3 ASME/ANS RA-Sa-2009 If components are screened out during or following the walkdown, DOCUMENT anchorage calculations and PROVIDE the basis justifying such a screening.

Addendum B Assessment Envelopes Addendum A The change implemented from Addendum A to Addendum B involves increased requirement to not only document anchorage screening but all screening (e.g. including functional or component structure).

ASME/ANS RA-Sb-2013 If components are screened out during or following the walkdown, DOCUMENT the basis, including any anchorage calculations that justify such a screening.

SFR-E4 ASME/ANS RA-Sa-2009 During the walkdown, FOCUS on the potential for seismically induced fire and flooding.

Addendum B Assessment Envelopes Addendum A The change from Addendum A to Addendum B involved changing "FOCUS" into the more precise action verb "EVALUATE" in addition to adding specific criteria pertaining to NUREG-1407.

ASME/ANS RA-Sb-2013 During the walkdown, EVALUATE the potential for seismically induced fire and flooding by focusing on the issues described in NUREG-1407 [5-7].

SFR-E5 ASME/ANS RA-Sa-2009 During the walkdown, EXAMINE potential sources of interaction (e.g.,

II/I issues, impact between cabinets, masonry walls, flammable and combustion sources, flooding, and spray) and consequences of such interactions on equipment contained in the systems model.

Addendum B Assessment Equates to Addendum A The change from Addendum A to Addendum B for this SR involved the replacement of "EXAMINE" with "EVALUATE." The action verb change was made to be consistent with accepted verb usage across SRs. These wording edits do not change capability category requirements of this SR..

ASME/ANS RA-Sb-2013 During the walkdown, EVALUATE potential sources of interaction (e.g., II/I issues, impact between cabinets, masonry walls, flammable and combustion sources, flooding, and spray) and consequences of such interactions on equipment contained in the systems model.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-26 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

HLR-SFR-F: The calculation of seismic-fragility parameters such as median capacity and variabilities shall be based on plant-specific data or, if necessary, on earthquake experience data, fragility test data, and generic qualification test data. Use of such generic data shall be justified.

SFR-F1 ASME/ANS RA-Sa-2009 BASE component seismic-fragility parameters such as median capacity and variabilities (logarithmic standard deviations reflecting randomness and uncertainty) on plant-specific data supplemented as appropriate by earthquake experience data, fragility test data, and generic qualification test data.

<not printed here; not focus of this assessment>

Addendum B Assessment Envelopes Addendum A Addendum B changes the action verb from "BASE" to the more precise and restrictive verb "CALCULATE" in keeping with the approved action verb list and adds more specificity to the use of sources beyond plant-specific data, including the provision to justify the appropriateness of generic fragility data.

ASME/ANS RA-Sb-2013 CALCULATE component seismic-fragility parameters such as median capacity and variabilities (logarithmic standard deviations reflecting randomness and uncertainty) based on plant-specific data or, if necessary, on earthquake experience data, fragility test data, and generic qualification test data.

Exception: JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.

<not printed here; not focus of this assessment>

SFR-F2 ASME/ANS RA-Sa-2009 For all structures, or systems, or components, or a combination thereof (SSCs) that appear in the dominant accident cut sets, ENSURE that they have site-specific fragility parameters that are derived based on plant-specific information, such as anchoring and installation of the component or structure and plant-specific material test data. Exception:

JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B changes the use of "dominant accident cut sets" in Addendum A to "significant accident sequences." This wording edit is for consistency with the convention used elsewhere in the PRA standard to be software neutral and does not change the capability category

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-27 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 For all SSCs that appear in the significant accident sequences, ENSURE that they have site-specific fragility parameters that are derived based on plant-specific information, such as anchoring and installation of the component or structure and plant-specific material test data. Exception: JUSTIFY the use of generic fragility for any SSC as being appropriate for the plant.

<not printed here; not focus of this assessment>

requirements of this SR.

SFR-F3 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

DEVELOP seismic fragilities for relays identified to be essential and that are included in the systems-analysis model.

Addendum B Assessment Equates to Addendum A The change from Addendum A to Addendum B for this SR was the replacement of "DEVELOP" with "CALCULATE." The action verb change was made to be consistent with accepted verb usage across SRs. These wording edits do not change capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

CALCULATE seismic fragilities for relays identified to be essential and that are included in the systems-analysis model.

SFR-F4 ASME/ANS RA-Sa-2009 DEVELOP seismic fragilities for structures, or systems, or components, or a combination thereof that are identified in the systems model as playing a role in the large early release frequency part of the seismic PRA. (See Requirements SPR-A1 and SPR-A3.)

Addendum B Assessment Equates to Addendum A The changes from Addendum A to Addendum B for this SR included the replacement of "DEVELOP" with "CALCULATE." The action verb change was made to be consistent with accepted verb usage across SRs. Also, SSC abbreviation used instead. These wording edits do not change capability category requirements of this SR.

ASME/ANS RA-Sb-2013 CALCULATE seismic fragilities for SSCs that are identified in the systems model as playing a role in the large early release frequency part of the seismic PRA. (See Requirements SPR-A1 and SPR-A3.)

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-28 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

HLR-SFR-G: Documentation of the seismic-fragility evaluation shall be consistent with the applicable supporting requirements.

SFR-G1 ASME/ANS RA-Sa-2009 DOCUMENT the seismic fragility analysis in a manner that facilitates PRA applications, upgrades, and peer review.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

ASME/ANS RA-Sb-2013 Identical to Addendum A SFR-G2 ASME/ANS RA-Sa-2009 DOCUMENT the process used in the seismic-fragility analysis. For example, this typically includes a description of (a) The methodologies used to quantify the seismic fragilities of structures, or systems, or components, or a combination thereof, together with key assumptions (b) The seismic fragilities of structures, or systems, or components, or a combination thereof (SSC) fragility values that includes the method of seismic qualification, the dominant failure mode(s), the source of information, and the location of the component (c) The fragility parameter values (i.e., median acceleration capacity, Br and Bu) and the technical bases for them for each analyzed SSC, and (d) the different elements of seismic-fragility analysis, such as (1) the seismic response analysis (2) the screening steps (3) the walkdown (4) the review of design documents (5) the identification of critical failure modes for each SSC, and (6) the calculation of fragility parameter values for each SSC modeled Addendum B Assessment Equates to Addendum A The only change in this SR is related to use of "structures, systems, and components" versus its acronym "SSC." This change is considered editorial and does not change the capability category requirements of this SR.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-29 Table 2: Comparison of Supporting Requirements of Addendum A and Addendum B for SFR SR Standard Rev.

Capability Category I

Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 DOCUMENT the process used in the seismic-fragility analysis. For example, this typically includes a description of (a) the methodologies used to quantify the seismic fragilities of SSCs, together with key assumptions (b) the SSC fragility values that includes the method of seismic qualification, the dominant failure mode(s), the source of information, and the location of the component (c) the fragility parameter values (i.e., median acceleration capacity, Br and Bu) and the technical bases for them for each analyzed SSC, and (d) the different elements of seismic-fragility analysis, such as (1) the seismic response analysis (2) the screening steps (3) the walkdown (4) the review of design documents (5) the identification of critical failure modes for each SSC, and (6) the calculation of fragility parameter values for each SSC modeled SFR-G3 ASME/ANS RA-Sa-2009 DOCUMENT the sources of model uncertainty and related assumptions associated with the seismic fragility analysis.

Vogtle Conforms to Addendum A Addendum B deleted this SR. However, the Plant Vogtle 1&2 SPRA documentation describes in detail the sources of model uncertainty and related assumptions associated with the seismic fragility analysis.

Therefore, the Vogtle SPRA conforms to Addendum A.

ASME/ANS RA-Sb-2013 Deleted.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-30 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

HLR-SPR-A: The seismic-PRA systems model shall include seismic-caused initiating events and other failures including seismic-induced SSC failures, non-seismic-induced unavailabilities, and human errors, that give rise to significant accident sequences and/or significant accident progression sequences.

SPR-A1 ASME/ANS RA-Sa-2009 ENSURE that earthquake-caused initiating events that give rise to significant accident sequences and/or significant accident progression sequences are included in the seismic-PRA system model using a systematic process.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. A minor clarification (i.e., very low magnitude earthquakes can be excluded from the quantification process) was added in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 Identical to Addendum A SPR-A2 ASME/ANS RA-Sa-2009 In the initiating-event selection process, DEVELOP a hierarchy to ensure that every earthquake greater than a certain defined size produces a plant shutdown within the systems model.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. A minor clarification (i.e., event ordering by consequence severity) was added in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 Identical to Addendum A SPR-A3 ASME/ANS RA-Sa-2009 USE the event trees and fault trees from the internal-event at-power PRA model as the basis for the seismic event trees.

Addendum B Assessment Equates to Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-31 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 USE the accident sequences and the systems logic model from the at-power, internal-event PRA model as the basis for the seismic-PRA model.

Some of the terms in this SR were changed in Addendum B so that they would not be less specific to a certain type of PRA modeling software. These term clarifications do not change the capability category requirements of this SR.

SPR-A4 (Add. B)

ASME/ANS RA-Sb-2013 This supporting requirement is new to Addendum B and not included in Addendum A.

Under special circumstances based on the judgment of the analyst, DEVELOP an ad hoc systems model tailored especially to the seismic-PRA configurations or issues being modeled, instead of starting with the internal-events model and adapting it, as in Requirement SPR-A3. If this approach is used, ENSURE that the resulting model is consistent with the internal-events systems model regarding plant response and the cause-effect relationships of the failures.

Addendum B Assessment Equates to Addendum A Addendum B added this SR to recognize that some utilities may build a separate stand-alone SPRA as opposed to adding seismic aspects into an existing internal events PRA (as described by SPR-A3). This new SR ensures that the technical capability of the base modeling would be consistent with the internal events technical capability requirements. For Vogtle, this specific SR is not applicable because the Vogtle 1&2 SPRA is built upon the internal events PRA per SR SPR-A3 and thus the Vogtle SPRA conforms to Addendum A.

SPR-A4 (Add. A)

SPR-A5 (Add. B)

ASME/ANS RA-Sa-2009 SPR-A4 of Addendum A:

ENSURE that the PRA systems models reflect earthquake-caused failures and nonseismically induced unavailabilities and human errors that give rise to significant accident sequences or significant accident progression sequences.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B.

Miscellaneous edits were made in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements ASME/ANS RA-Sb-2013 SPR-A5 of Addendum B is identical to SPR-A4 of Addendum A.

There is no change in the supporting requirement from Addendum A to Addendum B, except that the insertion of a new SPR-A4 in Addendum B changes the number for this

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-32 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus) requirement.

of this SR.

HLR-SPR-B: The seismic-PRA systems model shall be adapted to incorporate seismic-analysis aspects that are different from corresponding aspects found in the at-power, internal-events PRA systems model.

SPR-B1 ASME/ANS RA-Sa-2009 In each of the following aspects of the seismic-PRA systems-analysis work, SATISFY the corresponding requirements in Part 2, except where they are not applicable or where this Part includes additional requirements. DEVELOP a defined basis to support the claimed nonapplicability of any exceptions. The aspects governed by this requirement are (a) initiating-event analysis (b) accident-sequence analysis (c) success-criteria analysis (d) systems analysis (e) data analysis (f) human-reliability analysis (g) use of expert judgment When the Part 2 requirements are used, FOLLOW the Capability Category designations in Part 2, and for consistency USE the same Capability Category in this analysis.

Vogtle Conforms to Addendum A Addendum B removed the last sentence of this SR in response to an EPRI 2011 comment on the Addendum B ballot. The last sentence was removed in Addendum B because it was determined to be confusing as wells as inappropriate specificity to require all new aspects in the SPRA to meet the exact same CCs of Part 2 SRs. In addition, Addendum B changed the action verb to be consistent with accepted verb usage across SRs. The Addendum B SR requirement clarifications are appropriate. Regardless, the Plant Vogtle 1&2 SPRA builds upon the internal events PRA and uses the same

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-33 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 In each of the following aspects of the seismic-PRA systems-analysis work, SATISFY the corresponding requirements in Part 2, except where they are not applicable or where this Part includes additional requirements. SPECIFY a basis to support the claimed nonapplicability of any exceptions. The aspects governed by this requirement are (a) initiating-event analysis (b) accident-sequence analysis (c) success-criteria analysis (d) systems analysis (e) data analysis (f) human-reliability analysis (g) use of expert judgment general methodologies as used for Part 2 where applicable; therefore, the Vogtle SPRA conforms to Addendum A.

SPR-B2 ASME/ANS RA-Sa-2009 In the human reliability analysis (HRA) aspect, EXAMINE additional post earthquake stresses that can increase the likelihood of human errors or inattention, compared to the likelihood assigned in the internal-events HRA when the same activities are undertaken in no earthquake accident sequences.

Whether or not increases in error probabilities are used, JUSTIFY the basis for this decision about what error rates to use.

Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added CCI-II and CCIII capability differentiation as well as the requirement to include the seismic HEP impacts on the internal events based HEPs, not simply to Examine them. It also expanded on the considerations to emphasize PSFs beyond just stress. The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 INCLUDE the following seismic impacts on performance-shaping factors (PSFs) for the control room and ex-control room post-initiator actions as appropriate to the human reliability analysis (HRA) methodology used:

(a) additional post-earthquake workload and stress that can increase the likelihood of human errors or inattention

<not printed here; not focus of this assessment>

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-34 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

(b) seismic failures that impact access (c) cue availability SPR-B3 (Add. A)

SPR-B4a (Add. B)

ASME/ANS RA-Sa-2009 SPR-B3 of Addendum A:

If any screening is performed, PERFORM it using defined criteria that are documented in the PRA.

Addendum B Assessment Equates to Addendum A Addendum B changed the sentence structure to correct awkward wording and to use accepted verb. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 SPR-B4a of Addendum B:

If screening out on the basis of seismic capacity is performed in the systems model, SPECIFY the screening criterion.

SPR-B4 (Add. A)

SPR-B3 (Add. B)

ASME/ANS RA-Sa-2009 SPR-B4 of Addendum A:

PERFORM an analysis of seismic-caused dependencies and correlations in a way so that any screening of SSCs appropriately accounts for those dependencies and correlations.

USE bounding or generic correlation values and PROVIDE the basis for such use.

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B deleted the phrase "dependencies and" because they are redundant to the "correlation" term so as to avoid reviewer potential confusion. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 SPR-B3 of Addendum B:

PERFORM an analysis of seismic-caused dependencies and correlations in a way so that any screening of SSCs appropriately accounts for those correlations.

USE bounding or generic correlation values and PROVIDE the basis for such use.

<not printed here; not focus of this assessment>

SPR-B5 (Add. A)

ASME/ANS RA-Sa-2009 SPR-B5 of Addendum A:

ENSURE that any screening of human-error basic events and non-seismic-failure basic events does not significantly affect the PRAs results.

Addendum B Assessment Equates to Addendum A Addendum B deleted this SR because it is redundant to SR SPR-A5, which already requires modeling of operator actions that contribute to significant accident sequences.

ASME/ANS RA-Sb-2013 No SR of Addendum B directly matches with SPR-B5 of Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-35 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

Also, it is redundant in part to SR SPR-E3, which requires validation that any screening does not impact the results. Finally, Vogtle did not screen out any human-error or non-seismic events that were in the FPIE model and would propagate through seismic accident sequences, and so conforms to Addendum A.

SPR-B4b ASME/ANS RA-Sa-2009 Not included in Addendum A.

Addendum B Assessment Envelopes Addendum A This SR is new for Addendum B to ensure that recoveries added to the SPRA (i.e., not already included in the internal events PRA) are assessed for appropriateness.

Addendum B envelopes Addendum A with respect to this SR.

ASME/ANS RA-Sb-2013 SPR-B4b of Addendum B:

If post-earthquake recovery actions are included in the systems model, INCLUDE them on a documented basis.

SPR-B6 (Add. A)

SPR-B4 (Add. B)

ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

SPR-B6 of Addendum A:

EXAMINE the effects of the chatter of relays and similar devices.

Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added the requirement to include the effects of relay chatter in the model, not simply to examine them. The differentiation for "low ruggedness relays" is deleted in Addendum B because the issue of chatter fragility is addressed in SFR SRs. The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 SPR-B4 of Addendum B:

INCLUDE the effects of the chatter of relays and similar devices in the systems model.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-36 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SPR-B7 (Add. A)

SPR-B5 (Add. B)

ASME/ANS RA-Sa-2009 SPR-B7 of Addendum A:

In the systems-analysis models, for each basic event that represents a seismically caused failure, INCLUDE the complementary success state where applicable to a particular SSC.

Addendum B Assessment Equates to Addendum A Addendum B revised the wording of this SR to include a capability category distinction to explicitly model fragility complements for risk significant fragilities for CCI-II and for all modeled fragilities for CCIII. The Vogtle 1&2 SPRA uses the SPRA CAFTA suite of codes with the ACUBE module addressing the fragility complement modeling and so meets the intent of both Addenda A and B since the quantification accounts mathematically for the success states.

ASME/ANS RA-Sb-2013 SPR-B5 of Addendum B:

In the systems-analysis models, for each basic event that represents a significant seismically caused failure, INCLUDE the complementary success state where applicable to a particular SSC, and SPECIFY the criteria used for the term significant in this activity.

<not printed here; not focus of this assessment>

SPR-B8 (Add. A)

SPR-B6 (Add. B)

ASME/ANS RA-Sa-2009 SPR-B8 of Addendum A:

EXAMINE the possibility that a large earthquake can cause damage that blocks personnel access to safety equipment or controls, thereby inhibiting operator actions that might otherwise be credited.

Addendum B Assessment Equates to Addendum A Addendum B changed the action verb to be consistent with accepted verb usage across SRs. This wording edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 SPR-B6 of Addendum B:

EVALUATE the possibility that a large earthquake can cause damage that blocks personnel access to safety equipment or controls, thereby inhibiting operator actions that might otherwise be credited.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-37 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SPR-B9 (Add. A)

SPR-B7 (Add. B)

ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

SPR-B9 of Addendum A:

EXAMINE the likelihood that system recoveries modeled in the internal-events PRA may be more complex or even not possible after a large earthquake, and ADJUST the recovery models accordingly.

Addendum B CCII Assessment Equates to Addendum A CCII-III In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added three capability differentiations. CCII requirements are effectively the same for Addendum A and Addendum B. The Addendum B SR adds the clarification that generic and/or conservative recovery values are acceptable. The Addendum B SR CCII wording effectively equates to Addendum A CCII-III given the state of practice at the time (i.e., detailed plant-specific system recovery probability calculations were not typical practice at the time of Addendum A).

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

SPR-B7 of Addendum B:

EVALUATE the likelihood that system recoveries modeled in the internal-events PRA may be more complex or even not possible after a large earthquake, and ADJUST the recovery models accordingly. It is acceptable to use generic or conservative recovery values.

<not printed here; not focus of this assessment>

SPR-B10 (Add. A)

SPR-B8 ASME/ANS RA-Sa-2009 SPR-B10 of Addendum A:

EXAMINE the effect of including an earthquake-caused small-small loss-of-coolant accident as an additional fault within each sequence in the seismic-PRA model.

Addendum B Assessment Envelopes Addendum A Addendum B added differentiation of

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-38 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

(Add. B)

ASME/ANS RA-Sb-2013 SPR-B8 of Addendum B:

ASSUME the existence of an earthquake-caused very small loss-of-coolant accident in the seismic-PRA accident sequences and system modeling, unless it is demonstrated that such a LOCA can be excluded, based on a walkdown or on another examination of the possible sources of such a LOCA.

<not printed here; not focus of this assessment>

capability requirements to this SR that require modeling incorporation into the SPRA (if the topic requires it for a specific plant) whereas the EXAMINE verb in Addendum A did not require incorporation into the SPRA (i.e., it could be done as a sensitivity study). The Addendum B SR wording envelopes that of Addendum A.

SPR-B11 (Add. A)

SPR-B9 (Add. B)

ASME/ANS RA-Sa-2009 SPR-B11 of Addendum A:

In the seismic PRA walkdown, INCLUDE the potential for seismically induced fires and flooding following the guidance given in NUREG-1407.

Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B added the requirement to include risk significant scenarios into the SPRA models as opposed to only including them in the walkdown.

Reference to NUREG-1407 was removed in Addendum B because this SR refers to SFR-E4 for input and SFR-E4 already includes the reference to NUREG-1407. The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 SPR-B9 of Addendum B:

If the seismic PRA walkdown (see Requirement SFR-E4) identifies the potential for seismically induced fires and flooding, INCLUDE potential significant contributions to accident sequences in the systems model.

HLR-SPR-C: The seismic-PRA systems model shall reflect the as-built and as-operated plant being analyzed.

SPR-C1 ASME/ANS RA-Sa-2009 To ensure that the systems-analysis model reflects the as-built, as-operated plant, JUSTIFY any conservatisms or other distortions introduced by demonstrating that the seismic-PRAs validity for applications is maintained.

Addendum B Assessment Equates to Addendum A Addendum B changed the last clause of this

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-39 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

ASME/ANS RA-Sb-2013 To ensure that the systems-analysis model reflects the as-built, as-operated plant, JUSTIFY any conservatisms or other distortions that do not adequately reflect the as-built, as-operated plant.

SR because the wording was awkward. This wording refinement does not change the capability category requirements of this SR.

HLR-SPR-D: The list of SSCs selected for seismic-fragility analysis shall include the SSCs that participate in accident sequences included in the seismic-PRA systems model.

SPR-D1 ASME/ANS RA-Sa-2009 USE the seismic PRA systems model as the basis for developing the seismic equipment list, which is the list of all SSCs to be considered by the subsequent seismic-fragility evaluation task.

Addendum B Assessment Envelopes Addendum A Addendum B added additional clarifications and requirements into the text of this SR.

The Addendum B SR wording envelopes that of Addendum A.

ASME/ANS RA-Sb-2013 USE the PRA systems model as the basis for developing the seismic equipment list to support the fragility analysis of 5-2.2. INCLUDE structures and passive components that may not be present in the internal-events model but that require consideration in the seismic PRA. SUPPLEMENT the list based on the review of industry seismic-PRA seismic equipment lists (SELs), if available.

HLR-SPR-E: The analysis to quantify core damage frequency and large early release frequency shall appropriately integrate the seismic hazard, the seismic fragilities, and the systems-analysis aspects SPR-E1 ASME/ANS RA-Sa-2009 In the quantification of core damage frequency and large early release frequency, PERFORM the integration using the seismic hazard, fragility, and systems analyses.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. Minor edits were made in Addendum B to the clarifying non-mandatory footnote for this SR; this footnote adjustment does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 Identical to Addendum A

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-40 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SPR-E2 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

In quantifying core damage frequency and large early release frequency, PERFORM the quantification on a cut-set-by-cut set or accident-sequence-by-accident-sequence basis (or for defined groups of these), as well as on a comprehensive/integrated basis.

Addendum B Assessment Envelopes Addendum A Addendum B revised this SR to back-reference to Part 2 requirements for the accident sequence quantification. This edit was made for consistency across the Std Parts to refer back to Part 2 SRs where applicable. The wording edit in Addendum B to this SR expands the capability category requirements beyond the requirements of Addendum A by incorporating many more SRs.

ASME/ANS RA-Sb-2013 PERFORM seismic-sequence quantification in accordance with the applicable requirements described in 2-2.7.

SPR-E3 ASME/ANS RA-Sa-2009 In the analysis, USE the quantification process to ensure that any screening of SSCs does not affect the results, taking into account the various uncertainties.

Addendum B Assessment Equates to Addendum A In addition to minor wording changes, Addendum B revised this SR to remove the clause regarding consideration of uncertainties. The use of the phrase "confirm and support" allows for the analyst to determine the best way to validate the screening, whereas Addendum A went beyond "what to do" into "how to do it." The end result is the same.

ASME/ANS RA-Sb-2013 USE the quantification process to confirm and support the screening of SSCs (refer to Requirement SFR-B1).

SPR-E4 ASME/ANS RA-Sa-2009 In the integration/quantification analysis, ACCOUNT for all significant dependencies and correlations that affect the results.

It is acceptable to use generic correlation values. If used, PROVIDE the basis for such

<not printed here; not focus of this assessment>

Addendum B Assessment Equates to Addendum A Addendum B changed action verbs to be consistent with accepted verb usage across

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-41 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus) use.

SRs, and also deleted the redundant "dependencies" term. These wording edits do not change capability category requirements of this SR.

ASME/ANS RA-Sb-2013 In the integration/quantification analysis, INCLUDE the significant correlations that affect the results.

It is acceptable to use generic correlation values. If used, SPECIFY the basis for such use.

<not printed here; not focus of this assessment>

SPR-E5 ASME/ANS RA-Sa-2009

<not printed here; not focus of this assessment>

Identical to Addendum B CCII except Addendum A uses ACCOUNT verb.

Addendum B CCII Assessment Equates to Addendum A CCII-III Addendum B changed action verbs to be consistent with accepted verb usage across SRs. Three Capability Category distinctions are instituted for Addendum B (Addendum B CCII corresponds to Addendum A CCII-III).

These edits do not change the CCII capability category requirements of this SR.

ASME/ANS RA-Sb-2013

<not printed here; not focus of this assessment>

In the integration/quantification analysis, INCLUDE in the uncertainties in core damage frequency and large early release frequency results that arise from each of the several inputs (the seismic hazard, the seismic fragilities, and the systems-analysis aspects).

<not printed here; not focus of this assessment>

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-42 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SPR-E6 (Add. A)

ASME/ANS RA-Sa-2009 PERFORM appropriate sensitivity studies to illuminate the sensitivity of the core damage frequency and large early release frequency results to the assumptions used about dependencies and correlations.

Addendum B Assessment Envelopes Addendum A In response to an EPRI 2011 comment on the Addendum B ballot, Addendum B deleted this SR because performance of sensitivity studies is already addressed by another SR through the new back-reference to meeting the Part 2 quantification requirements (see SPR-E2), which includes the requirement to conduct appropriate sensitivity studies to address sources of uncertainty. This new back-reference implies requirements well beyond just sensitivity to correlations, and so the Addendum B approach envelopes Addendum A, even with this deletion. The Vogtle 1&2 SPRA documentation includes a sensitivity case related to seismic fragility correlation modeling.

ASME/ANS RA-Sb-2013 Deleted in Addendum B SPR-E6 (Add. B)

ASME/ANS RA-Sa-2009 New Requirement in Addendum B.

Addendum B Assessment Envelopes Addendum A Addendum B added this SR to back-reference to Part 2 requirements for the LERF analysis. This new SR was added for consistency across the Std Parts to refer back to Part 2 SRs where applicable. The ASME/ANS RA-Sb-2013 In the analysis of LERF, SATISFY the LERF requirements in 2-2.8, where applicable.

Note 6 - Those aspects of LERF analysis that are common to internal-events PRA and seismic PRA are referred to here. Also, the discussion of LERF analysis in the last four paragraphs of 5-1.3 is

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-43 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus) broadly applicable and should be referred to as background information.

Addendum B SR wording envelopes that of Addendum A given that Addendum A did not specifically cite this LERF back-referencing to Part 2.

HLR-SPR-F: The seismic-PRA analysis shall be documented in a manner that facilitates applying the PRA and updating it, and that enables peer review.

SPR-F1 ASME/ANS RA-Sa-2009 DOCUMENT the seismic plant response analysis and quantification in a manner that facilitates PRA applications, upgrades, and peer review.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. Addendum B edited the non-mandatory footnote for this SR. This footnote edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 Identical to Addendum A SPR-F2 ASME/ANS RA-Sa-2009 DOCUMENT the process used in the seismic plant response analysis and quantification. For example, this documentation typically includes a description of:

(a) the specific adaptations made in the internal events PRA model to produce the seismic-PRA model, and their motivation, and (b) the major outputs of a seismic PRA, such as mean core damage frequency (CDF), mean large early release frequency (LERF),

uncertainty distributions on CDF and LERF, results of sensitivity studies, significant risk contributors, and so on, are examples of the PRA results that are generally documented.

Addendum B Assessment Equates to Addendum A Addendum B moved the non-mandatory list of examples to the associated non-mandatory footnote. This edit does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 DOCUMENT the process used in the seismic plant response analysis and quantification.

Enclosure to NL-17-1201 SNC Response to NRC Request Regarding Risk-Informed Methodology E-44 Table 3: Comparison of Supporting Requirements of Addendum A and Addendum B for SPR SR Standard Rev.

Capability Category I Capability Category II Capability Category III Basis for Assessment (CC-II Focus)

SPR-F3 ASME/ANS RA-Sa-2009 DOCUMENT the sources of model uncertainty and related assumptions associated with the seismic plant response model development.

Addendum B Assessment Equates to Addendum A The wording for this SR is the same for Addendum A and Addendum B. Addendum A had a missing non-mandatory footnote (not all uncertainties need to be assigned a numerical distribution in the documentation) that was re-inserted in Addendum B. This footnote does not change the capability category requirements of this SR.

ASME/ANS RA-Sb-2013 Identical to Addendum A.