ML18009A838: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 2: | Line 2: | ||
| number = ML18009A838 | | number = ML18009A838 | ||
| issue date = 02/28/1991 | | issue date = 02/28/1991 | ||
| title = Monthly Operating Rept for Feb 1991 for Harris Nuclear Power Plant Unit 1 | | title = Monthly Operating Rept for Feb 1991 for Harris Nuclear Power Plant Unit 1 | ||
| author name = Hale M, Richey R | | author name = Hale M, Richey R | ||
| author affiliation = CAROLINA POWER & LIGHT CO. | | author affiliation = CAROLINA POWER & LIGHT CO. | ||
| Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:ACCELERATED D TRIBUTION DEMONS | {{#Wiki_filter:ACCELERATED D TRIBUTION DEMONS TION SYSTEM | ||
'a...r | |||
'r REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS) | |||
ACCESSION NBR:9103180102 | ACCESSION NBR:9103180102 DOC.DATE: 91/02/28 NOTARIZED: NO FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina AUTH.NAME | ||
RICHEY,R.B. | , AUTHOR AFFXLXATION HALE,M. | ||
RECIP.NAME | Carolina Power 6 Light Co. | ||
RICHEY,R.B. | |||
. Carolina Power 6 Light Co. | |||
RECIP.NAME RECIPIENT AFFILIATION DOCKET'g 05000400 R | |||
==SUBJECT:== | ==SUBJECT:== | ||
Monthly operating rept | Monthly operating rept for Feb 1991 for Harris Nuclear Power Plant Unit 1.W/910312 ltr. | ||
DXSTRIBUTION CODE | DXSTRIBUTION CODE IE24D COPIES RECEIVED:LTR ENCL SIZE: | ||
TITLE: Monthly Operating Report (per Tech Specs NOTES:Application for permit renewal filed. | TITLE: Monthly Operating Report (per Tech Specs NOTES:Application for permit renewal filed. | ||
RECIPXENT | o5ooo4oo / | ||
RECIPXENT ID CODE/NAME PD2-1 LA BECKER,D INTERNAL: ACRS AEOD/DSP/TPAB NRR/DOEA/OEAB RGN2 EXTERNAL: EG&G BRYCE,J.H NSIC COPIES LTTR ENCL 3 | |||
3 1 | |||
1 10 10 1 | |||
1 1 | |||
1 1 | |||
1 1 | |||
1 1 | |||
1 RECIPIENT ID CODE/NAME PD2-1 PD AEOD/DOA NRR/DLPQ/~LPEB10 R | |||
G &I-LE 1 | |||
NRC PDR COPIES LTTR ENCL 1 | |||
1 1 | |||
1 1 | |||
1, 1 | |||
1 1 | |||
1 D | |||
D D | |||
NOTE TO ALL"RIDS" RECIPIENTS: | |||
A D | A D | ||
D | D PLEASE HELP US TO REDUCE WASIE! CONTACTTHE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION'IPID FOR DOCUMENTS YOU DON T NEEDI TOTAL NUMBER OF COPIES REQUIRED: | ||
PLEASE HELP US TO REDUCE | LTTR 24 ENCL 24 | ||
Carolina Power & Light Company P. O. Box 165 ~ New Hill N. C. 27562 | Carolina Power & Light Company P. O. Box 165 ~ New Hill~ N. C. 27562 R. B. RICHEY Vice President Harris Nuclear Project MAR. | ||
1 2 1991 File Number'SHF/10-15505 Letter Number: | |||
R. B. RICHEY Vice President Harris Nuclear Project MAR. 1 | HO-913008 (0) | ||
Document | Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555 HARRIS NUCLEAR PROJECT DEPARTMENT UNIT NO. | ||
1 DOCKET NO. 50-400 LICENSE NO. NPF-63 MONTHLY OPERATIONS REPORT | |||
==Dear | ==Dear Sirs:== | ||
In accordance with Technical Specification 6.9.1.5 for the Harris Nuclear Power Plant, Unit No. | |||
In accordance with Technical Specification 6.9.1.5 for the Harris Nuclear Power Plant, Unit No. 1, Carolina Power & Light Company herewith submits the report of operation statistics and shutdown experience for the month of February 1991. | 1, Carolina Power | ||
Yours very | & Light Company herewith submits the report of operation statistics and shutdown experience for the month of February 1991. | ||
Mr. R. G. Oehl (DOE) | Yours very truly, 1 | ||
Mr. J. E. Tedrow (NRC-SHNPP) | R. | ||
MEM/DATAREPa/1/OS4 9i03130l02 910228 PDR | B. Richey Vice President Harris Nuclear Project MWH:svm Enclosure cc.'Mr. S. | ||
D. Ebneter (NRC-RII) | |||
Mr. R. | |||
G. Oehl (DOE) | |||
Mr. J. | |||
E. Tedrow (NRC-SHNPP) | |||
MEM/DATAREPa/1/OS4 9i03130l02 910228 PDR ADOCK 05000400 PDR | |||
1 p | 1 p | ||
IL | IL | ||
DOCKET NO.: | DOCKET NO.: | ||
050-400 UNIT: | |||
Harris Unit 1 | |||
DATE: | |||
February 1991 COMPLETED BY: | |||
Mark Hale OPERATIONS | |||
==SUMMARY== | ==SUMMARY== | ||
Harris Unit 1 | |||
Harris Unit | operated at a 100.00 percent Availability Factor for the referenced month and a | ||
There are | 97.44 percent Capacity Factor. | ||
In addition to the spent fuel, 60 new fuel assemblies were received from Westinghouse. | There were two events. | ||
Details are provided on the Unit Shutdowns and Power Reduction Sheets. | |||
There are 157 fuel assemblies in the reactor vessel and 438 spent fuel assemblies in the Spent Fuel Pools. | |||
306 of the spent fuel assemblies are BWR and were shipped to Harris from CP&L's Brunswick Plant. | |||
Twenty eight of the spent fuel assemblies in the Spent Fuel Pools are from CPSL's Robinson Plant. | |||
In addition to the spent | |||
: fuel, 60 new fuel assemblies were received from Westinghouse. | |||
MEM/DATAREPa/1/OS4 | MEM/DATAREPa/1/OS4 | ||
CnL | CnL CO'UH DATE 03/07/91 RUH TIME 14: 28: 00 PLANT PERFORMAHCE DATA SYSTEM OPERATING DATA REPORT HARRIS UNIT 1 | ||
PAGE RPD36-000 OPERATIHG STATUS DOCI(ET HO. 650"408 COMPLETED BY MARK W. | |||
HALE TELEPHONE | |||
<919)362-2944 UHIT HANE: | |||
HARRIS UHIT I | |||
NOTES 2. | |||
: 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 TI.IRU 7) SINCE | REPORTING PERIOD: | ||
FEBRUARY 91 I | |||
See operations 3. | |||
LICEHBED THERMAL POWER (MWT): 2775 I | |||
NAMEPLATE RATING (GROSS MWF): 958.9 I | |||
5. | |||
DESIGN ELECTRICAL RATING <HET MWE): 980.0 6. | |||
MAX DEPENDABLE CAPACITY (GROSS MWE): 920.8 7. | |||
NAX DEPENDABLE CAPAclTY (HET MWE): 860.8 | |||
: 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 TI.IRU 7) | |||
SINCE GIVE REASONS: N/A I | |||
summary. | |||
I I | |||
I I | |||
I LAST REPORT, 9. | |||
POWER LEVEL TO WHICH RESTRICTED IF ANY (NET NWE): None. | |||
10. | |||
REASONS FOR RESTRICTION IF ANY: N/A THIS MONTH YR TO DATE CUNUL ATIVE HOURS IN REPORTING PERIOD 12. | |||
: 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP: | NUMBER OF HOURS REACTOR CRITICAL 13. | ||
REACTOR RESERVE SHUTDOWN HRS 14. | |||
HOURS GENERATOR OH LINE 15. | |||
UHIT RESERVE SHUTDOWN HOURS 16. | |||
GROSS THERMAL ENERGY GEH. | |||
(MWH) 17. | |||
GROSS ELEC. | |||
ENERGY GEN. | |||
(MWH) 18. | |||
NET ELEC. | |||
ENERGY GEHERATED (MWH) 19. | |||
UNlT SERVICE FACTOR 20. | |||
UNIT AVAILABIIITY FACTOR 21. | |||
UNIT CAP. | |||
FACTOR | |||
<USING NDC NET) 22. | |||
UNIT CAP. | |||
FACTOR (USING DER NET) 23. | |||
UNIT FORCED OUTAGE RATE 24. | |||
SHUTDOWNS SCHED. | |||
OVER NEXT 6 MONT Refueling Outage, March 16th, 672.00 1416.00 672.80 1416.00 | |||
.08 | |||
.00 672.80 1416.00 | |||
.08 | |||
.00 1782562.32 3832583.58 600933.80 1292501.00 563<<6.68 12<<696.86 180.88 108.06 100.08 160.66 97.44 99.50 93.11 95.88 | |||
.88 | |||
.00 HS (TYPE, | |||
: DATE, AHD DURATION 1991 9 weeks. | |||
33577.08 27262.09 | |||
.66 26888.35 | |||
.08 78887827.88 23544435.00 21888866.80 88.08 | |||
'80. 68 75.80 72.43 4.43 OF EACH): | |||
: 25. IF SHUTDOWN AT END OF REPORT | |||
: PERIOD, ESTIMATED DATE OF START UP: | |||
26. | |||
UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): | |||
FORECAST ACHIEVED INITlALCRITICALITY INITIAL ELEC TRICITY COMMERCIAL OPERATIOH MEM/DATREPa/2/OS4 1.16 9 | |||
I I | I I | ||
CPhL CO | CPhL CO RUN DATE RUN TINE 03/07/93 34:27:58 PLANT PERFORMANCE DATA SYSTEH APPENDIX B AVERAGE DAILY POWER LEVEL HARRIS UNIT 3 | ||
$ 0 | PAGE RPD39-000 FEBRUARY 199'3 DAY AVG. DAILY POWER I EVEL (MWE-NET) | ||
DOCKET NO. 050-400 CONPLETED BY HARK W. | |||
HALE TELEPHONE (919)362-2944 DAY AVG. DAILY POWER LEVEL (HWE-NET) 882 SSO 823 17 29 874 872 873 873 | |||
$ 0 851 804 859 875 875 877 877 MEM/DATREPa/3/OS4 | |||
a | |||
UNIT SHUTDOWNS AND POWER REDUCTION REPORT MONTH: | |||
UNIT SHUTDOWNS AND POWER REDUCTION UNIT NAME: | February 1991 UNIT NAME: | ||
I | Harris DATE: | ||
E-Operator Training 8, License Examination | 3/7/91 COMPLETED BY: | ||
M. W. Hale TELEPHONE: | |||
(919) 362"2944 No. | |||
Date TI y | |||
P e | |||
Duration (Hours) | |||
R Method of Shutting Down Reactor Licensee Event Report f System Code 4 | |||
Component Code 5 | |||
Cause 8, Corrective Action to Prevent Recurrence 91-002 910203 0.0 HA VALVE Reduced unit power to 70$ to perform turbine valve testing. | |||
Unit was returned to 100$ power on 2-3-91. | |||
I F: Forced S: Scheduled 2 | |||
Reason: | |||
A-Equipment Failure (Explain) | |||
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training 8, License Examination F-Administrative G-Operational Error (Explain) 3 Method: | |||
I-Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Reduced Load 6-Other 4 | |||
Exhibit G-Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161) 5 Exhibit I - Same Source MEM/DATAREPa/4/OS4 | |||
UNIT SHUTDOWNS AND POWER REDUCTION UNIT NAME: | UNIT SHUTDOWNS AND POWER REDUCTION REPORT MONTH: | ||
1 | February 1991 UNIT NAME: | ||
E-Operator Training 8, License Examination | Harris DATE: | ||
MEM/DATAREPa/5/OS4}} | 3/7/91 COMPLETED BY: | ||
M. W. Hale TELEPHONE: | |||
(919) 362-2944 No. | |||
Date Tl y | |||
p e | |||
Duration (Hours) | |||
Method of Shutting Down Reactor Licensee Event Report f System Code 4 | |||
Component Code 5 | |||
Cause 4 Corrective Action to Prevent Recurrence 91-003 910224 0.0 N/A HC PIPE Reduced unit power to "305 power due to a tube leak in the west side of the condenser. | |||
One leaking tube was plugged. | |||
Eight additional tubes in adjacent areas were plugged to prevent future problems. | |||
Unit was returned to full load on 2-26-91. | |||
1 F: | |||
Forced S: | |||
Scheduled 2 | |||
Reason: | |||
A-Equipment Failure (Explain) | |||
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training 8, License Examination F-Administrative G-Operational Error (Explain) | |||
H-Other (Explain) 3 Method: | |||
I-Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Reduced Load 6-Other 4 | |||
Exhibit G-Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161) 5 Exhibit I - Same Source MEM/DATAREPa/5/OS4}} | |||
Latest revision as of 06:51, 7 January 2025
| ML18009A838 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 02/28/1991 |
| From: | Hale M, Richey R CAROLINA POWER & LIGHT CO. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| References | |
| HO-913008-(), HO-913008-(0), NUDOCS 9103180102 | |
| Download: ML18009A838 (10) | |
Text
ACCELERATED D TRIBUTION DEMONS TION SYSTEM
'a...r
'r REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:9103180102 DOC.DATE: 91/02/28 NOTARIZED: NO FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina AUTH.NAME
, AUTHOR AFFXLXATION HALE,M.
Carolina Power 6 Light Co.
RICHEY,R.B.
. Carolina Power 6 Light Co.
RECIP.NAME RECIPIENT AFFILIATION DOCKET'g 05000400 R
SUBJECT:
Monthly operating rept for Feb 1991 for Harris Nuclear Power Plant Unit 1.W/910312 ltr.
DXSTRIBUTION CODE IE24D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: Monthly Operating Report (per Tech Specs NOTES:Application for permit renewal filed.
o5ooo4oo /
RECIPXENT ID CODE/NAME PD2-1 LA BECKER,D INTERNAL: ACRS AEOD/DSP/TPAB NRR/DOEA/OEAB RGN2 EXTERNAL: EG&G BRYCE,J.H NSIC COPIES LTTR ENCL 3
3 1
1 10 10 1
1 1
1 1
1 1
1 1
1 RECIPIENT ID CODE/NAME PD2-1 PD AEOD/DOA NRR/DLPQ/~LPEB10 R
G &I-LE 1
NRC PDR COPIES LTTR ENCL 1
1 1
1 1
1, 1
1 1
1 D
D D
NOTE TO ALL"RIDS" RECIPIENTS:
A D
D PLEASE HELP US TO REDUCE WASIE! CONTACTTHE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION'IPID FOR DOCUMENTS YOU DON T NEEDI TOTAL NUMBER OF COPIES REQUIRED:
LTTR 24 ENCL 24
Carolina Power & Light Company P. O. Box 165 ~ New Hill~ N. C. 27562 R. B. RICHEY Vice President Harris Nuclear Project MAR.
1 2 1991 File Number'SHF/10-15505 Letter Number:
HO-913008 (0)
Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555 HARRIS NUCLEAR PROJECT DEPARTMENT UNIT NO.
1 DOCKET NO. 50-400 LICENSE NO. NPF-63 MONTHLY OPERATIONS REPORT
Dear Sirs:
In accordance with Technical Specification 6.9.1.5 for the Harris Nuclear Power Plant, Unit No.
1, Carolina Power
& Light Company herewith submits the report of operation statistics and shutdown experience for the month of February 1991.
Yours very truly, 1
R.
B. Richey Vice President Harris Nuclear Project MWH:svm Enclosure cc.'Mr. S.
D. Ebneter (NRC-RII)
Mr. R.
G. Oehl (DOE)
Mr. J.
E. Tedrow (NRC-SHNPP)
MEM/DATAREPa/1/OS4 9i03130l02 910228 PDR ADOCK 05000400 PDR
1 p
IL
DOCKET NO.:
050-400 UNIT:
Harris Unit 1
DATE:
February 1991 COMPLETED BY:
Mark Hale OPERATIONS
SUMMARY
Harris Unit 1
operated at a 100.00 percent Availability Factor for the referenced month and a
97.44 percent Capacity Factor.
There were two events.
Details are provided on the Unit Shutdowns and Power Reduction Sheets.
There are 157 fuel assemblies in the reactor vessel and 438 spent fuel assemblies in the Spent Fuel Pools.
306 of the spent fuel assemblies are BWR and were shipped to Harris from CP&L's Brunswick Plant.
Twenty eight of the spent fuel assemblies in the Spent Fuel Pools are from CPSL's Robinson Plant.
In addition to the spent
- fuel, 60 new fuel assemblies were received from Westinghouse.
MEM/DATAREPa/1/OS4
CnL CO'UH DATE 03/07/91 RUH TIME 14: 28: 00 PLANT PERFORMAHCE DATA SYSTEM OPERATING DATA REPORT HARRIS UNIT 1
PAGE RPD36-000 OPERATIHG STATUS DOCI(ET HO. 650"408 COMPLETED BY MARK W.
HALE TELEPHONE
<919)362-2944 UHIT HANE:
HARRIS UHIT I
NOTES 2.
REPORTING PERIOD:
FEBRUARY 91 I
See operations 3.
LICEHBED THERMAL POWER (MWT): 2775 I
NAMEPLATE RATING (GROSS MWF): 958.9 I
5.
DESIGN ELECTRICAL RATING <HET MWE): 980.0 6.
MAX DEPENDABLE CAPACITY (GROSS MWE): 920.8 7.
NAX DEPENDABLE CAPAclTY (HET MWE): 860.8
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 TI.IRU 7)
SINCE GIVE REASONS: N/A I
summary.
I I
I I
I LAST REPORT, 9.
POWER LEVEL TO WHICH RESTRICTED IF ANY (NET NWE): None.
10.
REASONS FOR RESTRICTION IF ANY: N/A THIS MONTH YR TO DATE CUNUL ATIVE HOURS IN REPORTING PERIOD 12.
NUMBER OF HOURS REACTOR CRITICAL 13.
REACTOR RESERVE SHUTDOWN HRS 14.
HOURS GENERATOR OH LINE 15.
UHIT RESERVE SHUTDOWN HOURS 16.
GROSS THERMAL ENERGY GEH.
(MWH) 17.
GROSS ELEC.
ENERGY GEN.
(MWH) 18.
NET ELEC.
ENERGY GEHERATED (MWH) 19.
UNlT SERVICE FACTOR 20.
UNIT AVAILABIIITY FACTOR 21.
UNIT CAP.
FACTOR
<USING NDC NET) 22.
UNIT CAP.
FACTOR (USING DER NET) 23.
UNIT FORCED OUTAGE RATE 24.
SHUTDOWNS SCHED.
OVER NEXT 6 MONT Refueling Outage, March 16th, 672.00 1416.00 672.80 1416.00
.08
.00 672.80 1416.00
.08
.00 1782562.32 3832583.58 600933.80 1292501.00 563<<6.68 12<<696.86 180.88 108.06 100.08 160.66 97.44 99.50 93.11 95.88
.88
.00 HS (TYPE,
- DATE, AHD DURATION 1991 9 weeks.
33577.08 27262.09
.66 26888.35
.08 78887827.88 23544435.00 21888866.80 88.08
'80. 68 75.80 72.43 4.43 OF EACH):
- 25. IF SHUTDOWN AT END OF REPORT
- PERIOD, ESTIMATED DATE OF START UP:
26.
UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
FORECAST ACHIEVED INITlALCRITICALITY INITIAL ELEC TRICITY COMMERCIAL OPERATIOH MEM/DATREPa/2/OS4 1.16 9
I I
CPhL CO RUN DATE RUN TINE 03/07/93 34:27:58 PLANT PERFORMANCE DATA SYSTEH APPENDIX B AVERAGE DAILY POWER LEVEL HARRIS UNIT 3
PAGE RPD39-000 FEBRUARY 199'3 DAY AVG. DAILY POWER I EVEL (MWE-NET)
DOCKET NO. 050-400 CONPLETED BY HARK W.
HALE TELEPHONE (919)362-2944 DAY AVG. DAILY POWER LEVEL (HWE-NET) 882 SSO 823 17 29 874 872 873 873
$ 0 851 804 859 875 875 877 877 MEM/DATREPa/3/OS4
a
UNIT SHUTDOWNS AND POWER REDUCTION REPORT MONTH:
February 1991 UNIT NAME:
Harris DATE:
3/7/91 COMPLETED BY:
M. W. Hale TELEPHONE:
(919) 362"2944 No.
Date TI y
P e
Duration (Hours)
R Method of Shutting Down Reactor Licensee Event Report f System Code 4
Component Code 5
Cause 8, Corrective Action to Prevent Recurrence 91-002 910203 0.0 HA VALVE Reduced unit power to 70$ to perform turbine valve testing.
Unit was returned to 100$ power on 2-3-91.
I F: Forced S: Scheduled 2
Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training 8, License Examination F-Administrative G-Operational Error (Explain) 3 Method:
I-Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Reduced Load 6-Other 4
Exhibit G-Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161) 5 Exhibit I - Same Source MEM/DATAREPa/4/OS4
UNIT SHUTDOWNS AND POWER REDUCTION REPORT MONTH:
February 1991 UNIT NAME:
Harris DATE:
3/7/91 COMPLETED BY:
M. W. Hale TELEPHONE:
(919) 362-2944 No.
Date Tl y
p e
Duration (Hours)
Method of Shutting Down Reactor Licensee Event Report f System Code 4
Component Code 5
Cause 4 Corrective Action to Prevent Recurrence 91-003 910224 0.0 N/A HC PIPE Reduced unit power to "305 power due to a tube leak in the west side of the condenser.
One leaking tube was plugged.
Eight additional tubes in adjacent areas were plugged to prevent future problems.
Unit was returned to full load on 2-26-91.
1 F:
Forced S:
Scheduled 2
Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training 8, License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain) 3 Method:
I-Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Reduced Load 6-Other 4
Exhibit G-Instructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161) 5 Exhibit I - Same Source MEM/DATAREPa/5/OS4