Line 16: |
Line 16: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:oEntergy Nuclear Operations, Inc.Vermont Yankee 320 Governor Hunt Rd Erteig" TVernon, VT 05354 Tel 802 257 7711 Christopher J. Wamser Site Vice President SVY 15-001 January 12, 2015 Mr. Christopher Recchia, Commissioner Vermont Public Service Department 112 State Street Montpelier, VT 05620-2601 | | {{#Wiki_filter:oEntergy Nuclear Operations, Inc. |
| | Vermont Yankee Erteig" 320 Governor Hunt Rd TVernon, VT 05354 Tel 802 257 7711 Christopher J. Wamser Site Vice President SVY 15-001 January 12, 2015 Mr. Christopher Recchia, Commissioner Vermont Public Service Department 112 State Street Montpelier, VT 05620-2601 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| Certifications of Permanent Cessation of Power Operations/Permanent Removal of Fuel from the Reactor Vessel and Establishment of Credit Agreements | | Certifications of Permanent Cessation of Power Operations/Permanent Removal of Fuel from the Reactor Vessel and Establishment of Credit Agreements - Vermont Yankee Nuclear Power Station |
| -Vermont Yankee Nuclear Power Station | |
|
| |
|
| ==Dear Mr. Recchia:== | | ==Dear Mr. Recchia:== |
| This letter is to inform the Vermont Public Service Department that Entergy Nuclear Operations, Inc. (ENO) has certified that the fuel has been permanently removed from the Vermont Yankee Nuclear Power Station ("VYNPS") | | |
| reactor vessel and placed in the spent fuel pool on January 12, 2015. ENO also certified to the NRC that VYNPS permanently ceased power operations on December 29, 2014. These certifications notify the NRC that VYNPS will no longer operate the reactor nor retain any fuel in the reactor vessel.Entergy would also like to inform the Department that Entergy Nuclear Vermont Yankee ("ENVY") closed on two credit facilities that will permit it to complete the planned spent nuclear fuel (SNF) loading campaign activities through the year 2020. This financial strategy should permit ENVY to minimize the use of the Nuclear Decommissioning Trust (NDT) from being utilized for those activities. | | This letter is to inform the Vermont Public Service Department that Entergy Nuclear Operations, Inc. (ENO) has certified that the fuel has been permanently removed from the Vermont Yankee Nuclear Power Station ("VYNPS") reactor vessel and placed in the spent fuel pool on January 12, 2015. ENO also certified to the NRC that VYNPS permanently ceased power operations on December 29, 2014. These certifications notify the NRC that VYNPS will no longer operate the reactor nor retain any fuel in the reactor vessel. |
| | Entergy would also like to inform the Department that Entergy Nuclear Vermont Yankee |
| | ("ENVY") closed on two credit facilities that will permit it to complete the planned spent nuclear fuel (SNF) loading campaign activities through the year 2020. This financial strategy should permit ENVY to minimize the use of the Nuclear Decommissioning Trust (NDT) from being utilized for those activities. |
| Should you have any questions regarding this information, please contact Joseph Lynch, Manager, Government Affairs, at 802-258-4107. | | Should you have any questions regarding this information, please contact Joseph Lynch, Manager, Government Affairs, at 802-258-4107. |
| Sincerely, CJW / jrl cc: Mr. Anthony R. Leshinskie State Nuclear Engineer & Decommissioning Coordinator Vermont Public Service Department 112 State Street Montpelier, VT 05620-2601}} | | Sincerely, CJW / jrl cc: Mr. Anthony R. Leshinskie State Nuclear Engineer & Decommissioning Coordinator Vermont Public Service Department 112 State Street Montpelier, VT 05620-2601}} |
|
---|
Category:Letter
MONTHYEARBVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000271/20220022023-02-22022 February 2023 Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station - NRC Inspection Report No. 05000271/2022002 BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond ML22347A2792022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 IR 05000271/20224012022-12-15015 December 2022 NRC Inspection Report No. 05000271/2022401, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont (Letter Only) BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection BVY 22-027, Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station2022-11-11011 November 2022 Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station BVY 22-026, Pre-Notice of Disbursement from Decommissioning Trust2022-10-31031 October 2022 Pre-Notice of Disbursement from Decommissioning Trust ML22273A1492022-10-0404 October 2022 Review of Decommissioning Funding Status 2022 BVY 22-025, Pre-Notice of Disbursement from Decommissioning Trust2022-10-0404 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-023, Pre-Notice of Disbursement from Decommissioning Trust2022-09-0101 September 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-022, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-22022 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-16016 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-020, Pre-Notice of Disbursement from Decommissioning Trust2022-08-0101 August 2022 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20220012022-08-0101 August 2022 NRC Inspection Report No. 05000271/2022001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 22-019, Pre-Notice of Disbursement from Decommissioning Trust2022-07-0606 July 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022 Notification of Revised Decommissioning Cost Estimate 2024-01-04
[Table view] |
Text
oEntergy Nuclear Operations, Inc.
Vermont Yankee Erteig" 320 Governor Hunt Rd TVernon, VT 05354 Tel 802 257 7711 Christopher J. Wamser Site Vice President SVY 15-001 January 12, 2015 Mr. Christopher Recchia, Commissioner Vermont Public Service Department 112 State Street Montpelier, VT 05620-2601
SUBJECT:
Certifications of Permanent Cessation of Power Operations/Permanent Removal of Fuel from the Reactor Vessel and Establishment of Credit Agreements - Vermont Yankee Nuclear Power Station
Dear Mr. Recchia:
This letter is to inform the Vermont Public Service Department that Entergy Nuclear Operations, Inc. (ENO) has certified that the fuel has been permanently removed from the Vermont Yankee Nuclear Power Station ("VYNPS") reactor vessel and placed in the spent fuel pool on January 12, 2015. ENO also certified to the NRC that VYNPS permanently ceased power operations on December 29, 2014. These certifications notify the NRC that VYNPS will no longer operate the reactor nor retain any fuel in the reactor vessel.
Entergy would also like to inform the Department that Entergy Nuclear Vermont Yankee
("ENVY") closed on two credit facilities that will permit it to complete the planned spent nuclear fuel (SNF) loading campaign activities through the year 2020. This financial strategy should permit ENVY to minimize the use of the Nuclear Decommissioning Trust (NDT) from being utilized for those activities.
Should you have any questions regarding this information, please contact Joseph Lynch, Manager, Government Affairs, at 802-258-4107.
Sincerely, CJW / jrl cc: Mr. Anthony R. Leshinskie State Nuclear Engineer & Decommissioning Coordinator Vermont Public Service Department 112 State Street Montpelier, VT 05620-2601