Press Release-13-102, NRC Approves Power Uprate for Monticello Nuclear Power Plant in Minnesota: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 12/11/2013
| issue date = 12/11/2013
| title = Press Release-13-102: NRC Approves Power Uprate for Monticello Nuclear Power Plant in Minnesota
| title = Press Release-13-102: NRC Approves Power Uprate for Monticello Nuclear Power Plant in Minnesota
| author name = McIntyre D T
| author name = Mcintyre D
| author affiliation = NRC/OPA
| author affiliation = NRC/OPA
| addressee name =  
| addressee name =  

Revision as of 19:46, 21 June 2019

Press Release-13-102: NRC Approves Power Uprate for Monticello Nuclear Power Plant in Minnesota
ML13345A079
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/11/2013
From: David Mcintyre
Office of Public Affairs
To:
References
Press Release-13-102
Download: ML13345A079 (1)


Text

No: 13-102 December 11, 2013 CONTACT: David McIntyre, 301

-415-8206 NRC Approves Power Uprate for Monticello Nuclear Power Plant in Minnesota The Nuclear Regulatory Commission has approved a request by Northern States Power Co. to increase the generating capacity of the Monticello nuclear power plant in Minnesota.

Northern States applied for the extended power uprate in November 2008. The license amendment, approved Dec. 9, allows the plant to increase its maximum core thermal power level from 1,775 megawatts thermal (MWt) to 2,004 MWt. This equates to an expected increase in electrical output from 600 megawatts electric (MWe) to 671 MWe. The NRC staff's review of the uprate plan included two unique issues: a Westinghouse

-designed steam dryer in use at the plant since 2011; and crediting containment accident pressure (CAP) in predicting the performance of emergency core cooling pumps during an accident. Monticello is the first U.S. plant to use the Westinghouse steam dryer, although the design has been in use in nine European nuclear plants over the past 25 years.

On CAP, the staff concluded that Northern States properly applied NRC guidance but noted that the issue may need to be revisited because of ongoing post-Fukushima actions.

Northern States expects to implement the uprate this month. That will require certain modifications to handle increased flows, heat transfer and power utilization. NRC's Resident Inspectors and special inspectors from the Region III office in Illinois will be at the plant to monitor the uprate implementation.