| | issue date = 09/09/1977 | | | issue date = 09/09/1977 |
| | title = Forwards Reformat of Quality Assurance Program Description for QA Activities During Design, Construction and Operation | | | title = Forwards Reformat of Quality Assurance Program Description for QA Activities During Design, Construction and Operation |
| | author name = Uhrig R E | | | author name = Uhrig R |
| | author affiliation = Florida Power & Light Co | | | author affiliation = Florida Power & Light Co |
| | addressee name = Boyd R S | | | addressee name = Boyd R |
| | addressee affiliation = NRC/NRR | | | addressee affiliation = NRC/NRR |
| | docket = 05000389, 05000335 | | | docket = 05000389, 05000335 |
|
---|
Category:Letter
MONTHYEARIR 05000335/20240032024-11-0707 November 2024 Integrated Inspection Report 05000335/2024003 and 05000389/2024003 ML24291A2862024-11-0101 November 2024 – Relief Request: Proposed Alternative in Accordance with 10 CFR 50.55a(Z)(1), Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-167, Correction to St. Lucie L-2024-132, 2024 Population Update Analysis2024-10-22022 October 2024 Correction to St. Lucie L-2024-132, 2024 Population Update Analysis IR 05000335/20250102024-10-21021 October 2024 Notification of St. Lucie Plant Units 1 & 2 Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000335/2025010 and 05000389/2025010 ML24227A9702024-10-18018 October 2024 Letter to Kenneth Mack Dir, License and Reg Compliance, NextEra Energy, Inc Response to Request Re Engagement Re Sub License Renewal Environmental Review - St Lucie Nuclear Plant 1 and 2 L-2024-085, Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results2024-10-15015 October 2024 Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-165, Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made2024-10-14014 October 2024 Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) ML24255A3092024-09-30030 September 2024 SLRA - Revised SE Letter L-2024-155, Subsequent License Renewal Application, Third Annual Update2024-09-27027 September 2024 Subsequent License Renewal Application, Third Annual Update L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes 05000335/LER-2024-001, Unplanned Reactor Scram2024-09-25025 September 2024 Unplanned Reactor Scram IR 05000335/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000335/2024011 and 05000389/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-138, License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles2024-09-11011 September 2024 License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles L-2024-148, Submittal of Offsite Dose Calculation Manual (Odcm), Revision 552024-09-0909 September 2024 Submittal of Offsite Dose Calculation Manual (Odcm), Revision 55 ML24228A2962024-09-0606 September 2024 NRC to NMFS, Designation of FPL as the Non-Federal Representative for St. Lucie IR 05000335/20240052024-08-22022 August 2024 Updated Inspection Plan for St. Lucie, Units 1 & 2 - Report 05000335/2024005 and 05000389/2024005 L-2024-133, Snubber Program Plan Submittal2024-08-14014 August 2024 Snubber Program Plan Submittal L-2024-140, Cycle 28 Core Operating Limits Report2024-08-14014 August 2024 Cycle 28 Core Operating Limits Report L-2024-132, 2024 Population Update Analysis2024-08-13013 August 2024 2024 Population Update Analysis IR 05000335/20240022024-08-13013 August 2024 Integrated Inspection Report 05000335-2024002 and 05000389-2024002 L-2024-129, Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval2024-08-0707 August 2024 Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval 05000389/LER-2024-003, Unplanned Reactor Scram2024-08-0505 August 2024 Unplanned Reactor Scram ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-121, Subsequent License Renewal Commitment 30 Revision2024-07-30030 July 2024 Subsequent License Renewal Commitment 30 Revision L-2024-123, Submittal of In-Service Inspection Program Owners Activity Report (OAR-1)2024-07-29029 July 2024 Submittal of In-Service Inspection Program Owners Activity Report (OAR-1) L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000389/LER-2024-002-01, Safety Injection Tank Vent Through Wall Leakage2024-07-11011 July 2024 Safety Injection Tank Vent Through Wall Leakage L-2024-110, Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake2024-07-10010 July 2024 Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-109, Schedule for Subsequent License Renewal Environmental Review2024-07-0303 July 2024 Schedule for Subsequent License Renewal Environmental Review ML24172A1562024-06-27027 June 2024 Relief Request - PSL2-I5-RR-01 Proposed Alternative to Amse Code XI Code Examination Requirements - System Leakage Test of Reactor Pressure Vessel Bottom Head and Class 1 and 2 Piping in Covered Trenches L-2024-104, Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 102024-06-26026 June 2024 Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 L-2024-097, Technical Specification Special Report2024-06-20020 June 2024 Technical Specification Special Report L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-090, Revised Steam Generator Tube Inspection Reports2024-06-0404 June 2024 Revised Steam Generator Tube Inspection Reports IR 05000335/20244012024-06-0303 June 2024 Security Baseline Inspection Report 05000335/2024401 and 05000389/2024401 ML24135A0642024-05-17017 May 2024 Correction Letter - Amendment Nos. 253 and 208 Regarding Conversion to Improved Standard Technical Specifications L-2024-075, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-05-13013 May 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation IR 05000335/20240012024-05-10010 May 2024 Integrated Inspection Report 05000335/2024001 and 05000389/2024001 ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-053, License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis2024-04-30030 April 2024 License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis L-2024-070, Cycle 32 Core Operating Limits Report2024-04-29029 April 2024 Cycle 32 Core Operating Limits Report L-2024-071, Cycle 27 Core Operating Limits Report2024-04-29029 April 2024 Cycle 27 Core Operating Limits Report 2024-09-09
[Table view] Category:Topical Report
MONTHYEARL-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal L-2022-082, NextEra Energy Seabrook, LLC, and NextEra Energy Point Beach, LLC, Quality Assurance Topical Report FPL-1, Revision 282022-05-23023 May 2022 NextEra Energy Seabrook, LLC, and NextEra Energy Point Beach, LLC, Quality Assurance Topical Report FPL-1, Revision 28 L-2021-234, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 27 Update2021-12-15015 December 2021 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 27 Update L-2021-115, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 26 Annual Submittal and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 102021-05-24024 May 2021 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 26 Annual Submittal and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 10 L-2016-129, NextEra Energy Quality Assurance Topical Report (QATR FPL-1) Revision 19 Annual Submittal2016-06-22022 June 2016 NextEra Energy Quality Assurance Topical Report (QATR FPL-1) Revision 19 Annual Submittal ML15356A1852015-12-31031 December 2015 ANP-3456NP, Revision 0, Response to SLU2 NRC Snpb RAI-9, Licensing Report. L-2015-160, WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 3 of 32015-05-31031 May 2015 WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 3 of 3 L-2015-160, WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 2 of 32015-05-31031 May 2015 WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 2 of 3 ML15154B0772015-05-31031 May 2015 WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 1 of 3 ML15154B0792015-05-31031 May 2015 WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 2 of 3 L-2015-160, WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 1 of 32015-05-31031 May 2015 WCAP-17939-NP, Revision 0, Analysis of Capsule 97 Degrees from the Florida Power & Light Company St. Lucie, Unit 2, Reactor Vessel Radiation Surveillance Program, Part 1 of 3 L-2013-208, Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 132013-07-0101 July 2013 Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 13 L-2011-418, ANP-2903Q1(NP), Revision 0, St Lucie Nuclear Plant Unit 1 EPU Cycle Realistic Large Break LOCA Summary Report with Zr-4 Fuel Cladding.2011-09-30030 September 2011 ANP-2903Q1(NP), Revision 0, St Lucie Nuclear Plant Unit 1 EPU Cycle Realistic Large Break LOCA Summary Report with Zr-4 Fuel Cladding. L-2010-138, Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 72010-06-28028 June 2010 Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 7 L-2010-078, ANP-2903(NP), Rev. 0, St. Lucie Nuclear Plant Unit 1 EPU Cycle Realistic Large Break LOCA Summary Report with Zr-4 Fuel Cladding.2010-04-16016 April 2010 ANP-2903(NP), Rev. 0, St. Lucie Nuclear Plant Unit 1 EPU Cycle Realistic Large Break LOCA Summary Report with Zr-4 Fuel Cladding. ML1011601972010-04-16016 April 2010 ANP-2903(NP), Rev. 0, St. Lucie Nuclear Plant Unit 1 EPU Cycle Realistic Large Break LOCA Summary Report with Zr-4 Fuel Cladding. L-2010-078, WCAP-17197-NP, Rev. 0, St. Lucie Unit 1 RCS Pressure & Temperature Limits & Low-Temperature Overpressure Protection Report for 54 Effective Full Power Years.2010-02-28028 February 2010 WCAP-17197-NP, Rev. 0, St. Lucie Unit 1 RCS Pressure & Temperature Limits & Low-Temperature Overpressure Protection Report for 54 Effective Full Power Years. ML1011602042010-02-28028 February 2010 WCAP-17197-NP, Rev. 0, St. Lucie Unit 1 RCS Pressure & Temperature Limits & Low-Temperature Overpressure Protection Report for 54 Effective Full Power Years. ML1035604482010-02-28028 February 2010 St. Lucie, Unit 1 - Extended Power Uprate Licensing Report, Attachment 5; Appendix G, WCAP-17197-NP, Revision 0, RCS Pressure and Temperature Limits and Low-Temperature Overpressure Protection Report for 54 Effective Full Power Years L-2010-259, Extended Power Uprate Licensing Report, Attachment 5; Appendix G, WCAP-17197-NP, Revision 0, RCS Pressure and Temperature Limits and Low-Temperature Overpressure Protection Report for 54 Effective Full Power Years2010-02-28028 February 2010 Extended Power Uprate Licensing Report, Attachment 5; Appendix G, WCAP-17197-NP, Revision 0, RCS Pressure and Temperature Limits and Low-Temperature Overpressure Protection Report for 54 Effective Full Power Years L-2009-134, Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 42009-06-29029 June 2009 Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 4 L-2008-150, Duane Arnold, and Point, Beach, Units 1 and 2, Quality Assurance Topical Report (QATR-FPL-1) Revisions 1 & 22008-06-27027 June 2008 Duane Arnold, and Point, Beach, Units 1 and 2, Quality Assurance Topical Report (QATR-FPL-1) Revisions 1 & 2 L-2007-110, Topical Quality Assurance Report (Fpltqar 1-76A)2007-07-0909 July 2007 Topical Quality Assurance Report (Fpltqar 1-76A) L-2006-246, Response to RAI Follow-Up Questions Regarding Fpl'S Common Quality Assurance Topical Report Request2006-11-15015 November 2006 Response to RAI Follow-Up Questions Regarding Fpl'S Common Quality Assurance Topical Report Request L-2006-164, Topical Quality Assurance Report (Fpltqar 1-76A)2006-06-30030 June 2006 Topical Quality Assurance Report (Fpltqar 1-76A) L-2006-067, Request for Approval of FPL Quality Assurance Topical Report2006-03-31031 March 2006 Request for Approval of FPL Quality Assurance Topical Report ML0527906922005-10-31031 October 2005 WCAP-16489-NP, Revision 0, St. Lucie Unit 2, 42-Percent Steam Generator Tube Plugging Licensing Report. L-2004-233, Westinghouse WCAP-15918-NP, Revision 2, Steam Generator Tube Repair for Combustion Engineering and Westinghouse Designed Plants with 3/4 Inch Inconel 600 Tubes Using Leak Limiting Alloy 800 Sleeves.2004-07-31031 July 2004 Westinghouse WCAP-15918-NP, Revision 2, Steam Generator Tube Repair for Combustion Engineering and Westinghouse Designed Plants with 3/4 Inch Inconel 600 Tubes Using Leak Limiting Alloy 800 Sleeves. ML0332302252003-11-12012 November 2003 Submittal of WCAP-16084-NP, Development of Risk-Informed Safety Analysis Approach and Pilot Application. ML0316107892003-05-31031 May 2003 Addendum 1 to WCAP-15306-NP-A, Addendum 1 to WCAP-15306-NP-A Qualification of Abb Critical Heat Flux Correlations with VIPRE-01 Code. L-2003-101, WCAP-16038-NP, Revision 0, Structural Integrity Evaluation or Reactor Vessel Upper Head Penetrations to Support Continued Operation: St. Lucie Unit 2, Table of Contents Through Figure 6.242003-03-31031 March 2003 WCAP-16038-NP, Revision 0, Structural Integrity Evaluation or Reactor Vessel Upper Head Penetrations to Support Continued Operation: St. Lucie Unit 2, Table of Contents Through Figure 6.24 L-2003-002, to Topical Report WCAP-15975-NP, NDE Inspection Strategy for the Tubesheet Region in St. Lucie Unit 2.2002-11-30030 November 2002 to Topical Report WCAP-15975-NP, NDE Inspection Strategy for the Tubesheet Region in St. Lucie Unit 2. ML0300205482002-11-30030 November 2002 WCAP-15945-NP, Rev. 1, Structural Integrity Evaluation of Reactor Vessel Upper Head Penetrations to Support Continued Operation: St. Lucie Unit 1. ML0223901832002-08-15015 August 2002 Combustion Engineering Owners Group Request for Review of CE Owners Group Report WCAP-15691 Rev 03, Joint Applications Report for Containment Integrated Leak Rate Test Interval Extension. L-2002-082, Part 2 of 2, St. Lucie, Unit 1 - Reactor Vessel Surveillance Capsule, Report of Test Results - Revision 1, Appendix B, Charpy V-Notch Plots for Each Capsule Using Hyperbolic Tangent Curve-Fitting Method2002-05-0202 May 2002 Part 2 of 2, St. Lucie, Unit 1 - Reactor Vessel Surveillance Capsule, Report of Test Results - Revision 1, Appendix B, Charpy V-Notch Plots for Each Capsule Using Hyperbolic Tangent Curve-Fitting Method ML18127A5261977-09-0909 September 1977 Forwards Reformat of Quality Assurance Program Description for QA Activities During Design, Construction and Operation 2024-07-10
[Table view] |
Text
NRC FORM 195 I2-76'), I p\.'(gRC DISTRIBUTION FoR PART 50 DOCKET MATERIAL DOCKET NUMBER-as%FILE NUMBER PSAR/FSAR AMDT DIST.TO: jBLETTE R ABORIGINAL Q COPY DESCRIPTION R S Boyd 0 NOTO 8 IZE D BGNC LASS I FIED PROP'lorida Power 6 Light Co Miami, Fla R E Uhrig INPUT FORM ENCl QSURE DATE OF DOCUMENT 9-9-77 DATE RECEIVED 9-14-77 NUMBER OF COPIES RECEIVED S lCQ Reformat of Quality Assurance Program Descript re FELTQAR 1-76A for use during construction design&operation,""~~~~2p 10P PLANT NAME: St Luci,e g2 9-14-77 ehf ASSIGNED AD: LTR BK4%CH CHIEF: PROJECT MANAGER'ICE I G ASST: LTR QO EvCL.IQ l?KPIZaeucS5 FOR ACTION/INFORMATION RC PDR I G E LAINAS IPPOLITO F.ROSA INTERNAL DISTR I BUTION P.COLLINS HOUSTON HELTEMES CASE (L'ZR)MIPC LTR KNIGHT LTR)BOSNAK SIHIKIL PANLICKI ROSS LTR NOVAK ROSZTOCZY CHECK TEDESCO LTR BENAROYA LPDRl~TIC NSIC ACRS 16 CYS SENT CAT GAIIMILL (2 VOLLIIER (LTR)BUNCH J.COLLINS KREGER EXTERNAL DISTRIBUTION G RY CONTROL NUMBER t>>d gii f P.O.BOX 013100, MIAMI, FL 33101 0 ivory%FLORIDA POWER 8E LIGHT COMPANY Office of Nuclear Reactor Regulation Attn: Mr..Roger S.Boyd, Director Division of Project Management U.S.Nuclear Regulatory Commission Washington, D.C.20555
Dear Mr.Boyd:
Re: St.Lucie Plant Unit No.2 Docket No.50-389 Qualit Assurance Pro ram Septembe 1977 L 77 2 6 SEP 141977~.i g~MUCH R~~>~II<COmA1SSleII
~J~tM r fQ The Florida Power&Light Company Topical Quality Assurance Report (FPLTQAR 1-76A)describes a generic Quality Assurance Program for all existing and future nuclear generating stations at Florida Power&Light.This report, has been reviewed by the Nuclear Regula-tory Commission and has received its approval.Our intent to ul-timately apply the Topical QA Report.to St.Lucie Unit No.2 has been stated in the report, and the desirability of doing this has been expressed previously by members of your staff.Xn accordance with our policy of utilizing the Topical QA Report where appropriate, we are herewith submitting a reformat of the Quality Assurance Pro-gram description for QA activities during design, construction and operation for St.Lucie Unit No.2'PSL-2).The PSL-2 Quality Assurance Program is described in the attachment to this letter, which specifically add'resses details applicable only to PSL-2,'and the Topical.Quality Assurance Report (FPLTQAR 1-76A).Xn combination, these documents are.responsive to the"Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants," and are, therefore, being implemented in place of the existing information in Chapter 17 of the PSL-2 Preliminary Safety Analysis Report.As described below, this represents an aug-mentation of the existing program for PSL-2.These documents will be incorporated by reference'into Chapter 17 of the PSL-2 Final Safety Analysis Report.Xt is FPL's policy to have direct control of quality-related activities where possible.'In keeping with this policy, we had previously assumed control of the audit, inspection, and verifica-tion functions on site in the area of construction.
This increased responsibility was determined to be satisfactory to=the NRC staff as discussed in Supplement 1 to the St.Lucie Unit, 2 Safety Evaluation Report.Florida Power&Light is now additionally assuming direct responsibility for all.site construe'tion activities,-'with the exception of design engineering and craft labor relations which'ill continue to be the responsibility of Ebasco Services,, Xnc.Under this PEOPLE...SERVING PEOPLE 0 F/P), t1 Office of Nuclear Reactor Regulation Attn: Mr.Roger S.Boyd, Director Division of Project Management Page Two September 9, 1977 L-77-286 organization, the responsible job-site individual will be a Florida Power 6 Light Company representative.
All quality-related site activities will be performed under the guidance of the FPL Topical QA Report.The off-site and Combustion Engineering functions will continue to be performed as specified in the PSL-2 PSAR.Very truly yours, Robert E.Uhrig Vice President REU/LLL:ltm Attachment cc: J.P.O'Reilly, Region II C.J.Heltemes Robert L.Lowenstein, Esq.M.H.Hodder, Esq.
ST.LUCIE UNIT 2 QUALITY ASSURANCE l.0 GENERAL The overall organization chart"for the St.Lucie project is shown on Figures 1 and 2.2.0 FLORIDA POWER 6 LIGHT (FPL)QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION The generic elements of the FPL Quality Assurance Program are described in the FPL Topical Quality Assurance Report (FPLTQAR 1-76A).The Topical QA Report defines departmental responsibilities by which FPL implements the corporate QA Program and is an integral part of the corporate Quality Assurance Manual (FPL-NQA-100).
Additionally, the FPL Topical Quality Assurance Report defines the guidance documents the QA Program follows.The following additional information and exceptions are applicable to the St.Lucie Unit 2 Project.FPL Construction Quality Control Organization.
The FPL On-Site Construction Quality Control organization is shown in Figure 3.The function and,responsibilities of the Area Quality Control Supervisors and Quality Control Supervisor (Receipt Inspection) are: Assure that all construction, in the Quality Control Supervisor's assigned area (mechanical, electrical,"civil or receipt inspection)
'is completed in accordance with the approved'rocedures.
%his includes coordination with the on-site contractors in the scheduling of inspections, ensuring adequate completion of inspections and inspection documentation and technical direction for assigned QC personnel'.
The Area Quality Control Supervisor recommends Stop Work to the Project Quality Control Supervisor if the situation dictates.b.Procurement Document Control.During the construction phase, FPL delegates to the Architect Engineer and the NSSS Supplier the responsibility for ensuring that correct technical and quality requirements are incorporated into procurement documents for items they procure.'PL will perform the field procurement functions in accordance with TQR 4.0 and 7.0 of the FPLTQAR.
ST.LUCXE UNXT 2 Quality Assurance Page Mo c.Control of Special Processes.
During plant construction the FPL Construction organization will be responsible for welding control.This includes review of procedures, inspection, qualification of welders and welding operations and weld material control.During construction, the FPL Construction Quality Control Organization is responsible for the approval and qualification of NDE procedures and assuring qualification.
and certification of NDE personnel.
d.Inspection.
During construction, the FPL On-Site Construction Quality Control organization performs on-site receiving in-process and final inspections in accordance with TQR 10.0 of the FPLTQAR.e.Test Control.the FPL Test Control Program for construction is described in TQR 11.0 of the FPLTQAR.f.Control of Measuring and Test Equipment.
During construction,'he FPL On-Site Construction Quality Control organization is responsible for the control, calibration and maintenance of measuring and test equipment in accordance with TQR 12.0 of the FPLTQAR.g.Handling, Storage and Shipping.During construction, the FPL Stores Department is responsible for on-site handling, storage, disbursal from stores, and shipping of stored items, in accordance with TQR 8.0 and 13.0 of the FPLTQAR.h.Nonconforming Materials, Parts and Components.
During construction, the FPL On-Site Construction Quality Control organization controls nonconforming materials, parts and components as described in TQR 15.0 of the FPLTQAR.i.Quality Assurance Records.During construction, FPL is responsible for the receipt, review, and storage of QA records retained on-site in accordance with TQR 17.0 of.the FPLTQAR.FPL QA Construction has responsibility as custodian of all QA records on-site until turned over to operating personnel.
The responsibility for retention of off-site design and procurement records is delegated to the Architect-Engineer and NSSS supplier and maintained in accordance with KQR 17.0.
ST.LUCIE UNIT 2 QUALITY ASSURANCE PAGE i'three j.Audits.During construction, the FPL Quality Assurance Department is.responsible for conducting an audit program as specified in'XQR 18.0 of the FPLTQAR including the audit of all on-site quality related activities.
UALITY ASSURANCE DURING THE OPERATIONS PHASE The generic elements of the FPL Quality Assurance Program are described in the FPL Topical Quality Assurance Report (FPLTQAR).The Topical QA Report defines departmental responsibilities by which FPL implements the Corporate QA Program, and is an integral part of the Corporate Quality Assurance Manual (FPL-NQA-100).
Additionally, the FPL Topical Quality Assurance Report defines the guidance documents the QA Program follows.The Topical Quality Assurance Report is, therefore, referenced by this letter, and only information which is in addition to that found in the Topical QA Report is contained herein.1.0 ORGANIZATION The FPL organizational structure, including the Plant Manager, is described in the FPL Topical Quality Assurance Report (TQR 1.0).Ihe St.Lucie Unit 2 Plant staff organization below the Plant Manager'is shown in Figure 4 attached.Plant Manager The Plant Manager has the direct responsibility for implementing Quality Assurance requirements for the Power Resources Department at the St.Lucie Unit 2 Plant.uality Control Supervisor Thh Plant Quality Control Supervisor is responsible for planning and administering.the Plant Quality Control Program which comprises inspection, monitoring, and surveillance of quality-related Power Resources activities on site.Lines of communication between the Quality Control Supervisor and the plant staff have not been indicated in Figure 4 because the Quality Control Supervisor'has the authority and freedom to communicate with all levels of the plant staff and line management involved with activities affecting the quality of nuclear safety-related structures, systems, E and components; The Quality Control Supervisor reports to the Plant I Manager and has sufficient authority to stop nonconforming work or operations.
Additional responsibilities of the Quality Control Supervisor include: a)providing guidance in the interpretation of federal regulations related to the Quality Assurance Program, and , provide guidance in other administrative requirements involving quality assurance activities; b)serving as the plant interface with the Quality Assurance Department and Nuclear Regulatory Commission inspectors; c)tracking plant nonconformances, inspection and audit open items;d)advising plant management, including the Plant Manager if necessary, of the need for timely corrective action;e)maintaining adequate records of quality-related site activities; f)and distributing and controlling plant procedures, instructions,:
and approved drawings.Plant Quality Control Department engineers and inspectors receive functional and administrative direction from the Quality Control Supervisor.
In addition to members of the Quality Control Department, experienced individuals in other plant departments who are qualified and certified as Quality Control inspectois, may function in a Quality Control role.When so functioning, the individuals do not perform or directly supervise the performance of, the activity being inspected.
16.0 CORRECTIVE ACTXON The controls which assure timely corrective action of open items identified by the Quality Assurance Department, and unresolved items and items of non-compliance identified by the Nuclear Regulatory Commission, are described in the PPL Topical Quality Assurance Report (TQR 16.0).Plant corrective action tracking of nonconformance and audit or inspection open items, including items identified during Plant Quality Gontrol inspections, are documented and tracked in accordance with Plant Administrative Procedures.
These Administrative Procedures require that Quality.Gontrol inspections are performed, using inspection forms or checklists approved by the Quality Control Supervisor, with inspection results reported to the Quality Control Supervisor.
Open items against the Plant, from all inspection sources, are tracked by the Plant Quality Control Department:, which transmits periodic status reports of all open items to the Plant Manager and Plant personnel responsible for corrective action.In addition, Plant Quality Control performs open item follow-up activities to obtain corrective action commitments and obtain the status of open commitments.
This tracking activity does not end until the corrective action committed to, has been accomplished.
'1 I'F PROJECT GENERAL MANAGER COST AND SCHEDULE STAFF CORPORATE SERVICES For Project Staff Support MIAMI MANAGER (ASST.PGM)NEW YORK MANAGER (ESQSCO PROJ.(MGRII QUALITY ASSURANCE PROJECT COORD.Engineering Project Manager General Engineering Team Member Environmental Team Member Licensing Team Member Contract Coordinator Purchasing Team Member Project Engineer Project Cost Engineer Project Purchasing Agent Lead Project Planner New York Q.A.Supervisor Sched.Analyst SITE MANAGER QUALITY ASSURANCE ADMINIS-TRATIVE ASSISTANT PROJECT DIRECTION j I Starts p Supervisor Project Quality Control Supervisor Construction Controland Coordinator Supt.Senior Resident Engineer Project Supt.Security Supervisor Services Supt, Site Project Engineer Functional Reporting Project Direction ST.LUCIE PLANT NO.2 PROJECT ORGANIZATION CHART FIGURE 1 li V l Florida Power 5 Light Dir.of Projects Supervision
-Administration of Work Assignments Routine Reporting of Quality Assurance Information FPL QUALITY ASSURANCE (SITE)FPL PROJECT QC SUPV.(SITE)L I I I J FPL SITE MANAGER Construction Control;Coord.Senior Resident Eng.Project Supt.Startup Supt.Services Supt.Security Supv.FPL MIAMI MANAGER (ASST.PGM)Eng.Protect.Mgr.General Eng.Environmental Licensing Purchasing FPL QUALITY ASSURANCE.(MIAMI)I I I I I I'I I I l l New York Manager (Ebasco Project Manager)Ebasco N.Y.Quality Assurance Organization I l I I I I I Florida Power 5 Light Project General Mgr.Combustion Engineering Project Manager Con:bustion Engineering Quality Assurance Organization I L I I Component Suppliers Containment Sub-Contractor Combustion Engineering Nuclear Steam Supply System CONSTRUCTION QUALITY ASSURANCE ORGANIZATION ST.LUCIE PLANT NO.2 FIGURE 2 SUPERINTENDENT QUALITY CONTROL CONSTRUCTION PROJECT QUALITY CONTROL SUPERVISOR Home Office Site AREA QUALITY CONTROL SUPV.AREA QUALITY CONTROL SUPV.AREA QUALITY CONTROL SUPV.QUALITY CONTROL SUPV.INSPECTORS INSPECTORS INSPECTORS INSPECTORS Sf.LUCIE PLANT NO.2 QUALITY CONTROL ORGAN IZATION FIGURE 3' PLANT MANAGER MAINTENANCE SUPT.TECHNICAL STAFF SECURITY SUPV ADMINISTRATIVE SUPV OPERATIONS SUPT QUALITY CONTROL SUPV ASST.MGR.QA OPERATING PLANTS OFF SITE ON SITE INSTRUMENT
&CONTROL SUPV ASST PLANT SUPT ELECTRICAL ASST PLANT SUPT MECHANICAL FACILITY REVIEW GROUP CHEMISTRY SUPV HEALTH PHYS SUPV REACTOR SUPV QC ENGRS.&INSPECTORS DOCUMENT CONTROL SUPV QA OPERATING PLANTS.QA ENGINEERS TRAINING SUPV OPERATIONS SUPV Administrative Reporting Communications FIGURE 4 ST.LUCIE PLANT PLANT QUALITY CONTROL ORGANIZATION AND INTERFACE WITH QUALITY ASSRANCE.