| {{#Wiki_filter:}} | | {{#Wiki_filter:3.18 Fatigue Monitoring Program a. Scope of Inspection Proposed SER Appendix-A Item 44, Metal Fatigue of Reactor Coolant Pressure Boundary, stated (in part): The existing program is credited. |
| | The program will be enhanced to use the EPRI-licensed FatiguePro cycle counting and fatigue usage factor tracking computer program.The inspectors interviewed the program manager and determined that the FatiguePro program, although in place and ready-to-go, has not been implemented. |
| | The existing, credited program, is currently the fatigue evaluation program of record. Exelon is waiting for the NRC to resolve its concerns about a mathematical summation technique used in FatiguePro, with industry working groups, prior to making FatiguePro the official fatigue evaluation program at Oyster Creek. The program was evaluated by the inspectors in March of 2006 (Report 05000219/20006007). |
| | The inspectors determined that Exelon's proposed implementation had not changed in the interim.b. Observations The inspectors determined that Exelon's proposed implementation had not changed in the since the NRC reviewed it in March of 2006.}} |
Revision as of 01:05, 20 September 2018
|
---|
Category:Inspection Report Correspondence
MONTHYEARML16336A1062016-12-0101 December 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML0919801252009-06-17017 June 2009 License Renewal Commitments Inspection, Exit Meeting - Tdb ML0919801262009-06-17017 June 2009 10/27/2008 Oyster Creek License Renewal Commitments Inspection, Entrance Meeting ML0919801272009-06-17017 June 2009 License Renewal Commitments Inspection, Exit Meeting - TBD ML0919801282009-06-17017 June 2009 License Renewal Commitments Inspection, Exit Meeting - TBD ML0919801292009-06-17017 June 2009 License Renewal Commitments Inspection, Exit Meeting - TBD ML0919801302009-06-17017 June 2009 12/03/2008 Oyster Creek License Renewal Commitments Inspection Exit Meeting ML0919802342009-06-17017 June 2009 License Renewal Commitments Inspection, Exit Meeting - TBD ML0919802332009-06-17017 June 2009 License Renewal Commitments Inspection, Exit Meeting - TBD ML0914903592009-05-0606 May 2009 Fatigue Monitoring Program ML0914903602009-05-0606 May 2009 Feeder for Oyster Creek ML0914903612009-05-0606 May 2009 Results of Detailed Review; Water Chemistry Management Program ML0712400082007-05-0303 May 2007 Drywell Trench Photographs During 4/29/07 Maintenance Outage IR 05000219/20060092006-11-0606 November 2006 (SGI) IR 05000219-06-009 on 10/02/06-10/05/06 for Oyster Creek Nuclear Generating Station; Physical Protection IR 05000219/20060042006-10-24024 October 2006 IR 05000219-06-004, on 07/01/2006 - 09/30/2006, Oyster Creek, Fire Protection, Maintenance Effectiveness, and Surveillance Testing IR 05000219/20060062006-06-20020 June 2006 IR 05000219-06-006, on 04/24/2006 - 05/19/2006, Oyster Creek; Biennial Baseline Inspection of the Identification and Resolution of Problems IR 05000219/20050112006-01-0909 January 2006 EA 05-199 Oyster Creek Generating Station -Final Significance Determination for a White Finding and Notice of Violation (NRC Event Followup Inspection Report No. 05000219/2005011) IR 05000219/20040032004-11-0202 November 2004 EA 04-142, Oyster Creek Generating Station - Final Significance Determination for a Green Finding (NRC Inspection Report 05000219-04-003) ML0227701532002-10-0404 October 2002 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000219/20020052002-05-28028 May 2002 IR 05000219-02-05; on 03/31-05/11/2002; Amergen Energy Company, LLC; Oyster Creek Generating Station; Integrated Report. No Violations Identified IR 05000219/20010132002-03-11011 March 2002 IR 05000219/2001-013, on 12/31/01-02/09/02, Amergen, Oyster Creek Generating Station, Equipment Alignment, Event Follow Up. Two non-cited Violations Noted IR 05000219/20010102002-01-17017 January 2002 IR 05000219/2001-010, Oyster Creek Generating Station, Inspection on 11/11/2001 - 12/30/01 Related to Emergent Work. No Violations Noted IR 05000219/20010052001-06-11011 June 2001 NRC Inspection Report 05000219/2001005 ML0631204891966-04-15015 April 1966 IR 05000219-66-001, on 03/22-23/1966, Oyster Creek, Construction Inspection Report Including Drywell Testing IR 05000219/19660011966-04-15015 April 1966 1966/04/15-IR 05000219-66-001, on 03/22-23/1966, Oyster Creek, Construction Inspection Report Including Drywell Testing 2016-12-01
[Table view] |
Text
3.18 Fatigue Monitoring Program a. Scope of Inspection Proposed SER Appendix-A Item 44, Metal Fatigue of Reactor Coolant Pressure Boundary, stated (in part): The existing program is credited.
The program will be enhanced to use the EPRI-licensed FatiguePro cycle counting and fatigue usage factor tracking computer program.The inspectors interviewed the program manager and determined that the FatiguePro program, although in place and ready-to-go, has not been implemented.
The existing, credited program, is currently the fatigue evaluation program of record. Exelon is waiting for the NRC to resolve its concerns about a mathematical summation technique used in FatiguePro, with industry working groups, prior to making FatiguePro the official fatigue evaluation program at Oyster Creek. The program was evaluated by the inspectors in March of 2006 (Report 05000219/20006007).
The inspectors determined that Exelon's proposed implementation had not changed in the interim.b. Observations The inspectors determined that Exelon's proposed implementation had not changed in the since the NRC reviewed it in March of 2006.