| issue date = 06/03/2010 | | issue date = 06/03/2010 | ||
| title = | | title = Notification of Inspection (IR 05000285-10-004) and Request for Information | ||
| author name = Farnholtz T A | | author name = Farnholtz T A | ||
| author affiliation = NRC/RGN-IV/DRS/EB-1 | | author affiliation = NRC/RGN-IV/DRS/EB-1 |
Revision as of 07:42, 13 April 2019
ML101550050 | |
Person / Time | |
---|---|
Site: | Fort Calhoun |
Issue date: | 06/03/2010 |
From: | Farnholtz T A Region 4 Engineering Branch 1 |
To: | Bannister D J Omaha Public Power District |
References | |
IR-10-004 | |
Download: ML101550050 (6) | |
See also: IR 05000285/2010004
Text
June 3, 2010
David J. Bannister, Vice President and Chief Nuclear Officer
Omaha Public Power District 444 South 16
th St. Mall Omaha, NE 68102-2247
SUBJECT: FORT CALHOUN STATION - NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT 05000285/2010004) AND REQUEST FOR INFORMATION
Dear Mr. Bannister:
From July 19 - 30, 2010, Reactor Inspectors from NRC's Region IV office will perform the baseline inspection of changes, tests, experiments, and permanent plant modifications at Fort Calhoun Station, using NRC Inspection Procedure 71111.17, "Evaluations of Changes, Tests, Experiments, and Permanent Plant Modifications."
Experience has shown that this inspection is resource intensive both for the NRC inspectors and your staff. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Erick Matzke of your licensing organization. If there are any questions about this inspection or the material requested, please contact the
lead inspector, Gerond A. George, at 817-276-6562 or by email Gerond.George@nrc.gov. UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125
Omaha Public Power District - 2 -
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/ Thomas A. Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety
Docket: 50-285
License: DPR-40
Enclosure: Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications Document Request cc w/enclosure: Jeffrey A. Reinhart Site Vice President Omaha Public Power District
Fort Calhoun Station FC-2-4 Adm. P.O. Box 550 Fort Calhoun, NE 68023-0550
Mr. Thomas C. Matthews
Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm. P.O. Box 550 Fort Calhoun, NE 68023-0550
David A. Repka Winston & Strawn 1700 K Street, NW Washington, DC 20006-3817
Chairman
Washington County Board of Supervisors P.O. Box 466 Blair, NE 68008
Omaha Public Power District - 3 -
Ms. Julia Schmitt, Manager Radiation Control Program Nebraska Health & Human Services Division of Public Health
P.O. Box 95026 Lincoln, NE 68509-5026
Ms. Melanie Rasmussen Radiation Control Program Officer
Bureau of Radiological Health Iowa Department of Public Health Lucas State Office Building, 5th Floor 321 East 12th Street Des Moines, IA 50319
Chief, Technological Hazards Branch
FEMA, Region VII 9221 Ward Parkway Suite 300 Kansas City, MO 64114-3372
Omaha Public Power District - 4 -
Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Chuck.Casto@nrc.gov) DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov) DRS Director (Roy.Caniano@nrc.gov) DRS Deputy Director (Troy.Pruett@nrc.gov) Senior Resident Inspector (John.Kirkland@nrc.gov) Resident Inspector (Jacob.Wingebach@nrc.gov)
Branch Chief, DRP/E (Jeff.Clark@nrc.gov) Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov) Project Engineer (William.Schaup@nrc.gov) FCS Administrative Assistant (Berni.Madison@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)
Project Manager (Lynnea.Wilkins@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov) OEMail Resource
R:\REACTORS\FC2010004 RFI rpt - GAG ADAMS ML ADAMS: No Yes SUNSI Review Complete Reviewer Initials:GAG
Publicly Available Non-Sensitive
Non-publicly Available Sensitive DRS/EB1 C: DRS/EB1
G. George T. Farnholtz 6 /2 /10 6 /2 /10 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
- 1 - Enclosure Evaluations of Changes, Tests, or Experiments and Permanent Plant Modification
Inspection Dates: July 19 - 30, 2010
Inspection Procedures: IP 71111.17 "Evaluation of Changes, Tests, or Experiments and Permanent Plant Modifications"
Inspectors: Gerond A. George, Reactor Inspector, Lead Inspector Isaac Anchondo, Reactor Inspector
Theresa Buchanan, Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic format (Certrec database preferred), in care of Gerond A. George, by July 12, 2010, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspectors will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection weeks. We ask that the specific items requested be available and ready for review on the first day of inspection. Also, we request that you categorize the documents in your response with the numbered list below.
Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the lead inspector as soon as possible.
1. A list with descriptions, of all 50.59 screenings (or equivalent) performed since August 14, 2006, which did not result in an evaluation. Note: Description of screenings should be brief, but of sufficient detail so that inspectors can determine the significance of the issue.
2. A list with descriptions, of all 10 CFR 50.59 evaluations performed which did not result in an application for license amendment to NRC from August 14, 2006, to the present. Note: Description of evaluations should be brief, but of sufficient detail so that inspectors can determine the significance of the issue.
3. Fort Calhoun Station procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
4. A list with descriptions of all Corrective Action documents related to 50.59 activities, including screenings and evaluations from August 14, 2006, to the present.
5. A list with descriptions of all permanent plant modifications, dating from August 14, 2006, Include sufficient detail to enable the inspector to determine the significance of each modification. For this inspection, permanent plant modifications include permanent plant changes, design changes, setpoint changes, procedure changes, equivalency evaluations, suitability analyses, calculations, and commercial grade dedications.
- 2 - Enclosure 6. Fort Calhoun Station procedure(s) for implementing and controlling permanent plant modifications.
7. A list with descriptions of all Corrective Action documents related to your permanent plant modification program and its implementation since August 14, 2006. Include
sufficient detail to enable the inspector to determine the significance of each modification.
8. A listing of personnel qualified to prepare 50.59 screenings and evaluations, including qualification dates.
9. A listing of personnel qualified to review and approve 50.59 screenings and/or evaluations, including qualification dates.
Inspector Contact Information:
Gerond George Isaac Anchondo Theresa Buchanan Reactor Inspector Reactor Inspector Reactor Inspector 817-276-6562 817-860-8152 817-276-6503 Gerond.George@nrc.gov Isaac.Anchondo@nrc.gov Theresa.Buchanan@nrc.gov
Mailing Address: US NRC Region IV Attn: Gerond George 612 E. Lamar Blvd., Suite 400
Arlington, TX 76011-4125