ML11249A192: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 22: Line 22:
                                               )
                                               )
(Pilgrim Nuclear Generating Station)          )
(Pilgrim Nuclear Generating Station)          )
____________________________________________________________________________
NRC STAFFS ANSWER TO PILGRIM WATCHS PETITION FOR REVIEW OF MEMORANDUM AND ORDER (DENYING PILGRIM WATCHS REQUESTS FOR HEARING ON CERTAIN NEW CONTENTIONS)
NRC STAFFS ANSWER TO PILGRIM WATCHS PETITION FOR REVIEW OF MEMORANDUM AND ORDER (DENYING PILGRIM WATCHS REQUESTS FOR HEARING ON CERTAIN NEW CONTENTIONS)
____________________________________________________________________________
Beth N. Mizuno Susan Uttal Andrea Z. Jones Counsel for NRC Staff September 6, 2011
Beth N. Mizuno Susan Uttal Andrea Z. Jones Counsel for NRC Staff September 6, 2011


Line 58: Line 56:
that PW did not meet the requirements for reopening is supported by precedent and is not in conflict with existing case law. Accordingly, PWs petition for review should be denied.
that PW did not meet the requirements for reopening is supported by precedent and is not in conflict with existing case law. Accordingly, PWs petition for review should be denied.
PROCEDURAL BACKGROUND Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc.s (Entergy or Applicant) submitted a license renewal application for the Pilgrim Nuclear Generating Station (Pilgrim) on January 25, 2006.1 In response to a Federal Register notice of opportunity for hearing,2 Pilgrim Watch filed a petition to intervene in this matter on May 25, 2006, submitting five contentions for consideration.3 The Board admitted two of Pilgrim Watchs proposed contentions-- Contention 1, challenging Entergys aging management program for buried piping and Contention 3, challenging Entergys Severe Accident Mitigation Alternatives (SAMA) analysis.4 On October 30, 2007, a Board majority granted the motion for summary disposition of Contention 3.5 On April 10, 2008, an evidentiary hearing was held on Contention 1, and shortly thereafter, on June 4, 2008, the Board formally closed the evidentiary record.6 The Board issued an initial decision disposing of Contention 1 in favor of the Applicant 1
PROCEDURAL BACKGROUND Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc.s (Entergy or Applicant) submitted a license renewal application for the Pilgrim Nuclear Generating Station (Pilgrim) on January 25, 2006.1 In response to a Federal Register notice of opportunity for hearing,2 Pilgrim Watch filed a petition to intervene in this matter on May 25, 2006, submitting five contentions for consideration.3 The Board admitted two of Pilgrim Watchs proposed contentions-- Contention 1, challenging Entergys aging management program for buried piping and Contention 3, challenging Entergys Severe Accident Mitigation Alternatives (SAMA) analysis.4 On October 30, 2007, a Board majority granted the motion for summary disposition of Contention 3.5 On April 10, 2008, an evidentiary hearing was held on Contention 1, and shortly thereafter, on June 4, 2008, the Board formally closed the evidentiary record.6 The Board issued an initial decision disposing of Contention 1 in favor of the Applicant 1
Entergy Nuclear Operations, Inc., License Renewal Application - Pilgrim Nuclear Power Station (January 25, 2006) (Agencywide Documents and Access Management System (ADAMS) Accession No.
Entergy Nuclear Operations, Inc., License Renewal Application - Pilgrim Nuclear Power Station (January 25, 2006) (Agencywide Documents and Access Management System (ADAMS) Accession No. ML060300028).
ML060300028).
2 Entergy Nuclear Operations, Inc., Pilgrim Nuclear Power Station; Notice of Acceptance for Docketing of the Application and Notice of Opportunity for Hearing Regarding Renewal of Facility Operating License No. DPR-35 for an Additional 20-Year Period, 71 Fed. Reg. 15,222 (Mar. 27, 2006).
2 Entergy Nuclear Operations, Inc., Pilgrim Nuclear Power Station; Notice of Acceptance for Docketing of the Application and Notice of Opportunity for Hearing Regarding Renewal of Facility Operating License No. DPR-35 for an Additional 20-Year Period, 71 Fed. Reg. 15,222 (Mar. 27, 2006).
3 Request for Hearing and Petition to Intervene by Pilgrim Watch (May 25, 2006) (ADAMS Accession No. ML061630125).
3 Request for Hearing and Petition to Intervene by Pilgrim Watch (May 25, 2006) (ADAMS Accession No. ML061630125).
Line 69: Line 66:
Until and unless some third party assumes responsibility for cleanup after a severe nuclear reactor accident to pre-accident conditions, sets a cleanup standard, and identifies a funding source, Entergy should be required to take all of the mitigation steps that would be required by a SAMA (severe accident mitigation alternative) analysis (i) based on a conservative source term using release fractions no lower than those specified in NUREG-1465 or used by the NRC in studies such as NUREG-1450, cleanup to a dose rate of not more than 15 millirem a year, and at least the 95th percentile of the total consequences determined by 7
Until and unless some third party assumes responsibility for cleanup after a severe nuclear reactor accident to pre-accident conditions, sets a cleanup standard, and identifies a funding source, Entergy should be required to take all of the mitigation steps that would be required by a SAMA (severe accident mitigation alternative) analysis (i) based on a conservative source term using release fractions no lower than those specified in NUREG-1465 or used by the NRC in studies such as NUREG-1450, cleanup to a dose rate of not more than 15 millirem a year, and at least the 95th percentile of the total consequences determined by 7
Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-08-22, 68 NRC 590, 593 (2008).
Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-08-22, 68 NRC 590, 593 (2008).
8 Pilgrim Watchs Petition for Review of LBP-08-22, LBP-07-13, LBP-06-23 and the Interlocutory Decisions in the Pilgrim Nuclear Power Station Proceeding at 11 (Nov. 12, 2008)(ADAMS Accession No.
8 Pilgrim Watchs Petition for Review of LBP-08-22, LBP-07-13, LBP-06-23 and the Interlocutory Decisions in the Pilgrim Nuclear Power Station Proceeding at 11 (Nov. 12, 2008)(ADAMS Accession No. ML083240599).
ML083240599).
9 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-14, 71 NRC ___ (June 17, 2010) (slip op. at 39).
9 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-14, 71 NRC ___ (June 17, 2010) (slip op. at 39).
10 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-11, 71 NRC 281, 317 (2010).
10 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-11, 71 NRC 281, 317 (2010).

Latest revision as of 17:05, 10 March 2020

NRC Staff'S Answer to Pilgrim Watch'S Petition for Review of Memorandum and Order (Denying Pilgrim Watch'S Requests for Hearing on Certain New Contentions)
ML11249A192
Person / Time
Site: Pilgrim
Issue date: 09/06/2011
From: Mizuno B
NRC/OGC
To:
NRC/OCM
SECY RAS
References
RAS 20928, 50-293-LR, ASLBP 06-848-02-LR
Download: ML11249A192 (19)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

ENTERGY NUCLEAR GENERATION ) Docket No. 50-293-LR COMPANY AND ENTERGY NUCLEAR )

OPERATIONS, INC. )

)

(Pilgrim Nuclear Generating Station) )

NRC STAFFS ANSWER TO PILGRIM WATCHS PETITION FOR REVIEW OF MEMORANDUM AND ORDER (DENYING PILGRIM WATCHS REQUESTS FOR HEARING ON CERTAIN NEW CONTENTIONS)

Beth N. Mizuno Susan Uttal Andrea Z. Jones Counsel for NRC Staff September 6, 2011

TABLE OF CONTENTS Page TABLE OF AUTHORITIES ........................................................................................................... ii INTRODUCTION .......................................................................................................................... 1 PROCEDURAL BACKGROUND .................................................................................................. 2 ARGUMENT ................................................................................................................................. 5 I. The Standard for Review of a Board Decision .................................................................. 5 II. The Standard for Reopening the Record .......................................................................... 6 III. The Boards Decision Is Supported by Precedent and Not in Conflict with Existing Law ...................................................................................................................... 7 A. The Board Did Not Err in Applying the Reopening Standard ................................ 7 B. Pilgrim Watchs Cable Contention 2 Does Not Meet the Reopening Standard and Was Not Timely .............................................................................. 8 C. Pilgrim Watchs Cleanup Contention Raises Issues that Are Beyond the Scope of this Proceeding, Requests Remedies that Were Rejected by the Commission, and Does Not Meet the Reopening Standard ..................... 11 CONCLUSION ............................................................................................................................ 13

ii TABLE OF AUTHORITIES Page JUDICIAL DECISIONS New Jersey Environmental Federation v. NRC, No. 09-2567, 2011 WL 1878642 (3rd Cir. May 18, 2011) ......................................................................................................... 10, 11 ADMINISTRATIVE DECISIONS Commission AmerGen Energy Co. LLC (Oyster Creek Nuclear Generating Station),

CLI-09-7, 69 NRC 235 (2009) ............................................................................................ 8, 9, 11 Amergen Energy Co., LLC (Oyster Creek Nuclear Generating Station),

CLI-08-28, 68 NRC 658 (2008) ..................................................................................................... 6 Dominion Nuclear Connecticut, Inc. (Millstone Power Station, Unit 3),

CLI-09-05, 69 NRC 115 (2009) ..................................................................................................... 7 Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Unit 3),

CLI-08-17, 68 NRC 213 (2008) ................................................................................................... 12 Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Units 2 and 3),

CLI-04-36, 60 NRC 631 (2004) ..................................................................................................... 7 Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc.

(Vermont Yankee Nuclear Power Station), CLI-11-02, 73 NRC ___, (March 10, 2011) ........ 9, 10 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), CLI-10-14, 71 NRC ___ (June 17, 2010) .................................. 3 Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), CLI-10-11, 71 NRC 281 (2010) ........................................... 3, 12 Private Fuel Storage, LLC (Independent Spent Fuel Storage Installation),

CLI-05-12, 61 NRC 345 (2005) ..................................................................................................... 6 Tennessee Valley Authority (Watts Bar Nuclear Plant, Unit 1; Sequoyah Plants, Units 1 & 2; Browns Ferry Nuclear Plant, Units 1,2 &3), CLI-04-24, 60 NRC 160 (2004) ................................ 5 USEC, Inc. (American Centrifuge Plant), CLI-06-0, 63 NRC 433 (2006) ...................................... 5

iii Atomic Safety and Licensing Board Duke Energy Carolinas, LLC (William States Lee III Nuclear Station, Units 1 and 2),

LBP-08-17, 68 NRC 451 (2008) .................................................................................................. 12 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), LBP-11-20, 74 NRC ___ (Aug. 11, 2011) ................................. 4 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), LBP-08-22, 68 NRC 590 (2008) ............................................... 3 Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), LBP-07-13, 66 NRC 131 (2007) ........................................... 2, 3 Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc.

(Pilgrim Nuclear Power Station), LBP-06-23, 64 NRC 257 (2006) ........................................... 2, 3 REGULATIONS 10 C.F.R. § 2.309(c) ..................................................................................................................... 6 10 C.F.R. § 2.309(f) ............................................................................................................ 6, 7, 12 10 C.F.R. § 2.326(a) ............................................................................................................... 8, 12 10 C.F.R. § 2.326(b) ..................................................................................................................... 6 10 C.F.R. § 2.326(d) ..................................................................................................................... 6 10 C.F.R. § 2.337(a) ..................................................................................................................... 6 10 C.F.R. § 2.341(a) ..................................................................................................................... 5 10 C.F.R. § 2.341(b) ............................................................................................................. 1, 4, 5

September 6, 2011 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

ENTERGY NUCLEAR GENERATION ) Docket No. 50-293-LR COMPANY AND ENTERGY NUCLEAR )

OPERATIONS, INC. )

)

(Pilgrim Nuclear Generating Station) )

NRC STAFFS ANSWER TO PILGRIM WATCHS PETITION FOR REVIEW OF MEMORANDUM AND ORDER (DENYING PILGRIM WATCHS REQUESTS FOR HEARING ON CERTAIN NEW CONTENTIONS)

INTRODUCTION Pursuant to 10 C.F.R. § 2.341(b)(3), the staff of the U.S. Nuclear Regulatory Commission (Staff) hereby answers Pilgrim Watchs (PW) Petition for Review of Memorandum and Order (Denying Pilgrim Watchs Request for Hearing on Certain New Contentions), ASLBP No. 68-8484-02-LR, August 11, 2011 (Petition for Review). After over five and a half years of litigation in this license renewal proceeding, an evidentiary hearing, several prehearing conferences and oral arguments, and the closing of the record, which was followed by Commission review and remand, PW filed two contentions asserting that the aging management program for submerged cables was inadequate and a contention claiming that the cost-benefit analysis in the severe accident mitigation analysis was flawed. In its Petition for Review, PW asserts that the Atomic Safety and Licensing Board (Board) erred when it applied the reopening standard to these contentions and when it found PWs contentions inadmissible for failure to satisfy that standard. As demonstrated herein, the Board did not err when it applied the reopening standard to the contentions. The Boards legal determination

that PW did not meet the requirements for reopening is supported by precedent and is not in conflict with existing case law. Accordingly, PWs petition for review should be denied.

PROCEDURAL BACKGROUND Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc.s (Entergy or Applicant) submitted a license renewal application for the Pilgrim Nuclear Generating Station (Pilgrim) on January 25, 2006.1 In response to a Federal Register notice of opportunity for hearing,2 Pilgrim Watch filed a petition to intervene in this matter on May 25, 2006, submitting five contentions for consideration.3 The Board admitted two of Pilgrim Watchs proposed contentions-- Contention 1, challenging Entergys aging management program for buried piping and Contention 3, challenging Entergys Severe Accident Mitigation Alternatives (SAMA) analysis.4 On October 30, 2007, a Board majority granted the motion for summary disposition of Contention 3.5 On April 10, 2008, an evidentiary hearing was held on Contention 1, and shortly thereafter, on June 4, 2008, the Board formally closed the evidentiary record.6 The Board issued an initial decision disposing of Contention 1 in favor of the Applicant 1

Entergy Nuclear Operations, Inc., License Renewal Application - Pilgrim Nuclear Power Station (January 25, 2006) (Agencywide Documents and Access Management System (ADAMS) Accession No. ML060300028).

2 Entergy Nuclear Operations, Inc., Pilgrim Nuclear Power Station; Notice of Acceptance for Docketing of the Application and Notice of Opportunity for Hearing Regarding Renewal of Facility Operating License No. DPR-35 for an Additional 20-Year Period, 71 Fed. Reg. 15,222 (Mar. 27, 2006).

3 Request for Hearing and Petition to Intervene by Pilgrim Watch (May 25, 2006) (ADAMS Accession No. ML061630125).

4 Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-06-23, 64 NRC 257, 348-49 (2006).

5 Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-07-13, 66 NRC 131 (2007).

6 Memorandum and Order (Ruling on Pilgrim Watch Motions Regarding Testimony and Proposed Additional Evidence Relating to Pilgrim Watch Contention 1) (June 4, 2008) at 3 (ADAMS Accession No. ML081560375).

and terminated the proceeding on October 30, 2008.7 Pilgrim Watch filed a petition for review of the Boards initial decision and other interlocutory decisions,8 which the Commission denied on June 17, 2010 in CLI-10-14.9 The Commission reversed the summary disposition of Contention 3 and remanded it to the Board for further proceedings as limited by the Commissions Order.10 On July 29, 2011, the Board issued a partial initial decision finding in favor of the Applicant on remanded Contention 3.11 The Boards decision on remanded Contention 3 is currently pending before the Commission on a petition for review filed by PW.12 A few months after it filed its petition for review, PW filed a request for a hearing on the first new contention asserting (hereinafter the Cleanup Contention):

Until and unless some third party assumes responsibility for cleanup after a severe nuclear reactor accident to pre-accident conditions, sets a cleanup standard, and identifies a funding source, Entergy should be required to take all of the mitigation steps that would be required by a SAMA (severe accident mitigation alternative) analysis (i) based on a conservative source term using release fractions no lower than those specified in NUREG-1465 or used by the NRC in studies such as NUREG-1450, cleanup to a dose rate of not more than 15 millirem a year, and at least the 95th percentile of the total consequences determined by 7

Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-08-22, 68 NRC 590, 593 (2008).

8 Pilgrim Watchs Petition for Review of LBP-08-22, LBP-07-13, LBP-06-23 and the Interlocutory Decisions in the Pilgrim Nuclear Power Station Proceeding at 11 (Nov. 12, 2008)(ADAMS Accession No. ML083240599).

9 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-14, 71 NRC ___ (June 17, 2010) (slip op. at 39).

10 Entergy Nuclear Generation Company and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-11, 71 NRC 281, 317 (2010).

11 See generally Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), LBP-11-18, 74 NRC __ (July 19, 2011)(slip op.).

12 Pilgrim Watch Request for Review of the Partial Initial Decision (Rejecting Upon Remand Pilgrim Watchs Challenge To Meteorological Modeling In SAMA analysis in Entergys License Renewal Application (July 19, 2011) (ADAMS Accession No. ML11215A133)

the EARLY and CHRON modules of the MACCS2 Code, and (ii) does not reduce any costs by use of a discount factor or probabilistic analysis.13 Shortly thereafter, PW filed the second new contention (Cable Contention 1) asserting:

Entergys Aging Management Plan for non-environmentally qualified (EQ) inaccessible cables and cable splices at Pilgrim Station is insufficient to provide reasonable assurance that these cables will be in compliance with NRC Regulations and public health and safety shall be protected during license renewal.14 A few weeks later, PW filed a third contention, similar to the second contention (Cable Contention 2), asserting:

Entergys Aging Management Plan (as amended by Entergy on January 7, 2011) for non-environmentally qualified (EQ) inaccessible cables and cable splices at Pilgrim Station is insufficient to provide reasonable assurance that these cables will be in compliance with NRC Regulations and public health and safety shall be protected during license renewal.15 The Board denied PWs requests for hearing on the Cleanup Contention and Cable Contentions 1 and 216 and on August 26, 2011, pursuant to 10 C.F.R. § 2.341(b)(1), PW filed a petition for review of the Boards decision denying the Cleanup Contention and Cable Contention 2.17 13 Pilgrim Watch Request for Hearing on a New Contention (November 29, 2010)(ADAMS Accession No. ML103420305).

14 Pilgrim Watch Request for Hearing on a New Contention: Inadequacy of Entergys Aging Management of Non-Environmentally Qualified Inaccessible Cables (Splices) at Pilgrim Station (December 13, 2010) (ADAMS Accession No. ML103500400).

15 Pilgrim Watch Request for Hearing on a New Contention: Inadequacy of Entergys Aging Management of Non-Environmentally Qualified Inaccessible Cables (Splices) at Pilgrim Station (January 20, 2010)(ADAMS Accession No. ML110200267).

16 Memorandum and Order (Denying Pilgrim Watchs Requests for Hearing on Certain New Contentions), LBP-11-20, 74 NRC ___ (Aug. 11, 2011) (slip op at 3.).

17 Petition for Review.

ARGUMENT I. Standard for Review of a Board Decision The procedural regulations at 10 C.F.R. § 2.341(a)(1) govern PWs petition for review.

Subsection (b)(4) provides that the Commission may grant a petition for review giving due weight to the existence of a substantial question with respect to one or more of the following considerations:

(1) a clearly erroneous finding of fact; (2) a necessary legal conclusion is without precedent or conflicts with existing law; (3) the appeal raises a substantial and important question of law or policy; (4) the proceeding involved a prejudicial procedural error; or (5) any other consideration the Commission determines to be in the public interest.

10 C.F.R. § 2.341(b)(4).

In this instance, the Board determined that the reopening standard applied and that PW had failed to meet that standard and, therefore, denied admission of the proffered contentions.

The question the Board determined was thus a question of law. There were no findings of fact; the appeal raises no substantial or important questions of law or policy; and PW has not claimed prejudicial procedural error. With respect to a boards conclusions of law, a petitioner must show an error of law or abuse of discretion by the board.18 The Commission will reverse a boards legal conclusions only if they are a departure from or contrary to established law.19 18 USEC, Inc. (American Centrifuge Plant), CLI-06-0, 63 NRC 433, 439 n.32 (2006).

19 Tennessee Valley Authority (Watts Bar Nuclear Plant, Unit 1; Sequoyah Plants, Units 1 & 2; Browns Ferry Nuclear Plant, Units 1,2 &3), CLI-04-24, 60 NRC 160, 190 (2004).

II. The Standard for Reopening the Record Once the record is closed, it will not be reopened except upon a strong, well-supported showing of singular circumstances. Accordingly, the regulations provide that a motion to re-open the record will not be granted unless it satisfies the following three criteria:

(1) The motion must be timely, except that an exceptionally grave issue may be considered in the discretion of the presiding officer even if untimely presented; (2) The motion must address a significant safety issue; and (3) The motion must demonstrate that a materially different result would be or would have been likely had the newly proffered evidence been considered initially.

10 C.F.R. § 2.326(a). Amergen Energy Co., LLC (Oyster Creek Nuclear Generating Station),

CLI-08-28, 68 NRC 658, 688 (2008). The motion must be accompanied by an affidavit that provides the factual and/or technical bases for the movants claim that the three criteria in section 2.326(a) are satisfied. 10 C.F.R. § 2.326(b). The evidence supporting the motion must satisfy the Commissions admissibility standards in 10 C.F.R. § 2.337(a); it must be relevant, material, and reliable. Id. at 672. Moreover, the moving papers must be strong enough, in the light of any opposing filings, to avoid summary disposition. Private Fuel Storage, LLC (Independent Spent Fuel Storage Installation), CLI-05-12, 61 NRC 345, 350 (2005).

The standard for admissibility of a contention associated with a motion to reopen is also high. See Private Fuel Storage, CLI-05-12, 61 NRC at 350. The contention must, of course, meet the general admissibility requirements at 10 C.F.R. § 2.309(f). But in addition, 10 C.F.R.

§ 2.326(d) expressly states that where the contention raises an issue not previously in controversy, the contention must satisfy the requirements for admission of nontimely contentions at 10 C.F.R. § 2.309(c). A nontimely contention will only be admitted upon a balancing of eight factors, the most important of which is good cause for the failure to file on

time.20 Finally, the contention must meet the standard for late-filed contentions, or contentions filed after the initial filing period has passed. Such contentions are allowed only upon a showing that - (i) [t]he information upon which the amended or new contention is based was not previously available; (ii) [t]he information upon which the amended or new contention is based is materially different than information previously available; and (iii) [t]he amended or new contention has been submitted in a timely fashion based on the availability of the subsequent information. Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Units 2 and 3), CLI-04-36, 60 NRC 631, 636 (2004) (quoting 10 C.F.R. § 2.309(f)(2)(i)-(iii) (alterations in original)).

III. The Boards Decision Is Supported by Precedent and Does Not Conflict with Existing Law A. The Board Did Not Err in Applying the Reopening Standard Having closed the evidentiary record in 2008, the Board properly viewed PWs Cleanup Contention and Cable Contentions 1 and 2 as attempts to reopen the record. PW argues that because this proceeding is still ongoing and a result has not yet been reached, the reopening standard does not apply.21 PW conflates the termination of the proceeding with the closing of the evidentiary record. These are two separate events, which may occur simultaneously or not. Judge Young explained the difference between the close of the proceeding and the close of the record in her statement concurring with the majority that the reopening standard must be applied:

[i]n the Vermont Yankee proceeding, in which the Commission on appeal of board initial decisions remanded the case for a limited purpose, it observed that, although the proceeding would remain open, Intervenors therein had to submit a motion to reopen to 20 Dominion Nuclear Connecticut, Inc. (Millstone Power Station, Unit 3), CLI-09-05, 69 NRC 115, 125-26 (2009).

21 Petition for Review at 4.

address any genuinely new issues related to the license renewal application that previously could not have been raised.

August 11 Memorandum and Order, J. Young Concurring in Part and Dissenting in Part, at 3.

The Boards application of the reopening standard was thus consistent with prior case law and the petition for review challenging this part of the Boards decision should, therefore, be denied.

B. Pilgrim Watchs Cable Contention 2 Does Not Meet the Reopening Standard and Was Not Timely The Board observed that throughout the proceeding, PW maintained that Cable Contention 2 was not subject to the reopening standard and thus steadfastly refused to address the criteria for reopening.22 The Board stated that PWs refusal to address the reopening criteria deprived the Board of the very information it would need in order to rule in favor of PW on reopening, particularly, a demonstration that a materially different result would have been likely had the proffered contention been admitted.23 In light of the Commissions stated position that it is the petitioner (not the board)24 who must supply the information required to show admissibility, the Boards determination that PW must establish that it met the reopening standard was correct.

Even if PW had addressed the reopening standard, the Board stated that it would have rejected Cable Contention 2 because PW failed to show that it had raised the issue in a timely manner, a showing required for reopening pursuant to 10 C.F.R. § 2.326(a)(1) and Commission precedent.25 In Cable Contention 2, PW argued that the Applicants aging management 22 August 11 Memorandum and Order at 12.

23 Id. at 23-24.

24 Id. at 15-16, quoting AmerGen Energy Co. LLC (Oyster Creek Nuclear Generating Station),

CLI-09-7, 69 NRC 235, 260 (2009).

25 Id. at 24-25.

program for submerged cables was inadequate and pointed to the Applicants recent amendment of the program in an attempt to justify its filing of the contention over five and half years after the initial period for filing contentions expired.26 But the Board noted that the Applicants amendment of its aging management program for cables expanded the scope of the program and the frequency of testing and inspection and thus constituted an enhancement to the program.27 The Board noted that if the enhanced program is inadequate, then the original, unenhanced program must also have been inadequate and PW should have challenged the original, unenhanced program when it filed its initial contentions, citing Oyster Creek, CLI-09-7, 69 NRC at 273-74.28 In a similar situation in which it approved the application of the reopening standard and the rejection of a similar contention as untimely, the Commission stated that the complaint, if true today, was equally true when [the applicant] filed its Application and that the intervenor could have and should have been aware of this when it first filed its contentions in the proceeding.29 In its Petition for Review, PW asserts that the Board misread the regulation governing reopening and that the reopening standards should only be applied to contentions that seek to raise issues that have been litigated and should not be applied to new contentions which have nothing to do with the closed portion of the record, and in fact [present] new questions that were not, and could not have been earlier litigated.30 This interpretation of the regulation at 10 26 Pilgrim Watch Request for Hearing on a New Contention: Inadequacy of Entergys Aging Management of Non-Environmentally Qualified Inaccessible Cables (Splices) at Pilgrim Station (January 20, 2010) at 24-25.

27 Id. at 27.

28 Id. at 28.

29 Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (Vermont Yankee Nuclear Power Station), CLI-11-02, 73 NRC ___ (Mar. 10, 2011) (slip op. at 9).

30 Petition for Review at 5.

C.F.R. § 2.326 is incorrect. As the Third Circuit held, such a reading of the regulation would render it a nullity.

Pursuant to 10 C.F.R. § 2.326(d), "[a] motion to reopen which relates to a contention not previously in controversy among the parties must also satisfy the requirements for nontimely contentions in § 2.309(c)."

(emphasis added). Thus, the regulations explicitly allow for contentions alleging previously nonlitigated issues to be raised through a motion to reopen. To accept Citizens' argument that the motion to reopen standard may never be applied in situations where a petitioner seeks to add previously unlitigated material would effectively render the regulation meaningless.

New Jersey Environmental Federation v. NRC, No. 09-2567, 2011 WL 1878642, at *9-10 (3rd Cir. May 18, 2011).

PW further argues that Cable Contention 2 was timely filed and that the Board misread the case law on the issue of timeliness. PW asserts that Vermont Yankee does not mandate denial of a contention merely because the contention is based on an amendment to an aging management program.31 While there may indeed be instances where an amendment to an aging management program may support a contention filed out of time, the main thrust of the decision, which the Board relied on, is that timeliness turns here on the threshold question of when [the petitioner] first had access to information sufficient to enable it to proffer [the contention]32 and that if a contention is raised late in the proceeding and was equally true when the proceeding was initiated, the contention is untimely.33 PW also disagrees with the Boards characterization of the Commissions holding in Oyster Creek; instead of an endorsement of the Boards approach, PW views the Commissions decision as merely affirming the Boards determination that, under the circumstances presented 31 Petition for Review at 8.

32 Vermont Yankee, CLI-11-02, 73 NRC ___,slip op. at 6.

33 Id. at 9-14.

in the proceeding before it, enhancement to a program did not constitute new information sufficient to support a new contention. The Staff, however, submits that the Commission ultimately affirmed the approach taken by the Oyster Creek Board and, indeed by the Board in this proceeding: that where a petitioner relies on an enhancement to an aging management program for admissibility of a contention years after the initial filing date has passed, and the petitioner could have -- but did not -- challenge the original program, the contention will be rejected as untimely.34 The Boards rejection of PWs Cable Contention 2 is thus consistent with precedent and should, therefore, be affirmed.

C. Pilgrim Watchs Cleanup Contention Raises Issues that Are Beyond the Scope of this Proceeding, Requests Remedies that Were Rejected by the Commission, and Does Not Meet the Reopening Standard The Board correctly held that PWs Cleanup Contention was inadmissible. It raises issues regarding policy matters that lie solely with the Commission and those issues are beyond the scope of this proceeding. It requests remedies that the Commission has already rejected.

And the contention was not supported by an affidavit and thus failed to meet this requirement under the reopening standards.

Fundamentally, PWs Cleanup Contention faults the NRC for failing to arrive at an agreement with the Environmental Protection Agency and the Federal Emergency Management Agency regarding radioactive cleanup. The Board recognized that Pilgrim Watch's dissatisfaction with NRC policy and interaction with other agencies regarding the clean-up of a severe accident raised policy issues that cannot be addressed by the Board but can only be 34 Oyster Creek, CLI-09-7, 69 NRC at 273-74, affd, New Jersey Environmental Federation v.

NRC, No. 09-2567, 2011 WL 1878642, at *9.

addressed by the Commission.35 Accordingly, the Board ruled that the contention raised issues that are beyond the scope of this proceeding and was, therefore, inadmissible.36 The Board also held that the contention was inadmissible because it challenged Commission rulings in this matter: rulings that had rejected the remedies PW was raising yet again in the contention.37 In its Cleanup Contention, PW sought a more conservative SAMA analysis, but, as the Board noted, that kind of analysis was specifically rejected by the Commission in Entergy Nuclear Generation Co. and Entergy Nuclear Operations, Inc. (Pilgrim Nuclear Power Station), CLI-10-11, 71 NRC 281, 316 (2010).

Finally, the Board stated that the Cleanup Contention was inadmissible because PW refused to address the reopening standards when it submitted the contention and, in particular, refused to submit an affidavit in support of the contention.38 The reopening standard requires the petitioner to demonstrate that a materially different result would have been likely had the new material been considered in the first instance. 10 C.F.R. § 2.326(a)(3). Because PW did not submit an affidavit in support of the contention, PW did not demonstrate that a materially different result was likely and did not satisfy this requirement for reopening. For this additional reason, the Board denied the contention.

The Boards rejection of PWs Cleanup Contention is consistent with the regulations, case law generally, and the law of the case here. The petition for review should, therefore, be denied.

35 August 11 Memorandum and Order at 19.

36 10 C.F.R. § 2.309(f)(1)(iii). Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power Station, Unit 3), CLI-08-17, 68 NRC 213, 242 (2008); Duke Energy Carolinas, LLC (William States Lee III Nuclear Station, Units 1 and 2), LBP-08-17, 68 NRC 451, 452 (2008) (contentions that constitute generalized grievances with respect to NRC policy raise issues beyond the scope of adjudicatory proceedings and are not admissible).

37 August 11 Memorandum and Order at 19.

38 Id. at 20.

CONCLUSION As shown above, the Atomic Safety and Licensing Board correctly applied the reopening standards to the contentions Pilgrim Watch filed after the record closed. The contentions did not meet the reopening standards because they were unsupported by the affidavits setting forth the factual bases supporting the contentions and demonstrating that a materially different result would have been likely had the contentions been admitted. Moreover, the contentions were not timely, raised issues beyond the scope of the proceeding, and requested remedies the Commission rejected earlier in the proceeding. The Boards legal determination that Pilgrim Watch did not meet the requirements for reopening is supported by precedent and is not in conflict with existing case law. Accordingly, Pilgrim Watchs petition for review should be denied.

Respectfully submitted,

/Electronically signed/

Beth N. Mizuno Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O15-D21 Washington, DC 20555 Telephone: (301) 415-3122 E-mail: Beth.Mizuno@nrc.gov Dated at Rockville, Maryland This 6th day of September, 2011

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

ENTERGY NUCLEAR GENERATION )

COMPANY AND ENTERGY NUCLEAR ) Docket No. 50-293-LR OPERATIONS, INC. )

)

(Pilgrim Nuclear Generating Station) )

CERTIFICATE OF SERVICE I hereby certify that copies of the NRC STAFFS ANSWER TO PILGRIM WATCHS PETITION FOR REVIEW OF MEMORANDUM AND ORDER (DENYING PILGRIM WATCHS REQUESTS FOR HEARING ON CERTAIN NEW CONTENTIONS) have been served upon the following by the Electronic Information Exchange this 6th day of September, 2011:

Administrative Judge Administrative Judge Richard F. Cole Paul B. Abramson Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop: T-3F23 Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: Richard.Cole@nrc.gov E-mail: Paul.Abramson@nrc.gov Administrative Judge Office of Commission Appellate Ann Marshall Young, Chair Adjudication Atomic Safety and Licensing Board Mail Stop: O-16G4 Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail:

E-mail: Ann.Young@nrc.gov Atomic Safety and Licensing Board Office of the Secretary Mail Stop: T-3F23 Attn: Rulemakings and Adjudications Staff U.S. Nuclear Regulatory Commission Mail Stop: O-16G4 Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission (VIA INTERNAL MAIL ONLY) Washington, DC 20555-0001 E-mail: Hearing.Docket@nrc.gov Sheila Slocum Hollis Terence A. Burke, Esq.

Duane Morris LLP Entergy Nuclear 505 9th St., NW, Suite 1000 1340 Echelon Parkway Washington, DC 20004 Mail Stop: M-ECH-62 E-mail: sshollis@duanemorris.com Jackson, MS 39213 E-mail: tburke@entergy.com

Mary Lampert David R. Lewis, Esq.

148 Washington Street Paul A. Gaukler, Esq.

Duxbury, MA 02332 Pillsbury, Winthrop, Shaw, Pittman, LLP E- mail: mary.lampert@comcast.net 2300 N Street, NW Washington, DC 20037-1137 E-mail: david.lewis@pillsburylaw.com paul.gaukler@pillsburylaw.com Chief Kevin M. Nord Town Manager Fire Chief & Director Duxbury Emergency Town of Plymouth Management Agency 11 Lincoln St.

668 Tremont Street Plymouth, MA 02360 Duxbury, MA 02332 E-mail: marrighi@townhall.plymouth.ma.us E-mail: nord@town.duxbury.ma.us Richard R. MacDonald Matthew Brock Town Manager Assistant Attorney General 878 Tremont Street Commonwealth of Massachusetts Duxbury, MA 02332 One Ashburton Place E-mail: macdonald@town.duxbury.ma.us Boston, MA 02108 Martha.Coakley@state.ma.us Matthew.Brock@state.ma.us

/Electronically signed/

Beth N. Mizuno Counsel for the NRC Staff Dated at Rockville, Maryland This 6th day of September, 2011