ML16285A378

From kanterella
Jump to navigation Jump to search
Petitioners' Response to NRC Staff'S and Entergy'S Opposition to Peitioners' Request for Hearing Regarding Entergy'S Request for Extension to Comply with NRC Order EA-13-109
ML16285A378
Person / Time
Site: Pilgrim
Issue date: 10/11/2016
From: Lampert M
Entergy Nuclear Operations, Pilgrim Watch
To:
NRC/OGC
SECY RAS
References
50-293-EA, EA-13-109, Enforcement Action, RAS 51375
Download: ML16285A378 (31)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION

)

In the Matter of: ) Docket No. 50-293-EA

)

ENTERGY NUCLEAR GENERATION CO. & )

ENTERGY NUCLEAR OPERATIONS, INC. )

)

(Pilgrim Nuclear Power Station) ) October 11, 2016

)

PETITIONERS RESPONSE TO NRC STAFFS AND ENTERGYS OPPOSITION TO PETITIONERS REQUEST FOR HEARING REGARDING ENTERGYS REQUEST FOR EXTENSION TO COMPLY WITH NRC ORDER EA-13-109 Counsel for Entergy filed Entergys Answer Opposing Request for Hearing Regarding Pilgrim and EA-13-109 (hereinafter Entergy Opposition) on October 3, 2016. Counsel for the NRC Staff filed NRCs Staffs Response to Pilgrim Watch and Co-Petitioners Request for Hearing (hereinafter Staff Response) on the same day. The arguments the respective counsel made are much the same. For the convenience of the Commission, this Petitioners Response replies to both. 1 1

Seven days from October 3, 2016 is October 10. Since October 10 is Columbus Day, a federal legal holiday designated by Congress, this response is timely filed on October 11, as provided by 10 CFR 2.306.

1

There is one point that Petitioners must address before turning to the substance of these two responses.

Footnote 26 on page 6 of the Staff Response insinuates that Petitioners September 7, 2016 Request was not timely. That is not simply not true.

Petitioners understand that there are at least two different versions of ADAMS; and that the public has access to only one. Petitioners do not know when Entergys request was added to the version of ADAMS to which the Staff, but not the public, had access, or to what record in ADAMS the Staff footnote refers.

The important fact, as shown by extract from the Web-based ADAMS to which Petitioners had access (Exhibit A hereto), is that Entergys June 26, 2016 Request for Extension was added to ADAMS, at least the public version to which Petitioners had access (Declarations of Mary E. Lampert and Paul Gunther attached as Exhibit B), at 8:25 am on July 13, 2016, not on July 5 as the Staff footnote asserts. Petitioners Request was filed less than 60 days later.

Despite the footnote, the Staff Response tellingly does not argue that Petitioners Request was not timely. In fact, it was timely; and the Staffs misleading footnote should not mislead the Commission into thinking otherwise.

I. Introduction Before getting into the legal arguments of Entergys Opposition and the Staff Response, it is important that the Commission have a plain English understanding of what this is really all about.

Fukushima was a disaster, and a wake-up call particularly about the risks and dangers of Boiling Water Reactors like that at Fukushima and Pilgrim. The NRC recognized the potential 2

danger. In March of 2012 the NRC issued an immediately effective Order (EA-12-50) requiring installation of reliable hardened containment venting system; and about 15 months later, it issued a second immediately effective Order (EA-13-109) that, among other things, required Pilgrim to install a severe-accident capable reliable hardened venting system no later than the Spring of 2017.

The NRC set that Spring 2017 deadline because, as the Order says, the reliable hardened venting system the Order requires is necessary to protect health and to minimize danger to life or property and reduce the risks posed to the public from the operation of nuclear power plants such as Pilgrim (Order, p. 7.) The Commission found that the required system was cost-effective, necessary to ensure reasonable assurance of adequate protection of public health and safety, and that the public health, safety and interest require that this Order be made immediately effective (Order, p. 10) and this additional severe accident venting capability should be with minimal delays (Order, p. 4)

From July 6, 2013 when EA-13-109 was issued until the end of 2015, Entergy repeatedly told the NRC that it could and would comply with the Spring 2017 deadline. Even today, Entergy has never said that it cannot do so. 2 Nonetheless, in November of 2015, Entergy filed the Request that is the subject of this proceeding - not only asking that the date for compliance be delayed for some two and one-half years, but also making clear that it intended never to comply. (See Staff Response, p. 5)

Entergys position seems to be that a so-called Relaxation Provision in EA-13-109 was an open invitation for Entergy to avoid doing what the Order required by Spring 2017, despite the 2

Status Updates. NRC Website: http://www.nrc.gov/reactors/operating/ops-experience/japan/plants/pilg.html 3

Commissions findings that continued operation without a reliable hardened containment venting system would not protect health, minimize danger to life or property, or provide the reasonable assurance that the AEA requires.

According to Entergy, the NRC should relax or rescind the Order and grant the request without any hearing, simply because Entergy has said that Pilgrim will shut-down some three years from now - even though the Entergys Opposition says that very little more work needs to be done, and that apparently only a short period of time, would be required for Entergy to comply. (See Entergy Opposition, p.2; and Staff Response, pp 5-6)

Entergys Opposition and the Staff Response say very little about these realities. Much of what they do say is inaccurate and mischaracterizes Petitioners Request. 3 Stripped to their essentials, Entergys and the Staffs positions reduce to two unsustainable propositions:

1. AEA requirement for a hearing doesnt apply because the Order included what Staff and Entergy call a relaxation provision.
2. Petitioners lack standing because they cannot rely on proximity, and their Request is insufficient to satisfy the traditional standing requirements of 10 CFR 2.309(d)(1).

The first is wrong as a matter of fact and law; as discussed in Section II below, the Acts hearing requirement cannot be avoided by simply giving what is clearly a license amendment a different name; and the Staff admits that Orders issued under 10 C.F.R. § 2.202 ... fall under the terms of section 189a of the AEA.

The second should not require any response. Petitioners, both organizations and individuals, are entitled to, and standing under the proximity presumption. Even if the proximity 3

See Section IV, below.

4

presumption did not apply, what the Order itself says, and what Petitioners say in their Request, is clearly sufficient to satisfy the traditional standing requirements of 10 CFR 2.309(d)(1).

II. The AEA Requires a Hearing Section 189a of the Atomic Energy Act says that the Commission shall grant a hearing in any proceeding under the ACT, for the amending of any license, as Entergy and the Staff agree. (Staff Response, 6, Entergy Opposition, 11). The Staff Response even admits that Orders issued under 10 C.F.R. § 2.202 4 alter the requirements of a license and therefore fall under the terms of section 189a of the AEA (Staff Response p. 7).

A. Entergys request to change the date for compliance is an amendment subject to Section 189a.

Entergy and the Staff also seem to agree that EA-13-109, issued under 10 CR 2.202 on June 6, 2013 (hereinafter the Order), amended Pilgrims operating license to, among other things, set specific dates by which Pilgrim was required comply with the Orders Phase 1 and Phase 2 requirements. (Entergy Opposition, pp., 2, 7; Staff Response, p. 3)

They also agreed that Entergys request for an extension of time would change the Phase I compliance date that is part of Pilgrims current operating license. (Entergy Opposition, pp., 2, 9; Staff Response, p. 5)

Petitioners recognize that Order says relaxation requests should be directed to the Director, Office of Nuclear Regulation, and that the Director may in writing, relax or rescind any of the above conditions (Order, p. 14). But section 2.7.8 of the Enforcement Manual is clear that the Director cannot do so without involving the offices (here the Commission).

4 EA-13-109 was issued pursuant to ... the Commission's regulations in 10 CFR 2.202. (Order, p.

10).

5

Most important, although the Order recognizes a potential of relaxation, neither the NRC Staff nor Entergy suggests that simply calling what Entergy seeks a relaxation, or writing an Order to delegate administrative responsibility to the Director of NRR, somehow allows the NRC to avoid the requirement of Section 189a that the Commission shall grant a hearing in any proceeding under the ACT, for the amending of any license.

The Staffs and Entergys position thus reduces itself to their argument that a Sec. 189a hearing is not required because Entergys requested change to the compliance date set by Pilgrims license somehow is not an amendment, but is rather only a relaxation (Entergy Opposition, pp 7, 9, 15, 16, 26; Staff Response, pp. 14, 18-19), or part of [the Staffs] ongoing oversight activities (Entergy Opposition, p. 17).

Given the Staffs admission that Orders issued under 10 C.F.R. § 2.202 5 alter the requirements of a license and therefore fall under the terms of section 189a of the AEA(Staff Response p. 7), Petitioners have difficulty in understanding why simply characterizing a change to a license as a relaxation, or the fact that the Order did not explicitly require[] Entergy to seek relaxation in the form of a license request (See Staff Response, pp. 14, 19 are substantively important, or even relevant.

Contrary to what the Staff, and Entergy seem to assume, whether what Entergy has requested is neither a question of form nor a word game. As a matter of substance, consistent with the Staffs admission, the Courts and the Commission have made clear that, no matter what it may be called, an NRC action that alters the terms of a license, is an amendment and triggers Section 189a hearing rights.

5 The Order was issued pursuant to ... the Commission's regulations in 10 CFR 2.202. (Order, p. 10).

6

In Citizens Awareness Network v. NRC, 59 F.3d 284 (1st Cir. 1995), the First Circuit was very clear that it is the substance of the NRC action that determines entitlement to a section 189(a) hearing, not the particular label that the NRC chooses to assign to its action. (Slip Op, 43), and that CAN was entitled to a hearing under section 189(a):

The Commission elevates labels over substance. It would have us determine that a "proceeding" specifically aimed at excusing a licensee from filing a petition to amend its license is not the functional equivalent of a proceeding to allow a de facto "amendment" to its license. As this construct would eviscerate the very procedural protections Congress envisioned in its enactment of section 189(a), we decline to permit the Commission to do by indirection what it is prohibited from doing directly. See 42 U.S.C. Sec. 2239(a)(1)(A)

(Commission must afford hearing "in any proceeding for the ... modification of rules and regulations dealing with the activities of licensees.")

(Id.)

The NRCs Staff Practice and Procedure Digest, Section 6.1.4 Hearing Requirements for License/Permit Proceedings, agrees:

Section 189.a. hearing rights are triggered despite Commission assertion that it did not amend the license when the Commission abruptly changed its policy so as to retroactively enlarge extant licensees authority, and licensees original license did not authorize licensee to implement major-component dismantling of type undertaken in project. Citizens Awareness Network v. NRC, 59 F.3d 284, 294 (1st Cir. 1995). The statutes phrase modification of rules and regulations encompasses substantive interpretative policy changes, and the Commission cannot effect such modifications without complying with the statutes notice and hearing provisions. 59 F.3d at 292.

In evaluating whether an NRC authorization represents a license amendment within the meaning of section 189a of the Atomic Energy Act, courts repeatedly have considered whether the NRC approval granted the licensee any greater operating authority or otherwise altered the original terms of a license. Cleveland Electric Illuminating Co. (Perry Nuclear Power Plant, Unit 1), CLI-96-13, 44 NRC 315, 326 (1996).

A technical specification is a license condition. A license request to change that condition constitutes a request to amend the license and therefore creates adjudicatory hearing rights under Atomic Energy Act § 189a, 42 U.S.C. § 2239(a). See Cleveland 7

Electric Illuminating Co. (Perry Nuclear Power Plant, Unit 1), CLI-93-21, 38 NRC 87, 91 n.6, 93 (1993); General Public Utilities Nuclear Corp. (Oyster Creek Nuclear Generating Station), LBP-96-23, 44 NRC 143, 150 n.6 (1996).

The Practice and Procedure Digest also makes clear that the only relevant situation in which an NRC authorization does not amend a license, and a hearing may not be required is (Id.):

Where an NRC approval does not permit the licensee to operate in any greater capacity than originally prescribed and all relevant regulations and license terms remain applicable. Cleveland Electric Illuminating Co. (Perry Nuclear Power Plant, Unit 1), CLI-96-13, 44 NRC 315,327(1996).

The Commissions recent decision in Diablo Canyon, CLI-16-09 (2016) makes very clear that the test for whether an NRC action not formally labeled a license amendment could constitute a de facto license amendment and trigger hearing rights under Atomic Entergy Act section 289a is whether that action (1) granted the licensee any greater authority or (2) otherwise altered the original terms of the license. (Diablo p. 3). Entergy admits that The Order effectively imposed a Phase 1 implementation deadline of Spring 2017 on Pilgrim (Entergy Opposition, p. 2). Entergys Request for Extension to Comply extension indisputably would amend that Phase 1 implementation deadline, i.e., would alter the terms of the Pilgrims license as it now exists; and, also indisputably, it would give Pilgrim greater authority, i.e.,

authority to operate after the Spring of 2017 without installing what Phase 1 requires.

Entergys argument that Part 1 of Petitioners contention is immaterial [and] unsupported (Entergy Response, pp 26-27) approaches the ludicrous. Whether what the Request seeks is legally and factually an amendment is the central disputed question here. Petitioners have shown that there plainly is a genuine dispute between Petitioner and Entergy (and the Staff) as to whether the Extension would [] result in a license amendment. (Entergy Response, p. 26) 8

Beyond that, Petitioners position is fully supported by the established law and facts discussed above. What has no legal or factual support is Entergys (and the Staffs) erroneous assumption that the change in compliance dates sought by Entergys Request is not a de facto amendment.

No matter what Entergy and the Staff may call it, a license amendment by any other name is still an amendment, the Commission shall grant a hearing under Section 189(a), and Petitioners Contention admissible.

The Staffs argument that Petitioners contention is outside the scope of hearings on orders under Marble Hill and Bellotti (Staff Response, 19) is wrong, and is discussed in Section IV(C) below. 6 III. Petitioners Have Standing Petitioners have fully met the standing requirements of 10 CFR 2.309(d)(1). Pages 2-8 of Petitioners Request for Hearing set forth the name, address and telephone number of each petitioner, the nature of petitioners right under the AEA to be a party to this proceeding, the nature and extent of the petitioners property, financial or other interest in the proceeding, and that any decision or order might grant Entergys Request would harm the petitioners recognized interests.

6 Entergys Opposition does not mention Marble Hill or Bellotti. The caption to Energys argument that Part 1 is inadmissible (Entergy Opposition, 26) says that it is outside scope, but to the extent Petitioners understand Entergys argument it seems to be only that, if the Staff were sometime to make a no significant hazards consideration, 10 CFR §50.59(b)(c) would bar Petitioners from appealing that determination.

Assuming this is Entergys outside scope argument, Entergy misses the point. Petitioners Request said only that Given the findings that the Commission has already made in the Order, the staff properly could not make a no significant hazards consideration finding here. Petitioners Request, p. 18. Petitioners have not made any NSHC challenge; and we assume that any NSHC decision the Staff might make will be proper.

9

Taking Pilgrim Watch and its Director Mary Lampert as an example, Petitioners Request said:

Pilgrim Watch (hereinafter, PW) is a non-profit citizen organization that serves the public interest in issues regarding the Pilgrim Nuclear Power Station, a Mark I BWR.

The organizations director and representative in this matter is Mary Lampert who resides at 148 Washington Street, Duxbury, Massachusetts, 02332. (Email:

mary.lampert@comcast.net; Telephone: 718-934-0389) Ms. Lampert, PWs director, makes her residence (that she owns and in which she has a financial interest) and her place of occupation and recreation within approximately six (6) miles of Pilgrim Nuclear Power Station. Many of PWs members live within the immediate neighborhood of the reactor, and others either within the 10-mile Emergency Planning Zone or within the 50-mile ingestion pathway. Ms. Lampert is also reasonably concerned for her and their health and safety, as the NRC has already found, in the event NRC does not require Entergy to meet EA-13-109s compliance date. (Pet. Request at 2)

All other Petitioners provided the same type information, as required.

According to the Staff and Entergy (Staff Response, p. 8; see also Entergy Response, pp 18-19), a Petitioner must show is (1) a distinct harm that constitutes an injury- in-fact; (2) that the injury can be traced to the challenged action; and (3) that the injury is likely to be redressed by a favorable decision.

The second and third require only brief comment. As shown in Section III, below, the injury to Petitioners can be traced to, and indeed would be the direct effect of, extending the date for compliance; and that injury plainly would be redressed if Entergys request was denied.

As for the first, Entergy and Staff have made a number of arguments in an attempt to show that there is no threatened injury- in- fact:

1. Petitioners are not entitled to the 50-mile presumption (See Entergy Opposition, pp. 19-21, and Staff Response, pp 9,17);

10

2. Petitioners have not stated any obvious potential for offsite consequences. (Entergy Opposition, pp. 4, 19, 22; Staff Response, p. 18); and
3. Petitioners Response does not demonstrate a concrete and particularized injury-in-fact (Staff Response 17) and that Petitioners concerns about their property and financial interests are far too vague to establish traditional standing (Entergy Opposition, pp 20, 22, 23; Staff Response, p 16) and only Pilgrim Watch and Beyond Nuclear have shown that the respective organizations have authorized the named individuals to represent them (Staff Response, p, 17, Fn. 73).

Each of these is wrong. Petitioners have met the requirements of 2.309(d)(1) and do have 7

standing.

1. Petitioners are entitled to the 50-mile presumption Entergy and the Staff seem to admit that Petitioners have standing if they are entitled to rely on proximity to the plant to support standing (Staff Response, p. 17-18; see also Entergy Opposition, p. 23). The Staff recognized that [t]he Commission and licensing boards have normally allowed petitioners to satisfy standing requirements in construction permit and operating license proceedings for power reactors by demonstrating that they reside, or otherwise have frequent contacts, within 50 miles of the subject facility. (Staff Response, p. 9, Fn. 40). Entergy agrees that proximity standing has been found for petitioners who reside within 50 miles of the facility in question. (Entergy Opposition, p.

19).

7 Contrary to what the Staff says (See Staff Response, p. 16), Petitioners participation in prior NRC proceedings is a factor supporting standing.

11

Petitioners Request is clear that at least two of the eight (8) organization petitioners have members that live within 10 miles of Pilgrim, and that all have members that live within Pilgrims 50-mile radius. 8 As shown in the NRCs Staff Practice and Procedure Digest, Section 2.10.4.1.1.1.E Injury Due to Proximity to a Facility Section 6.1.4 Hearing Requirements for License/Permit Proceedings, it is clearly established that persons living within the roughly 50-mile radius of the facility face a realistic threat of harm if a release from the facility of radioactive material were to occur, and that such a person, such as all the Petitioners here, need not show a causal relationship between injury to its interest and the licensing action being sought in order to establish standing.

8 I.e.:

  • Pilgrim Watch: Many of PWs members live within the immediate neighborhood of the reactor, and others either within the 10-mile Emergency Planning Zone or within the 50-mile ingestion pathway. (Petitioners Request, p 2)
  • Pilgrim Coalition: All of its most active members live within the 50-mile Emergency Planning Zone; many live less than 10 miles from Pilgrim Station. (Petitioners Request, p 3)
  • The Pilgrim Legislative Advisory Coalition: The more than 40 members of the Pilgrim Legislative Advisory Coalition make their residence throughout the fifteen towns on Cape Cod, on Marthas Vineyard or in other neighboring communities on the South Shore of Massachusetts, all of which are within the 50-mile Ingestion Zone. (Petitioners Request, p 5)
  • Cape Downwinders: members living throughout the fifteen towns on Cape Cod and both Marthas Vineyard Island and Nantucket. These communities are within the 50-mile Emergency Planning Zone.

(Petitioners Request, p. 6)

  • Cape Downwinders Cooperative: Its members reside on Cape Cod, within Pilgrim Nuclear Power Stations 50-mile ingestion pathway. (Petitioners Request, p 7)
  • Massachusetts Downwinders: ...a coalition of citizen organizations with members living throughout the state of Massachusetts working to protect the public interest in the event of a radiological accident at Pilgrim. Many represented communities are within the Emergency Planning Zone and would be negatively impacted if an accident at Pilgrim occurred. (Petitioners Request, p. 7)
  • CAN: has members living in the 50-mile Emergency Planning Zone for the Pilgrim reactor (Petitioners Request, p 8)
  • Beyond Nuclear: Beyond Nuclear has members within Pilgrim Stations Emergency Planning Zone.

(Petitioners Request, p. 4) 12

The Digest also makes clear that Close proximity has always been deemed enough standing alone, to establish the requisite interest for intervention, that the proximity presumption rests on the NRC finding that persons living within the roughly 50-mile radius of the facility face a realistic risk of harm if a release from the facility of radioactive material were to occur, and that each of the Petitioners thus may base its standing upon a showing that its residence, or that of its members, is within the geographical zone that might be affected by an accidental release of fission products.

Staff and Entergy tried to avoid the unfortunate (for Staff and Entergy) fact that all of the Petitioners reside within the 50-mile proximity zone by pretending that this is somehow not licensing case, despite Entergys admission that this is a license proceeding[] (Entergy Opposition, p. 19).

EA-13-109 itself is titled, in bold and full capital letters, Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, and on page 10 says, again in full capital letters, that IT IS HEREBY ORDERED, EFFECTIVE IMMEDIATELY, THAT ALL LICENSES IDENTIFIED IN ATTACHMENT 1 TO THIS ORDER ARE MODIFIED AS FOLLOWS; and that these modifications amended Pilgrims operating license Staff and Entergy ignore also the plain fact that, as shown in Section II, above, Entergys Request would further amend Pilgrims current operating license (that includes the modifications made by EA-13-109) by changing the compliance dates that the amended license sets forth, This is a licensing case, and the proximity presumption principle applies.

13

B. Petitioners Also Proved their Traditional Right to Standing.

Even if this were not a licensing case, Petitioners would still have standing. See Staff Response, p. 9. The Staffs and Entergys arguments that Petitioners have not stated any obvious potential for offsite consequences. (Entergy Opposition, pp. 4, 19, 22; Staff Response, p. 18), and have only vaguely expressed the potential injury- in- fact to their property and financial interests and their health and safety, ignore both what Petitioners said in their Request and what the NRC found in EA-13-109.

1. Petitioners have shown the obvious potential for offsite consequences.

Entergys assertion that Petitioners did not even recognize or attempt to address the obvious potential for offsite consequences (Entergy Opposition, p. 20) is simply wrong.

Petitioners doubt that even Entergy would deny that a failure of Pilgrims containment would have an obvious potential for offsite consequences.

Petitioners Request repeatedly said that a containment failure could have dire consequences: letting Entergy remain out of compliance would deprive citizens of a severe capable wetwell vent that reduces the likelihood of containment failures and thereby enhances the defense-in-depth protections for plants with Mark I and Mark II containments; and would place Pilgrim, among other very important things, at a relatively high probability[y] that [its]

containment[s] would fail should an accident progress to melting the core. (Petitioners Request, p. 21)

Pilgrims request also quoted EA-13-109s explicit finding that a venting system should be available during severe accident conditions (to) enhance[e] the defense-in-depth characteristics of Mark I and Mark II containments by addressing the relatively high probabilities that those containments would fail should an accident progress to melting the core 14

(See Petitioners Request p. 22 quoting Order, p. 6, italics added), and that the Phase I requirements are needed to protect health and to minimize danger to life or property because they will give licensees greater capabilities to respond to severe accidents and limit the uncontrolled release of radioactive materials (See Petitioners Request, p. 21,quoting Order, p.

7, italics added) .

The NRC has long known that Pilgrims containment is too small (See Order, p. 2: small containments such as the Mark I and Mark II designs.). Does either the Staff or Entergy really believe that an uncontrolled release of radioactive materials would not have an obvious potential for offsite consequences?

2. Petitioners Expressed Concerns Are Not Vague.

The Staff admits that Petitioners Request says that all of the identified members of the petitioner organizations said that they are reasonably concerned that granting Entergys Request would adversely affect their financial interests and health and safety and that if Entergys Request is granted, it would deny Petitioners the protection a severe accident capable wetwell venting system would provide during at least the two remaining years of Pilgrims operations. Staff also admits that the two members of Beyond Nuclear assert that they are concerned that if the NRC grants Entergys Request, the continued operation of PNPS could adversely affect their lives, their families, their communities, and the environment, and that they are particularly concerned about the undue risk an extension to comply presents for an accidental release of radiation and the potential harm that it would cause to public health and the environment. (Staff Response, p. 17) 15

Entergys Opposition simply says that Petitioners statements that they are reasonably concerned about health and safety (Entergy Response, p. 20) and their property and financial interests are far too vague (Entergy Response, p. 20.

One wonders if the Staff or Entergy lawyers read, or simply failed to appreciate, what Petitioners said at pages 20-23 of Petitioners Request.

The NRC finding in EA-13-103, that there was at Pilgrim a high probability of an uncontrolled release of radioactive materials (See Petitioners Request, p. 21, quoting Order,

p. 7), would reasonably concern any person living near Pilgrim about their health and safety and about the effects that such a release would have on their property and financial interest; It certainly concerned the Petitioners.

Petitioners concrete and particularized concerns for their health, safety, and property and financial interests were heightened by the NRCs additional findings that the Phase 1s required installation of a reliable hardened venting system that is capable of performing under severe accident conditions is needed to protect health and safety and to minimize danger to life or property (Petitioners Request, p. 22, quoting EA-13-109, p. 7), and it was necessary to make the order immediately effective so that the required severe accident venting capability is provided with minimal delays. (EA-13-109, p. 4).

The Staffs apparent view that granting Entergys request to delay installation for at least two years of continued Pilgrim operation does not further demonstrate a concrete and particularized injury-in- fact (Staff Response, p. 17) defies common sense. The Commission said that the system is needed to protect health and safety and to minimize danger to life or property and that it should be installed with minimal delays. (EA-13-109, p. 4). The 16

Commission gave Pilgrim almost four years to install the system. Whether a four-year delay is minimal is open to question; at least six and a half years (from June of 2013 until December of 2019, and likely forever, is not.

Petitioners expressed concerns are based on EA-13-109 itself, and on also on Entergys attempt not only to delay, but to avoid ever having to do, what that Order requires. These concerns and the reasons that Petitioners have them. are concrete and particularized, and fully support their right to standing - even if we were to assume, contrary to fact and law, that Petitioners are not entitled to standing simply because of their proximity to Pilgrim. 9

3. Plaintiffs Right to Standing is not Negated by a Claim that Pilgrim already has a severe accident capable HCVS.

Entergy claims that Pilgrim already has a severe accident capable HCVS and that it has made diligent progress toward installing the features required by EA-13-109. (Entergy Response, p. 21). This statement admits that Entergy as of today has not met the Phase 1 requirements, and the Staff agrees that it has not. 10 If Pilgrim had already complied with EA 109, Entergy would not be requesting an extension to comply until after Pilgrim closed, and for so long as Pilgrim continues to operate to leave everyone near Pilgrim at risk without the modifications needed to protect health and to minimize danger to life or property because they will give licensees greater capabilities to respond to severe accidents and limit the uncontrolled release of radioactive materials. (Order, p.,7, quoted in Request at 21) 9 Although it is unlikely that the Commission will need to do, Petitioners point out that, at this stage of a proceeding, a petition must be construed in favor of the petitioners. Georgia Tech Research Reactor, Atlanta, Georgia, CLI 12, 42 NRC 111, 115 (1995) 10 The Staff says that Entergy admits that three are at least three areas in which the current design of [Pilgrims]

wetwell venting system does not meet EA-12-109s requirements. Staff Response, p. 5 17

Exactly what Energy has done, and how closely that might conform to EA-13-109, remain to be proved. Most important here is that Entergys allegations have nothing to do with Petitioners right to standing at the required189.a hearing. It will be for the ASLB to consider whether Entergys allegations are complete or correct, to consider all of the evidence, and then to decide whether and to what extent Pilgrims license should be amended.

4. The Petitioner Organizations Have Standing Petitioners do not dispute the Staffs statement that (Staff Response, p. 9) that Where an organization seeks to establish representational standing, it must demonstrate that at least one of its members would be affected by the proceeding and identify any such members by name and address. Also, the organization must show that the identified members would have standing to intervene in their own right, and that these members have authorized the organization to request a hearing on their behalf.

Petitioners have shown that at least one member of each organization would suffer an injury- in-fact if Entergys request were granted and thus would have standing in their own right. See Section III, above.

As for whether that these organization their named representative to act on their behalf, the Staff admits that the Pilgrim Watch and Beyond Nuclear representatives have shown that they are authorized.

Contrary to what the Staff says, the representatives of the other organization are authorized also. As said in Petitioners Request, Joseph Waldstein is an officer of the Pilgrim Coalition, Diane Turco is the Director of Cape Downwinders, and Paula Sharaga is Massachusetts Downwinders Boston area coordinator. PLAC and Cape Downwinders Cooperative are consensus based-organizations. Each delegated a member to represent the organization. CANs 18

director Deb Katz designated a member of the organization who resides within Pilgrims 50-mile zone. 11 IV. Entergys and the Staffs Other Arguments Are Wrong or Irrelevant A. Petitioners are not Challenging EA-13-109 Petitioners do not challenge any part of EA-13-109. It is Entergy, not Petitioners, that seeks to amend it.

Contrary to what Entergy says, Petitioners do not challenge the inclusion and/or substantive provisions of the Relaxation Provision (Entergy Opposition, p. 4; see also p. 14). Petitioners understand that such a provision is routinely included in Non-Enforcement Orders such as E 109. But it is clear that simply including such a provision in an Order could not excuse the Commission, or anyone to who it might delegate any of the Commissions authority, from complying with the Atomic Energy Act. 12 The Staff also seems to suggest that Petitioners are challenging the facts stated in the Order or the Orders remedy. Again, that is simply not so. Petitioners Request accepts that the facts stated in the Order are true, 13 and that the Orders remedy (compliance with the Phase I and II requirements by the date the Order set) is supported by those facts. See Public Service Co. of Indiana (Marble Hill Nuclear Generating Station), CLI-80-10, 11 NRC 438, 441 (1980), cited at

p. 7, fn. 31 of the Staff Response.

11 If the Commission wants affidavits/declarations, Petitioners will provide them.

12 It seems far from clear that the NRC has any right to delegate the question whether a Section 189.a is required.

See NRC Staff Practice and Procedure Digest, Section 2.10.4.1: In this vein, a more recent case reiterating the rule that a Licensing Board may not delegate its obligation to decide significant issues to the NRC Staff is Pub. Serv. Co.

of Ind. (Marble Hill Nuclear Generating Station, Units 1 & 2), ALAB-461, 7 NRC 313, 318 (1978).

13 These facts support Petitioners right to standing. See Section II, below.

19

B. Petitioners do not say that Entergy has not complied with the Order.

EA-13-109 109 requires Entergy to comply with the Phase 1 requirements no later than startup from the second refueling outage that begins after June 30, 2014, or June 30, 2018, whichever comes first (Order IV(B), p. 11); i.e., in the Spring of 2017 (Entergy Opposition, p.2). That date is several months in the future.

Entergy admits that what it has accomplished to date is not enough to meet all of the Phase 1 requirements, but Petitioners quite properly do not say that fact means that Entergy, as of today, has not complied with the Order.

As for the fact that Entergy did not submit anything pursuant to the notice requirement in Section IV.C.1 of the order (Staff Response, 11), Petitioners agree with the Staffs observation that the Order did not explicitly require[] Entergy to seek relaxation in the form of a license request (See Staff Response, pp. 14). 14 That said, whether Pilgrims license should be amended will, of course, be the central issue at the hearing to which Petitioners are entitled, and they expect to prove what Contention 1, Part 2 alleges at that hearing. Entergys decision not to make any filing under the notice requirement will be evidence the license should not be amended as Entergy requests, as will the fact that to be timely Entergys Request for Extension should have been filed as soon as Entergy knew that it intended to close Pilgrim early. 15 14 Petitioners similarly do not say that Entergy is barred from filing a request to amend its license by changing the compliance dates set forth in the Order. What if any amendment should be allowed is, of course, a question to be resolved at the required Section 189.a hearing.

15 The allegations made in Entergys request about the extent to which it has already complied in fact must be proved. At the hearing, Petitioner expect to prove that Pilgrim is fully capable of complying with the Phase requirements without any extension of the Orders dates, and that even Entergys allegations were to be proved, they would not justify amending the license to change the ordered compliance dates.

20

21 C. Petitioners Request is not outside the scope of hearings.

In saying that Petitioners claim is outside the scope of hearings (Staff Response, p.19) the Staff obviously failed to recognize that Citizens Awareness Network, Cleveland Electric Illuminating Co., and Cleveland Electric Illuminating Co, supra at pp. 5-6, all squarely held that a Petitioners Section 189.a. hearing rights are triggered when, as here, a licensee seeks, de facto or explicitly, to amend its license.

Rather, and not unexpectedly, the Staff turned to Bellotti and Marble Hill as its last refuge from conceding that Part 1 of Petitioners Contention is admissible. Neither supports the Staffs view.

In Bellotti¸ the D.C. Court of Appeals could not have more clearly said that (italics added)

The Commission's power to define the scope of a proceeding will lead to the denial of intervention only when the Commission amends a license to require additional or better safety measures. If, on the other hand, the Commission proposes to amend a license to remove a restriction upon the licensee, the scope of the proceeding is defined by that proposal and section 189(a) permits public participation to oppose that relaxation.

The NRCs Staff Practice and Procedure Digest, Section 2.10.4.1 Judicial Standing to Intervene, also shows that Bellotti and Marble Hill have potential relevance only if a Petitioner claims that an order in an enforcement should have provided more extensive relief and seeks to have the NRC impose a stricter penalty:

The Commission applies judicial tests of injury- in- fact and arguably within the zone of interest to determine standing. Injury as a premise to standing must come from an action, in contrast to failure to take an action. One who claims that an order in an enforcement action should have provided for more extensive relief does not show injury from relief granted and thus does not have standing to contest the order. Pub. Serv. Co. of Indiana (Marble Hill Nuclear Generating Station, Units 1 & 2), CLI-80-10, 11 NRC 438, 439 (1980); Maine Yankee Atomic 22

Power Co. (Maine Yankee Atomic Power Station), CLI-04-5, 59 NRC 52, 57-58 (2004).

One cannot seek to intervene in an enforcement proceeding to have the NRC impose a stricter penalty than the NRC seeks. Issues in enforcement proceedings are only those set out in the order. Public Service Co. of Indiana (Marble Hill Nuclear Generating Station, Units 1 & 2), CLI-80-10, 11 NRC 438, 442 (1980).

One who seeks a stricter penalty than the NRC proposes has no standing to intervene because it is not injured by the lesser penalty. Public Service Co. of Indiana (Marble Hill Nuclear Generating Station, Units 1 & 2), CLI-80-10, 11 NRC 438, 442 (1980).

State of Alaska Dept of Transp. and Pub. Facilities, CLI-04-26, 60 NRC 399, 404 (2004), reconsid. denied, CLI-04-38, 60 NRC 652 (2004).

The Commission may limit the issues in enforcement proceedings to whether the facts as stated in the order are true and whether the remedy selected is supported by those facts. Boston Edison Co. (Pilgrim Nuclear Power Station), CLI-82-16, 16 NRC 44, 45 (1982), affd sub nom. Bellotti v. NRC, 725 F.2d 1380 (D.C. Cir 1983); Public Service Co. of Indiana (Marble Hill Nuclear Generating Station, Units 1 & 2), CLI-80-10, 11 NRC 438, 441-442 (1980); Sequoyah Fuels Corp. (UF6 Production Facility),

CLI-86-19, 24 NRC 508, 512 n.2 (1986).

The Court of Appeals in Bellotti succinctly summarized why Petitioners contention that Entergys Request requires a Section 189.a hearing is admissible is NOT outside the scope of hearing:

[A]utomatic participation at a hearing may be denied only when the Commission is seeking to make a facility's operation safer. Public participation is automatic with respect to all Commission actions that are potentially harmful to the public health and welfare.

Granting Entergys request to delay making the required Fukushima fixes would not make Pilgrims operation less safe, and plainly would be potentially harmful to the public health and welfare.

D. Petitioners Contention is Admissible.

Petitioners have made a single Contention: Entergys Request for Extension to implement Phase 1 (severe accident capable wetwell venting system) should be denied. (Petitioners 23

Request, p.9). That Contention had four Parts. Part 1 says that Entergys Request should be denied because it in reality is a request to amend Entergys current license and that such an amendment cannot be granted without a hearing pursuant to Section 189.a of the Atomic Energy Act. See Section II, above. Parts 2-4 set forth reasons that that the Entergys request for delay in complying with the Order should be denied with or without a hearing, i.e., that

  • Entergys delay in making its Request until more than two and one-half years after EA-13-109 evidences that there is no good cause for extending the date for compliance for some two and one half more years.
  • Granting Entergys request would, for deny those near Pilgrim the protection of the reliable severe accident capable wetwell venting system for years longer than the Order envisioned.
  • Entergys supposed partial compliance with the Order is not a reason to delay completing implementation of what the Order requires.

Each of Parts I through IV provide reasons that Entergys Request should be denied, and that Petitioners contention is admissible V. Conclusion Entergys request to extend the date by which it must comply with the Phase I requirement is a de facto request to amend its current license and triggers Petitioners right to a hearing under Section 189.a of the Atomic Energy Act. The individual representatives of the organization petitioners have standing, and through them the organizations have standing also.

Petitioners Request for Hearing Regarding Entergys Request for Extension to comply with NRC Order EA-13-109 should be granted.

24

Respectfully submitted by Pilgrim Watch on behalf of Co-Petitioners, Signed (electronically) by Mary Lampert Pilgrim Watch, Director 148 Washington Street, Duxbury, MA 02332 Tel. 781-934-0389/Email: mary.lampert@comcast.net October 11, 2016 25

EXHIBIT A 26

EXHIBIT B 27

28 29 30 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE NUCLEAR REGULATORY COMMISSION In the Matter of Pilgrim 50-293-EA Entergys Request for Extension to Comply With NRC Order EA-13-109, Pilgrim Station October 11, 2016 CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305 (revised), I hereby certify that copies of the foregoing PETITIONERS RESPONSE TO NRC STAFFS AND ENTERGYS OPPOSITION TO PETITIONERS REQUEST FOR HEARING REGARDING ENTERGYS REQUEST FOR EXTENSION TO COMPLY WITH NRC ORDER EA-13-109 dated October 11, 2016 have been filed through the Electronic Information Exchange, the NRCs E-Filing System, in the above-captioned proceeding, on October 11, 2016.

(Signed (electronically) by, Mary Lampert Pilgrim Watch, Director 148 Washington Street, Duxbury, MA 02332 Tel. 781-934-0389/Email: mary.lampert@comcast.net October 11, 2016 31