|
|
Line 2: |
Line 2: |
| | number = ML101060365 | | | number = ML101060365 |
| | issue date = 04/19/2010 | | | issue date = 04/19/2010 |
| | title = Request for Additional Information, Regarding Individual Plant Examination (TAC No. ME3334) | | | title = Request for Additional Information, Regarding Individual Plant Examination |
| | author name = Milano P D | | | author name = Milano P D |
| | author affiliation = NRC/NRR/DORL/LPWB | | | author affiliation = NRC/NRR/DORL/LPWB |
Letter Sequence RAI |
---|
|
|
MONTHYEARML1004915352010-02-0909 February 2010 Probabilistic Risk Assessment Individual Plant Examination Summary Report Project stage: Request ML1004801162010-02-18018 February 2010 User Need Memorandum - Request for Review of Individual Plant Examination and Individual Plant Examination of External Events for Watts Bar Nuclear Plant, Unit 2 Project stage: Approval ML1010603652010-04-19019 April 2010 Request for Additional Information, Regarding Individual Plant Examination Project stage: RAI ML1016005592010-06-0808 June 2010 Request for Additional Information Regarding Individual Plant Examination Project stage: Request ML1016800722010-06-23023 June 2010 Supplemental Request for Additional Information Regarding Individual Plant Examination Project stage: RAI ML1022805852010-08-12012 August 2010 Request for Additional Information Regarding Individual Plant Examination Project stage: Request ML1103400402011-01-31031 January 2011 Request for Additional Information (RAI) Regarding Individual Plant Examination Project stage: Request ML1119602282011-08-12012 August 2011 Plant, Unit 2 - Review of Individual Plant Examination Submittal - Internal Events and Internal Flood Project stage: Approval ML14177A1672014-06-25025 June 2014 Probabilistic Risk Assessment (PRA) Summary Report - Information Previously Committed to Provide (TAC ME3334). Part 4 of 4 Project stage: Other ML14177A7262014-06-25025 June 2014 Probabilistic Risk Assessment (PRA) Summary Report - Information Previously Committed to Provide (TAC ME3334). Part 2 of 4 Project stage: Other ML14177A7252014-06-25025 June 2014 Probabilistic Risk Assessment (PRA) Summary Report - Information Previously Committed to Provide (TAC ME3334). Part 1 of 4 Project stage: Other ML14177A1662014-06-25025 June 2014 Probabilistic Risk Assessment (PRA) Summary Report - Information Previously Committed to Provide (TAC ME3334). Part 3 of 4 Project stage: Other 2010-06-08
[Table View] |
|
---|
Category:Letter
MONTHYEARCNL-24-080, Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011)2024-11-20020 November 2024 Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011) IR 05000390/20240032024-11-13013 November 2024 Integrated Inspection Report 05000390/2024003, 05000391/2024003 & 07201048/2024001 CNL-24-021, Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020)2024-11-12012 November 2024 Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020) IR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-014, License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22)2024-11-0404 November 2024 License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22) CNL-24-064, Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R52024-11-0404 November 2024 Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R5 CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) 2024-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24318A8602024-10-29029 October 2024 NRR E-mail Capture - Draft Request for Additional Information -Tennessee Valley Authority (TVA) License Amendment Request (LAR) to Revise Watts Bar TS 3.7.11 for Main Control Room Chiller Extension of Completion Time ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Revised the TVA Plants Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to TVAs Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21102A1312021-04-19019 April 2021 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 ML21095A0402021-04-0202 April 2021 NRR E-mail Capture - Request for Additional Information Re Generic Letter 95-05 90-Day Report and LAR to Adjust Growth Rate for Thot (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0422021-04-0202 April 2021 NRR E-mail Capture - Added Clarification to RAI 2 for Thot LAR ML21091A0772021-04-0101 April 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Technical Specification 5.7.2.19, Containment Leakage Rate Testing Program ML21095A0442021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0412021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0462021-03-22022 March 2021 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Generic Letter 95-05 90-Day Report for Watts Bar Unit 2 ML21039A6402021-02-0808 February 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 1 Technical Specifications Related to Steam Generator Tube Inspection Frequency ML21012A2032021-01-11011 January 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar UFSAR to Use Alternate Probability of Detection ML20350B5592020-12-15015 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Adopt Traveler TSTF-490 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20322A4412020-11-17017 November 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20322A4392020-11-0505 November 2020 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20308A3512020-11-0202 November 2020 Request for Additional Information on WBN Request for Exemption from 10 CFR Part 73, Appendix B, Section VI for the Conduct of an Annual Force-on-Force Exercise (EPID L-2020-LLE-0165 (COVID-19)) ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information ML20196L8622020-07-14014 July 2020 NRR E-mail Capture - Watts Bar Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Implement the Full Spectrum LOCA Methodology ML20086G4802020-03-26026 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) - Part 2 ML20085G3572020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20084M1942020-03-24024 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20083J3952020-03-12012 March 2020 NRR E-mail Capture - Draft Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML19340A6842019-12-0505 December 2019 NRR E-mail Capture - Request for Additional Information for WBN2 Request for One-Time Extension of Completion Time for TS 3.7.8 (L-2019-LLA-0020) ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19186A4352019-07-0505 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Correction to Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19169A3592019-06-18018 June 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19106A0462019-04-15015 April 2019 NRR E-mail Capture - Watts BAR, Units 1 and 2 Request for Additional Informatin (RAI) Regarding Changes to Technical Specifications Sections 3.8.1, 3.8.7, 3.8.8, and 3.8.9 ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program ML18313A2202018-11-0707 November 2018 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML18282A6372018-10-0909 October 2018 NRR E-mail Capture - RAIs (Final) - LAR to Revise the Steam Generator Technical Specifications for Watts Bar Nuclear Plant, Unit 2 2024-09-10
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 ADril 19, 2010 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 WATTS BAR NUCLEAR PLANT, UNIT 2 -REQUEST FOR ADDITIONAL INFORMATION REGARDING INDIVIDUAL PLANT EXAMINATION (TAC NO. ME3334)
Dear Mr. Bhatnagar:
In its letter dated February 9,2010, Tennessee Valley Authority (TVA) provided the results of the Individual Plant Evaluation (IPE) for Watts Bar Nuclear Plant, Unit 2 (WBN Unit 2). In U.S. Nuclear Regulatory Commission (NRC) Generic Letter (GL) 88-20, "Individual Plant Examination
[IPEl for Severe Accident Vulnerabilities," dated November 23,1988, as supplemented, the staff requested licensees and construction permit holders to perform a systematic examination to identify any plant-specific vulnerabilities to severe accidents and report the results to the NRC. The NRC staff is reviewing the IPE Summary Report in TVA's letter of February 9,2010, in support of the information requested in GL 88-20 for WBN Unit 2. The staff has determined that it needs additional information to complete its review. The specific information is detailed in the enclosed request for additional information (RAI). In this regard, the NRC staff requests a response to this RAI within 30 days of receipt of this letter. If you should have any questions, please contact me at 301-415-1457.
Sincerely, Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
RAI cc w/encl: Distribution via Listserv REQUEST FOR ADDITIONAL INFORMATION WADS BAR NUCLEAR PLANT, UNIT 2 INDIVIDUAL PLANT EXAMINATION AND PROBABILISTIC RISK ASSESSMENT TENNESSEE VALLEY AUTHORITY DOCKET NO. 50-391 In a letter dated February 9, 2010, Tennessee Valley Authority (TVA) provided the results of the Individual Plant Evaluation (IPE) for Watts Bar Nuclear Plant, Unit 2 (WBN Unit 2). In U.S. Nuclear Regulatory Commission (NRC) Generic Letter 88-20, "Individual Plant Examination
[IPE] for Severe Accident Vulnerabilities," dated November 23, 1988, as supplemented, the staff requested licensees and construction permit holders to perform a systematic examination to identify any plant-specific vulnerabilities to severe accidents and report the results to the NRC. In the February 9 letter, TVA provided an IPE summary report and stated that the IPE was performed in accordance with the applicable portions of American Society of Mechanical Engineers (ASME) Standard RA-Sb-2005, "Standard for Probabilistic Risk Assessment
[PRA] for Nuclear Power Applications," and NRC Regulatory Guide (RG) 1.200, Revision 1, "An Approach for Determining the Technical Adequacy of Probabilistic Risk Assessment Results for Risk Informed Activities." The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing this report and finds that additional information is needed to complete its review. The specific information is described as follows in this request for additional information: TVA states the IPE was performed using ASME Standard RA-Sb-2005.
However, it appears that the peer review that was performed used RA-Sa-2009.
Clarify which version of the standard was used to conduct the peer review. If RA-Sa-2009 was used, how were the differences addressed?
For example, if a requirement changed from 2005 to 2009 version, or a new requirement added, which specific findings and observations (F&Os) address these changes? If not included in the submittal, provide the F&Os. When the peer review was performed, did the peer review members take into account the NRC staff's positions on the requirements in the ASME standard as described in RG 1.200? If not, what was the basis for not considering the NRC position? The standard provides specific requirements for a peer review, and the NRC staff took a few exceptions to these in RG 1.200. How were the NRC exceptions to the peer review requirements addressed? As discussed in RG 1.200, meeting the standard involves both meeting the technical requirements and the peer review requirements as endorsed in RG 1.200. Should this be accomplished.
the NRC staff stated in RG 1.200 that a detailed staff review would be Enclosure
-2 obviated, allowing the staff to focus on, for example, assumptions.
In this regard, the staff finds the information in the submittal on the peer review to be very brief. Thus, address the following: The submittal states there are 112 F&O, but there only appears to be 50 F&Os submitted.
Even taking into account that some of the F&Os address more than one supporting requirement (SR), the number still does not add up to 112 F&Os. The submittal states that nine SRs were judged not applicable, and no justification or identification of these SRs was provided.
Which SRs from the standard were judged not applicable?
Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 WATTS BAR NUCLEAR PLANT, UNIT 2 -REQUEST FOR ADDITIONAL INFORMATION REGARDING INDIVIDUAL PLANT EXAMINATION (TAC NO. ME3334)
Dear Mr. Bhatnagar:
In its letter dated February 9, 2010, Tennessee Valley Authority (TVA) provided the results of the Individual Plant Evaluation (IPE) for Watts Bar Nuclear Plant, Unit 2 (WBN Unit 2). In U.S. Nuclear Regulatory Commission (NRC) Generic Letter (GL) 88-20, "Individual Plant Examination
[IPE] for Severe Accident Vulnerabilities," dated November 23, 1988, as supplemented, the staff requested licensees and construction permit holders to perform a systematic examination to identify any plant-specific vulnerabilities to severe accidents and report the results to the NRC. The NRC staff is reviewing the IPE Summary Report in TVA's letter of February 9,2010, in support of the information requested in GL 88-20 for WBN Unit 2. The staff has determined that it needs additional information to complete its review. The specific information is detailed in the enclosed request for additional information (RAI). In this regard, the NRC staff requests a response to this RAI within 30 days of receipt of this letter. If you should have any questions, please contact me at 301-415-1457.
Sincerely, IRA! Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
RAI cc w/encl: Distribution via Listserv DISTRIBUTION:
RidsOgcRp Resource RidsRgn2MailCenter Resource PUBLIC RidsNrrDorlLpwb Resource RidsResDraPrb Resource LPWB Reading File RidsNrrLABClayton Resource RidsNrrPMWattsBar2 Resource RidsAcrsAcnw_MailCTR Resource RidsNrrDoriDpr M. Drouin, RES ADAMS Accession No MI-101060365 OFFICE LPWB/PM LPWB/LA RES/DRAlPRB/BC OGC LPWB/BC NAME PMilano BClayton GDeMoss DRoth LRaQhavan DATE 04/16/10 04/16/10 04/09/10 04/16/10 04/19/10 OFFICIAL AGENCY RECORD