ML082120730: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML082120730
| number = ML082120730
| issue date = 08/27/2008
| issue date = 08/27/2008
| title = Limerick, Unit 1 - Tech Spec Pages for Amendment 154 Increase in Emergency Diesel Generator Day Tank Minimum Fuel Volume
| title = Tech Spec Pages for Amendment 154 Increase in Emergency Diesel Generator Day Tank Minimum Fuel Volume
| author name =  
| author name =  
| author affiliation = NRC/NRR/DORL/LPLI-2
| author affiliation = NRC/NRR/DORL/LPLI-2
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:                 (4)      Pursuant to the Act and 10 CFR Parts 30, 40, 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive* apparatus or components; and (5)      Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility, and to receive and possess, but not separate, such source, byproduct, and special nuclear materials as contained in the fuel assemblies and fuel channels from the Shoreham Nuclear Power Station.
C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below) and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)      Maximum Power Level Exelon Generation Company is authorized to operate the facility at reactor core power levels of 3458 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)      Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised.
through Amendment No. 154 , are hereby incorporated into this license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3)      Fire Protection (Section 9.5, SSER-2, -4)*
Exelon Generation Company shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report for the facility, and as approved in the NRC Safety Evaluation Report dated August 1983 through Supplement 9, dated August 1989, and Safety Evaluation dated November 20, 1995, subject to the following provision:
The licensee may make changes to the approved fire protection program without prior approval of the Commission only ifthose changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.
*The parenthetical notation following the title of license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition is discussed.
Amendment.No. 4, 27,-54-, 68, 92, -8  154
 
3/4.8    ELECTRICAL POWER SYSTEMS 3/4.8.1    A.C. SOURCES A.C. SOURCES    -  OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1, As a. minimum, the following A.C.      electrical power sources shall  be OPERABLE:
: a.      Two physically independent circuits between the offsite transmission network and the onsite Class lE distribution system, and
: b.      Four separate and independent diesel generators, each with:
: 1.      A separate day tank containing a minimum of 250 gallons of fuel,
: 2.      A separate fuel storage system containing a minimum of 33,500 gallons of fuel, and
: 3.      A separate fuel transfer pump.
APPLICABILITY:      OPERATIONAL CONDITIONS 1, 2,  and 3.
ACTION:
: a.      With one diesel generator of the above required A.C. electrical power.
sources inoperable, demonstrate the OPERABILITY of the remaining A.C.
sources by performing Surveillance Requirement 4.8.1.1.1.a within 24 hours and at least once per 7 days thereafter.      If the diesel generator became inoperable due to any cause other than an inoperable support system, an independently testable component, or preplanned preventive maintenance'or testing, demonstrate the OPERABILITY of the remaining. operable diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 for one diesel generator at a time, within 24 hours, unless the:absence of any potential common-mode failure for the remaining diesel generators is determined.      Restore the inoperable diesel generator to OPERABLE status within 30 days or be in at least HOT SHUTDOWN within the next 12 hours and in COLD SHUTDOWN within the following 24 hours. See also ACTION e.
: b.      With two diesel generators of the above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C.
sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour and at least once per 8 hours thereafter.      If either of the diesel generators became inoperable due to any cause other than an inoperable support system, an independently testable component, or preplanned preventive maintenance or testing, demonstrate the OPERABILITY of the remaining diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 for one diesel generator at a time, within 8 hours, unless the absence of any potential common-mode failure for the remaining diesel generators is determined.        Restore at least one of the inoperable diesel generators to OPERABLE status within 72 hours or be in at least HOT SHUTDOWN within the next 12 hours and in COLD SHUTDOWN within the following 24 hours.      See also ACTION e.
LIMERICK - UNIT 2                              3/4 8-1i                Amendment No. 4-9-4,154
 
FIFUTRTCAl POWER SYSTFMS A.C. SOURCES    SHUTDOWN LIMITING CONDITION FOR OPERATION 3.8.1.2 As a minimum,    the following A.C. electrical power sources shall be OPERABLE:
: a. One circuit between the offsite transmission network and the onsite Class 1E distribution system, and
: b. Two diesel generators each with:
: 1.      A day fuel tank containinga minimum of 250 gallons of fuel.
: 2.      A fuel storage system containing a minimum of 33,500 gallons of fuel.
: 3.      A fuel  transfer pump.
APPLICABILITY:    OPERATIONAL CONDITIONS 4,    5,  and
* ACTION:
: a. With less than the above required A.C. electrical power sources OPERABLE, suspend CORE ALTERATIONS, handlingof irradiated fuel in the secondary- containment, operations with a potential for draining the reactor vessel and crane operations over the spent fuel storage pool when fuel assemblies are stored therein.      In addition, when in OPERATIONAL CONDITION 5 with the water level less than 22 feet above the reactor pressure vessel flange, immediately initiate corrective action to restore the required power sources to OPERABLE status as soon as practical.
: b. The provisions of Specification 3.0.3 are not applicable.
SURVEILLANCE REOUIREMENTS 4.8.1.2 At least the above required A.C. electrical power sources shall be demonstrated OPERABLE per Surveillance Requirements 4.8.1.1.1 and 4.8.1.1.2.
*When  handling irradiated fuel in the secondary containment.
LIMERICK - UNIT 2                          3/4 8-9                Amendment No.A-    154}}

Latest revision as of 15:29, 14 November 2019

Tech Spec Pages for Amendment 154 Increase in Emergency Diesel Generator Day Tank Minimum Fuel Volume
ML082120730
Person / Time
Site: Limerick Constellation icon.png
Issue date: 08/27/2008
From:
Plant Licensing Branch 1
To:
Bamford, Peter J., NRR/DORL 415-2833
Shared Package
ML082120704 List:
References
TAC MD6600
Download: ML082120730 (3)


Text

(4) Pursuant to the Act and 10 CFR Parts 30, 40, 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive* apparatus or components; and (5) Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility, and to receive and possess, but not separate, such source, byproduct, and special nuclear materials as contained in the fuel assemblies and fuel channels from the Shoreham Nuclear Power Station.

C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below) and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1) Maximum Power Level Exelon Generation Company is authorized to operate the facility at reactor core power levels of 3458 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.

(2) Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised.

through Amendment No. 154 , are hereby incorporated into this license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

(3) Fire Protection (Section 9.5, SSER-2, -4)*

Exelon Generation Company shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Updated Final Safety Analysis Report for the facility, and as approved in the NRC Safety Evaluation Report dated August 1983 through Supplement 9, dated August 1989, and Safety Evaluation dated November 20, 1995, subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only ifthose changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

  • The parenthetical notation following the title of license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition is discussed.

Amendment.No. 4, 27,-54-, 68, 92, -8 154

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES A.C. SOURCES - OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1, As a. minimum, the following A.C. electrical power sources shall be OPERABLE:

a. Two physically independent circuits between the offsite transmission network and the onsite Class lE distribution system, and
b. Four separate and independent diesel generators, each with:
1. A separate day tank containing a minimum of 250 gallons of fuel,
2. A separate fuel storage system containing a minimum of 33,500 gallons of fuel, and
3. A separate fuel transfer pump.

APPLICABILITY: OPERATIONAL CONDITIONS 1, 2, and 3.

ACTION:

a. With one diesel generator of the above required A.C. electrical power.

sources inoperable, demonstrate the OPERABILITY of the remaining A.C.

sources by performing Surveillance Requirement 4.8.1.1.1.a within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and at least once per 7 days thereafter. If the diesel generator became inoperable due to any cause other than an inoperable support system, an independently testable component, or preplanned preventive maintenance'or testing, demonstrate the OPERABILITY of the remaining. operable diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 for one diesel generator at a time, within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, unless the:absence of any potential common-mode failure for the remaining diesel generators is determined. Restore the inoperable diesel generator to OPERABLE status within 30 days or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. See also ACTION e.

b. With two diesel generators of the above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C.

sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter. If either of the diesel generators became inoperable due to any cause other than an inoperable support system, an independently testable component, or preplanned preventive maintenance or testing, demonstrate the OPERABILITY of the remaining diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 for one diesel generator at a time, within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, unless the absence of any potential common-mode failure for the remaining diesel generators is determined. Restore at least one of the inoperable diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. See also ACTION e.

LIMERICK - UNIT 2 3/4 8-1i Amendment No. 4-9-4,154

FIFUTRTCAl POWER SYSTFMS A.C. SOURCES SHUTDOWN LIMITING CONDITION FOR OPERATION 3.8.1.2 As a minimum, the following A.C. electrical power sources shall be OPERABLE:

a. One circuit between the offsite transmission network and the onsite Class 1E distribution system, and
b. Two diesel generators each with:
1. A day fuel tank containinga minimum of 250 gallons of fuel.
2. A fuel storage system containing a minimum of 33,500 gallons of fuel.
3. A fuel transfer pump.

APPLICABILITY: OPERATIONAL CONDITIONS 4, 5, and

  • ACTION:
a. With less than the above required A.C. electrical power sources OPERABLE, suspend CORE ALTERATIONS, handlingof irradiated fuel in the secondary- containment, operations with a potential for draining the reactor vessel and crane operations over the spent fuel storage pool when fuel assemblies are stored therein. In addition, when in OPERATIONAL CONDITION 5 with the water level less than 22 feet above the reactor pressure vessel flange, immediately initiate corrective action to restore the required power sources to OPERABLE status as soon as practical.
b. The provisions of Specification 3.0.3 are not applicable.

SURVEILLANCE REOUIREMENTS 4.8.1.2 At least the above required A.C. electrical power sources shall be demonstrated OPERABLE per Surveillance Requirements 4.8.1.1.1 and 4.8.1.1.2.

LIMERICK - UNIT 2 3/4 8-9 Amendment No.A- 154