ML16113A218: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(4 intermediate revisions by the same user not shown)
Line 9: Line 9:
| docket = 05000295, 05000304
| docket = 05000295, 05000304
| license number =  
| license number =  
| contact person = Edwards R A
| contact person = Edwards R
| document type = Slides and Viewgraphs
| document type = Slides and Viewgraphs
| page count = 16
| page count = 16
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:Decommissioning Power Reactors:
Zion Decommissioning Project CRCPD - May 18, 2016
 
Safely remove a facility from service and reduce residual radioactivity to a level that permits:
(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1
 
2 3
Financial Safe Storage of Spent Equipment  Fuel    Community 4
 
5 Personnel Safety Radiological Safe            Decommissioning Storage of Spent Fuel            Environment Site Restoration 6
 
Decommissioning
* Fuel removed from            Inspections
* License termination core
* Transition from
* Inspection Manual Reactor Oversight    Chapter 2561 Process
* Flexible
* Inspection reports publicly available in ADAMS Enter Program                                End Program 8
 
Zion Nuclear Power Station
* Two unit Westinghouse Pressurized Water Reactor
* ~40 miles North of Chicago in Zion, IL
* Permanently Shutdown February 13, 1998
* License transfer to ZionSolutions on September 1, 2010 9
 
Zion Radiological Decommissioning Status Completed:
* Spent fuel transfer to Independent Spent Fuel Storage Installation
* Greater Than Class C (GTCC) waste removed
* Class B and C waste removed
* Demolition of Crib house and South Guardhouse 10
 
Zion Survey Units 11
* Final Status Surveys (FSS):
* Performed by licensee
* Demonstrate compliance with the release criteria
* Communication between regulator, licensee, and state
* Inspections during FSS:
* Evaluate compliance with License Termination Plan
* Independent confirmatory surveys
* NRC contract with Oak Ridge Associated Universities
* What happens after License Termination?
12
 
13 14 Safe Storage  Questions?
of Spent Fuel 15
 
Decommissioning Power Reactors:
Zion Decommissioning Project CRCPD - May 18, 2016
 
Safely remove a facility from service and reduce residual radioactivity to a level that permits:
(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1
 
2 3
Financial Safe Storage of Spent Equipment  Fuel    Community 4
 
5 Personnel Safety Radiological Safe            Decommissioning Storage of Spent Fuel            Environment Site Restoration 6
 
Decommissioning
* Fuel removed from            Inspections
* License termination core
* Transition from
* Inspection Manual Reactor Oversight    Chapter 2561 Process
* Flexible
* Inspection reports publicly available in ADAMS Enter Program                                End Program 8
 
Zion Nuclear Power Station
* Two unit Westinghouse Pressurized Water Reactor
* ~40 miles North of Chicago in Zion, IL
* Permanently Shutdown February 13, 1998
* License transfer to ZionSolutions on September 1, 2010 9
 
Zion Radiological Decommissioning Status Completed:
* Spent fuel transfer to Independent Spent Fuel Storage Installation
* Greater Than Class C (GTCC) waste removed
* Class B and C waste removed
* Demolition of Crib house and South Guardhouse 10
 
Zion Survey Units 11
* Final Status Surveys (FSS):
* Performed by licensee
* Demonstrate compliance with the release criteria
* Communication between regulator, licensee, and state
* Inspections during FSS:
* Evaluate compliance with License Termination Plan
* Independent confirmatory surveys
* NRC contract with Oak Ridge Associated Universities
* What happens after License Termination?
12
 
13 14 Safe Storage  Questions?
of Spent Fuel 15}}

Latest revision as of 20:43, 30 October 2019

Decommissioning Power Reactors: Zion Decommissioning Project; Crcpd Presentation
ML16113A218
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 05/18/2016
From:
NRC/RGN-III
To:
Edwards R
References
Download: ML16113A218 (16)


Text

Decommissioning Power Reactors:

Zion Decommissioning Project CRCPD - May 18, 2016

Safely remove a facility from service and reduce residual radioactivity to a level that permits:

(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1

2 3

Financial Safe Storage of Spent Equipment Fuel Community 4

5 Personnel Safety Radiological Safe Decommissioning Storage of Spent Fuel Environment Site Restoration 6

Decommissioning

  • Fuel removed from Inspections
  • License termination core
  • Transition from
  • Inspection Manual Reactor Oversight Chapter 2561 Process
  • Flexible
  • Inspection reports publicly available in ADAMS Enter Program End Program 8

Zion Nuclear Power Station

  • Two unit Westinghouse Pressurized Water Reactor
  • ~40 miles North of Chicago in Zion, IL
  • Permanently Shutdown February 13, 1998
  • License transfer to ZionSolutions on September 1, 2010 9

Zion Radiological Decommissioning Status Completed:

  • Spent fuel transfer to Independent Spent Fuel Storage Installation
  • Greater Than Class C (GTCC) waste removed
  • Class B and C waste removed
  • Demolition of Crib house and South Guardhouse 10

Zion Survey Units 11

  • Final Status Surveys (FSS):
  • Performed by licensee
  • Demonstrate compliance with the release criteria
  • Communication between regulator, licensee, and state
  • Inspections during FSS:
  • Evaluate compliance with License Termination Plan
  • Independent confirmatory surveys
  • NRC contract with Oak Ridge Associated Universities
  • What happens after License Termination?

12

13 14 Safe Storage Questions?

of Spent Fuel 15

Decommissioning Power Reactors:

Zion Decommissioning Project CRCPD - May 18, 2016

Safely remove a facility from service and reduce residual radioactivity to a level that permits:

(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1

2 3

Financial Safe Storage of Spent Equipment Fuel Community 4

5 Personnel Safety Radiological Safe Decommissioning Storage of Spent Fuel Environment Site Restoration 6

Decommissioning

  • Fuel removed from Inspections
  • License termination core
  • Transition from
  • Inspection Manual Reactor Oversight Chapter 2561 Process
  • Flexible
  • Inspection reports publicly available in ADAMS Enter Program End Program 8

Zion Nuclear Power Station

  • Two unit Westinghouse Pressurized Water Reactor
  • ~40 miles North of Chicago in Zion, IL
  • Permanently Shutdown February 13, 1998
  • License transfer to ZionSolutions on September 1, 2010 9

Zion Radiological Decommissioning Status Completed:

  • Spent fuel transfer to Independent Spent Fuel Storage Installation
  • Greater Than Class C (GTCC) waste removed
  • Class B and C waste removed
  • Demolition of Crib house and South Guardhouse 10

Zion Survey Units 11

  • Final Status Surveys (FSS):
  • Performed by licensee
  • Demonstrate compliance with the release criteria
  • Communication between regulator, licensee, and state
  • Inspections during FSS:
  • Evaluate compliance with License Termination Plan
  • Independent confirmatory surveys
  • NRC contract with Oak Ridge Associated Universities
  • What happens after License Termination?

12

13 14 Safe Storage Questions?

of Spent Fuel 15