ML23221A243

From kanterella
Jump to navigation Jump to search

Final Summer 2023 Confirmatory Survey Criteria
ML23221A243
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 08/10/2023
From: Caponi L, Gregory Chapman, Karen Pinkston, Amy Snyder
Exelon Generation Co
To:
Office of Nuclear Material Safety and Safeguards
Snyder, Amy 301-415-6822
References
Download: ML23221A243 (18)


Text

Zion Nuclear Power Station Summer 2023 Final Confirmatory Survey Scope and Methods ZION TEAM:

Amy Snyder, Greg Chapman, Karen Pinkston, and Louis Caponi

Executive Summary

  • Staff plan to conduct & complete 2 surveys (surface and subsurface) that will detect radionuclides of concern (per LTP) as residual contamination and DRPs/DROs (to confirm DRP/DRO identification and remediation)
  • Hand scanning for DRPs/DROs will be conducted using the same methodology as ZionSolutions used for its hand scanning in its DRP Data Quality Objectives.
  • The depth of subsurface investigations for DRPs will be no deeper than ZS surface cover or backfill as identified in the LTP. Subsurface sampling will be statistically based.
  • All DRPs identified, if any, will be removed.
  • If DRPs are found, staff will also leverage RES sponsored Dose Coefficients for Discrete Radioactive Particles to determine if any are of concern (dose over regulatory limit) and document in SER.
  • The completion of the planned surveys will provide NRC valuable data to risk inform future decision making.
  • Staff set a threshold of 10 DRPs of concern to trigger Zion explanation of extent of condition (localized and removed) or if not localized whether the licensee wants to proceed with additional remediation under approved LTP or if the Licensee wants to choose to submit a LTP LAR for residual DRPs to demonstrate compliance with regulations.

2

Scope of ORISE Surveys:

  • 100% of previously not-hand scanned survey
  • Surveys can reasonably detect radionuclides units bounded by previously identified DRPs (see previously identified onsite either as residual Surface slide 6)
  • Low coverage survey of hand-scanned areas contamination or as a DRP*

Surveys (~10% scan) to confirm the licensees hand scan

  • Judgement sample collection
  • Sufficient areas are excavated to reasonably characterize subsurface (computer-based statistical sampling)
  • Presence or Absence survey provides reasonable assurance for subsurface excavation DRP characterization
  • Presence or Absence survey technique (see
  • Leverage RES sponsored Dose Coefficients for Subsurface slide 9)
  • Excavate (grid or transects) to ~3 and scan Discrete Radioactive Particles May 2023 to identify Surveys excavation and spoils before backfilling DRPs of concern.
  • Statistical sample collection
  • NRC staff understands the term DRP to mean discrete radioactive particle or object 3

Survey Design Criteria: Surface Scans

  • Hand scan using the same methodology as ZionSolutions (ZS) used for its hand scanning in its DRP Data Quality Objectives (DQOs)
  • Leveraging the Minimum Detectable Concentrations provided by ORISE in Estimating Scan Minimum Detectable Activities of Discrete Radioactive Particles Technical Report, dated October 31, 2022 (ML22304A137), as the licensee did not provide one in the RAI Response.
  • Perform hand scans using appropriate detector and scan speed
  • ORISE to collect and remove any DRP found and send to lab for analysis; NRC staff to document in SER 4

Surface Survey Decision: Survey Unit Inclusion and Coverage (See Slide 6 for Map)

Does the NRC have reasonable assurance Yes the area is unlikely to No ORISE surveys planned.

have DRPs based on information gathered to date?

No Did ZionSolutions hand Yes ORISE to conduct low coverage survey ~100 % of the survey needed (10%) to confirm area using Zions DRP the licensees hand scan Perform some DQOs?

judgmental surveys as deemed necessary in field No ORISE surveys needed (100%)

specific for DRPs

Zion Site Map: Areas not Included in ORISE Survey ISFSI: Not in Scope Switchyard Scoped out of ORISE Survey: NRC has reasonable assurance based on site history, process knowledge, ISFSI and April 2021 ORISE surveys 6

Zion Site Map:

Areas Included in ORISE Surface Survey Not currently in scope ORISE Survey 10% (NRC verification)-

ZS handed scanned areas ORISE Survey 100% (Confirmatory Surveys needed for reasonable assurance) ISFSI

- Scan speed for DRPs and past contamination control practices 7

Survey Design Criteria: Subsurface Survey

  • Presence or Absence survey technique- randomized grid or trench transect sampling, statistically based. Would only tell one about the sampling location, may be used to estimate number of DRPs if distribution considered homogeneous.
  • Excavate (grid or if appropriate based on topography, trench transects) to ~3 below ground surface or depth of cover and scan excavation and spoils before backfilling (based on cover requirements in LTP) - e.g., grided 1m x 1m x 1m areas selected in the survey unit(s) of interest.
  • ORISE will remove and send DRPs, if found, to lab for analysis.
  • From lab results, the staff to conservatively estimate size/calculate dose to determine whether LLBP could apply or if a potential site issue.

8

Subsurface Survey Decision: Survey Unit Inclusion and Coverage (See Slide 10 for Map)

Does the NRC have reasonable assurance the area Yes is unlikely to have DRPs based No ORISE surveys planned.

on information gathered to date?

No Yes Excavate and scan excavation surface and spoils Soil disturbed at depth >6 (statistically based sampling and analysis plan over inches?

area)

No No ORISE surveys planned.

9

Zion Site Map:

Areas Included in ORISE Subsurface Survey Not currently in scope of ORISE survey (from slide 5)

Scoped out of ORISE subsurface survey Included in Presence or Absence ORISE subsurface survey ISFSI 10

Risk-Informed Scenarios Based on Results of Confirmatory Survey Decision Criteria

3) Less than 10 total DRPs of concern 4) 10 or more total DRPs of concern are
1) Zero DRPs are found onsite 2) DRPs found are found and removed found and removed
  • Document in SER Staff to evaluate DRP survey *Conduct Subsurface Survey
  • Conduct Subsurface Survey
  • Finalize PSR review results: *Document in SER
  • Document in SER & hold need additional FSS information
  • NRC staff to consider factors Guideline:
  • ZS to evaluate extent of condition-listed on slide 11 explanation or via sampling and
  • See slide 11 for factors for analysis *ZS to evaluate extent of analysis of, as applicable, based on of DRP survey results condition, if needed. survey results: may cover any
  • If less than 10 DRPs of concern are combination of the following based on identified, proceed to Step 3. site specific results:
  • If 10 or more DRPs of concern are
  • If the potential dose is >100 1.Specific subsurface survey units identified, proceed to Step 4. mrem TEDE for LLBP or >50 rem where DRPs were found where >6
  • NRC staff does not have SDE, then we are outside cover applied after FSS reasonable assurance that DRPs precedent - then go to Step 4 (last 2.Surface DRPs found at perimeter of two bullets) ORISE survey boundary are not a site characteristic.

3.Survey unit where DPR was found that ORISE scanned at 10% coverage.

  • If LLPB potential dose still not acceptable, PSR review delayed until either:
  • ZS remediates, as necessary, and re-performs FSS for those survey units that indicate unreasonable risk to the public (do not meet dose criterion for LLBP) OR
  • ZS submits an LTP LAR to address leaving some DRPs behind to meet the NRC regulatory requirements.

11

Factors for evaluating survey results for PSR review Factors determining DRP of Concern Notes Weight Quantity: Related to reasonable assurance of adequate protection over the large area (more area covered than Medium General criteria is less than 10 total 2021 Confirmatory Survey) based on:

DRPs found and removed through

  • At least 10 DRPs would exceed expectations for misses during the FSS and indicate that previously collection conducted FSSs were inadequate to identify and remove DRPs.
  • Staff professional technical judgement Analysis:

Location DRPs found are localized to one area versus DRPs found spread across large portions/the entirety of the Medium site Size DRP: <1mm Low DRO: >1mm Radionuclide mix If DRPs found contain radionuclides that are consistent with the majority of other DRPs found onsite Low and have minor dose consequence as a particle (e.g., Eu particles of concrete or Co-60 activated metal vs spent fuel particle).

If DRPs found contain other radionuclides (i.e., Am-241, etc.) and/or were easily detectable by ORISE survey techniques.

Activity/Dose If the potential dose is under the 25 mrem/y TEDE criteria or 100 mrem/y TEDE LLBP precedent and 50 High rem SDE occupational dose criteria.

If the potential dose is >100 mrem TEDE for LLBP or >50 rem SDE, then we are outside precedent and there are potential policy issues (will not be determined until after survey is completed)

Depth of DRP(s) (surface vs. subsurface) will be considered for dose assessment. All DRPs found were on the surface.

Conclusions needed to Approve the Zion PSR

  • In accordance with 10 CFR 50.82(a)(11), the Commission shall terminate the license if it determines that:
  • (i) the remaining dismantlement has been performed in accordance with the approved LTP, and
  • (ii) the final radiation survey and associated documentation, including an assessment of dose contributions associated with parts released for use before approval of the LTP, demonstrate that the facility and site have met the criteria for decommissioning in 10 CFR Part 20, Subpart E
  • 10 CFR 20, Subpart E, unrestricted release are met
  • Dose criteria in 10 CFR 20.1402 (25 mrem/yr +ALARA, less likely but plausible dose is acceptable

[NRC precedent is to accept non-compliance doses up to 100 mrem/yr using less likely but plausible scenarios])

  • Site has been adequately characterized to make a determination that Subpart E is met (10 CFR 20 Subpart F must be met to ensure compliance with Subpart E)
  • Site conditions are within the bounds of the previously approved LTP 13

Summary

  • NRC initiated survey will be completed in its entirety
  • Data will provide additional information on the site characterization
  • DRPs identified will be collected and removed
  • Staff will use key factors to determine if DRPs found should be considered a concern for the PSR
  • Staff sure and depth of sub subsurface will be consistent with ZSs requirements within the LTP
  • Staff will consider feedback from FO and subsequently ZS on the initial survey plan before finalizing.
  • Staff will share with FO detailed survey plan once developed and prior to ZS 14

Backup Slides:

15

Particles Identified during Redo of FSS in 2021 of the 12203 and 12112-12113 Survey Units 16

Green and Yellow areas:

orange areas: DRPs found hand-scanned either on with DRP surface or at DQOs depth (<1 ft) 17

Survey Units -

ZS Performed Surface Light purple areas:

towed array and Surveys Using DRP Data hand scan for DRPs Quality Objectives (DQOs)

Post April 2021 18