Decommissioning Power Reactors:

Zion Decommissioning Project CRCPD - May 18, 2016

Safely remove a facility from service and reduce residual radioactivity to a level that permits:

(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1

2

3

Safe Storage of Spent Fuel Equipment Financial Community 4

5

Safe Storage of Spent Fuel Personnel Safety Radiological Decommissioning Environment Site Restoration 6

  • Fuel removed from core
  • Transition from Reactor Oversight Process Enter Program
  • Flexible
  • Inspection reports publicly available in ADAMS Decommissioning Inspections
  • License termination End Program 8

Zion Nuclear Power Station

  • ~40 miles North of Chicago in Zion, IL
  • Permanently Shutdown February 13, 1998
  • License transfer to ZionSolutions on September 1, 2010 9

Completed:

  • Spent fuel transfer to Independent Spent Fuel Storage Installation
  • Greater Than Class C (GTCC) waste removed
  • Class B and C waste removed
  • Demolition of Crib house and South Guardhouse Zion Radiological Decommissioning Status 10

11 Zion Survey Units

  • Final Status Surveys (FSS):

Performed by licensee Demonstrate compliance with the release criteria Communication between regulator, licensee, and state

  • Inspections during FSS:

Evaluate compliance with License Termination Plan Independent confirmatory surveys NRC contract with Oak Ridge Associated Universities

  • What happens after License Termination?

12

13

14

Safe Storage of Spent Fuel Questions?

15

Decommissioning Power Reactors:

Zion Decommissioning Project CRCPD - May 18, 2016

Safely remove a facility from service and reduce residual radioactivity to a level that permits:

(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1

2

3

Safe Storage of Spent Fuel Equipment Financial Community 4

5

Safe Storage of Spent Fuel Personnel Safety Radiological Decommissioning Environment Site Restoration 6

  • Fuel removed from core
  • Transition from Reactor Oversight Process Enter Program
  • Flexible
  • Inspection reports publicly available in ADAMS Decommissioning Inspections
  • License termination End Program 8

Zion Nuclear Power Station

  • ~40 miles North of Chicago in Zion, IL
  • Permanently Shutdown February 13, 1998
  • License transfer to ZionSolutions on September 1, 2010 9

Completed:

  • Spent fuel transfer to Independent Spent Fuel Storage Installation
  • Greater Than Class C (GTCC) waste removed
  • Class B and C waste removed
  • Demolition of Crib house and South Guardhouse Zion Radiological Decommissioning Status 10

11 Zion Survey Units

  • Final Status Surveys (FSS):

Performed by licensee Demonstrate compliance with the release criteria Communication between regulator, licensee, and state

  • Inspections during FSS:

Evaluate compliance with License Termination Plan Independent confirmatory surveys NRC contract with Oak Ridge Associated Universities

  • What happens after License Termination?

12

13

14

Safe Storage of Spent Fuel Questions?

15