ML16113A218

From kanterella
Jump to navigation Jump to search
Decommissioning Power Reactors: Zion Decommissioning Project; Crcpd Presentation
ML16113A218
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 05/18/2016
From:
NRC/RGN-III
To:
Edwards R
References
Download: ML16113A218 (16)


Text

Decommissioning Power Reactors:

Zion Decommissioning Project CRCPD - May 18, 2016

Safely remove a facility from service and reduce residual radioactivity to a level that permits:

(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1

2 3

Financial Safe Storage of Spent Equipment Fuel Community 4

5 Personnel Safety Radiological Safe Decommissioning Storage of Spent Fuel Environment Site Restoration 6

Decommissioning

  • Fuel removed from Inspections
  • License termination core
  • Transition from
  • Inspection Manual Reactor Oversight Chapter 2561 Process
  • Flexible
  • Inspection reports publicly available in ADAMS Enter Program End Program 8

Zion Nuclear Power Station

  • ~40 miles North of Chicago in Zion, IL
  • Permanently Shutdown February 13, 1998
  • License transfer to ZionSolutions on September 1, 2010 9

Zion Radiological Decommissioning Status Completed:

  • Spent fuel transfer to Independent Spent Fuel Storage Installation
  • Greater Than Class C (GTCC) waste removed
  • Class B and C waste removed
  • Demolition of Crib house and South Guardhouse 10

Zion Survey Units 11

  • Final Status Surveys (FSS):
  • Performed by licensee
  • Demonstrate compliance with the release criteria
  • Communication between regulator, licensee, and state
  • Inspections during FSS:
  • Evaluate compliance with License Termination Plan
  • Independent confirmatory surveys
  • NRC contract with Oak Ridge Associated Universities
  • What happens after License Termination?

12

13 14 Safe Storage Questions?

of Spent Fuel 15

Decommissioning Power Reactors:

Zion Decommissioning Project CRCPD - May 18, 2016

Safely remove a facility from service and reduce residual radioactivity to a level that permits:

(a) release of the property for unrestricted use, and terminate the license; or (b) release of the property under restricted conditions, and terminate the license 1

2 3

Financial Safe Storage of Spent Equipment Fuel Community 4

5 Personnel Safety Radiological Safe Decommissioning Storage of Spent Fuel Environment Site Restoration 6

Decommissioning

  • Fuel removed from Inspections
  • License termination core
  • Transition from
  • Inspection Manual Reactor Oversight Chapter 2561 Process
  • Flexible
  • Inspection reports publicly available in ADAMS Enter Program End Program 8

Zion Nuclear Power Station

  • ~40 miles North of Chicago in Zion, IL
  • Permanently Shutdown February 13, 1998
  • License transfer to ZionSolutions on September 1, 2010 9

Zion Radiological Decommissioning Status Completed:

  • Spent fuel transfer to Independent Spent Fuel Storage Installation
  • Greater Than Class C (GTCC) waste removed
  • Class B and C waste removed
  • Demolition of Crib house and South Guardhouse 10

Zion Survey Units 11

  • Final Status Surveys (FSS):
  • Performed by licensee
  • Demonstrate compliance with the release criteria
  • Communication between regulator, licensee, and state
  • Inspections during FSS:
  • Evaluate compliance with License Termination Plan
  • Independent confirmatory surveys
  • NRC contract with Oak Ridge Associated Universities
  • What happens after License Termination?

12

13 14 Safe Storage Questions?

of Spent Fuel 15