| | number = ML18030B076 | | | number = ML18030B076 |
| | issue date = 03/13/2018 | | | issue date = 03/13/2018 |
| | title = Edwin I. Hatch Nuclear Plant, Units 1 and 2 Staff Assessment of Flooding Focused Evaluation (CAC Nos. MF9687 and MF9868;EPID Nos. 00495/05000321/L-2017-JLD-0029 and 000495/0500366/L-2017-JLD-0029)(Public) | | | title = Staff Assessment of Flooding Focused Evaluation (CAC Nos. MF9687 and MF9868;EPID Nos. 00495/05000321/L-2017-JLD-0029 and 000495/0500366/L-2017-JLD-0029)(Public) |
| | author name = Vega F G | | | author name = Vega F |
| | author affiliation = NRC/NRR/DLP/PBMB | | | author affiliation = NRC/NRR/DLP/PBMB |
| | addressee name = Hutto J J | | | addressee name = Hutto J |
| | addressee affiliation = Southern Nuclear Operating Co, Inc | | | addressee affiliation = Southern Nuclear Operating Co, Inc |
| | docket = 05000321, 05000366 | | | docket = 05000321, 05000366 |
Line 14: |
Line 14: |
| | document type = Letter | | | document type = Letter |
| | page count = 12 | | | page count = 12 |
| | project = CAC:MF9687, EPID:L-2017-JLD-0029, CAC:MF9868 | | | project = CAC:MF9687, CAC:MF9868, EPID:L-2017-JLD-0029 |
| | stage = Other | | | stage = Other |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:OFFICIAL USE ONLY: SEGURITY-RElATED INFORMATION UNITED ST ATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 13, 2018 Mr. J. J. Hutto Regulatory Affairs Director Southern Nuclear Operating Co., Inc. P.O. Box 1295 /BIN B038 Birmingham, AL 35201-1295 | | {{#Wiki_filter:OFFICIAL USE ONLY: SEGURITY-RElATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 13, 2018 Mr. J. J. Hutto Regulatory Affairs Director Southern Nuclear Operating Co., Inc. |
| | P.O. Box 1295 /BIN B038 Birmingham, AL 35201-1295 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -STAFF ASSESSMENT OF FLOODING FOCUSED EVALUATION (CAC NOS. MF9687 AND MF9868; EPID NOS. 000495/05000321/L-2017-JLD-0029 AND 000495/05000366/L-2017-JLD-0029) | | EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 - STAFF ASSESSMENT OF FLOODING FOCUSED EVALUATION (CAC NOS. MF9687 AND MF9868; EPID NOS. 000495/05000321/L-2017-JLD-0029 AND 000495/05000366/L-2017-JLD-0029) |
|
| |
|
| ==Dear Mr. Hutto:== | | ==Dear Mr. Hutto:== |
| By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f), "Conditions of Licenses" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTTF) report (ADAMS Accession No. ML 111861807). Enclosure 2 to the 50.54(f) letter requested that licensees reevaluate flood hazards for their sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML 12056A046). By letter dated March 6, 2014 (ADAMS Accession No. ML 14069A054), Southern Nuclear Operating Company, Inc. (SNC, the licensee) responded to this request for Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch). After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML 15321 A 156), the NRG issued an interim staff response (ISR) letter for Hatch. The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for other assessments associated with NITF Recommendation 2.1 "Flooding". As stated in the letter, because the local intense precipitation (LIP) and Combined Effects Flooding (Probable Maximum Flood (PMF) with upstream dam overtopping with wind-induced waves) are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. Enclosure 1 transmitted herewith contains Security-Related Information. When separated from Enclosure 1, this document is decontrolled. OFFIGIAb USE ONLY: SECURITY.RELATED INF9RMATION J. Hutto OFFICIAL USE C>NLY SECURfT¥-RELATED INFORMATION By letter dated June 22, 2017 (ADAMS Accession No. ML 17173A777), the licensee submitted the focused evaluation (FE) for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters; 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. The purpose of this letter is to provide the NRC's assessment of the Hatch FE. As set forth in the attached staff assessment, the NRC staff has concluded that the Hatch FE was performed consistent with the guidance described in Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML 16165A178). Guidance document NEI 16-05, Revision 1, has been endorsed by Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML 16162A301 ). The NRC staff has further concluded that the licensee has demonstrated that effective flood protection, if appropriately implemented, exists for the LIP and Combined Effects Flooding mechanisms during a beyond-design-basis external flooding event at Hatch. This closes out the licensee's response for Hatch for the reevaluated flooding hazard portion of the 50.54(f) letter and the NRC's efforts associated with CAC Nos. MF9687 and MF9868. If you have any questions, please contact me at 301-415-1617 or at Frankie.Vega@nrc.gov. | | |
| | By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f), "Conditions of Licenses" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTTF) report (ADAMS Accession No. ML111861807). Enclosure 2 to the 50.54(f) letter requested that licensees reevaluate flood hazards for their sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML12056A046). By letter dated March 6, 2014 (ADAMS Accession No. ML14069A054), |
| | Southern Nuclear Operating Company, Inc. (SNC, the licensee) responded to this request for Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch). |
| | After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML15321A156), the NRG issued an interim staff response (ISR) letter for Hatch. |
| | The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for other assessments associated with NITF Recommendation 2.1 "Flooding". As stated in the letter, because the local intense precipitation (LIP) and Combined Effects Flooding (Probable Maximum Flood (PMF) with upstream dam overtopping with wind-induced waves) are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. |
| | Enclosure 1 transmitted herewith contains Security-Related Information. When separated from Enclosure 1, this document is decontrolled. |
| | OFFIGIAb USE ONLY: SECURITY.RELATED INF9RMATION |
| | |
| | OFFICIAL USE C>NLY SECURfT¥-RELATED INFORMATION J. Hutto By letter dated June 22, 2017 (ADAMS Accession No. ML17173A777), the licensee submitted the focused evaluation (FE) for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters; |
| | : 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. The purpose of this letter is to provide the NRC's assessment of the Hatch FE. |
| | As set forth in the attached staff assessment, the NRC staff has concluded that the Hatch FE was performed consistent with the guidance described in Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML16165A178). Guidance document NEI 16-05, Revision 1, has been endorsed by Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML16162A301 ). The NRC staff has further concluded that the licensee has demonstrated that effective flood protection, if appropriately implemented, exists for the LIP and Combined Effects Flooding mechanisms during a beyond-design-basis external flooding event at Hatch. This closes out the licensee's response for Hatch for the reevaluated flooding hazard portion of the 50.54(f) letter and the NRC's efforts associated with CAC Nos. MF9687 and MF9868. |
| | If you have any questions, please contact me at 301-415-1617 or at Frankie.Vega@nrc.gov. |
| | Sincerely, Fra~i:anager Beyond-Design-Basis Management Branch Division of Licensing Projects Office of Nuclear Reactor Regulation |
|
| |
|
| ==Enclosures:== | | ==Enclosures:== |
| 1 . Staff Assessment Related to the Flooding Focused Evaluation for Hatch (non-public) 2. Staff Assessment Related to the Flooding Focused Evaluation for Hatch (public) Docket Nos: 50-321 and 50-366 cc w/encl: Distribution via Listserv Sincerely, Fra~i:anager Beyond-Design-Basis Management Branch Division of Licensing Projects Office of Nuclear Reactor Regulation OFFIGIAL USE ONbY-SECURIT¥-RELATED INFORMATION OFFICIAL USE ONL¥-SEGURIT¥-RELATED INFORMATION STAFF ASSESSMENT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO THE FOCUSED EVALUATION FOR EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 AS A RESULT OF THE REEVALUATED FLOODING HAZARD NEAR-TERM TASK FORCE RECOMMENDATION 2.1 -FLOODING (CAC NOS. MF9687 AND MF9868) | | : 1. Staff Assessment Related to the Flooding Focused Evaluation for Hatch (non-public) |
| | : 2. Staff Assessment Related to the Flooding Focused Evaluation for Hatch (public) |
| | Docket Nos: 50-321 and 50-366 cc w/encl: Distribution via Listserv OFFIGIAL USE ONbY- SECURIT¥-RELATED INFORMATION |
| | |
| | OFFICIAL USE ONL¥-SEGURIT¥-RELATED INFORMATION STAFF ASSESSMENT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO THE FOCUSED EVALUATION FOR EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 AS A RESULT OF THE REEVALUATED FLOODING HAZARD NEAR-TERM TASK FORCE RECOMMENDATION 2.1 - FLOODING (CAC NOS. MF9687 AND MF9868) |
| | |
| | ==1.0 INTRODUCTION== |
| | |
| | By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1O of the Code of Federal Regulations (10 CFR), Section 50.54(f) (hereafter referred to as the "50.54(f) letter''). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTIF) report (ADAMS Accession No. ML111861807). |
| | Enclosure 2 of the 50.54(f) letter requested that licensees reevaluate flood hazards for their respective sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML12056A046). lf the reevaluated hazard for any flood-causing mechanism is not bounded by the plant's current design basis (COB) flood hazard, an additional assessment of plant response would be necessary. Specifically, the 50.54(f) letter stated that an integrated assessment should be submitted, and described the information that the integrated assessment should contain. By letter dated November 30, 2012 (ADAMS Accession No. ML12311A214), |
| | the NRC staff issued Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2012-05, "Guidance for Performing the Integrated Assessment for External Flooding." |
| | On June 30, 2015 (ADAMS Accession No.ML15153A104), the NRC staff issued COMSECY 0019, describing the closure plan for the reevaluation of flooding hazards for operating nuclear power plants. The Commission approved the closure plan on July 28, 2015 (ADAMS Accession No. ML15209A682). COMSECY-15-0019 outlines a revised process for addressing cases in which the reevaluated flood hazard is not bounded by the plant's COB. The revised process describes a graded approach in which licensees with hazards exceeding their COB flood will not be required to complete an integrated assessment, but instead will perform a focused evaluation (FE). As part of the FE, licensees will assess the impact of the hazard(s) on their site and then evaluate and implement any necessary programmatic, procedural, or plant modifications to address the hazard exceedance. |
| | Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML16165A178), has been endorsed by the NRC as an appropriate methodology for licensees to perform the focused evaluation in response to the 50.54(f) letter. |
| | Enclosure 2 OFFICIAL USE ONL¥ SEGURl+V-RELA+ED INFQRMA+IQN |
| | |
| | OFFICIAL USE ONLY SECURITV-RELAlE9 INFORMATION The NRC's endorsement of NEI 16-05, including exceptions, clarifications, and additions, is described in NRC JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML16162A301 ). |
| | Therefore, NEI 16-05, Revision 1, as endorsed, describes acceptable methods for demonstrating that Edwin I. Hatch, Units 1 and 2 (Hatch) has effective flood protection. |
|
| |
|
| ==1.0 INTRODUCTION== | | ==2.0 BACKGROUND== |
| By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1 O of the Code of Federal Regulations (10 CFR), Section 50.54(f) (hereafter referred to as the "50.54(f) letter''). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTIF) report (ADAMS Accession No. ML 111861807). Enclosure 2 of the 50.54(f) letter requested that licensees reevaluate flood hazards for their respective sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML 12056A046). lf the reevaluated hazard for any flood-causing mechanism is not bounded by the plant's current design basis (COB) flood hazard, an additional assessment of plant response would be necessary. Specifically, the 50.54(f) letter stated that an integrated assessment should be submitted, and described the information that the integrated assessment should contain. By letter dated November 30, 2012 (ADAMS Accession No. ML 12311A214), the NRC staff issued Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) ISG-2012-05, "Guidance for Performing the Integrated Assessment for External Flooding." On June 30, 2015 (ADAMS Accession No.ML 15153A104), the NRC staff issued COMSECY-15-0019, describing the closure plan for the reevaluation of flooding hazards for operating nuclear power plants. The Commission approved the closure plan on July 28, 2015 (ADAMS Accession No. ML 15209A682). COMSECY-15-0019 outlines a revised process for addressing cases in which the reevaluated flood hazard is not bounded by the plant's COB. The revised process describes a graded approach in which licensees with hazards exceeding their COB flood will not be required to complete an integrated assessment, but instead will perform a focused evaluation (FE). As part of the FE, licensees will assess the impact of the hazard(s) on their site and then evaluate and implement any necessary programmatic, procedural, or plant modifications to address the hazard exceedance. Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML 16165A178), has been endorsed by the NRC as an appropriate methodology for licensees to perform the focused evaluation in response to the 50.54(f) letter. Enclosure 2 OFFICIAL USE ONL¥ SEGURl+V-RELA+ED INFQRMA+IQN OFFICIAL USE ONLY SECURITV-RELAlE9 INFORMATION The NRC's endorsement of NEI 16-05, including exceptions, clarifications, and additions, is described in NRC JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML 16162A301 ). Therefore, NEI 16-05, Revision 1, as endorsed, describes acceptable methods for demonstrating that Edwin I. Hatch, Units 1 and 2 (Hatch) has effective flood protection. 2.0 BACKGROUND This document provides the final NRC staff assessment associated with the information that the licensee provided in response to the reevaluated flooding hazard portion of the 50.54(f) letter. Therefore, this background section includes a summary description of the reevaluated flood information provided by the licensee and the associated assessments performed by the NRC staff. The reevaluated flood information includes: 1) the flood hazard reevaluation report (FHRR); 2) the mitigation strategies assessment (MSA); and 3) the focused evaluation. Flood Hazard Reevaluation Report By letter dated March 6, 2014 (ADAMS Accession No. ML 14069A054), as supplemented by letters dated August 6, 2014, June 3, 2015, and March 7, 2016 (ADAMS Accession Nos. ML 14219A570 (non-public), ML 15154B601 (non-public), and ML 16069A088 (non-public), respectively), Southern Nuclear Operating Company, Inc. (SNC, the licensee) submitted its FHRR for Hatch. After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML 15321A156), the NRC issued an interim staff response (ISR) letter for Hatch. The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for the mitigating strategies assessment (MSA) and the FE. As stated in the letter, because the local intense precipitation (LIP), flooding in rivers and streams, and failures of dams and onsite water control structures flooding mechanisms are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. The NRC staff issued a final staff assessment of the FHRR in a letter dated October 11, 2016 (ADAMS Accession No. ML 16237A095). The NRC staff's conclusions regarding LIP, flooding in rivers and streams, failures of dams and onsite water control structures exceeding the Hatch COB remained unchanged from the information provided in the ISR letter. Mitigation Strategies Assessment By letter dated December 16, 2016 (ADAMS Accession No. ML 16351A087), SNC submitted the Hatch MSA for review by the NRC staff. The MSAs are intended to confirm that licensees have adequately addressed the reevaluated flooding hazards within their mitigation strategies for beyond-design-basis external events. By letter dated April 13, 2017 (ADAMS Accession No. ML 17069A234), the NRC issued its assessment of the Hatch MSA. The NRC staff concluded that the Hatch MSA was performed consistent with the guidance described in Appendix G of NEI 12-06, Revision 2, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide" (ADAMS Accession No. ML 16005A625). The NRC's endorsement of NEI 12-06, Revision 2, is described in JLD-ISG-2012-01, Revision 1, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML 15357 A 163). The NRC staff further concluded that the licensee has demonstrated that the mitigation strategies, if appropriately implemented, are reasonably protected from reevaluated flood hazards conditions for beyond-design-basis external events. OFFICIAL:: USE ONbY--SECURfTY..RELATEO INFORM.MION OFFIGJ-AL USE ONLY SEGURA"¥ RELA:rED INFORMATION Focused Evaluation By letter dated June 22, 2017 (ADAMS Accession No. ML 17173A777), the licensee submitted the FE for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters; 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. These 3 options associated with performing an FE are referred to as Path 1, 2, or 3, as described in NEI 16-05, Revision 1. The purpose of this staff assessment is to provide the results of the NRC's evaluation of the Hatch FE.
| |
|
| |
|
| ==3.0 TECHNICAL EVALUATION==
| | This document provides the final NRC staff assessment associated with the information that the licensee provided in response to the reevaluated flooding hazard portion of the 50.54(f) letter. Therefore, this background section includes a summary description of the reevaluated flood information provided by the licensee and the associated assessments performed by the NRC staff. The reevaluated flood information includes: 1) the flood hazard reevaluation report (FHRR); 2) the mitigation strategies assessment (MSA); and 3) the focused evaluation. |
| The licensee stated that its FE followed Path 2 of NEI 16-05, Revision 1 and utilized Appendix B for guidance on evaluating the site strategy. The following flooding mechanisms from the FHRR were not bounded by the COB: LIP; flooding in rivers and streams (all season probable maximum flood (PMF) with a 1/2 PMF antecedent storm); seismic upstream dam failure; PMF with upstream overtopping dam failure; and combined effects flooding (CEF) (PMF with upstream dam failure with wind-induced waves). In its MSA, the licensee states that three of these mechanisms have maximum flooding elevations that are below the elevation of the intake structure and power block and are therefore not required to be further evaluated in the MSA. The NRC agreed with this assessment for flooding in rivers and streams (all season PMF with a 1/2 PMF antecedent storm), seismic upstream dam failure, and PMF with upstream overtopping dam failure and no further flooding evaluations are required for these flooding mechanism. Further evaluation of the LIP and CEF protection features was provided by Hatch in its FE. This technical evaluation will address the following topics: characterization of flood parameters; evaluation of flood impact assessments; evaluation of available physical margin; reliability of flood protection features; and overall site response. 3.1 Characterization of Flood Parameters Associated effects (AEs) and flood event duration (FED) parameters were assessed by SNC and have already been reviewed by the NRC, as summarized by letter dated October 11, 2016 (ADAMS Accession No. ML 16237 A095), and letter dated April 13, 2017 (ADAMS Accession No. ML 17069A234 ). The licensee used the AE and FED parameters as input to the Hatch FE and concluded that the site's flood strategy is effective in protecting structures, systems, and components (SSCs) that support key safety functions (KSFs). The licensee supported its conclusion of adequate flood protection by demonstrating adequate available physical margin (APM) and reliable flood protection features for LIP and CEF. In its FE for Hatch, SNC indicated that the site does not require manual actions by plant personnel to protect key SSCs; therefore, an evaluation of the overall site response was not necessary. The Hatch plant grade and floor elevations for the power block (Reactor, Turbine and Control buildings) are 130 feet (ft.) National Geodetic Vertical Datum of 1929 (NGVD29). Table 3.1 of this assessment provides the maximum exterior water surface elevations for the two reevaluated flood mechanisms in the FE. For the LIP condition, the licensee relies on permanent passive flood protection features such as doors, to demonstrate that adequate protection is available. For the CEF, the stillwater elevation i~] NGVD29 and with wind induced waves the flood height is -NGVD29, which has the potential to impact QFFlCIAL USE QNLY SECURITY RELA+ED INJ:GRMAl'.ION OFFICIAL USE ONL¥ SECURITY RELATED INFORMATION the intake structure with plant elevation of 111 ft. NGVD29, but not the power block. The potential impacts from this flooding-causing mechanisms were further evaluated by SNC as part of the Hatch FE. Table 3.1 Summary of Reevaluated Flood Hazards Elevations Included in the Hatch FE. Mechanism Local Intense Precipitation Control Building Intake Structure Diesel Generator Building Turbine and Reactor Building Combined Effect Flood (PMF with overtopping dam failure with wind-induced waves) Stillwater Wind-Wave Run Elevation u 130.5 ft. NGVD29 N/A 111.2 ft. NGVD29 N/A 130.2 ft. NGVD29 N/A 130.4 ft. NGVD29 N/A NGVD29]] NGVD29}1 3.2 Evaluation of Flood Impact Assessment for LIP 3.2.1 Description of Impact of Unbounded Hazard The Hatch FE identified the potential impacts on key SSCs as a result of water ingress due to LIP. The beyond-design-basis (BOB) LIP event leads to flood water surface elevations above the plant floor elevations at some locations. In order to assess the impacts of the unbounded flood levels, the licensee identified the maximum water surface elevations at the exterior door openings, maximum flood depths above the door threshold, and duration of when the flood levels are above the door threshold. With this information, the licensee assessed the impacts of water ingress and potential for accumulation into rooms housing key SSCs. The licensee's evaluation indicated that the LIP mechanism will produce ingress of flood waters through several doors that co'uld impact key SSCs in the main power block. The licensee determined that water must enter the power block buildings through open pathways at 130.0 ft. NGVD29 since all the penetrations below 130 ft. NVGD29 were inspected and confirmed sealed during the Recommendation 2.3 Flooding Walk downs. Therefore, the licensee identified the door characteristics, such as gap dimensions, and floor areas to determine water accumulation at floor elevations of 130 ft. NGVD29. In addition, the licensee assumed that all water volume used to evaluate flood height at the 130 ft. floor area will enter the Turbine and Control Buildings and flood their basement floors (112 ft. NGVD29 elevation). After determining the water accumulation on floor areas, the licensee compared the flooding height with the minimum elevations of key SSCs housed in each area. The licensee concluded that:
| | Flood Hazard Reevaluation Report By letter dated March 6, 2014 (ADAMS Accession No. ML14069A054), as supplemented by letters dated August 6, 2014, June 3, 2015, and March 7, 2016 (ADAMS Accession Nos. |
| * Flood water ingress due to the LIP flood would not impact the plant's key safety functions because the estimated water accumulation would not reach the elevation of key SSCs at the Reactor, Turbine and Control buildings; and QFFtCtAk USE QNLY.-SECURITY-RELAlE9 INFQRMATION GFRG-IAl= USE ONLY SECURITY RELATED INFORMARON
| | ML14219A570 (non-public), ML15154B601 (non-public), and ML16069A088 (non-public), |
| * Water was determined to not accumulate in the Intake Structure due to building configuration and site topography that will drain water back to the river. The NRC staff reviewed the information provided by the licensee in order to ensure that adequate flood parameters were used for the calculation of water ingress and water accumulation. Specifically, the NRC staff verified that the assumed duration of flooding above threshold elevation was consistent with previous information reviewed by the staff for the Hatch FHRR and MSA. 3.2.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features The licensee relies on passive features and existing doors to justify that there is available margin using a deterministic approach. Therefore, the licensee evaluated the key SSC elevations when compared to water ingress accumulation from exterior doors to obtain the APM. Water Ingress through Exterior Doors The licensee determined the lowest elevations ( equipment is raised off the floor) of key SSCs needed for safe shutdown. These elevations are shown below:
| | respectively), Southern Nuclear Operating Company, Inc. (SNC, the licensee) submitted its FHRR for Hatch. After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML15321A156), the NRC issued an interim staff response (ISR) letter for Hatch. The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for the mitigating strategies assessment (MSA) and the FE. As stated in the letter, because the local intense precipitation (LIP), flooding in rivers and streams, and failures of dams and onsite water control structures flooding mechanisms are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. The NRC staff issued a final staff assessment of the FHRR in a letter dated October 11, 2016 (ADAMS Accession No. ML16237A095). The NRC staff's conclusions regarding LIP, flooding in rivers and streams, failures of dams and onsite water control structures exceeding the Hatch COB remained unchanged from the information provided in the ISR letter. |
| * Reactor Building, Units 1 and 2, 130 ft. NGVD29 elevation: 4 inches
| | Mitigation Strategies Assessment By letter dated December 16, 2016 (ADAMS Accession No. ML16351A087), SNC submitted the Hatch MSA for review by the NRC staff. The MSAs are intended to confirm that licensees have adequately addressed the reevaluated flooding hazards within their mitigation strategies for beyond-design-basis external events. By letter dated April 13, 2017 (ADAMS Accession No. ML17069A234), the NRC issued its assessment of the Hatch MSA. The NRC staff concluded that the Hatch MSA was performed consistent with the guidance described in Appendix G of NEI 12-06, Revision 2, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide" (ADAMS Accession No. ML16005A625). The NRC's endorsement of NEI 12-06, Revision 2, is described in JLD-ISG-2012-01, Revision 1, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML15357A163). The NRC staff further concluded that the licensee has demonstrated that the mitigation strategies, if appropriately implemented, are reasonably protected from reevaluated flood hazards conditions for beyond-design-basis external events. |
| * Turbine and Control Building, Unit 1, 130 ft. NGVD29 elevation: 3 inches;
| | OFFICIAL:: USE ONbY--SECURfTY..RELATEO INFORM.MION |
| * Turbine and Control Building, Unit 2, 130 ft. NGVD29 elevation: 4 inches; and
| | |
| * Turbine and Control Building, Unit 1 and 2, 112 ft. NGVD29 elevation: 1 inch. The licensee estimated the accumulation of flood water due to LIP water ingress as follows:
| | OFFIGJ-AL USE ONLY SEGURA"¥ RELA:rED INFORMATION Focused Evaluation By letter dated June 22, 2017 (ADAMS Accession No. ML17173A777), the licensee submitted the FE for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters; |
| * Reactor Building-Licensee assumed that all Unit 2 Truck Bay flooding volume will enter the Reactor Building in Unit 2, creating an estimated flooding depth of 0.03 feet when distributed over the Reactor Building, Unit 2 area of 17,446 ft.2. The licensee determined that the .03 feet of flood height is well below the lowest key SSC which is located 0.33 ft. ( 4 inches) off the finished floor.
| | : 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. These 3 options associated with performing an FE are referred to as Path 1, 2, or 3, as described in NEI 16-05, Revision 1. The purpose of this staff assessment is to provide the results of the NRC's evaluation of the Hatch FE. |
| * Turbine and Control Buildings-Licensee estimated the flooding depths on the 130 ft. NGVD29 elevation to be 0.05 ft. (0.64 inches). The licensee determined that the flooding height is well below the lowest elevation of the key SSCs which are raised at 3.0 inches or higher off the floor. The flooding depths in the Turbine and Control Building on the 112 ft. NGVD29 elevation were estimated to be 0.04 ft. (0.47 inches). The licensee determined that the flooding height is below the lowest elevation of the key SSCs which are 1.0 inch off the floor. As a result, the licensee concluded that adequate APM exits based on the high factor of safety associated with the computation of the flooding depths and the lowest elevations where the key SSCs would be impacted. Furthermore, the licensee stated that several conservative assumptions were made in the estimation of water ingress, such as not crediting storm drains in the computation of water heights at the exterior doors and not considering the reduction due to water leakage through doors during the time of inundation. OFFICIAL USE 0Nb¥-SECURITY.RELATED INFORMATIGN OFFICIAL USE ONLY SECURITY RELATED INFORMATION The NRC staff concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated LIP mechanism. The calculation assumed that the water head at the exterior doors was at its maximum height over the entire duration of the event, and treated the door gap as a sluice gate to obtain the estimated flow. Therefore, the NRC staff agrees that the licensee's estimation of water accumulation is conservative. Therefore, the NRC staff concludes that the licensee has demonstrated that adequate passive features exist to provide flood protection of key SSCs. Evaluation of Reliability of Protection Features Hatch relies on permanent passive flooding protection features such as exterior doors to provide protection for flooding from LIP. The licensee evaluated the ability of these passive engineering features to protect key SSCs by limiting floodwater inflow into plant floors during the LIP flood conditions through engineering evaluations. The reliability of the doors to withstand the pressure from floodwater was not specifically evaluated by Hatch. Because the exterior water depths at the doors is relatively small, in the order of inches, the NRC staff used engineering judgment to conclude that the design capacity of the doors should not be compromised and that the doors are a reliable passive protection feature. The NRC staff performed an audit of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016, in accordance with an NRC audit plan dated July 18, 2017 (ADAMS Accession No. ML 17192A452). Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that areas containing key SSCs will not be adversely impacted by water ingress from the LIP reevaluated hazard, and that the flood protection features associated with key SSCs will ensure their continued function in the event of LIP. In addition, the licensee indicated that credited flood protection features are passive features that are checked as part of normal operator rounds. Therefore, the NRC staff concludes, with the information provided by the licensee as the basis, that the above-mentioned passive features are evaluated by an appropriate maintenance and inspection regime to ensure they will continue to be available to perform their intended flood protection function. Because increased focus has been placed on flood protection since the accident at Fukushima, licensees and NRC inspectors have identified deficiencies with equipment, procedures, and analyses relied on to either prevent or mitigate the effects of external flooding at a number of licensed facilities. Recent examples include those found in Information Notice 2015-01, "Degraded Ability to Mitigate Flooding Events" (ADAMS Accession No. ML 14279A268). In addition, the NRC is cooperatively performing research with the Electric Power Research Institute to develop flood protection systems guidance that focuses on flood protection feature descriptions, design criteria, inspections, and available testing methods in accordance with a memorandum of understanding dated September 28, 2016 (ADAMS Accession No. ML 16223A495). The NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff further expects that continued research involving flood protection systems will be performed and shared with licensees in accordance with the guidance provided in Management Directive 8.7, "Reactor Operating Experience Program" (ADAMS Accession No. ML 122750292), as appropriate. The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1. GFFICIAb-USE 0Nb~EGURl-l'¥-RELATED INFGRMATION OFFICIAL USE ONLY SECURITY RELATED INFORMATION 3.2.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB LIP event. As described above, the licensee's evaluation relied on passive existing flood protection features to demonstrate adequate flood protection; therefore, there is no need to review overall site response. 3.3 Evaluation of Flood Impact Assessment for combined effects flooding (PMF with upstream dam failure with wind-induced waves) 3.3.1 Description of Impact of Unbounded Hazard As described in the FE, the stillwater elevation from the CEF mechanism i NGVD29 and the maximum flood elevation including wind-induced waves is NGVD29. The licensee indicates that the primary feature protecting the site from the reevaluated flood hazard along the Altamaha River is site topography and grading. Since the main power block buildings (i.e., Reactor, Turbine, and Control Buildings) are located at elevation 130 ft. NGVD29, no impacts were identified on key SSCs located in such buildings. Therefore, for the main power block, the licensee calculated an APM o for stillwater and NGVD29)]] for wind-wave run-up. For the Intake Structure, the wind-induced waves exceed the Intake Structure elevation of 111 feet NGVD29. The intake structure houses the Plant Service Water and Residual Heat Removal pumps, both key SSCs required for shutdown. However, the licensee indicates that the reevaluated CEF mechanism does not impact key SSCs at the Intake structure because: 1) the bathymetry of the site will allow the waves to break before impacting the intake structure; 2) the Intake Structures doors are placed in labyrinth offsets and are weather-stripped; and 3) in the case of water ingress the floor gratings will drain the water into a pit that houses two submersible water pumps that will drain the water out. Therefore, for the Intake Structure, the licensee calculated an APM o for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features described above. As a result, the licensee concluded that the CEF mechanism has no impacts to key SSCs. 3.3.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features As described above, the licensee calculated an APM for the main power block o stillwater and -for wind-wave run-up. The licensee calculated an APM of for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features on the Intake Structure. The licensee also stated that there would be no impact to the structural integrity of the Intake Structure from the reevaluated CFE mechanism. The NRC staff reviewed the APM calculation and concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated CEF mechanism. The natural topography around the site provides effective flood protection against the CEF, with adequate margin. Furthermore, the NRG staff reviewed the methodology used to evaluate the structural OFFICIAL USE ONLY SEGURITY-REbATED INFORMATION OFFICIAL USE ONL¥-SEGURITY RELATED INFORMATION integrity of the walls and foundations from the increased flood/wave heights elevation and found it to be acceptable. Evaluation of Reliability of Protection Features Hatch relies on the natural topography around the site to provide protection from the reevaluated CEF conditions. For the main power block, the site topography provides adequate APM for buildings housing key SSCs. Since this feature is already credited as part of the Hatch design-basis flood protection, the NRC staff concludes that a reliability analysis of these features is not necessary in accordance with the guidance found in NEI 16-05, Revision 1. For the Intake Structure, Hatch relies on passive features such as the configuration of doors and drainage capabilities around the Intake Structure. Furthermore, Hatch evaluated the structural integrity of the Intake Structure through engineering evaluations to verify that the loads from the reevaluated CFE will not affect the structural integrity of the walls. This calculation was provided as part of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016. The licensee evaluated the loads imposed on the structural walls of the Intake Structure and concluded that it will not create any impacts. The licensee determined that the maximum hydrostatic pressure and force on the Intake Structure walls due to the CEF mechanism is , respectively. In addition, the maximum hydrodynamic pressure and force on the Intake Structure walls due to breaking wave is 4,312 lb/ft.2and 93,648 lb/ft., respectively. With this information, the licensee concluded that the maximum hydrodynamic and hydrostatic pressures are less than the concrete strength of 4,000 pounds per square inch (psi} (or 576,000 lb/ft.2} at the Intake Structure. Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that the Intake Structure has adequate flood protection such that its functions will not be adversely impacted by the CFE reevaluated hazard. As noted in Section 3.2.2 of this document, the NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1. 3.3.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB Probable Maximum Storm Surge event. As described above, the licensee's evaluation relied on passive existing features to demonstrate adequate flood protection. Therefore, there is no need to review overall site response. 4.0 AUDIT REPORT The July 18, 2017, generic audit plan describes the NRC staff's intention to issue an audit report that summarizes and documents the NRC's regulatory audit of the licensee's FE. The NRC staff's Hatch audit was limited to the review of the calculation number SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016, and drawings listed at the end of this section. Because this staff assessment appropriately summarizes the results of the audit, the NRC staff concludes a separate audit report is not necessary, and that this document serves as the audit report described in the staff's July 18, 2017, letter. OFFICIAL l:ISE ONLY SEGlJRITY-REbATED INFORMATION QFFICIAL USE QNLY SEGYRITY REbATED INFQRMMIQN
| |
| * Drawing H-12192 Version 11.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 Outdoor Concrete Intake Structure General Arrangement," February 12, 1971.
| |
| * Drawing E-10173 Version 23.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 & 2 General Building Site Plan."
| |
| * Drawing H-21102 Version 20.0, ""Edwin I. Hatch Nuclear Plant Unit No. 2 Piping-Service Water at River Intake Structure," April 7, 1971.
| |
| * Drawing H12610 Version 5.0, ""Edwin I. Hatch Nuclear Plant Unit No. 1 Architectural River Intake Structure Pump Room-Plans, Elevations & Details," September 29, 2009.
| |
|
| |
|
| ==5.0 CONCLUSION== | | ==3.0 TECHNICAL EVALUATION== |
| The NRC staff concludes that SNC performed the Hatch FE in accordance with the guidance described in NEI 16-05, Revision 1, as endorsed by JLD-ISG-2016-01, and that the licensee has demonstrated that effective flood protection exists against the reevaluated flood hazards. Furthermore, the NRC staff concludes that Hatch screens out of performing an integrated assessment based on the guidance found in JLD-ISG-2016-01 . As such, in accordance with Phase 2 of the process outlined in the 50.54(f) letter, additional regulatory actions associated with the reevaluated flood hazard, beyond those associated with mitigation strategies assessment, are not warranted. The licensee has satisfactorily completed providing responses to the 50.54(f) activities associated with the reevaluated flood hazards. QFFJCIAL USE QNl.¥-SEGURl'f¥ RElA+ED INFQRMAllON OFFICIAL USE ONLV-SEGURl"fV REl::ATEE) INFORMATION J. Hutto
| |
|
| |
|
| ==SUBJECT:==
| | The licensee stated that its FE followed Path 2 of NEI 16-05, Revision 1 and utilized Appendix B for guidance on evaluating the site strategy. The following flooding mechanisms from the FHRR were not bounded by the COB: LIP; flooding in rivers and streams (all season probable maximum flood (PMF) with a 1/2 PMF antecedent storm); seismic upstream dam failure; PMF with upstream overtopping dam failure; and combined effects flooding (CEF) (PMF with upstream dam failure with wind-induced waves). In its MSA, the licensee states that three of these mechanisms have maximum flooding elevations that are below the elevation of the intake structure and power block and are therefore not required to be further evaluated in the MSA. |
| EDWIN I. HATCHNUCLEAR PLANT, UNITS 1 AND 2 -STAFF ASSESSMENT OF FLOODING FOCUSED EVALUATION DATED MARCH 13, 2018 DISTRIBUTION: Public PBMB R/F RidsNRR Dip Resource RidsNrrDorlLpl2-1 Resource RidsNrrDorl Resource RidsNrrPMHatch Resource RidsNrrlaSLent Resource EBowman, NRR RidsOpaMail Resource RidsACRS_MailCtr Resource RidsRgn2MailCenter Resource JMarcano, NMSS ADAMS Accession Nos.: PKG ML 180308055; ML 18029A915 (NON-PUBLIC); ML 180308076 (PUBLIC) *via email OFFICE NMSS/FCSS/PORSB* NRR/DLP/PBMB/PM NRR/DLP/PBMB/LA NAME JMarcano FVeaa SLent DATE 01/26/2018 02/28/2018 01/30/2018 OFFICE NRR/DLP/PBMB/BC{A) NRR/DLP/PBMB/PM NAME EBowman (BTitus for) FVeQa DATE 03/02/2018 03/13/2018 OFFICIAL RECORD COPY OFFICIAL USE ONLY-SECURITY-RELATED INFGRMATION
| | The NRC agreed with this assessment for flooding in rivers and streams (all season PMF with a 1/2 PMF antecedent storm), seismic upstream dam failure, and PMF with upstream overtopping dam failure and no further flooding evaluations are required for these flooding mechanism. |
| }}
| | Further evaluation of the LIP and CEF protection features was provided by Hatch in its FE. This technical evaluation will address the following topics: characterization of flood parameters; evaluation of flood impact assessments; evaluation of available physical margin; reliability of flood protection features; and overall site response. |
| | 3.1 Characterization of Flood Parameters Associated effects (AEs) and flood event duration (FED) parameters were assessed by SNC and have already been reviewed by the NRC, as summarized by letter dated October 11, 2016 (ADAMS Accession No. ML16237A095), and letter dated April 13, 2017 (ADAMS Accession No. ML17069A234). The licensee used the AE and FED parameters as input to the Hatch FE and concluded that the site's flood strategy is effective in protecting structures, systems, and components (SSCs) that support key safety functions (KSFs). The licensee supported its conclusion of adequate flood protection by demonstrating adequate available physical margin (APM) and reliable flood protection features for LIP and CEF. In its FE for Hatch, SNC indicated that the site does not require manual actions by plant personnel to protect key SSCs; therefore, an evaluation of the overall site response was not necessary. |
| | The Hatch plant grade and floor elevations for the power block (Reactor, Turbine and Control buildings) are 130 feet (ft.) National Geodetic Vertical Datum of 1929 (NGVD29). Table 3.1 of this assessment provides the maximum exterior water surface elevations for the two reevaluated flood mechanisms in the FE. For the LIP condition, the licensee relies on permanent passive flood protection features such as doors, to demonstrate that adequate protection is available. For the CEF, the stillwater elevation i ~ ] NGVD29 and with wind induced waves the flood height is - NGVD29, which has the potential to impact QFFlCIAL USE QNLY SECURITY RELA+ED INJ:GRMAl'.ION |
|
| |
|
| =Text=
| | OFFICIAL USE ONL¥ SECURITY RELATED INFORMATION the intake structure with plant elevation of 111 ft. NGVD29, but not the power block. The potential impacts from this flooding-causing mechanisms were further evaluated by SNC as part of the Hatch FE. |
| {{#Wiki_filter:OFFICIAL USE ONLY: SEGURITY-RElATED INFORMATION UNITED ST ATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 13, 2018 Mr. J. J. Hutto Regulatory Affairs Director Southern Nuclear Operating Co., Inc. P.O. Box 1295 /BIN B038 Birmingham, AL 35201-1295
| | Table 3.1 Summary of Reevaluated Flood Hazards Elevations Included in the Hatch FE. |
| | Mechanism Stillwater Wind-Wave Run Elevation u Local Intense Precipitation Control Building 130.5 ft. NGVD29 N/A Intake Structure 111.2 ft. NGVD29 N/A Diesel Generator Building 130.2 ft. NGVD29 N/A Turbine and Reactor Building 130.4 ft. NGVD29 N/A Combined Effect Flood (PMF with overtopping dam failure with wind-induced NGVD29)) NGVD29}1 waves) 3.2 Evaluation of Flood Impact Assessment for LIP 3.2.1 Description of Impact of Unbounded Hazard The Hatch FE identified the potential impacts on key SSCs as a result of water ingress due to LIP. The beyond-design-basis (BOB) LIP event leads to flood water surface elevations above the plant floor elevations at some locations. In order to assess the impacts of the unbounded flood levels, the licensee identified the maximum water surface elevations at the exterior door openings, maximum flood depths above the door threshold, and duration of when the flood levels are above the door threshold. With this information, the licensee assessed the impacts of water ingress and potential for accumulation into rooms housing key SSCs. |
| | The licensee's evaluation indicated that the LIP mechanism will produce ingress of flood waters through several doors that co'uld impact key SSCs in the main power block. The licensee determined that water must enter the power block buildings through open pathways at 130.0 ft. |
| | NGVD29 since all the penetrations below 130 ft. NVGD29 were inspected and confirmed sealed during the Recommendation 2.3 Flooding Walk downs. Therefore, the licensee identified the door characteristics, such as gap dimensions, and floor areas to determine water accumulation at floor elevations of 130 ft. NGVD29. In addition, the licensee assumed that all water volume used to evaluate flood height at the 130 ft. floor area will enter the Turbine and Control Buildings and flood their basement floors (112 ft. NGVD29 elevation). After determining the water accumulation on floor areas, the licensee compared the flooding height with the minimum elevations of key SSCs housed in each area. |
| | The licensee concluded that: |
| | * Flood water ingress due to the LIP flood would not impact the plant's key safety functions because the estimated water accumulation would not reach the elevation of key SSCs at the Reactor, Turbine and Control buildings; and QFFtCtAk USE QNLY.-SECURITY-RELAlE9 INFQRMATION |
|
| |
|
| ==SUBJECT:== | | GFRG-IAl= USE ONLY SECURITY RELATED INFORMARON |
| EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 -STAFF ASSESSMENT OF FLOODING FOCUSED EVALUATION (CAC NOS. MF9687 AND MF9868; EPID NOS. 000495/05000321/L-2017-JLD-0029 AND 000495/05000366/L-2017-JLD-0029)
| | * Water was determined to not accumulate in the Intake Structure due to building configuration and site topography that will drain water back to the river. |
| | The NRC staff reviewed the information provided by the licensee in order to ensure that adequate flood parameters were used for the calculation of water ingress and water accumulation. Specifically, the NRC staff verified that the assumed duration of flooding above threshold elevation was consistent with previous information reviewed by the staff for the Hatch FHRR and MSA. |
| | 3.2.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features The licensee relies on passive features and existing doors to justify that there is available margin using a deterministic approach. Therefore, the licensee evaluated the key SSC elevations when compared to water ingress accumulation from exterior doors to obtain the APM. |
| | Water Ingress through Exterior Doors The licensee determined the lowest elevations ( equipment is raised off the floor) of key SSCs needed for safe shutdown. These elevations are shown below: |
| | * Reactor Building, Units 1 and 2, 130 ft. NGVD29 elevation: 4 inches |
| | * Turbine and Control Building, Unit 1, 130 ft. NGVD29 elevation: 3 inches; |
| | * Turbine and Control Building, Unit 2, 130 ft. NGVD29 elevation: 4 inches; and |
| | * Turbine and Control Building, Unit 1 and 2, 112 ft. NGVD29 elevation: 1 inch. |
| | The licensee estimated the accumulation of flood water due to LIP water ingress as follows: |
| | * Reactor Building- Licensee assumed that all Unit 2 Truck Bay flooding volume will enter the Reactor Building in Unit 2, creating an estimated flooding depth of 0.03 feet when distributed over the Reactor Building, Unit 2 area of 17,446 ft. 2 . The licensee determined that the .03 feet of flood height is well below the lowest key SSC which is located 0.33 ft. |
| | (4 inches) off the finished floor. |
| | * Turbine and Control Buildings- Licensee estimated the flooding depths on the 130 ft. |
| | NGVD29 elevation to be 0.05 ft. (0.64 inches). The licensee determined that the flooding height is well below the lowest elevation of the key SSCs which are raised at 3.0 inches or higher off the floor. The flooding depths in the Turbine and Control Building on the 112 ft. NGVD29 elevation were estimated to be 0.04 ft. (0.47 inches). The licensee determined that the flooding height is below the lowest elevation of the key SSCs which are 1.0 inch off the floor. |
| | As a result, the licensee concluded that adequate APM exits based on the high factor of safety associated with the computation of the flooding depths and the lowest elevations where the key SSCs would be impacted. Furthermore, the licensee stated that several conservative assumptions were made in the estimation of water ingress, such as not crediting storm drains in the computation of water heights at the exterior doors and not considering the reduction due to water leakage through doors during the time of inundation. |
| | OFFICIAL USE 0Nb¥-SECURITY.RELATED INFORMATIGN |
|
| |
|
| ==Dear Mr. Hutto:==
| | OFFICIAL USE ONLY SECURITY RELATED INFORMATION The NRC staff concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated LIP mechanism. The calculation assumed that the water head at the exterior doors was at its maximum height over the entire duration of the event, and treated the door gap as a sluice gate to obtain the estimated flow. Therefore, the NRC staff agrees that the licensee's estimation of water accumulation is conservative. Therefore, the NRC staff concludes that the licensee has demonstrated that adequate passive features exist to provide flood protection of key SSCs. |
| By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f), "Conditions of Licenses" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTTF) report (ADAMS Accession No. ML 111861807). Enclosure 2 to the 50.54(f) letter requested that licensees reevaluate flood hazards for their sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML 12056A046). By letter dated March 6, 2014 (ADAMS Accession No. ML 14069A054), Southern Nuclear Operating Company, Inc. (SNC, the licensee) responded to this request for Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch). After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML 15321 A 156), the NRG issued an interim staff response (ISR) letter for Hatch. The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for other assessments associated with NITF Recommendation 2.1 "Flooding". As stated in the letter, because the local intense precipitation (LIP) and Combined Effects Flooding (Probable Maximum Flood (PMF) with upstream dam overtopping with wind-induced waves) are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. Enclosure 1 transmitted herewith contains Security-Related Information. When separated from Enclosure 1, this document is decontrolled. OFFIGIAb USE ONLY: SECURITY.RELATED INF9RMATION J. Hutto OFFICIAL USE C>NLY SECURfT¥-RELATED INFORMATION By letter dated June 22, 2017 (ADAMS Accession No. ML 17173A777), the licensee submitted the focused evaluation (FE) for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters; 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. The purpose of this letter is to provide the NRC's assessment of the Hatch FE. As set forth in the attached staff assessment, the NRC staff has concluded that the Hatch FE was performed consistent with the guidance described in Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML 16165A178). Guidance document NEI 16-05, Revision 1, has been endorsed by Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML 16162A301 ). The NRC staff has further concluded that the licensee has demonstrated that effective flood protection, if appropriately implemented, exists for the LIP and Combined Effects Flooding mechanisms during a beyond-design-basis external flooding event at Hatch. This closes out the licensee's response for Hatch for the reevaluated flooding hazard portion of the 50.54(f) letter and the NRC's efforts associated with CAC Nos. MF9687 and MF9868. If you have any questions, please contact me at 301-415-1617 or at Frankie.Vega@nrc.gov.
| | Evaluation of Reliability of Protection Features Hatch relies on permanent passive flooding protection features such as exterior doors to provide protection for flooding from LIP. The licensee evaluated the ability of these passive engineering features to protect key SSCs by limiting floodwater inflow into plant floors during the LIP flood conditions through engineering evaluations. The reliability of the doors to withstand the pressure from floodwater was not specifically evaluated by Hatch. Because the exterior water depths at the doors is relatively small, in the order of inches, the NRC staff used engineering judgment to conclude that the design capacity of the doors should not be compromised and that the doors are a reliable passive protection feature. |
| | The NRC staff performed an audit of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", |
| | Version 1.0 dated December 14, 2016, in accordance with an NRC audit plan dated July 18, 2017 (ADAMS Accession No. ML17192A452). Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that areas containing key SSCs will not be adversely impacted by water ingress from the LIP reevaluated hazard, and that the flood protection features associated with key SSCs will ensure their continued function in the event of LIP. |
| | In addition, the licensee indicated that credited flood protection features are passive features that are checked as part of normal operator rounds. Therefore, the NRC staff concludes, with the information provided by the licensee as the basis, that the above-mentioned passive features are evaluated by an appropriate maintenance and inspection regime to ensure they will continue to be available to perform their intended flood protection function. |
| | Because increased focus has been placed on flood protection since the accident at Fukushima, licensees and NRC inspectors have identified deficiencies with equipment, procedures, and analyses relied on to either prevent or mitigate the effects of external flooding at a number of licensed facilities. Recent examples include those found in Information Notice 2015-01, "Degraded Ability to Mitigate Flooding Events" (ADAMS Accession No. ML14279A268). In addition, the NRC is cooperatively performing research with the Electric Power Research Institute to develop flood protection systems guidance that focuses on flood protection feature descriptions, design criteria, inspections, and available testing methods in accordance with a memorandum of understanding dated September 28, 2016 (ADAMS Accession No. ML16223A495). The NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff further expects that continued research involving flood protection systems will be performed and shared with licensees in accordance with the guidance provided in Management Directive 8.7, "Reactor Operating Experience Program" (ADAMS Accession No. ML122750292), as appropriate. |
| | The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1. |
| | GFFICIAb-USE 0Nb~EGURl-l'¥-RELATED INFGRMATION |
|
| |
|
| ==Enclosures:==
| | OFFICIAL USE ONLY SECURITY RELATED INFORMATION 3.2.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB LIP event. As described above, the licensee's evaluation relied on passive existing flood protection features to demonstrate adequate flood protection; therefore, there is no need to review overall site response. |
| 1 . Staff Assessment Related to the Flooding Focused Evaluation for Hatch (non-public) 2. Staff Assessment Related to the Flooding Focused Evaluation for Hatch (public) Docket Nos: 50-321 and 50-366 cc w/encl: Distribution via Listserv Sincerely, Fra~i:anager Beyond-Design-Basis Management Branch Division of Licensing Projects Office of Nuclear Reactor Regulation OFFIGIAL USE ONbY-SECURIT¥-RELATED INFORMATION OFFICIAL USE ONL¥-SEGURIT¥-RELATED INFORMATION STAFF ASSESSMENT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO THE FOCUSED EVALUATION FOR EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 AS A RESULT OF THE REEVALUATED FLOODING HAZARD NEAR-TERM TASK FORCE RECOMMENDATION 2.1 -FLOODING (CAC NOS. MF9687 AND MF9868)
| | 3.3 Evaluation of Flood Impact Assessment for combined effects flooding (PMF with upstream dam failure with wind-induced waves) 3.3.1 Description of Impact of Unbounded Hazard As described in the FE, the stillwater elevation from the CEF mechanism i NGVD29 and the maximum flood elevation including wind-induced waves is NGVD29. The licensee indicates that the primary feature protecting the site from the reevaluated flood hazard along the Altamaha River is site topography and grading. Since the main power block buildings (i.e., Reactor, Turbine, and Control Buildings) are located at elevation 130 ft. NGVD29, no impacts were identified on key SSCs located in such buildings. |
| | Therefore, for the main power block, the licensee calculated an APM o for stillwater and NGVD29))) for wind-wave run-up. |
| | For the Intake Structure, the wind-induced waves exceed the Intake Structure elevation of 111 feet NGVD29. The intake structure houses the Plant Service Water and Residual Heat Removal pumps, both key SSCs required for shutdown. However, the licensee indicates that the reevaluated CEF mechanism does not impact key SSCs at the Intake structure because: 1) the bathymetry of the site will allow the waves to break before impacting the intake structure; 2) the Intake Structures doors are placed in labyrinth offsets and are weather-stripped; and 3) in the case of water ingress the floor gratings will drain the water into a pit that houses two submersible water pumps that will drain the water out. Therefore, for the Intake Structure, the licensee calculated an APM o for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features described above. As a result, the licensee concluded that the CEF mechanism has no impacts to key SSCs. |
| | 3.3.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features As described above, the licensee calculated an APM for the main power block o stillwater and - for wind-wave run-up. The licensee calculated an APM of for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features on the Intake Structure. The licensee also stated that there would be no impact to the structural integrity of the Intake Structure from the reevaluated CFE mechanism. |
| | The NRC staff reviewed the APM calculation and concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated CEF mechanism. The natural topography around the site provides effective flood protection against the CEF, with adequate margin. Furthermore, the NRG staff reviewed the methodology used to evaluate the structural OFFICIAL USE ONLY SEGURITY-REbATED INFORMATION |
|
| |
|
| ==1.0 INTRODUCTION==
| | OFFICIAL USE ONL¥-SEGURITY RELATED INFORMATION integrity of the walls and foundations from the increased flood/wave heights elevation and found it to be acceptable. |
| By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1 O of the Code of Federal Regulations (10 CFR), Section 50.54(f) (hereafter referred to as the "50.54(f) letter''). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTIF) report (ADAMS Accession No. ML 111861807). Enclosure 2 of the 50.54(f) letter requested that licensees reevaluate flood hazards for their respective sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML 12056A046). lf the reevaluated hazard for any flood-causing mechanism is not bounded by the plant's current design basis (COB) flood hazard, an additional assessment of plant response would be necessary. Specifically, the 50.54(f) letter stated that an integrated assessment should be submitted, and described the information that the integrated assessment should contain. By letter dated November 30, 2012 (ADAMS Accession No. ML 12311A214), the NRC staff issued Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) ISG-2012-05, "Guidance for Performing the Integrated Assessment for External Flooding." On June 30, 2015 (ADAMS Accession No.ML 15153A104), the NRC staff issued COMSECY-15-0019, describing the closure plan for the reevaluation of flooding hazards for operating nuclear power plants. The Commission approved the closure plan on July 28, 2015 (ADAMS Accession No. ML 15209A682). COMSECY-15-0019 outlines a revised process for addressing cases in which the reevaluated flood hazard is not bounded by the plant's COB. The revised process describes a graded approach in which licensees with hazards exceeding their COB flood will not be required to complete an integrated assessment, but instead will perform a focused evaluation (FE). As part of the FE, licensees will assess the impact of the hazard(s) on their site and then evaluate and implement any necessary programmatic, procedural, or plant modifications to address the hazard exceedance. Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML 16165A178), has been endorsed by the NRC as an appropriate methodology for licensees to perform the focused evaluation in response to the 50.54(f) letter. Enclosure 2 OFFICIAL USE ONL¥ SEGURl+V-RELA+ED INFQRMA+IQN OFFICIAL USE ONLY SECURITV-RELAlE9 INFORMATION The NRC's endorsement of NEI 16-05, including exceptions, clarifications, and additions, is described in NRC JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML 16162A301 ). Therefore, NEI 16-05, Revision 1, as endorsed, describes acceptable methods for demonstrating that Edwin I. Hatch, Units 1 and 2 (Hatch) has effective flood protection. 2.0 BACKGROUND This document provides the final NRC staff assessment associated with the information that the licensee provided in response to the reevaluated flooding hazard portion of the 50.54(f) letter. Therefore, this background section includes a summary description of the reevaluated flood information provided by the licensee and the associated assessments performed by the NRC staff. The reevaluated flood information includes: 1) the flood hazard reevaluation report (FHRR); 2) the mitigation strategies assessment (MSA); and 3) the focused evaluation. Flood Hazard Reevaluation Report By letter dated March 6, 2014 (ADAMS Accession No. ML 14069A054), as supplemented by letters dated August 6, 2014, June 3, 2015, and March 7, 2016 (ADAMS Accession Nos. ML 14219A570 (non-public), ML 15154B601 (non-public), and ML 16069A088 (non-public), respectively), Southern Nuclear Operating Company, Inc. (SNC, the licensee) submitted its FHRR for Hatch. After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML 15321A156), the NRC issued an interim staff response (ISR) letter for Hatch. The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for the mitigating strategies assessment (MSA) and the FE. As stated in the letter, because the local intense precipitation (LIP), flooding in rivers and streams, and failures of dams and onsite water control structures flooding mechanisms are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. The NRC staff issued a final staff assessment of the FHRR in a letter dated October 11, 2016 (ADAMS Accession No. ML 16237A095). The NRC staff's conclusions regarding LIP, flooding in rivers and streams, failures of dams and onsite water control structures exceeding the Hatch COB remained unchanged from the information provided in the ISR letter. Mitigation Strategies Assessment By letter dated December 16, 2016 (ADAMS Accession No. ML 16351A087), SNC submitted the Hatch MSA for review by the NRC staff. The MSAs are intended to confirm that licensees have adequately addressed the reevaluated flooding hazards within their mitigation strategies for beyond-design-basis external events. By letter dated April 13, 2017 (ADAMS Accession No. ML 17069A234), the NRC issued its assessment of the Hatch MSA. The NRC staff concluded that the Hatch MSA was performed consistent with the guidance described in Appendix G of NEI 12-06, Revision 2, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide" (ADAMS Accession No. ML 16005A625). The NRC's endorsement of NEI 12-06, Revision 2, is described in JLD-ISG-2012-01, Revision 1, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML 15357 A 163). The NRC staff further concluded that the licensee has demonstrated that the mitigation strategies, if appropriately implemented, are reasonably protected from reevaluated flood hazards conditions for beyond-design-basis external events. OFFICIAL:: USE ONbY--SECURfTY..RELATEO INFORM.MION OFFIGJ-AL USE ONLY SEGURA"¥ RELA:rED INFORMATION Focused Evaluation By letter dated June 22, 2017 (ADAMS Accession No. ML 17173A777), the licensee submitted the FE for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters; 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. These 3 options associated with performing an FE are referred to as Path 1, 2, or 3, as described in NEI 16-05, Revision 1. The purpose of this staff assessment is to provide the results of the NRC's evaluation of the Hatch FE.
| | Evaluation of Reliability of Protection Features Hatch relies on the natural topography around the site to provide protection from the reevaluated CEF conditions. For the main power block, the site topography provides adequate APM for buildings housing key SSCs. Since this feature is already credited as part of the Hatch design-basis flood protection, the NRC staff concludes that a reliability analysis of these features is not necessary in accordance with the guidance found in NEI 16-05, Revision 1. |
| | For the Intake Structure, Hatch relies on passive features such as the configuration of doors and drainage capabilities around the Intake Structure. Furthermore, Hatch evaluated the structural integrity of the Intake Structure through engineering evaluations to verify that the loads from the reevaluated CFE will not affect the structural integrity of the walls. This calculation was provided as part of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016. The licensee evaluated the loads imposed on the structural walls of the Intake Structure and concluded that it will not create any impacts. The licensee determined that the maximum hydrostatic pressure and force on the Intake Structure walls due to the CEF mechanism is , respectively. In addition, the maximum hydrodynamic pressure and force on the Intake Structure walls due to breaking wave is 4,312 lb/ft. 2 and 93,648 lb/ft., respectively. With this information, the licensee concluded that the maximum hydrodynamic and hydrostatic pressures are less than the concrete strength of 4,000 pounds per square inch (psi} (or 576,000 lb/ft. 2 } at the Intake Structure. Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that the Intake Structure has adequate flood protection such that its functions will not be adversely impacted by the CFE reevaluated hazard. |
| | As noted in Section 3.2.2 of this document, the NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1. |
| | 3.3.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB Probable Maximum Storm Surge event. As described above, the licensee's evaluation relied on passive existing features to demonstrate adequate flood protection. |
| | Therefore, there is no need to review overall site response. |
| | 4.0 AUDIT REPORT The July 18, 2017, generic audit plan describes the NRC staff's intention to issue an audit report that summarizes and documents the NRC's regulatory audit of the licensee's FE. The NRC staff's Hatch audit was limited to the review of the calculation number SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016, and drawings listed at the end of this section. Because this staff assessment appropriately summarizes the results of the audit, the NRC staff concludes a separate audit report is not necessary, and that this document serves as the audit report described in the staff's July 18, 2017, letter. |
| | OFFICIAL l:ISE ONLY SEGlJRITY-REbATED INFORMATION |
|
| |
|
| ==3.0 TECHNICAL EVALUATION==
| | QFFICIAL USE QNLY SEGYRITY REbATED INFQRMMIQN |
| The licensee stated that its FE followed Path 2 of NEI 16-05, Revision 1 and utilized Appendix B for guidance on evaluating the site strategy. The following flooding mechanisms from the FHRR were not bounded by the COB: LIP; flooding in rivers and streams (all season probable maximum flood (PMF) with a 1/2 PMF antecedent storm); seismic upstream dam failure; PMF with upstream overtopping dam failure; and combined effects flooding (CEF) (PMF with upstream dam failure with wind-induced waves). In its MSA, the licensee states that three of these mechanisms have maximum flooding elevations that are below the elevation of the intake structure and power block and are therefore not required to be further evaluated in the MSA. The NRC agreed with this assessment for flooding in rivers and streams (all season PMF with a 1/2 PMF antecedent storm), seismic upstream dam failure, and PMF with upstream overtopping dam failure and no further flooding evaluations are required for these flooding mechanism. Further evaluation of the LIP and CEF protection features was provided by Hatch in its FE. This technical evaluation will address the following topics: characterization of flood parameters; evaluation of flood impact assessments; evaluation of available physical margin; reliability of flood protection features; and overall site response. 3.1 Characterization of Flood Parameters Associated effects (AEs) and flood event duration (FED) parameters were assessed by SNC and have already been reviewed by the NRC, as summarized by letter dated October 11, 2016 (ADAMS Accession No. ML 16237 A095), and letter dated April 13, 2017 (ADAMS Accession No. ML 17069A234 ). The licensee used the AE and FED parameters as input to the Hatch FE and concluded that the site's flood strategy is effective in protecting structures, systems, and components (SSCs) that support key safety functions (KSFs). The licensee supported its conclusion of adequate flood protection by demonstrating adequate available physical margin (APM) and reliable flood protection features for LIP and CEF. In its FE for Hatch, SNC indicated that the site does not require manual actions by plant personnel to protect key SSCs; therefore, an evaluation of the overall site response was not necessary. The Hatch plant grade and floor elevations for the power block (Reactor, Turbine and Control buildings) are 130 feet (ft.) National Geodetic Vertical Datum of 1929 (NGVD29). Table 3.1 of this assessment provides the maximum exterior water surface elevations for the two reevaluated flood mechanisms in the FE. For the LIP condition, the licensee relies on permanent passive flood protection features such as doors, to demonstrate that adequate protection is available. For the CEF, the stillwater elevation i~] NGVD29 and with wind induced waves the flood height is -NGVD29, which has the potential to impact QFFlCIAL USE QNLY SECURITY RELA+ED INJ:GRMAl'.ION OFFICIAL USE ONL¥ SECURITY RELATED INFORMATION the intake structure with plant elevation of 111 ft. NGVD29, but not the power block. The potential impacts from this flooding-causing mechanisms were further evaluated by SNC as part of the Hatch FE. Table 3.1 Summary of Reevaluated Flood Hazards Elevations Included in the Hatch FE. Mechanism Local Intense Precipitation Control Building Intake Structure Diesel Generator Building Turbine and Reactor Building Combined Effect Flood (PMF with overtopping dam failure with wind-induced waves) Stillwater Wind-Wave Run Elevation u 130.5 ft. NGVD29 N/A 111.2 ft. NGVD29 N/A 130.2 ft. NGVD29 N/A 130.4 ft. NGVD29 N/A NGVD29]] NGVD29}1 3.2 Evaluation of Flood Impact Assessment for LIP 3.2.1 Description of Impact of Unbounded Hazard The Hatch FE identified the potential impacts on key SSCs as a result of water ingress due to LIP. The beyond-design-basis (BOB) LIP event leads to flood water surface elevations above the plant floor elevations at some locations. In order to assess the impacts of the unbounded flood levels, the licensee identified the maximum water surface elevations at the exterior door openings, maximum flood depths above the door threshold, and duration of when the flood levels are above the door threshold. With this information, the licensee assessed the impacts of water ingress and potential for accumulation into rooms housing key SSCs. The licensee's evaluation indicated that the LIP mechanism will produce ingress of flood waters through several doors that co'uld impact key SSCs in the main power block. The licensee determined that water must enter the power block buildings through open pathways at 130.0 ft. NGVD29 since all the penetrations below 130 ft. NVGD29 were inspected and confirmed sealed during the Recommendation 2.3 Flooding Walk downs. Therefore, the licensee identified the door characteristics, such as gap dimensions, and floor areas to determine water accumulation at floor elevations of 130 ft. NGVD29. In addition, the licensee assumed that all water volume used to evaluate flood height at the 130 ft. floor area will enter the Turbine and Control Buildings and flood their basement floors (112 ft. NGVD29 elevation). After determining the water accumulation on floor areas, the licensee compared the flooding height with the minimum elevations of key SSCs housed in each area. The licensee concluded that:
| |
| * Flood water ingress due to the LIP flood would not impact the plant's key safety functions because the estimated water accumulation would not reach the elevation of key SSCs at the Reactor, Turbine and Control buildings; and QFFtCtAk USE QNLY.-SECURITY-RELAlE9 INFQRMATION GFRG-IAl= USE ONLY SECURITY RELATED INFORMARON
| |
| * Water was determined to not accumulate in the Intake Structure due to building configuration and site topography that will drain water back to the river. The NRC staff reviewed the information provided by the licensee in order to ensure that adequate flood parameters were used for the calculation of water ingress and water accumulation. Specifically, the NRC staff verified that the assumed duration of flooding above threshold elevation was consistent with previous information reviewed by the staff for the Hatch FHRR and MSA. 3.2.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features The licensee relies on passive features and existing doors to justify that there is available margin using a deterministic approach. Therefore, the licensee evaluated the key SSC elevations when compared to water ingress accumulation from exterior doors to obtain the APM. Water Ingress through Exterior Doors The licensee determined the lowest elevations ( equipment is raised off the floor) of key SSCs needed for safe shutdown. These elevations are shown below:
| |
| * Reactor Building, Units 1 and 2, 130 ft. NGVD29 elevation: 4 inches
| |
| * Turbine and Control Building, Unit 1, 130 ft. NGVD29 elevation: 3 inches;
| |
| * Turbine and Control Building, Unit 2, 130 ft. NGVD29 elevation: 4 inches; and
| |
| * Turbine and Control Building, Unit 1 and 2, 112 ft. NGVD29 elevation: 1 inch. The licensee estimated the accumulation of flood water due to LIP water ingress as follows:
| |
| * Reactor Building-Licensee assumed that all Unit 2 Truck Bay flooding volume will enter the Reactor Building in Unit 2, creating an estimated flooding depth of 0.03 feet when distributed over the Reactor Building, Unit 2 area of 17,446 ft.2. The licensee determined that the .03 feet of flood height is well below the lowest key SSC which is located 0.33 ft. ( 4 inches) off the finished floor.
| |
| * Turbine and Control Buildings-Licensee estimated the flooding depths on the 130 ft. NGVD29 elevation to be 0.05 ft. (0.64 inches). The licensee determined that the flooding height is well below the lowest elevation of the key SSCs which are raised at 3.0 inches or higher off the floor. The flooding depths in the Turbine and Control Building on the 112 ft. NGVD29 elevation were estimated to be 0.04 ft. (0.47 inches). The licensee determined that the flooding height is below the lowest elevation of the key SSCs which are 1.0 inch off the floor. As a result, the licensee concluded that adequate APM exits based on the high factor of safety associated with the computation of the flooding depths and the lowest elevations where the key SSCs would be impacted. Furthermore, the licensee stated that several conservative assumptions were made in the estimation of water ingress, such as not crediting storm drains in the computation of water heights at the exterior doors and not considering the reduction due to water leakage through doors during the time of inundation. OFFICIAL USE 0Nb¥-SECURITY.RELATED INFORMATIGN OFFICIAL USE ONLY SECURITY RELATED INFORMATION The NRC staff concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated LIP mechanism. The calculation assumed that the water head at the exterior doors was at its maximum height over the entire duration of the event, and treated the door gap as a sluice gate to obtain the estimated flow. Therefore, the NRC staff agrees that the licensee's estimation of water accumulation is conservative. Therefore, the NRC staff concludes that the licensee has demonstrated that adequate passive features exist to provide flood protection of key SSCs. Evaluation of Reliability of Protection Features Hatch relies on permanent passive flooding protection features such as exterior doors to provide protection for flooding from LIP. The licensee evaluated the ability of these passive engineering features to protect key SSCs by limiting floodwater inflow into plant floors during the LIP flood conditions through engineering evaluations. The reliability of the doors to withstand the pressure from floodwater was not specifically evaluated by Hatch. Because the exterior water depths at the doors is relatively small, in the order of inches, the NRC staff used engineering judgment to conclude that the design capacity of the doors should not be compromised and that the doors are a reliable passive protection feature. The NRC staff performed an audit of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016, in accordance with an NRC audit plan dated July 18, 2017 (ADAMS Accession No. ML 17192A452). Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that areas containing key SSCs will not be adversely impacted by water ingress from the LIP reevaluated hazard, and that the flood protection features associated with key SSCs will ensure their continued function in the event of LIP. In addition, the licensee indicated that credited flood protection features are passive features that are checked as part of normal operator rounds. Therefore, the NRC staff concludes, with the information provided by the licensee as the basis, that the above-mentioned passive features are evaluated by an appropriate maintenance and inspection regime to ensure they will continue to be available to perform their intended flood protection function. Because increased focus has been placed on flood protection since the accident at Fukushima, licensees and NRC inspectors have identified deficiencies with equipment, procedures, and analyses relied on to either prevent or mitigate the effects of external flooding at a number of licensed facilities. Recent examples include those found in Information Notice 2015-01, "Degraded Ability to Mitigate Flooding Events" (ADAMS Accession No. ML 14279A268). In addition, the NRC is cooperatively performing research with the Electric Power Research Institute to develop flood protection systems guidance that focuses on flood protection feature descriptions, design criteria, inspections, and available testing methods in accordance with a memorandum of understanding dated September 28, 2016 (ADAMS Accession No. ML 16223A495). The NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff further expects that continued research involving flood protection systems will be performed and shared with licensees in accordance with the guidance provided in Management Directive 8.7, "Reactor Operating Experience Program" (ADAMS Accession No. ML 122750292), as appropriate. The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1. GFFICIAb-USE 0Nb~EGURl-l'¥-RELATED INFGRMATION OFFICIAL USE ONLY SECURITY RELATED INFORMATION 3.2.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB LIP event. As described above, the licensee's evaluation relied on passive existing flood protection features to demonstrate adequate flood protection; therefore, there is no need to review overall site response. 3.3 Evaluation of Flood Impact Assessment for combined effects flooding (PMF with upstream dam failure with wind-induced waves) 3.3.1 Description of Impact of Unbounded Hazard As described in the FE, the stillwater elevation from the CEF mechanism i NGVD29 and the maximum flood elevation including wind-induced waves is NGVD29. The licensee indicates that the primary feature protecting the site from the reevaluated flood hazard along the Altamaha River is site topography and grading. Since the main power block buildings (i.e., Reactor, Turbine, and Control Buildings) are located at elevation 130 ft. NGVD29, no impacts were identified on key SSCs located in such buildings. Therefore, for the main power block, the licensee calculated an APM o for stillwater and NGVD29)]] for wind-wave run-up. For the Intake Structure, the wind-induced waves exceed the Intake Structure elevation of 111 feet NGVD29. The intake structure houses the Plant Service Water and Residual Heat Removal pumps, both key SSCs required for shutdown. However, the licensee indicates that the reevaluated CEF mechanism does not impact key SSCs at the Intake structure because: 1) the bathymetry of the site will allow the waves to break before impacting the intake structure; 2) the Intake Structures doors are placed in labyrinth offsets and are weather-stripped; and 3) in the case of water ingress the floor gratings will drain the water into a pit that houses two submersible water pumps that will drain the water out. Therefore, for the Intake Structure, the licensee calculated an APM o for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features described above. As a result, the licensee concluded that the CEF mechanism has no impacts to key SSCs. 3.3.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features As described above, the licensee calculated an APM for the main power block o stillwater and -for wind-wave run-up. The licensee calculated an APM of for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features on the Intake Structure. The licensee also stated that there would be no impact to the structural integrity of the Intake Structure from the reevaluated CFE mechanism. The NRC staff reviewed the APM calculation and concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated CEF mechanism. The natural topography around the site provides effective flood protection against the CEF, with adequate margin. Furthermore, the NRG staff reviewed the methodology used to evaluate the structural OFFICIAL USE ONLY SEGURITY-REbATED INFORMATION OFFICIAL USE ONL¥-SEGURITY RELATED INFORMATION integrity of the walls and foundations from the increased flood/wave heights elevation and found it to be acceptable. Evaluation of Reliability of Protection Features Hatch relies on the natural topography around the site to provide protection from the reevaluated CEF conditions. For the main power block, the site topography provides adequate APM for buildings housing key SSCs. Since this feature is already credited as part of the Hatch design-basis flood protection, the NRC staff concludes that a reliability analysis of these features is not necessary in accordance with the guidance found in NEI 16-05, Revision 1. For the Intake Structure, Hatch relies on passive features such as the configuration of doors and drainage capabilities around the Intake Structure. Furthermore, Hatch evaluated the structural integrity of the Intake Structure through engineering evaluations to verify that the loads from the reevaluated CFE will not affect the structural integrity of the walls. This calculation was provided as part of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016. The licensee evaluated the loads imposed on the structural walls of the Intake Structure and concluded that it will not create any impacts. The licensee determined that the maximum hydrostatic pressure and force on the Intake Structure walls due to the CEF mechanism is , respectively. In addition, the maximum hydrodynamic pressure and force on the Intake Structure walls due to breaking wave is 4,312 lb/ft.2and 93,648 lb/ft., respectively. With this information, the licensee concluded that the maximum hydrodynamic and hydrostatic pressures are less than the concrete strength of 4,000 pounds per square inch (psi} (or 576,000 lb/ft.2} at the Intake Structure. Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that the Intake Structure has adequate flood protection such that its functions will not be adversely impacted by the CFE reevaluated hazard. As noted in Section 3.2.2 of this document, the NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1. 3.3.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB Probable Maximum Storm Surge event. As described above, the licensee's evaluation relied on passive existing features to demonstrate adequate flood protection. Therefore, there is no need to review overall site response. 4.0 AUDIT REPORT The July 18, 2017, generic audit plan describes the NRC staff's intention to issue an audit report that summarizes and documents the NRC's regulatory audit of the licensee's FE. The NRC staff's Hatch audit was limited to the review of the calculation number SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016, and drawings listed at the end of this section. Because this staff assessment appropriately summarizes the results of the audit, the NRC staff concludes a separate audit report is not necessary, and that this document serves as the audit report described in the staff's July 18, 2017, letter. OFFICIAL l:ISE ONLY SEGlJRITY-REbATED INFORMATION QFFICIAL USE QNLY SEGYRITY REbATED INFQRMMIQN
| |
| * Drawing H-12192 Version 11.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 Outdoor Concrete Intake Structure General Arrangement," February 12, 1971. | | * Drawing H-12192 Version 11.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 Outdoor Concrete Intake Structure General Arrangement," February 12, 1971. |
| * Drawing E-10173 Version 23.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 & 2 General Building Site Plan." | | * Drawing E-10173 Version 23.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 & 2 General Building Site Plan." |
| * Drawing H-21102 Version 20.0, ""Edwin I. Hatch Nuclear Plant Unit No. 2 Piping-Service Water at River Intake Structure," April 7, 1971. | | * Drawing H-21102 Version 20.0, ""Edwin I. Hatch Nuclear Plant Unit No. 2 Piping-Service Water at River Intake Structure," April 7, 1971. |
| * Drawing H12610 Version 5.0, ""Edwin I. Hatch Nuclear Plant Unit No. 1 Architectural River Intake Structure Pump Room-Plans, Elevations & Details," September 29, 2009. | | * Drawing H12610 Version 5.0, ""Edwin I. Hatch Nuclear Plant Unit No. 1 Architectural River Intake Structure Pump Room-Plans, Elevations & Details," September 29, 2009. |
| | |
| | ==5.0 CONCLUSION== |
|
| |
|
| ==5.0 CONCLUSION==
| | The NRC staff concludes that SNC performed the Hatch FE in accordance with the guidance described in NEI 16-05, Revision 1, as endorsed by JLD-ISG-2016-01, and that the licensee has demonstrated that effective flood protection exists against the reevaluated flood hazards. |
| The NRC staff concludes that SNC performed the Hatch FE in accordance with the guidance described in NEI 16-05, Revision 1, as endorsed by JLD-ISG-2016-01, and that the licensee has demonstrated that effective flood protection exists against the reevaluated flood hazards. Furthermore, the NRC staff concludes that Hatch screens out of performing an integrated assessment based on the guidance found in JLD-ISG-2016-01 . As such, in accordance with Phase 2 of the process outlined in the 50.54(f) letter, additional regulatory actions associated with the reevaluated flood hazard, beyond those associated with mitigation strategies assessment, are not warranted. The licensee has satisfactorily completed providing responses to the 50.54(f) activities associated with the reevaluated flood hazards. QFFJCIAL USE QNl.¥-SEGURl'f¥ RElA+ED INFQRMAllON OFFICIAL USE ONLV-SEGURl"fV REl::ATEE) INFORMATION J. Hutto | | Furthermore, the NRC staff concludes that Hatch screens out of performing an integrated assessment based on the guidance found in JLD-ISG-2016-01 . As such, in accordance with Phase 2 of the process outlined in the 50.54(f) letter, additional regulatory actions associated with the reevaluated flood hazard, beyond those associated with mitigation strategies assessment, are not warranted. The licensee has satisfactorily completed providing responses to the 50.54(f) activities associated with the reevaluated flood hazards. |
| | QFFJCIAL USE QNl.¥-SEGURl'f¥ RElA+ED INFQRMAllON |
|
| |
|
| ==SUBJECT:==
| | PKG ML180308055; ML18029A915 (NON-PUBLIC); |
| EDWIN I. HATCHNUCLEAR PLANT, UNITS 1 AND 2 -STAFF ASSESSMENT OF FLOODING FOCUSED EVALUATION DATED MARCH 13, 2018 DISTRIBUTION: Public PBMB R/F RidsNRR Dip Resource RidsNrrDorlLpl2-1 Resource RidsNrrDorl Resource RidsNrrPMHatch Resource RidsNrrlaSLent Resource EBowman, NRR RidsOpaMail Resource RidsACRS_MailCtr Resource RidsRgn2MailCenter Resource JMarcano, NMSS ADAMS Accession Nos.: PKG ML 180308055; ML 18029A915 (NON-PUBLIC); ML 180308076 (PUBLIC) *via email OFFICE NMSS/FCSS/PORSB* NRR/DLP/PBMB/PM NRR/DLP/PBMB/LA NAME JMarcano FVeaa SLent DATE 01/26/2018 02/28/2018 01/30/2018 OFFICE NRR/DLP/PBMB/BC{A) NRR/DLP/PBMB/PM NAME EBowman (BTitus for) FVeQa DATE 03/02/2018 03/13/2018 OFFICIAL RECORD COPY OFFICIAL USE ONLY-SECURITY-RELATED INFGRMATION
| | ML180308076 (PUBLIC) *via email OFFICE NMSS/FCSS/PORSB* NRR/DLP/PBMB/PM NRR/DLP/PBMB/LA NAME JMarcano FVeaa SLent DATE 01/26/2018 02/28/2018 01/30/2018 OFFICE NRR/DLP/PBMB/BC{A) NRR/DLP/PBMB/PM NAME EBowman (BTitus for) FVeQa DATE 03/02/2018 03/13/2018}} |
| }} | |
Similar Documents at Hatch |
---|
Category:Letter
MONTHYEARML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 NL-24-0237, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0240, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0166, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 NL-24-0157, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint NL-24-0144, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 IR 05000321/20230062024-02-28028 February 2024 Annual Assessment Letter Edwin I. Hatch Nuclear Plant Units 1 and 2 - Nrc Inspection Report 05000321/2023006 and 05000366/2023006 NL-24-0067, 10 CFR 72.48(d)(2) Biennial Report2024-02-26026 February 2024 10 CFR 72.48(d)(2) Biennial Report NL-24-0051, License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-02-20020 February 2024 License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers IR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. IR 05000321/20233012024-01-17017 January 2024 – NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) 2024-09-09
[Table view] |
Text
OFFICIAL USE ONLY: SEGURITY-RElATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 13, 2018 Mr. J. J. Hutto Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
P.O. Box 1295 /BIN B038 Birmingham, AL 35201-1295
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 - STAFF ASSESSMENT OF FLOODING FOCUSED EVALUATION (CAC NOS. MF9687 AND MF9868; EPID NOS. 000495/05000321/L-2017-JLD-0029 AND 000495/05000366/L-2017-JLD-0029)
Dear Mr. Hutto:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f), "Conditions of Licenses" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTTF) report (ADAMS Accession No. ML111861807). Enclosure 2 to the 50.54(f) letter requested that licensees reevaluate flood hazards for their sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML12056A046). By letter dated March 6, 2014 (ADAMS Accession No. ML14069A054),
Southern Nuclear Operating Company, Inc. (SNC, the licensee) responded to this request for Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch).
After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML15321A156), the NRG issued an interim staff response (ISR) letter for Hatch.
The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for other assessments associated with NITF Recommendation 2.1 "Flooding". As stated in the letter, because the local intense precipitation (LIP) and Combined Effects Flooding (Probable Maximum Flood (PMF) with upstream dam overtopping with wind-induced waves) are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary.
Enclosure 1 transmitted herewith contains Security-Related Information. When separated from Enclosure 1, this document is decontrolled.
OFFIGIAb USE ONLY: SECURITY.RELATED INF9RMATION
OFFICIAL USE C>NLY SECURfT¥-RELATED INFORMATION J. Hutto By letter dated June 22, 2017 (ADAMS Accession No. ML17173A777), the licensee submitted the focused evaluation (FE) for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters;
- 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. The purpose of this letter is to provide the NRC's assessment of the Hatch FE.
As set forth in the attached staff assessment, the NRC staff has concluded that the Hatch FE was performed consistent with the guidance described in Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML16165A178). Guidance document NEI 16-05, Revision 1, has been endorsed by Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML16162A301 ). The NRC staff has further concluded that the licensee has demonstrated that effective flood protection, if appropriately implemented, exists for the LIP and Combined Effects Flooding mechanisms during a beyond-design-basis external flooding event at Hatch. This closes out the licensee's response for Hatch for the reevaluated flooding hazard portion of the 50.54(f) letter and the NRC's efforts associated with CAC Nos. MF9687 and MF9868.
If you have any questions, please contact me at 301-415-1617 or at Frankie.Vega@nrc.gov.
Sincerely, Fra~i:anager Beyond-Design-Basis Management Branch Division of Licensing Projects Office of Nuclear Reactor Regulation
Enclosures:
- 1. Staff Assessment Related to the Flooding Focused Evaluation for Hatch (non-public)
- 2. Staff Assessment Related to the Flooding Focused Evaluation for Hatch (public)
Docket Nos: 50-321 and 50-366 cc w/encl: Distribution via Listserv OFFIGIAL USE ONbY- SECURIT¥-RELATED INFORMATION
OFFICIAL USE ONL¥-SEGURIT¥-RELATED INFORMATION STAFF ASSESSMENT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO THE FOCUSED EVALUATION FOR EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 AS A RESULT OF THE REEVALUATED FLOODING HAZARD NEAR-TERM TASK FORCE RECOMMENDATION 2.1 - FLOODING (CAC NOS. MF9687 AND MF9868)
1.0 INTRODUCTION
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12053A340), the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 1O of the Code of Federal Regulations (10 CFR), Section 50.54(f) (hereafter referred to as the "50.54(f) letter). The request was issued in connection with implementing lessons learned from the 2011 accident at the Fukushima Dai-ichi nuclear power plant, as documented in the NRC's Near-Term Task Force (NTIF) report (ADAMS Accession No. ML111861807).
Enclosure 2 of the 50.54(f) letter requested that licensees reevaluate flood hazards for their respective sites using present-day methods and regulatory guidance used by the NRC staff when reviewing applications for early site permits and combined licenses (ADAMS Accession No. ML12056A046). lf the reevaluated hazard for any flood-causing mechanism is not bounded by the plant's current design basis (COB) flood hazard, an additional assessment of plant response would be necessary. Specifically, the 50.54(f) letter stated that an integrated assessment should be submitted, and described the information that the integrated assessment should contain. By letter dated November 30, 2012 (ADAMS Accession No. ML12311A214),
the NRC staff issued Japan Lessons-Learned Division (JLD) interim staff guidance (ISG) JLD-ISG-2012-05, "Guidance for Performing the Integrated Assessment for External Flooding."
On June 30, 2015 (ADAMS Accession No.ML15153A104), the NRC staff issued COMSECY 0019, describing the closure plan for the reevaluation of flooding hazards for operating nuclear power plants. The Commission approved the closure plan on July 28, 2015 (ADAMS Accession No. ML15209A682). COMSECY-15-0019 outlines a revised process for addressing cases in which the reevaluated flood hazard is not bounded by the plant's COB. The revised process describes a graded approach in which licensees with hazards exceeding their COB flood will not be required to complete an integrated assessment, but instead will perform a focused evaluation (FE). As part of the FE, licensees will assess the impact of the hazard(s) on their site and then evaluate and implement any necessary programmatic, procedural, or plant modifications to address the hazard exceedance.
Nuclear Energy Institute (NEI) 16-05, Revision 1, "External Flooding Assessment Guidelines" (ADAMS Accession No. ML16165A178), has been endorsed by the NRC as an appropriate methodology for licensees to perform the focused evaluation in response to the 50.54(f) letter.
Enclosure 2 OFFICIAL USE ONL¥ SEGURl+V-RELA+ED INFQRMA+IQN
OFFICIAL USE ONLY SECURITV-RELAlE9 INFORMATION The NRC's endorsement of NEI 16-05, including exceptions, clarifications, and additions, is described in NRC JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flood Hazard Reevaluation" (ADAMS Accession No. ML16162A301 ).
Therefore, NEI 16-05, Revision 1, as endorsed, describes acceptable methods for demonstrating that Edwin I. Hatch, Units 1 and 2 (Hatch) has effective flood protection.
2.0 BACKGROUND
This document provides the final NRC staff assessment associated with the information that the licensee provided in response to the reevaluated flooding hazard portion of the 50.54(f) letter. Therefore, this background section includes a summary description of the reevaluated flood information provided by the licensee and the associated assessments performed by the NRC staff. The reevaluated flood information includes: 1) the flood hazard reevaluation report (FHRR); 2) the mitigation strategies assessment (MSA); and 3) the focused evaluation.
Flood Hazard Reevaluation Report By letter dated March 6, 2014 (ADAMS Accession No. ML14069A054), as supplemented by letters dated August 6, 2014, June 3, 2015, and March 7, 2016 (ADAMS Accession Nos.
ML14219A570 (non-public), ML15154B601 (non-public), and ML16069A088 (non-public),
respectively), Southern Nuclear Operating Company, Inc. (SNC, the licensee) submitted its FHRR for Hatch. After its review of the licensee's response, by letter dated December 4, 2015 (ADAMS Accession No. ML15321A156), the NRC issued an interim staff response (ISR) letter for Hatch. The ISR letter provided the reevaluated flood hazard mechanisms that exceeded the current design basis (COB) for Hatch and parameters that are suitable for the mitigating strategies assessment (MSA) and the FE. As stated in the letter, because the local intense precipitation (LIP), flooding in rivers and streams, and failures of dams and onsite water control structures flooding mechanisms are not bounded by the plant's COB, additional assessments of the flood hazard mechanisms are necessary. The NRC staff issued a final staff assessment of the FHRR in a letter dated October 11, 2016 (ADAMS Accession No. ML16237A095). The NRC staff's conclusions regarding LIP, flooding in rivers and streams, failures of dams and onsite water control structures exceeding the Hatch COB remained unchanged from the information provided in the ISR letter.
Mitigation Strategies Assessment By letter dated December 16, 2016 (ADAMS Accession No. ML16351A087), SNC submitted the Hatch MSA for review by the NRC staff. The MSAs are intended to confirm that licensees have adequately addressed the reevaluated flooding hazards within their mitigation strategies for beyond-design-basis external events. By letter dated April 13, 2017 (ADAMS Accession No. ML17069A234), the NRC issued its assessment of the Hatch MSA. The NRC staff concluded that the Hatch MSA was performed consistent with the guidance described in Appendix G of NEI 12-06, Revision 2, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide" (ADAMS Accession No. ML16005A625). The NRC's endorsement of NEI 12-06, Revision 2, is described in JLD-ISG-2012-01, Revision 1, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML15357A163). The NRC staff further concluded that the licensee has demonstrated that the mitigation strategies, if appropriately implemented, are reasonably protected from reevaluated flood hazards conditions for beyond-design-basis external events.
OFFICIAL:: USE ONbY--SECURfTY..RELATEO INFORM.MION
OFFIGJ-AL USE ONLY SEGURA"¥ RELA:rED INFORMATION Focused Evaluation By letter dated June 22, 2017 (ADAMS Accession No. ML17173A777), the licensee submitted the FE for Hatch. The FEs are intended to confirm that licensees have adequately demonstrated, for unbounded mechanisms identified in the ISR letter, that: 1) a flood mechanism is bounded based on further reevaluation of flood mechanism parameters;
- 2) effective flood protection is provided for the unbounded mechanism; or 3) a feasible response is provided if the unbounded mechanism is local intense precipitation. These 3 options associated with performing an FE are referred to as Path 1, 2, or 3, as described in NEI 16-05, Revision 1. The purpose of this staff assessment is to provide the results of the NRC's evaluation of the Hatch FE.
3.0 TECHNICAL EVALUATION
The licensee stated that its FE followed Path 2 of NEI 16-05, Revision 1 and utilized Appendix B for guidance on evaluating the site strategy. The following flooding mechanisms from the FHRR were not bounded by the COB: LIP; flooding in rivers and streams (all season probable maximum flood (PMF) with a 1/2 PMF antecedent storm); seismic upstream dam failure; PMF with upstream overtopping dam failure; and combined effects flooding (CEF) (PMF with upstream dam failure with wind-induced waves). In its MSA, the licensee states that three of these mechanisms have maximum flooding elevations that are below the elevation of the intake structure and power block and are therefore not required to be further evaluated in the MSA.
The NRC agreed with this assessment for flooding in rivers and streams (all season PMF with a 1/2 PMF antecedent storm), seismic upstream dam failure, and PMF with upstream overtopping dam failure and no further flooding evaluations are required for these flooding mechanism.
Further evaluation of the LIP and CEF protection features was provided by Hatch in its FE. This technical evaluation will address the following topics: characterization of flood parameters; evaluation of flood impact assessments; evaluation of available physical margin; reliability of flood protection features; and overall site response.
3.1 Characterization of Flood Parameters Associated effects (AEs) and flood event duration (FED) parameters were assessed by SNC and have already been reviewed by the NRC, as summarized by letter dated October 11, 2016 (ADAMS Accession No. ML16237A095), and letter dated April 13, 2017 (ADAMS Accession No. ML17069A234). The licensee used the AE and FED parameters as input to the Hatch FE and concluded that the site's flood strategy is effective in protecting structures, systems, and components (SSCs) that support key safety functions (KSFs). The licensee supported its conclusion of adequate flood protection by demonstrating adequate available physical margin (APM) and reliable flood protection features for LIP and CEF. In its FE for Hatch, SNC indicated that the site does not require manual actions by plant personnel to protect key SSCs; therefore, an evaluation of the overall site response was not necessary.
The Hatch plant grade and floor elevations for the power block (Reactor, Turbine and Control buildings) are 130 feet (ft.) National Geodetic Vertical Datum of 1929 (NGVD29). Table 3.1 of this assessment provides the maximum exterior water surface elevations for the two reevaluated flood mechanisms in the FE. For the LIP condition, the licensee relies on permanent passive flood protection features such as doors, to demonstrate that adequate protection is available. For the CEF, the stillwater elevation i ~ ] NGVD29 and with wind induced waves the flood height is - NGVD29, which has the potential to impact QFFlCIAL USE QNLY SECURITY RELA+ED INJ:GRMAl'.ION
OFFICIAL USE ONL¥ SECURITY RELATED INFORMATION the intake structure with plant elevation of 111 ft. NGVD29, but not the power block. The potential impacts from this flooding-causing mechanisms were further evaluated by SNC as part of the Hatch FE.
Table 3.1 Summary of Reevaluated Flood Hazards Elevations Included in the Hatch FE.
Mechanism Stillwater Wind-Wave Run Elevation u Local Intense Precipitation Control Building 130.5 ft. NGVD29 N/A Intake Structure 111.2 ft. NGVD29 N/A Diesel Generator Building 130.2 ft. NGVD29 N/A Turbine and Reactor Building 130.4 ft. NGVD29 N/A Combined Effect Flood (PMF with overtopping dam failure with wind-induced NGVD29)) NGVD29}1 waves) 3.2 Evaluation of Flood Impact Assessment for LIP 3.2.1 Description of Impact of Unbounded Hazard The Hatch FE identified the potential impacts on key SSCs as a result of water ingress due to LIP. The beyond-design-basis (BOB) LIP event leads to flood water surface elevations above the plant floor elevations at some locations. In order to assess the impacts of the unbounded flood levels, the licensee identified the maximum water surface elevations at the exterior door openings, maximum flood depths above the door threshold, and duration of when the flood levels are above the door threshold. With this information, the licensee assessed the impacts of water ingress and potential for accumulation into rooms housing key SSCs.
The licensee's evaluation indicated that the LIP mechanism will produce ingress of flood waters through several doors that co'uld impact key SSCs in the main power block. The licensee determined that water must enter the power block buildings through open pathways at 130.0 ft.
NGVD29 since all the penetrations below 130 ft. NVGD29 were inspected and confirmed sealed during the Recommendation 2.3 Flooding Walk downs. Therefore, the licensee identified the door characteristics, such as gap dimensions, and floor areas to determine water accumulation at floor elevations of 130 ft. NGVD29. In addition, the licensee assumed that all water volume used to evaluate flood height at the 130 ft. floor area will enter the Turbine and Control Buildings and flood their basement floors (112 ft. NGVD29 elevation). After determining the water accumulation on floor areas, the licensee compared the flooding height with the minimum elevations of key SSCs housed in each area.
The licensee concluded that:
- Flood water ingress due to the LIP flood would not impact the plant's key safety functions because the estimated water accumulation would not reach the elevation of key SSCs at the Reactor, Turbine and Control buildings; and QFFtCtAk USE QNLY.-SECURITY-RELAlE9 INFQRMATION
GFRG-IAl= USE ONLY SECURITY RELATED INFORMARON
- Water was determined to not accumulate in the Intake Structure due to building configuration and site topography that will drain water back to the river.
The NRC staff reviewed the information provided by the licensee in order to ensure that adequate flood parameters were used for the calculation of water ingress and water accumulation. Specifically, the NRC staff verified that the assumed duration of flooding above threshold elevation was consistent with previous information reviewed by the staff for the Hatch FHRR and MSA.
3.2.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features The licensee relies on passive features and existing doors to justify that there is available margin using a deterministic approach. Therefore, the licensee evaluated the key SSC elevations when compared to water ingress accumulation from exterior doors to obtain the APM.
Water Ingress through Exterior Doors The licensee determined the lowest elevations ( equipment is raised off the floor) of key SSCs needed for safe shutdown. These elevations are shown below:
- Reactor Building, Units 1 and 2, 130 ft. NGVD29 elevation: 4 inches
- Turbine and Control Building, Unit 1, 130 ft. NGVD29 elevation: 3 inches;
- Turbine and Control Building, Unit 2, 130 ft. NGVD29 elevation: 4 inches; and
- Turbine and Control Building, Unit 1 and 2, 112 ft. NGVD29 elevation: 1 inch.
The licensee estimated the accumulation of flood water due to LIP water ingress as follows:
- Reactor Building- Licensee assumed that all Unit 2 Truck Bay flooding volume will enter the Reactor Building in Unit 2, creating an estimated flooding depth of 0.03 feet when distributed over the Reactor Building, Unit 2 area of 17,446 ft. 2 . The licensee determined that the .03 feet of flood height is well below the lowest key SSC which is located 0.33 ft.
(4 inches) off the finished floor.
- Turbine and Control Buildings- Licensee estimated the flooding depths on the 130 ft.
NGVD29 elevation to be 0.05 ft. (0.64 inches). The licensee determined that the flooding height is well below the lowest elevation of the key SSCs which are raised at 3.0 inches or higher off the floor. The flooding depths in the Turbine and Control Building on the 112 ft. NGVD29 elevation were estimated to be 0.04 ft. (0.47 inches). The licensee determined that the flooding height is below the lowest elevation of the key SSCs which are 1.0 inch off the floor.
As a result, the licensee concluded that adequate APM exits based on the high factor of safety associated with the computation of the flooding depths and the lowest elevations where the key SSCs would be impacted. Furthermore, the licensee stated that several conservative assumptions were made in the estimation of water ingress, such as not crediting storm drains in the computation of water heights at the exterior doors and not considering the reduction due to water leakage through doors during the time of inundation.
OFFICIAL USE 0Nb¥-SECURITY.RELATED INFORMATIGN
OFFICIAL USE ONLY SECURITY RELATED INFORMATION The NRC staff concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated LIP mechanism. The calculation assumed that the water head at the exterior doors was at its maximum height over the entire duration of the event, and treated the door gap as a sluice gate to obtain the estimated flow. Therefore, the NRC staff agrees that the licensee's estimation of water accumulation is conservative. Therefore, the NRC staff concludes that the licensee has demonstrated that adequate passive features exist to provide flood protection of key SSCs.
Evaluation of Reliability of Protection Features Hatch relies on permanent passive flooding protection features such as exterior doors to provide protection for flooding from LIP. The licensee evaluated the ability of these passive engineering features to protect key SSCs by limiting floodwater inflow into plant floors during the LIP flood conditions through engineering evaluations. The reliability of the doors to withstand the pressure from floodwater was not specifically evaluated by Hatch. Because the exterior water depths at the doors is relatively small, in the order of inches, the NRC staff used engineering judgment to conclude that the design capacity of the doors should not be compromised and that the doors are a reliable passive protection feature.
The NRC staff performed an audit of SNC calculation SCNH-16-007, "MSA Hazard Evaluation",
Version 1.0 dated December 14, 2016, in accordance with an NRC audit plan dated July 18, 2017 (ADAMS Accession No. ML17192A452). Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that areas containing key SSCs will not be adversely impacted by water ingress from the LIP reevaluated hazard, and that the flood protection features associated with key SSCs will ensure their continued function in the event of LIP.
In addition, the licensee indicated that credited flood protection features are passive features that are checked as part of normal operator rounds. Therefore, the NRC staff concludes, with the information provided by the licensee as the basis, that the above-mentioned passive features are evaluated by an appropriate maintenance and inspection regime to ensure they will continue to be available to perform their intended flood protection function.
Because increased focus has been placed on flood protection since the accident at Fukushima, licensees and NRC inspectors have identified deficiencies with equipment, procedures, and analyses relied on to either prevent or mitigate the effects of external flooding at a number of licensed facilities. Recent examples include those found in Information Notice 2015-01, "Degraded Ability to Mitigate Flooding Events" (ADAMS Accession No. ML14279A268). In addition, the NRC is cooperatively performing research with the Electric Power Research Institute to develop flood protection systems guidance that focuses on flood protection feature descriptions, design criteria, inspections, and available testing methods in accordance with a memorandum of understanding dated September 28, 2016 (ADAMS Accession No. ML16223A495). The NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff further expects that continued research involving flood protection systems will be performed and shared with licensees in accordance with the guidance provided in Management Directive 8.7, "Reactor Operating Experience Program" (ADAMS Accession No. ML122750292), as appropriate.
The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1.
GFFICIAb-USE 0Nb~EGURl-l'¥-RELATED INFGRMATION
OFFICIAL USE ONLY SECURITY RELATED INFORMATION 3.2.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB LIP event. As described above, the licensee's evaluation relied on passive existing flood protection features to demonstrate adequate flood protection; therefore, there is no need to review overall site response.
3.3 Evaluation of Flood Impact Assessment for combined effects flooding (PMF with upstream dam failure with wind-induced waves) 3.3.1 Description of Impact of Unbounded Hazard As described in the FE, the stillwater elevation from the CEF mechanism i NGVD29 and the maximum flood elevation including wind-induced waves is NGVD29. The licensee indicates that the primary feature protecting the site from the reevaluated flood hazard along the Altamaha River is site topography and grading. Since the main power block buildings (i.e., Reactor, Turbine, and Control Buildings) are located at elevation 130 ft. NGVD29, no impacts were identified on key SSCs located in such buildings.
Therefore, for the main power block, the licensee calculated an APM o for stillwater and NGVD29))) for wind-wave run-up.
For the Intake Structure, the wind-induced waves exceed the Intake Structure elevation of 111 feet NGVD29. The intake structure houses the Plant Service Water and Residual Heat Removal pumps, both key SSCs required for shutdown. However, the licensee indicates that the reevaluated CEF mechanism does not impact key SSCs at the Intake structure because: 1) the bathymetry of the site will allow the waves to break before impacting the intake structure; 2) the Intake Structures doors are placed in labyrinth offsets and are weather-stripped; and 3) in the case of water ingress the floor gratings will drain the water into a pit that houses two submersible water pumps that will drain the water out. Therefore, for the Intake Structure, the licensee calculated an APM o for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features described above. As a result, the licensee concluded that the CEF mechanism has no impacts to key SSCs.
3.3.2 Evaluation of Available Physical Margin and Reliability of Flood Protection Features As described above, the licensee calculated an APM for the main power block o stillwater and - for wind-wave run-up. The licensee calculated an APM of for stillwater and qualitatively considered a justification of adequate APM for the wind wind-wave run-up given the protection features on the Intake Structure. The licensee also stated that there would be no impact to the structural integrity of the Intake Structure from the reevaluated CFE mechanism.
The NRC staff reviewed the APM calculation and concludes, based on the information provided by SNC, that adequate margin exists for the reevaluated CEF mechanism. The natural topography around the site provides effective flood protection against the CEF, with adequate margin. Furthermore, the NRG staff reviewed the methodology used to evaluate the structural OFFICIAL USE ONLY SEGURITY-REbATED INFORMATION
OFFICIAL USE ONL¥-SEGURITY RELATED INFORMATION integrity of the walls and foundations from the increased flood/wave heights elevation and found it to be acceptable.
Evaluation of Reliability of Protection Features Hatch relies on the natural topography around the site to provide protection from the reevaluated CEF conditions. For the main power block, the site topography provides adequate APM for buildings housing key SSCs. Since this feature is already credited as part of the Hatch design-basis flood protection, the NRC staff concludes that a reliability analysis of these features is not necessary in accordance with the guidance found in NEI 16-05, Revision 1.
For the Intake Structure, Hatch relies on passive features such as the configuration of doors and drainage capabilities around the Intake Structure. Furthermore, Hatch evaluated the structural integrity of the Intake Structure through engineering evaluations to verify that the loads from the reevaluated CFE will not affect the structural integrity of the walls. This calculation was provided as part of SNC calculation SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016. The licensee evaluated the loads imposed on the structural walls of the Intake Structure and concluded that it will not create any impacts. The licensee determined that the maximum hydrostatic pressure and force on the Intake Structure walls due to the CEF mechanism is , respectively. In addition, the maximum hydrodynamic pressure and force on the Intake Structure walls due to breaking wave is 4,312 lb/ft. 2 and 93,648 lb/ft., respectively. With this information, the licensee concluded that the maximum hydrodynamic and hydrostatic pressures are less than the concrete strength of 4,000 pounds per square inch (psi} (or 576,000 lb/ft. 2 } at the Intake Structure. Based on the audit of this calculation, the NRC staff concludes that there is reasonable assurance that the Intake Structure has adequate flood protection such that its functions will not be adversely impacted by the CFE reevaluated hazard.
As noted in Section 3.2.2 of this document, the NRC staff expects that licensees will continue to maintain flood protection features in accordance with their current licensing basis. The NRC staff concludes that the Hatch flood protection features described above are reliable to maintain key safety functions as defined in Appendix B of NEI 16-05, Rev 1.
3.3.3 Overall Site Response The licensee does not rely on any personnel actions or new modifications to the plant in order to respond to the BOB Probable Maximum Storm Surge event. As described above, the licensee's evaluation relied on passive existing features to demonstrate adequate flood protection.
Therefore, there is no need to review overall site response.
4.0 AUDIT REPORT The July 18, 2017, generic audit plan describes the NRC staff's intention to issue an audit report that summarizes and documents the NRC's regulatory audit of the licensee's FE. The NRC staff's Hatch audit was limited to the review of the calculation number SCNH-16-007, "MSA Hazard Evaluation", Version 1.0 dated December 14, 2016, and drawings listed at the end of this section. Because this staff assessment appropriately summarizes the results of the audit, the NRC staff concludes a separate audit report is not necessary, and that this document serves as the audit report described in the staff's July 18, 2017, letter.
OFFICIAL l:ISE ONLY SEGlJRITY-REbATED INFORMATION
QFFICIAL USE QNLY SEGYRITY REbATED INFQRMMIQN
- Drawing H-12192 Version 11.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 Outdoor Concrete Intake Structure General Arrangement," February 12, 1971.
- Drawing E-10173 Version 23.0, "Edwin I. Hatch Nuclear Plant Unit No. 1 & 2 General Building Site Plan."
- Drawing H-21102 Version 20.0, ""Edwin I. Hatch Nuclear Plant Unit No. 2 Piping-Service Water at River Intake Structure," April 7, 1971.
- Drawing H12610 Version 5.0, ""Edwin I. Hatch Nuclear Plant Unit No. 1 Architectural River Intake Structure Pump Room-Plans, Elevations & Details," September 29, 2009.
5.0 CONCLUSION
The NRC staff concludes that SNC performed the Hatch FE in accordance with the guidance described in NEI 16-05, Revision 1, as endorsed by JLD-ISG-2016-01, and that the licensee has demonstrated that effective flood protection exists against the reevaluated flood hazards.
Furthermore, the NRC staff concludes that Hatch screens out of performing an integrated assessment based on the guidance found in JLD-ISG-2016-01 . As such, in accordance with Phase 2 of the process outlined in the 50.54(f) letter, additional regulatory actions associated with the reevaluated flood hazard, beyond those associated with mitigation strategies assessment, are not warranted. The licensee has satisfactorily completed providing responses to the 50.54(f) activities associated with the reevaluated flood hazards.
QFFJCIAL USE QNl.¥-SEGURl'f¥ RElA+ED INFQRMAllON
PKG ML180308055; ML18029A915 (NON-PUBLIC);
ML180308076 (PUBLIC) *via email OFFICE NMSS/FCSS/PORSB* NRR/DLP/PBMB/PM NRR/DLP/PBMB/LA NAME JMarcano FVeaa SLent DATE 01/26/2018 02/28/2018 01/30/2018 OFFICE NRR/DLP/PBMB/BC{A) NRR/DLP/PBMB/PM NAME EBowman (BTitus for) FVeQa DATE 03/02/2018 03/13/2018