| | title = Nuclear Regulatory Commission Plan for the Audit of Pseg Nuclear Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Salem Nuclear Generating Station, Units 1 and 2 | | | title = Nuclear Regulatory Commission Plan for the Audit of PSEG Nuclear Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Salem Nuclear Generating Station, Units 1 and 2 |
| | author name = Govan T V | | | author name = Govan T |
| | author affiliation = NRC/NRR/JLD | | | author affiliation = NRC/NRR/JLD |
| | addressee name = Braun R | | | addressee name = Braun R |
Line 14: |
Line 14: |
| | page count = 5 | | | page count = 5 |
| | project = TAC:MF3790, TAC:MF3791 | | | project = TAC:MF3790, TAC:MF3791 |
| | stage = | | | stage = Other |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:Mr. Robert Braun President and CNO PSEG Nuclear LLC-N09 P. 0. Box 236 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 1, 2015 Hancocks Bridge, NJ 08038 SUBJECT: NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (TAC NOS. MF3790 AND MF3791) Dear Mr. Braun: This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of PSEG Nuclear LLC's (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for Salem Nuclear Generating Station, Units 1 and 2 (Salem). This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits,'' dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session. The audit will provide the NRC staff with a better understanding of the Salem FHRR which was submitted March 11, 2014 (ADAMS Accession No. ML 14071 A401 ). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the Salem FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment. The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. William Mc Tigue of your staff. | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 1, 2015 Mr. Robert Braun President and CNO PSEG Nuclear LLC-N09 P. 0. Box 236 Hancocks Bridge, NJ 08038 |
| R. Braun -2 -If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov. Docket Nos. 50-272 and 50-311 Enclosure: Audit Plan cc w/encl: Distribution via Listserv Sincerely, L----_ Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation NRC PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1 -FLOODING FOR SALEM NUCLEAR GENERATING STATION, UNITS 1AND2 BACKGROUND AND AUDIT BASIS: By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai:.ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f). By letter dated March 11, 2014, PSEG Nuclear LLC (PSEG, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Salem Nuclear Generating Station, Units 1 and 2 (Salem) (Agencywide Documents Access and Management System Accession No. ML 14071A401). The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of PSEG to aid in its review of the licensee's FHRR. REGULATORY AUDIT SCOPE AND METHODOLGY: The areas of focus for the regulatory audit is the information contained in the Salem FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary. Enclosure | | |
| -2 -INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT: The information required for the audit is the licensee's models and supporting calculations, as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled. NRC AUDIT TEAM: Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Kevin Quinlan NRC Technical Manaqer Mike Willinqham NRC Technical Support Various Contractors Department of Energy National Laboratory LOGISTICS: The audit meetings will be coordinated with PSEG staff. DELIVERABLES: The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available. The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review.
| | ==SUBJECT:== |
| R. Braun -2 -If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov. Docket Nos. 50-272 and 50-311 Enclosure: Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION: PUBLIC JLD R/F RidsNRRJLD Resource RidsNrrPMSalem Resource BHarvey,NRO RidsNrrDorllpl1-2 Resource MShams, NRR MWillingham, NRO ARivera, NRO KErwin, NRO TGovan, NRR KQuinlan, NRR ADAMS Accession No.: ML15146A220 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NAME TGovan Slent DATE 05/27/15 05/27/15 Sincerely, IRA/ Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation MFranovich, NRR JBowen, NRR BHarvey, NRO CParker, NRR CCook, NRO NRR/JLD/JHMB/BC MS hams 05/31/15 NRR/JLD/JHMB/PM TGovan 06/01/15 OFFICAL RECORD COPY | | NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (TAC NOS. MF3790 AND MF3791) |
| }} | | |
| | ==Dear Mr. Braun:== |
| | |
| | This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of PSEG Nuclear LLC's (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for Salem Nuclear Generating Station, Units 1 and 2 (Salem). |
| | This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits,'' dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session. |
| | The audit will provide the NRC staff with a better understanding of the Salem FHRR which was submitted March 11, 2014 (ADAMS Accession No. ML14071A401 ). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the Salem FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment. |
| | The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. William Mc Tigue of your staff. |
| | |
| | R. Braun If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov. |
| | Sincerely, JL°"v~ L----_ |
| | Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311 |
| | |
| | ==Enclosure:== |
| | |
| | Audit Plan cc w/encl: Distribution via Listserv |
| | |
| | NRC PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1 - FLOODING FOR SALEM NUCLEAR GENERATING STATION, UNITS 1AND2 BACKGROUND AND AUDIT BASIS: |
| | By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), |
| | Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai:.ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f). |
| | By letter dated March 11, 2014, PSEG Nuclear LLC (PSEG, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Salem Nuclear Generating Station, Units 1 and 2 (Salem) (Agencywide Documents Access and Management System Accession No. ML14071A401). The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of PSEG to aid in its review of the licensee's FHRR. |
| | REGULATORY AUDIT SCOPE AND METHODOLGY: |
| | The areas of focus for the regulatory audit is the information contained in the Salem FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary. |
| | Enclosure |
| | |
| | INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT: |
| | The information required for the audit is the licensee's models and supporting calculations, as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled. |
| | NRC AUDIT TEAM: |
| | Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Kevin Quinlan NRC Technical Manaqer Mike Willinqham NRC Technical Support Various Contractors Department of Energy National Laboratory LOGISTICS: |
| | The audit meetings will be coordinated with PSEG staff. |
| | DELIVERABLES: |
| | The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available. |
| | The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review. |
| | |
| | R. Braun If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov. |
| | Sincerely, IRA/ |
| | Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311 |
| | |
| | ==Enclosure:== |
| | |
| | Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION: |
| | PUBLIC MShams, NRR MFranovich, NRR JLD R/F MWillingham, NRO JBowen, NRR RidsNRRJLD Resource ARivera, NRO BHarvey, NRO RidsNrrPMSalem Resource KErwin, NRO CParker, NRR BHarvey,NRO TGovan, NRR CCook, NRO RidsNrrDorllpl1-2 Resource KQuinlan, NRR ADAMS Accession No.: ML15146A220 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME TGovan Slent MS hams TGovan DATE 05/27/15 05/27/15 05/31/15 06/01/15 OFFICAL RECORD COPY}} |
Letter Sequence Other |
---|
|
|
MONTHYEARML14071A4012014-03-11011 March 2014 PSEG Nuclear Llc'S Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Generating Station Flood Hazard Reevaluation Project stage: Request ML14168A2422014-06-28028 June 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation Project stage: RAI ML15146A2202015-06-0101 June 2015 Nuclear Regulatory Commission Plan for the Audit of PSEG Nuclear Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Salem Nuclear Generating Station, Units 1 and 2 Project stage: Other ML15238B7042015-09-10010 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54 Information Request - Flood Causing Mechanism Reevaluation Project stage: Other ML15243A4472015-09-10010 September 2015 Master Report - Tables 1 and 2 Project stage: Other 2014-06-28
[Table View] |
Similar Documents at Salem |
---|
Category:Audit Plan
MONTHYEARML16259A1892016-12-0505 December 2016 Nuclear Regulatory Commission Plan for the Audit of Mitigation Strategies Assessment Submittals Related to Order EA-12-049, Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16127A0292016-05-11011 May 2016 Regulatory Audit Plan for May 23 - 26, 2016 in Support of the License Amendment Request to Modify the Chilled Water System Requirements ML15146A2202015-06-0101 June 2015 Nuclear Regulatory Commission Plan for the Audit of PSEG Nuclear Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Salem Nuclear Generating Station, Units 1 and 2 ML14183A0152014-07-11011 July 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 ML13127A1882013-05-31031 May 2013 Plan for the Regulatory Audit Regarding Flooding Walkdowns to Support Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident - Oyster Creek Nuclear Generating Station ML13127A4552013-05-20020 May 2013 Plan for the Regulatory Audit Regarding Flooding Walkdowns to Support Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident 2016-05-11
[Table view] Category:Letter
MONTHYEARML24296B1932024-10-23023 October 2024 Project Manager Assignment LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) IR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 LR-N24-0038, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 2024-09-25
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 1, 2015 Mr. Robert Braun President and CNO PSEG Nuclear LLC-N09 P. 0. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
NUCLEAR REGULATORY COMMISSION PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1-FLOODING FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (TAC NOS. MF3790 AND MF3791)
Dear Mr. Braun:
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff's plan to perform a regulatory audit of PSEG Nuclear LLC's (the licensee) supporting calculations of the Flood Hazard Reevaluation Report (FHRR) submittal related to the Near-Term Task Force Recommendation 2.1, Flooding for Salem Nuclear Generating Station, Units 1 and 2 (Salem).
This technical audit will be performed consistent with NRC Office of Nuclear Reactor Regulation, Office Instruction LIC-111, "Regulatory Audits, dated December 29, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML082900195). The audit will be conducted over multiple sessions, as needed, and the NRC staff will develop an audit summary report to document its observations and conclusions within 90 days of the final audit session.
The audit will provide the NRC staff with a better understanding of the Salem FHRR which was submitted March 11, 2014 (ADAMS Accession No. ML14071A401 ). Specifically, the audit will provide the NRC with a better understanding of the analyses of the flooding hazards presented in the Salem FHRR. The audit is intended to support completion of the staff's review of the FHRR and the subsequent issuance of a Staff Assessment.
The enclosed audit plan outlines the process that will allow the NRC staff to identify additional information potentially necessary for licensees to supplement their FHRRs, and resolve potential technical concerns. The details of this audit have been discussed with Mr. William Mc Tigue of your staff.
R. Braun If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov.
Sincerely, JL°"v~ L----_
Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv
NRC PLAN FOR THE AUDIT OF PSEG NUCLEAR LLC'S FLOOD HAZARD REEVALUATION REPORT SUBMITTAL RELATING TO THE NEAR-TERM TASK FORCE RECOMMENDATION 2.1 - FLOODING FOR SALEM NUCLEAR GENERATING STATION, UNITS 1AND2 BACKGROUND AND AUDIT BASIS:
By letter dated March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued a request for information to all power reactor licensees and holders of construction permits in active or deferred status, pursuant to Title 10 of the Code of Federal Regulations (10 CFR),
Section 50.54(f) "Conditions of license" (hereafter referred to as the "50.54(f) letter"). The request was issued in connection with implementing lessons-learned from the 2011 accident at the Fukushima Dai:.ichi nuclear power plant, as documented in The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident. Recommendation 2.1 of that document recommended that the staff issue orders to all licensees to reevaluate seismic and flooding for their sites against current NRC requirements and guidance. Subsequent Staff Requirements Memoranda associated with Commission Papers SECY 11-0124 and SECY-11-0137, instructed the NRC staff to issue requests for information to licensees pursuant to 10 CFR 50.54(f).
By letter dated March 11, 2014, PSEG Nuclear LLC (PSEG, the licensee) submitted its Flood Hazard Reevaluation Report (FHRR) for Salem Nuclear Generating Station, Units 1 and 2 (Salem) (Agencywide Documents Access and Management System Accession No. ML14071A401). The NRC staff has begun its review of the aforementioned submittals and plans to conduct a regulatory audit of PSEG to aid in its review of the licensee's FHRR.
REGULATORY AUDIT SCOPE AND METHODOLGY:
The areas of focus for the regulatory audit is the information contained in the Salem FHRR submittal, and all associated and relevant supporting documentation used in the development of the aforementioned document including, but not limited to, methodology, process information, calculations, computer models, etc. The audit will be conducted and completed over several meetings that are to be determined, as necessary.
Enclosure
INFORMATION AND OTHER MATERIAL NECESSARY FOR THE REGULATORY AUDIT:
The information required for the audit is the licensee's models and supporting calculations, as well as documentation related to the storm surge and site specific probable maximum precipitation analyses. Other information needs will be discussed as audit meetings are scheduled.
NRC AUDIT TEAM:
Title Team Member Affiliation Team Leader, NRR/JLD Tekia Govan NRC Branch Chief, NRO/DSEA Chris Cook NRC Technical Lead Kevin Quinlan NRC Technical Manaqer Mike Willinqham NRC Technical Support Various Contractors Department of Energy National Laboratory LOGISTICS:
The audit meetings will be coordinated with PSEG staff.
DELIVERABLES:
The NRC team will develop an audit summary report to convey the audit results. The report will be placed in ADAMS within 90 days of the completion of the final audit session, and will be publicly available.
The information discussed in the audit may be included, fully or in part, in the development of the NRC technical staff's assessments as a result of the FHRR review.
R. Braun If you have any questions, please contact me at (301) 415-6197 or by e-mail at Tekia.Govan@nrc.gov.
Sincerely, IRA/
Tekia V. Govan, Project Manager Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
Audit Plan cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC MShams, NRR MFranovich, NRR JLD R/F MWillingham, NRO JBowen, NRR RidsNRRJLD Resource ARivera, NRO BHarvey, NRO RidsNrrPMSalem Resource KErwin, NRO CParker, NRR BHarvey,NRO TGovan, NRR CCook, NRO RidsNrrDorllpl1-2 Resource KQuinlan, NRR ADAMS Accession No.: ML15146A220 OFFICE NRR/JLD/JHMB/PM NRR/JLD/JHMB/LA NRR/JLD/JHMB/BC NRR/JLD/JHMB/PM NAME TGovan Slent MS hams TGovan DATE 05/27/15 05/27/15 05/31/15 06/01/15 OFFICAL RECORD COPY