|
|
(One intermediate revision by the same user not shown) |
Line 14: |
Line 14: |
| | document type = OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING, TEXT-LICENSE APPLICATIONS & PERMITS | | | document type = OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING, TEXT-LICENSE APPLICATIONS & PERMITS |
| | page count = 12 | | | page count = 12 |
| | | project = |
| | | stage = Request |
| }} | | }} |
|
| |
|
Line 85: |
Line 87: |
| +emands of the various steady states loads and the charging capacity to restore the battery from the design minimum charge state to the fully charged state, irrespective of the status of the plant during which these demands occur." | | +emands of the various steady states loads and the charging capacity to restore the battery from the design minimum charge state to the fully charged state, irrespective of the status of the plant during which these demands occur." |
|
| |
|
| d.c. system is approxi- | | d.c. system is approxi-The normal continuous load on each mately 85 amps. The shutdown loads that are required in the event of a loss of offsite power are listed in FSAR Table 8.2-.2. |
| '
| |
| The normal continuous load on each mately 85 amps. The shutdown loads that are required in the event of a loss of offsite power are listed in FSAR Table 8.2-.2. | |
| The only steady state (8 hour) load listed, other than the in-verter, which operate both during normal operation and for safe plant shutdown, is the Turbine-Driven Auxiliary Feedwater Pump DC Oil Pump. This pump represents an additional potential 22 amp load on Battery 1B. The largest possible combined load-could thus occur during a plant shutdown following loss of offsite power, when all normal load continued operating, and the turbine-driven auxiliary feedwater pump was also engaged. This combined load of 85 amps plus 22 amps, for a total of 107 amps, is much | | The only steady state (8 hour) load listed, other than the in-verter, which operate both during normal operation and for safe plant shutdown, is the Turbine-Driven Auxiliary Feedwater Pump DC Oil Pump. This pump represents an additional potential 22 amp load on Battery 1B. The largest possible combined load-could thus occur during a plant shutdown following loss of offsite power, when all normal load continued operating, and the turbine-driven auxiliary feedwater pump was also engaged. This combined load of 85 amps plus 22 amps, for a total of 107 amps, is much |
| '- lower than the capacity of the 150 amp battery chargers. It is therefore apparent that the battery charger sizing criteria of Regulatory Guide 1.3.2, and IEEE 308-1974, Section 5.3.4 are easily met. | | '- lower than the capacity of the 150 amp battery chargers. It is therefore apparent that the battery charger sizing criteria of Regulatory Guide 1.3.2, and IEEE 308-1974, Section 5.3.4 are easily met. |
Similar Documents at Ginna |
---|
Category:OPERATING LICENSES-APPLIATION TO AMEND-RENEW EXISTING
MONTHYEARML17265A6921999-06-28028 June 1999 Application for Amend to License DPR-18 to Revise ITS Associated with RCS Leakage Detection Instrumentation.Lar Proposed as Result of Commitment That Rg&E Submit as Part of Staff Review of Application of leak-before-break Status ML17265A5691999-03-0101 March 1999 Application for Amend to License DPR-18,proposing Change in ITS to Revise Battery Cell Parameters Limit for Specific Gravity (SR 3.8.6.3 & SR 3.8.6.6) ML17265A4651998-11-24024 November 1998 Application for Amend to License DPR-18,revising Improved Tech Spec Description of Fuel Cladding Matl (TS 4.2.1) & Updating References Provided in TS 5.6.5 for COLR ML17265A2431998-04-27027 April 1998 Application for Amend to License DPR-18,revising Requirements Associated W/Sfp to Reflect Planned Mod to Storage Racks & Temporarily Addressing Boraflex Degradation within Pool ML17264B0431997-09-29029 September 1997 Application for Amend to License DPR-18,revising Administrative Controls W/Respect to RCS Pressure & Temp Limits Rept ML17264B0381997-09-29029 September 1997 Application for Amend to License DPR-18,revising TS Re Allowable Value & Trip Setpoint for High Steam Flow Input Into LCO Table 3.3.2-1,Function 4d (Main Steam Isolation) to Address Issues Identified in Revised Setpoint Analysis ML17264B0021997-08-19019 August 1997 Application for Amend to License DPR-18,allowing Testing of Certain ECCS motor-operated Valves in Mode 4 Which Currently Requires Entry in LCO 3.0.3 ML17264A9981997-08-19019 August 1997 Application for Amend to License DPR-18,correcting Specified Accumulator Borated Water Volume Values in SR 3.5.1.2 to Match Associated Accumulator Percent Level Values ML17264A8661997-04-24024 April 1997 Application for Amend to License DPR-18,revising RCP PT & Administrative Control Requirements ML17264A8471997-03-31031 March 1997 Application for Amend to License DPR-18,revising Spent Fuel Pool Storage Requirements ML20134D9911996-10-29029 October 1996 Application for Amend to License DPR-18,requesting Change to Mode of Applicability for Auxiliary Feedwater Pump Actuation on Main Feedwater Pump ML17264A7121996-10-29029 October 1996 Application for Amend to License DPR-18 Requesting Change to Required Actions for Inoperable Channels Associated with Auxiliary Feedwater Pump ML17264A5991996-09-13013 September 1996 Application for Amend to License DPR-18,revising RCS Pressure & Temp Limits Rept ML17264A4701996-05-0808 May 1996 Application for Amend to License DPR-18,correcting Typos ML17264A4041996-03-15015 March 1996 Application for Amend to License DPR-18,revising TS to Incorporate Methodology for Determining RCS P/T Limits & LTOP Limits in Administrative Controls Section of RCS P/T Limits Rept ML17264A3441996-02-0909 February 1996 Application for Amend to License DPR-18,revising TS Table 3.3.2-1,Function 5b, Feedwater Isolation,Sg Water Level - High to Raise Allowable Value & Trip Setpoint ML17264A3381996-02-0909 February 1996 Application for Amend to License DPR-18,revising TS to Incorporate Ref to Methodology for Determining LTOP Limits Into Administrative Controls Section for RCS PT Limits Rept ML17264A3331996-02-0909 February 1996 Application for Amend to License DPR-18,revising Requirements for Containment Closure During Mode 6 to Allow Use of Installed Overhead Door Assembly to Isolate Equipment Hatch Opening ML17264A3221996-01-26026 January 1996 Application for Amend to License DPR-18,incorporating Changes Necessary to Reflect Revised Nuclear Fuel Loading ML17264A2521995-11-27027 November 1995 Application for Amend to License DPR-18,revising TS to Implement 10CFR50,App J,Option B ML17264A2551995-11-20020 November 1995 Application for Amend to License DPR-18,submitting Changes to TS Instrumentation Requirements & Conversion to Improved TS ML17264A1501995-08-31031 August 1995 Application for Amend to License DPR-18,proposing Ts,By Implementing WCAP-10271,its Assoc Suppls & Other Re Changes W/Respect to RTS & ESFAS ML17263B0671995-05-26026 May 1995 Application for Amend to License DPR-18,revising TSs in Entirety to Convert to Improved TSs ML17263A9771995-03-13013 March 1995 Application for Amend to License DPR-18,to Revise TS 4.4.2.4.a to Replace Specific Leakage Testing Frequencies for Containment Isolation Valves ML17309A5501994-07-15015 July 1994 Application for Amend to License DPR-18,proposing TS 3.5, Providing NRC W/Opportunity to Communicate at Early Stage Any Concerns W/Respect to Differences from NUREG-1431 ML17263A7141994-06-24024 June 1994 Application for Amend to License DPR-18,re Upgrading of Administrative Controls Section 6 ML17263A7071994-06-15015 June 1994 Notarized Application for Amend to License DPR-18 Re Reactor Coolant Activity ML17263A6551994-05-23023 May 1994 Application for Amend to License DPR-18,increasing Allowable Reactor Coolant Activity Levels to Improved TS (NUREG-1431) ML17263A6411994-05-13013 May 1994 Application for Amend to License DPR-18,revising TS Administrative Controls Section 6.0 Consistent W/Improved TS ML17263A3181993-07-13013 July 1993 Application for Amend to License Revisions for License DPR-18 Re Removing Containment Isolation Valve Table 3.6-1 from TS ML17263A2081993-04-0505 April 1993 Application for Amend to License DPR-18,revising TS to Remove Containment Isolation Valve Table 3.6-1 & Maintain Required Listing in Updated FSAR ML17262B1171992-12-17017 December 1992 Application for Amend to License DPR-19,revising TS Sections 3.2 & 3.3 to Eliminate Use of High Concentration Boric Acid as safety-related Source of SI Pumps & Increasing Allowable Outage Times ML17262B0991992-11-30030 November 1992 Application for Amend to License DPR-18,revising TS to Remove Table of Containment Isolation Valves & Provide Ref in Bases to UFSAR ML17262B0571992-10-0808 October 1992 Corrected Application for Amend to License DPR-18,adding Addl Requirements to Auxiliary Electrical Sys TS & Action Statements for Instrument Bus Sys,Consisting of Notarized Page Two ML17262B0431992-10-0808 October 1992 Application for Amend to License DPR-18,adding Addl Requirements to Auxiliary Electrical Sys TS & Action Statements for Instrument Bus Sys,Per Guidance Provided in GL 91-11 Re Resolution of GI 48 ML17262B0201992-09-15015 September 1992 Application for Amend to License DPR-18,revising TS Sections 3.1.1.4,3.1.1.6,4.3.4 & Adding site-specific Basis Sections to Address GL 90-06 Re Resolution of Generic Issues 70 & 94 ML17262A9121992-06-22022 June 1992 Application for Amend to License DPR-18,revising TS 4.3.1 Per Guidance Provided in Generic Ltr 91-01, Removal of Schedule for Withdrawal of Reactor Vessel Matl Specimens from Ts. ML17262A8311992-04-23023 April 1992 Application for Amend to License DPR-18,changing TSs to Redefine Snubber Visual Insp Schedule,Per Generic Ltr 90-09 Guidance ML17262A8211992-04-21021 April 1992 Application for Amend to License DPR-18,instituting Std License Condition for Fire Protection Program & Removing Requirements for Fire Protection Sys from Tss,Per Guidance in Generic Ltrs 86-10 & 88-12 ML17262A7861992-03-23023 March 1992 Application for Amend to License DPR-18,revising Tech Spec Section 6.5.1, Plant Operations Review Committee Function. ML17262A7801992-03-20020 March 1992 Application for Amend to License DPR-18,revising TS 5.1 Figure 5.1-1 to Describe Rather than Depict Site Area Boundary to Evaluate Radiological Releases to Unrestricted Area ML17262A7901992-03-20020 March 1992 Application for Amend to License DPR-18,revising Tech Specs 6.9.1.2 & 6.9.2.5 ML17262A6321991-10-25025 October 1991 Application for Amend to License DPR-18 to Delete TS 5.1 & Figure 5.1-1 ML17262A5331991-06-20020 June 1991 Application for Amend to License DPR-18,to Incorporate Changes to Specifications & Action Statements for Offsite & Onsite Power Sources Available for Operation of Plant Auxiliaries ML17262A4121991-03-0808 March 1991 Application for Amend to License DPR-18,removing Table 3.6-1 Re Containment Isolation Valves from Tech Specs ML17262A3831991-02-15015 February 1991 Application for Amend to License DPR-18,revising Tech Specs to Modify Method of Locking Open Motor Operated Valve 856, Refueling Water Storage Tank Delivery Valve When Reactor Coolant Sys at or Above 350 F ML17262A3751991-02-15015 February 1991 Application for Amend to License DPR-18,revising Heatup/Cooldown Curves & Associated Low Temp Overpressure Protection Setpoint to Implement Reg Guide 1.99,Rev 2 Methodology ML17262A3721991-02-15015 February 1991 Application for Amend to License DPR-18,providing Clarification of Which QA Activities Subj to Audit Considerations & Changing Audit Frequency Described in Tech Spec 6.5.2.8d ML17262A3871991-02-15015 February 1991 Application for Amend to License DPR-18,revising Tech Spec Tables 3.5-5 & 4.1-5 Based on Mods to Radiation Monitoring Sys ML17262A2951991-01-14014 January 1991 Application for Amend to License DPR-18,changing Tech Specs to Limit Containment Internal Pressure to 1 Psig Vs 6 Psig Per Initial Condition Assumptions in Containment Integrity Analysis 1999-06-28
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML17265A6921999-06-28028 June 1999 Application for Amend to License DPR-18 to Revise ITS Associated with RCS Leakage Detection Instrumentation.Lar Proposed as Result of Commitment That Rg&E Submit as Part of Staff Review of Application of leak-before-break Status ML17265A5691999-03-0101 March 1999 Application for Amend to License DPR-18,proposing Change in ITS to Revise Battery Cell Parameters Limit for Specific Gravity (SR 3.8.6.3 & SR 3.8.6.6) ML17265A4651998-11-24024 November 1998 Application for Amend to License DPR-18,revising Improved Tech Spec Description of Fuel Cladding Matl (TS 4.2.1) & Updating References Provided in TS 5.6.5 for COLR ML17265A2431998-04-27027 April 1998 Application for Amend to License DPR-18,revising Requirements Associated W/Sfp to Reflect Planned Mod to Storage Racks & Temporarily Addressing Boraflex Degradation within Pool ML17264B0431997-09-29029 September 1997 Application for Amend to License DPR-18,revising Administrative Controls W/Respect to RCS Pressure & Temp Limits Rept ML17264B0381997-09-29029 September 1997 Application for Amend to License DPR-18,revising TS Re Allowable Value & Trip Setpoint for High Steam Flow Input Into LCO Table 3.3.2-1,Function 4d (Main Steam Isolation) to Address Issues Identified in Revised Setpoint Analysis ML17264B0021997-08-19019 August 1997 Application for Amend to License DPR-18,allowing Testing of Certain ECCS motor-operated Valves in Mode 4 Which Currently Requires Entry in LCO 3.0.3 ML17264A9981997-08-19019 August 1997 Application for Amend to License DPR-18,correcting Specified Accumulator Borated Water Volume Values in SR 3.5.1.2 to Match Associated Accumulator Percent Level Values ML17264A8661997-04-24024 April 1997 Application for Amend to License DPR-18,revising RCP PT & Administrative Control Requirements ML17264A8471997-03-31031 March 1997 Application for Amend to License DPR-18,revising Spent Fuel Pool Storage Requirements ML20134D9911996-10-29029 October 1996 Application for Amend to License DPR-18,requesting Change to Mode of Applicability for Auxiliary Feedwater Pump Actuation on Main Feedwater Pump ML17264A7121996-10-29029 October 1996 Application for Amend to License DPR-18 Requesting Change to Required Actions for Inoperable Channels Associated with Auxiliary Feedwater Pump ML17264A5991996-09-13013 September 1996 Application for Amend to License DPR-18,revising RCS Pressure & Temp Limits Rept ML17264A4701996-05-0808 May 1996 Application for Amend to License DPR-18,correcting Typos ML17264A4041996-03-15015 March 1996 Application for Amend to License DPR-18,revising TS to Incorporate Methodology for Determining RCS P/T Limits & LTOP Limits in Administrative Controls Section of RCS P/T Limits Rept ML17264A3441996-02-0909 February 1996 Application for Amend to License DPR-18,revising TS Table 3.3.2-1,Function 5b, Feedwater Isolation,Sg Water Level - High to Raise Allowable Value & Trip Setpoint ML17264A3381996-02-0909 February 1996 Application for Amend to License DPR-18,revising TS to Incorporate Ref to Methodology for Determining LTOP Limits Into Administrative Controls Section for RCS PT Limits Rept ML17264A3331996-02-0909 February 1996 Application for Amend to License DPR-18,revising Requirements for Containment Closure During Mode 6 to Allow Use of Installed Overhead Door Assembly to Isolate Equipment Hatch Opening ML17264A3221996-01-26026 January 1996 Application for Amend to License DPR-18,incorporating Changes Necessary to Reflect Revised Nuclear Fuel Loading ML17264A2521995-11-27027 November 1995 Application for Amend to License DPR-18,revising TS to Implement 10CFR50,App J,Option B ML17264A2551995-11-20020 November 1995 Application for Amend to License DPR-18,submitting Changes to TS Instrumentation Requirements & Conversion to Improved TS ML17264A1501995-08-31031 August 1995 Application for Amend to License DPR-18,proposing Ts,By Implementing WCAP-10271,its Assoc Suppls & Other Re Changes W/Respect to RTS & ESFAS ML17263B0671995-05-26026 May 1995 Application for Amend to License DPR-18,revising TSs in Entirety to Convert to Improved TSs ML17263A9771995-03-13013 March 1995 Application for Amend to License DPR-18,to Revise TS 4.4.2.4.a to Replace Specific Leakage Testing Frequencies for Containment Isolation Valves ML17309A5501994-07-15015 July 1994 Application for Amend to License DPR-18,proposing TS 3.5, Providing NRC W/Opportunity to Communicate at Early Stage Any Concerns W/Respect to Differences from NUREG-1431 ML17263A7141994-06-24024 June 1994 Application for Amend to License DPR-18,re Upgrading of Administrative Controls Section 6 ML17263A7071994-06-15015 June 1994 Notarized Application for Amend to License DPR-18 Re Reactor Coolant Activity ML17263A6551994-05-23023 May 1994 Application for Amend to License DPR-18,increasing Allowable Reactor Coolant Activity Levels to Improved TS (NUREG-1431) ML17263A6411994-05-13013 May 1994 Application for Amend to License DPR-18,revising TS Administrative Controls Section 6.0 Consistent W/Improved TS ML17263A3181993-07-13013 July 1993 Application for Amend to License Revisions for License DPR-18 Re Removing Containment Isolation Valve Table 3.6-1 from TS ML17263A2081993-04-0505 April 1993 Application for Amend to License DPR-18,revising TS to Remove Containment Isolation Valve Table 3.6-1 & Maintain Required Listing in Updated FSAR ML17262B1171992-12-17017 December 1992 Application for Amend to License DPR-19,revising TS Sections 3.2 & 3.3 to Eliminate Use of High Concentration Boric Acid as safety-related Source of SI Pumps & Increasing Allowable Outage Times ML17262B0991992-11-30030 November 1992 Application for Amend to License DPR-18,revising TS to Remove Table of Containment Isolation Valves & Provide Ref in Bases to UFSAR ML17262B0571992-10-0808 October 1992 Corrected Application for Amend to License DPR-18,adding Addl Requirements to Auxiliary Electrical Sys TS & Action Statements for Instrument Bus Sys,Consisting of Notarized Page Two ML17262B0431992-10-0808 October 1992 Application for Amend to License DPR-18,adding Addl Requirements to Auxiliary Electrical Sys TS & Action Statements for Instrument Bus Sys,Per Guidance Provided in GL 91-11 Re Resolution of GI 48 ML17262B0201992-09-15015 September 1992 Application for Amend to License DPR-18,revising TS Sections 3.1.1.4,3.1.1.6,4.3.4 & Adding site-specific Basis Sections to Address GL 90-06 Re Resolution of Generic Issues 70 & 94 ML17262A9121992-06-22022 June 1992 Application for Amend to License DPR-18,revising TS 4.3.1 Per Guidance Provided in Generic Ltr 91-01, Removal of Schedule for Withdrawal of Reactor Vessel Matl Specimens from Ts. ML17262A8311992-04-23023 April 1992 Application for Amend to License DPR-18,changing TSs to Redefine Snubber Visual Insp Schedule,Per Generic Ltr 90-09 Guidance ML17262A8211992-04-21021 April 1992 Application for Amend to License DPR-18,instituting Std License Condition for Fire Protection Program & Removing Requirements for Fire Protection Sys from Tss,Per Guidance in Generic Ltrs 86-10 & 88-12 ML17262A7861992-03-23023 March 1992 Application for Amend to License DPR-18,revising Tech Spec Section 6.5.1, Plant Operations Review Committee Function. ML17262A7801992-03-20020 March 1992 Application for Amend to License DPR-18,revising TS 5.1 Figure 5.1-1 to Describe Rather than Depict Site Area Boundary to Evaluate Radiological Releases to Unrestricted Area ML17262A7901992-03-20020 March 1992 Application for Amend to License DPR-18,revising Tech Specs 6.9.1.2 & 6.9.2.5 ML17262A6321991-10-25025 October 1991 Application for Amend to License DPR-18 to Delete TS 5.1 & Figure 5.1-1 ML17262A5331991-06-20020 June 1991 Application for Amend to License DPR-18,to Incorporate Changes to Specifications & Action Statements for Offsite & Onsite Power Sources Available for Operation of Plant Auxiliaries ML17262A4121991-03-0808 March 1991 Application for Amend to License DPR-18,removing Table 3.6-1 Re Containment Isolation Valves from Tech Specs ML17262A3831991-02-15015 February 1991 Application for Amend to License DPR-18,revising Tech Specs to Modify Method of Locking Open Motor Operated Valve 856, Refueling Water Storage Tank Delivery Valve When Reactor Coolant Sys at or Above 350 F ML17262A3751991-02-15015 February 1991 Application for Amend to License DPR-18,revising Heatup/Cooldown Curves & Associated Low Temp Overpressure Protection Setpoint to Implement Reg Guide 1.99,Rev 2 Methodology ML17262A3721991-02-15015 February 1991 Application for Amend to License DPR-18,providing Clarification of Which QA Activities Subj to Audit Considerations & Changing Audit Frequency Described in Tech Spec 6.5.2.8d ML17262A3871991-02-15015 February 1991 Application for Amend to License DPR-18,revising Tech Spec Tables 3.5-5 & 4.1-5 Based on Mods to Radiation Monitoring Sys ML17262A2951991-01-14014 January 1991 Application for Amend to License DPR-18,changing Tech Specs to Limit Containment Internal Pressure to 1 Psig Vs 6 Psig Per Initial Condition Assumptions in Containment Integrity Analysis 1999-06-28
[Table view] |
Text
~ \
UNXTED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Xn the Matter of )
'I
)
Rochester Gas and Electric Corporation ) Docket No. 50-244 (R. E. Ginna Nuclear Power Plant, )
Unit No. l) )
APPLICATION FOR AMENDMENT TO OPERATING LICENSE Pursuant to Section 50.90 of the regulations of the U.S.
Nuclear Regulatory Commission (the "Commission" ), Rochester Gas and Electric Corporation ("RG&E"), holder of Provisional Operating License No. DPR-18, hereby requests that the Technical Specifica-tion 3.7 set forth in Appendix A to that license be amended to modify the requirements for operability of the d.c. electrical systems.
I The proposed technical specification change is set forth in Attachment A to this Application. A safety evaluation is set forth in Attachment B. This evaluation also demonstrates that the proposed change does not involve a significant change in the types or a significant increase in the amounts of effluents or any change in the authorized power level of the facility. Justi-
-fication for classification of the amendment pursuant to 10 CFR Section 170.22 is included as Attachment C. A check for the appropriate fee accompanies this Application.
WHEREFORE, Applicant respectfully requests that Appendix A to Provisional Operating License No. DPR-18 be amended in the form attached hereto as Attachment A.
Rochester Gas and Electric Corporation By L.D. Nhi e, Jr.
Vice President,
.Electric and Steam Production Subscribed and sworn to before me on this/O day of October, 1978.
SHARON G. CAVALERI NOTARY PUBLIC, State of N.Y., h'lonroe County My Commfssion Expires March 30, 29/.g
Attachment A Replace Technical Specification pages 3.7-1 through 3.7-4 with the revised pages 3.7-1 through 3.7-4.
3.7 AUXILIARY ELECTRICAL SYSTEMS A plicabilit Applies to the availability of electrical power for the operation of plant auxiliaries.
To define those conditions of electrical power availability necessary (1) to provide for safe reactor operation, and (2) to provide for the continuing availability of engineered safeguards.
S ecification 3.7.1 The reactor shall not be maintained critical without:
- a. The 34.5 KV-4160 Volt station service transformer in service.
- b. 480-volt buses 14, 16, 17 and 18 energized.
- c. 4160-volt buses 12A and 12B energized.
- d. Two diesel generators operable with onsite supply of 10,000 gallons of fuel available.
- e. Both batteries and both d.c. systems operable, and r
at least one 150 amp battery charger-or two 75 amp battery chargers in service for each battery.
3.7.2 During reactor operation the requirement of 3.7.1 may be modified as follows:
3 ~ 7 1
- a. Power operation may continue with 'the station service transformer out of service provided (a) the failure shall be reported to NRC within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> with an outline of the plans for prompt restoration of offsite power and the .
additional precautions to be taken while the transformer W
is out of service and (b) both diesel. generators are operable. Under conditions of fulfillment of (b) and non-fulfillment of (a), continued power operation shall not extend beyond 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Non-fulfillment of (b) shall be i de'emed sufficient cause for immediate reactor shutdown.
- b. Power operation may continue if one diesel generator is out of service provided (a) the remaining diesel generator is run continuously, and (b) the station service trans-former is in service and (c) such operation is not in excess of 7 day (total for both diesels) during any month.
- c. Power operation may continue if the battery charger(s) forl one d.c. system are inoperable, as long as the inoperable battery chargers are restored to operable status within two hours. If not restored, the reactor shall be placed;:
in the hot shutdown condition within the next six hours and in the cold shutdown condition within the following 30 hours..
Basis: '
i(
The electrical syst'm equipment is arranged so that no single contingency can inactivate enough safeguards equipment to jeopardize the plant safety. The 480-volt equipment is arranged 3~7 2
on 6 buses. The 4160-volt equipment, also is supplied from 4 buses.
Two separate outside sources supply station service power to the plant.
The plant auxiliary is arranged electrically so that mul-tiple items receive their power from the two different sources.
The charging pumps are supplied from the 480-volt buses No.
14 and 16. The four containment fans are divided between 480-volt buses No. 14 and 16. The two residual heat pumps are on separate 480-volt buses. Valves are supplied from I
motor control centers.
One outside source of power is required to give sufficient power to run normal operating equipment. One transmission line can supply all the plant auxiliary power. The 115-34.5 kv station service transformer can supply all the auxiliary loads.
The bus arrangements specified for operation ensure that power is available to an adequate number of safeguards auxiliaries.
With additional switching, more equipment could be out of service without infringing on safety.
Two diesel generators have sufficient capacity to start and run at design load all the engineered safeguards equipment. The S /
safeguards operated from one diesel generator can adequately lC cool the core for any loss-of-coolant incident, and they also 3~7 3
maintain the containment pressure within the design value.
The minimum diesel fuel oil inventory at all times is maintained to assure the operation of both diesels carrying design load of all the engineered safeguards equipment for at least 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />. - Commercial oil supplies and trucking facilities exist to assure deliveries within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
At least one 150 amp battery charger or two 75 amp battery chargers shall be in. service for each battery so that the batteries will t
always be at full charge. This ensures that adequate dc power will be available.
The plant can be safely shutdown without the use of offsite power since all vital loads (sa'fety systems, instruments etc.)
can be supplied from the emergency diesel generators.
The two diesel generators, each capable of supplying safeguards loads, and the station auxiliary transformer provide three separate sources of power supply system meets the single failure criteria required of safety systems. (2)
\
Refernces:
(1) FSAR Section-8.2.1 (2) FSAR Appendix 8A s j pl 3.7-4
Attachment. B Technical Specification 3.7.1 e presently requires that only one battery charger (which has a 150 amp capacity) needs to be operable while the reactor is critical.
The total normal d.c. load is presently about 170 amps. Two additional battery chargers, each with a 75 amp charging capacity, have been installed. With all battery chargers operational and in their normal configuration, there is a total battery charger capacity of 225 amps per battery. In the event either of the 150 amp battery chargers becomes inoperable, manual transfer of one 75 amp battery charger will result in a battery charger capacity to each battery of 150 amps.
This configuration and capacity is consistent. with the guidance provided in Regulatory Guides 1.6 and 1.32. Regulatory Guide 1.6, Rev. 0, position D.3, states that "each d.c. load group should be energized by a battery and battery charger. The battery-charger combination should have no automatic connection to any other redundant d.c. load group." This guidance is satisfied by having only manual connection between d.c. load groups. Regulatory ~ P' Guide 1.32, Rev. 2, Section C.l.b, states that"... the capacity of the battery charger supply should be based on the largest combined
+emands of the various steady states loads and the charging capacity to restore the battery from the design minimum charge state to the fully charged state, irrespective of the status of the plant during which these demands occur."
d.c. system is approxi-The normal continuous load on each mately 85 amps. The shutdown loads that are required in the event of a loss of offsite power are listed in FSAR Table 8.2-.2.
The only steady state (8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />) load listed, other than the in-verter, which operate both during normal operation and for safe plant shutdown, is the Turbine-Driven Auxiliary Feedwater Pump DC Oil Pump. This pump represents an additional potential 22 amp load on Battery 1B. The largest possible combined load-could thus occur during a plant shutdown following loss of offsite power, when all normal load continued operating, and the turbine-driven auxiliary feedwater pump was also engaged. This combined load of 85 amps plus 22 amps, for a total of 107 amps, is much
'- lower than the capacity of the 150 amp battery chargers. It is therefore apparent that the battery charger sizing criteria of Regulatory Guide 1.3.2, and IEEE 308-1974, Section 5.3.4 are easily met.
If the battery charger for one d.c. system were found to be inoperable, it would be possible in most cases to effect repairs and restore the system to operability within a relatively short r
time. This configuration would not negate the ability of the d.c.
I system to perform its function, but it would reduce the redundancy provided in the reactor desi.'gn, and thereby limit the ability to tolerate additional equipment failures. (Although it'should be noted that the batteriesl by themselves could carry all shutdown loads for- 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />). The redundant d.c. system would be thoroughly checked to ensure its operability. If it developed that the
~ ~ ~
inoperable d.c. system could not be made operable within two hours, the reactor would be placed in the hot shutdown condition, to provide for reduction of decay heat from the fuel. If after another six hours the malfunction were not corrected, the reactor would be placed in a cold shutdown condition within 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />, using normal shutdown and cooldown procedures. These time periods are consistent with the guidance provided in Regulatory Guide 1.93, Rev. 0, "Availability of Electric Power Sources", Regulatory Position 5.
P' r
~
~
I Att'achme'nt C.
The proposed Amendment to the Provisional Operating License has been evaluated and determined to fall within the definition of Class III of 10 CFR Section 170.22 thereby requiring a fee of
$ 4,000. The proposed amendment simply clarifies a single safety issue, battery charger capacity. The issue has been clearly identified by NRC regulatory guides.
C
P
~ t